Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹16.4 L
EMD Value
₹17,000
Closing Date
23 Nov 2026, 6:00 pmDue today
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
EXECUTIVE ENGINEER’S OFFICE, SURAT (R&B) DIVISION NO.1, SURAT
Consultancy Services for Qaulity Assurance of Construction of Categary-E type 32 Units Residential Quarters for the Judicial Officers at Nanpura, Surat.
363954
13-1 of 2026-27
Open
Consultancy Services
Works
Surat
9 documents required · 9 mandatory
₹900
Executive Engineer, Surat (R&B) Division 1, Surat
₹17,000
6 Nov 2026
6 Nov 2026
6 Nov 2026
23 Nov 2026
6 Nov 2026
120 days
must be submitted not later than the following date and time : as stated in technical Bid /
letter of invitation.
TECHNICAL PROPOSAL
TECHNICAL PROPOSAL – STANDARD FORMS
3A Technical Proposal Submission form
3B Firm’s Reference
3C Comments and suggestions on the Terms of Reference and on data services, and
facilities to be provided by the Client
3D Description of the methodology and work plan for performing the assignment
3E Team composition and task assignments
3F Format of curriculum Vitae of proposed key professional staff
3G Time schedule for professional personnel
3H Activity (work) schedule
3A TECHNICAL PROPOSAL SUBMISSION FORM
[LOCATION DATE]
FROM: (NAME OF FIRM) TO : [NAME AND ADDRESS OF CLIENT]
Ladies / Gentlemen:
Subject: Consultancy Service for Quality Assurance of Construction of Categary-E
type 32 Units Residential Quarters for the Judicial Officers at Nanpura,
Technical Proposal
We, the undersigned, offer to provide the consulting services for the above in accordance
with your Request for Proposal dated (Date) and our attained proposal. The Proposal which, we
are hereby submitting, includes a Technical Proposal and a Financial Proposal. If selected to
implement the services during the validity period of (period), we undertake to negotiate the
contract on the basis of the proposed staff. Our proposal is binding upon us and subject to the
modifications resulting from contract negotiations.
We understand you are not bound to accept any Proposal you receive.
Your sincerely,
Authorized Signature
Name and Title of Signatory
3 B. FIRM’S REFERENCES
Relevant Services Carried Out in the Last Five Years
That Best Illustrate Qualifications
Using the format below provide information on each reference assignment for which your
firm either individual as a corporate entity or as one of the major with association was
legally contracted by the Client stated below …
Assignment Name Country
Location within country Key professional staff provided by your
Name of Client : No. of Staff :
No. of man-months :
Address : No. of support staff :
No. of man-months :
Start Date (Month/Year): Completion date : Approx, Value of services (in Rupees in
(Month/Year) : Lacs):
Name of Associated consultants if any : No. of Months of key professional staff,
provided by Associated Consultants :
Name & qualification of senior staff ( Project Director/ Coordinator, Team Leader) involved and
functions performed :
Narrative description of Project :
Description of Actual Services Provided by your Staff :
Firm’s Name & authorized signature : _____________________
Note : Support document in reference to above data shall be provided.
Summary Sheet for form - 3B
Sr. Nos. of Projects in
No. last five year
Experience in similar nature and
size of projects (Total)
2 Experience in similar region (out of above)
3C. COMMENTS AND SUGGESTIONS OF CONSULTANTS ON THE TERMS OF
REFERENCE AND ON DATA, SERVICES, AND FACILITIES TO BE PROVIDED BY
On the Terms of Reference :
On the data, services, and facilities to be provided by the Client
Consulting Firm’s Name
3D. DESCRIPTION OF THE METHODOLOGY AND WORK PLAN FOR PERFORMING
3E. TEAM COMPOSITION AND TASK ASSIGNMENTS
1. Technical / Key Staff
Sr. No. Name Position Task
2. Support Staff
Sr. No. Name Position Task
3F. FORMAT OF CURRICULUM VITAE (CV) FOR
PROPOSED KEY PROFESSIONAL STAFF
Date of Birth : ________________ Age : _____ Years with Firm/Entity : _________
Nationality : _________ Membership in Professional Societies : ________________
Key Qualifications :
[Give an outline of staff member’s experience and training, and position most
pertinent to tasks on assignment. Describe degree of responsibility held by staff
member on relevant previous assignments and give dates and locations. Use about
half a page preferably in tabular form]
[Summarized college/university’s and other specialized education of staff member,
giving names of schools, dates attended and degree obtained. Use about one
quarter of a page preferably in tabular form]
Employment Records :
[Starting with present position. List in reverse order every employment held. List all
positions held by staff member since graduation, giving dates, names of employing
organizations, titles of positions held, and locations of assignment. For experience in
last ten years, also give types of activities performed and Client references, where
appropriate. Use about three quarters of a page preferably in tabular form.]
[For each language indicate proficiency excellent, good, fair or poor; in speaking,
reading, and writing]
Certification :
I, the undersigned, certify that to the best of my knowledge and belief, these data
correctly describe me, my qualifications, and my experience.
[Signature of staff member and authorized representative of the Firm] Day / Month
Full name of authorized representative : __________________________________
Note :- It is advised to attach summary sheet of CV for key staff indicating(a)
position proposed (b) name (c) qualification (d) age (e) total experience in nos. of
months (f) relevant experience in nos. of months (g) position held.
3G. TIME SCHEDULE FOR PROFESSIONAL PERSONNEL
Sr. Reports Due/ Months (in the form of a Bar chart)
Name Position Months
1. Sub total (1)
2. Sub total (2)
Reports Due : ________________
Activities Duration : ________________
(Authorized Representative )
3H. ACTIVITY (WORK) SCHEDULE
A. Field Investigation and Study Items :
Month wise Program ( in form of Bar chart)
Sr. No. Item of Activity (Work) [1st , 2nd etc. are months from the start of assignment]
B. Completion and Submission of Reports
Reports : Programme : (Date)
1. Inception Report
2. Monthly Progress Report
3. Quarterly Report
4. Final Completion Report and certificates
FINANCIAL PROPOSAL
FINANCIAL PROPOSAL – STANDARD FORMS
4A Financial Proposal.
4B Summary of Costs – Appendix B of Price Bid & Appendix B1 & B2
Note :- Financial proposal must be supported by necessary documents like Form–16 of employee
and authorized last pay slip, to justify remuneration of the employee.
4 – A FINANCIAL PROPOSAL SUBMISSION FORM
[Location, date]
FROM : (Name of Firm) TO : (Name and Address of Client)
Ladies / Gentlemen :
Subject : Consultancy Service for Quality Assurance of Construction of Categary-E type 32 Units
Residential Quarters for the Judicial Officers at Nanpura, Surat.
Financial Proposal
We, the undersigned, offer to provide the consulting services for the above in accordance with your Request
for Proposal date [Date], and our attached Financial Proposal for the sum of [Amount in words and figures]. This
amount is inclusive of all taxes which we have estimated at prevailing rates.
If selected to implement the services during the validity period of the proposal i.e. [period], our Proposal
shall be biding upon us subject to the modifications resulting from contract negotiations.
We undertake that, in completing for (and, if the award is made to us, in executing) the above contract, we
will strictly observe the laws against fraud and corruption in force in India namely “Prevention of Corruption Act
We understand you are not bound to accept any Proposal you receive.
Yours Sincerely,
Authorized Signature
Name and Title of Signatory
Name of the Firm
4B :- Summary of cost
No. Details Amounts (Rs.)
1 Remuneration (4B-1)
2 Out of Pocket Expenses (4B-2)
Note : Grand total will be considered for evaluation
Note : Grand total will be considered for evaluation
4 B-1 Remuneration
Sr. Name Position Remuneration Nos. of Days Gross
No. per month Remuneration
(a) Key Personnel
4B–2 Out of Pocket Expenses
No. Details Cost
DECLARATION / UNDERTAKING
DECLARATION / UNDERTAKING
1. I / We agree that the decision of the R & B Department, Sachivalaya, Gandhinagar hereby referred
as Client in selection of Applicants / Contractor, phasing of works and in any other Project related
matter, will be final and bidding to me / us.
2. All the information and date finished herewith are correct to my / our best of knowledge.
3. I / We agree that we have no objection if inquiries are made about our works, its related areas and any
other inquiry regarding all details, projects and works listed by us in the Pre-Qualification document.
4. I / We also understand that furnishing of wrong information or hiding of any information shall be a
cause for disqualification.
Date : Signature with Seal of the Company
TERMS OF REFERANCE
TERMS OF REFERENCE
Consultancy Service for Quality Assurance of Construction of Categary-E type
Units Residential Quarters for the Judicial Officers at Nanpura, Surat.
ROADS AND BUILDINGS DEPARTMENT
GOVERNMENT OF GUJARAT
Consultancy Service for Quality Assurance of Construction of Categary-E type
Units Residential Quarters for the Judicial Officers at Nanpura, Surat.
CONTRACT BETWEEN
ROADS & BUILDINGS EPARTMENT
(THE CONSULTANT)
TERMS OF REFERENCE
TERMS OF REFERENCE FOR
Consultancy Service for Quality Assurance of Construction of Category-E type
Units Residential Quarters for the Judicial Officers at Nanpura, Surat.
1.0 INTRODUCTION AND BACK GROUND
1.01 Nanpura of Surat is in Northwest of the central city area of Surat. The Legal
Department,Government Of Gujarat has Approved Categary-E type 32 Units Residential Quarters
for the Judicial Officers in Sundaram judges Colony.
1.02 The Roads and Buildings Department (R&BD), Government of Gujarat, intends to engage a
consultancy firm to provide Third Party Quality Assurance and Technical Audit (TA/QA)
Services for the Consultancy Service for Quality Assurance of Construction of Category-E type
units Residential Quarters for the Judicial Officers at Nanpura, Surat The prioritization of works
has been carried out by R & B Deptt. Roads and Building Department, Government of Gujarat
will be the supervising and Implementing agency for the Projects. The works will be executed
through the contractors appointed by Govt. of Gujarat through open competition tendering system.
It is intended that the buildings be upgraded to standard of National Building Code and IS Code.
specifications, respective guidelines and R&BD standard specifications.
1.03 The scope of work shall include inspection and monitoring of building construction. The building
works shall include RCC work with P+8 floor. The inspection shall also cover installation of
cautionary, warning, and mandatory signage in compliance with relevant standards and
specifications.
1.04 In order to achieve high standard in quality of building constructions works, R&BD is intended to
hire consultancy services for providing quality Assurance and Technical Audit of works being
carried out under the schemes as specified. Primarily responsibility of day to day supervision of
works will be that of R & B engineers and consultant’s role shall be of Quality Assurance and
Technical Audit and Carrying out safety audit through a qualified and experienced building safety
Auditor as per NBC and IS code guidelines and submission of report with cost effective measures
and its estimate.
2.01 The main objective of these consulting services is to conduct technical audits and / Carrying out
safety audit through a qualified and experienced Building Safety Auditor as per NBC and IS
guidelines and submission of report with cost effective measures and its estimate of the execution of the
identified Consultancy Service for Quality Assurance of Construction of Category-E type 32 units
Residential Quarters for the Judicial Officers at Nanpura, Surat as specified in Annexure- II. of whereby
the consultant will render professional services to improve the quality of construction of Building and
2.02 To ensure achieving high standards in quality of construction works.
2.03 To ensure that all the works carried out under the scheme fully comply with the technical
specifications drawings established codes/standards and sound engineering practices.
2.04 To assure R&B and GOG for the quality of works being executed comply the quality norms and
standards laid down in contract specifications.
2.05 To provide technical audit and advisory services for the works.
2.06 Primarily responsibility of day to day supervision of works will be that of R & BD engineers and
consultant’s role shall be of Quality Assurance and Technical Audit and Carrying out safety audit
through a qualified and experienced Road & Building Safety Auditor as per NBC and IS
guidelines, Tender Specification and submission of report with cost effective measures and its
3.0 SCOPE OF SERVICES
3.01 Estimated level of services :
R & B has assessed the expertise required for carrying out the assignment as follows
Specialist / Position & Numbers (Key Positions whose Person months for package
CV will be evaluated) (Estimated)
24Months (10 days per Month) or
1 Team Leader extended time limit of work whichever is
24Months or extended time limit of work
2 Quality Control Engineer whichever is later
24Months or extended time limit of work
3 Site Engineer whichever is later
1 Office hire charges 24Months or extended time limit of work
2 Stationary and printing charges 24Months or extended time limit of work
3 Computer and Laptop charges 24Months or extended time limit of work
4 Local transportation charges for Hiring Vehicle. 24Months or extended time limit of work
TEAM COMPISITION AND STAFF QUALIFICATIONS
3.01.1 An experienced and qualified senior engineer with min. 10 Years of relevant experience, in the
management of Buildins, procurement, quality control. He will have degree in Civil Engineering
and preferably master’s degree. He will be the Team Leader.
3.01.2 An experienced and qualified 01 No. Quality Control with min 5 years of relevant experience, in
the management of building, procurement, quality control. He will have degree in Civil
3.01.3 01 No. of Site Engineers with minimum experience of 5 years in field of supervision / survey /
quality of large civil works/projects to assist technical works or supervision work of quality. They
will have degree or diploma in civil engineering.
3.02 The consultants shall familiarize himself, with the help of sample surveys, visits and inspections in
the field and by examination initially of one set of documents such as detailed estimates, contract
documents, including specifications, interim certificates, quality control test results and other
relevant documents as per 3.04. All line and levels shall be checked & to be done in consultants
3.03 The consultant will examine that the description, procedure and quality of works accurately
reflects conditions in the field; work progress monitoring as per schedule-C of original work and
field supervision procedures have been followed correctly; site journals, reports of site meetings,
and other documents are maintained in accordance with the Procedures acceptable to R & B.
3.04 Assist and guide the R & B staff in interpretation of the technical specification, etc. as and when
required. Also consultant has to assured the work quality as per tender specification and qty. as per
3.05 Review contractor’s detailed work program, suitability of contractor’s key personals,
constructions methods and test results of construction materials and workmanship and suggest
necessary action and rectifications if required on these activities.
3.06 Assist R & B in implementation of quality control measures to ensure quality of work, and also in
approval of field testing laboratories in respect of facilities, adequacy, arrangements, equipment’s
and staff as per contract document.
3.07 Review the construction methods proposed by the contractor for carrying out the works to ensure
that these are satisfactory with particular reference to the technical requirements, the Project
Implementation Schedule and environmental aspects, as well as safety of the works, property,
personnel and the general publics.
3.08 Review the tests Results/ certificates of all construction materials and the sources for assessing
their suitability in works. All field experiments shall be done in witness of consultant. The
consultant shall undertake random sample checks independently for quality control using
contractors / GERI / Polytechnic / Engineering Colleges / approved private laboratory and
recommended solutions for improving road and building quality to meet the specifications.
Consultant shall also collect independently core samples as per IS 516 (Methods of Tests for
Strength of Concrete) and IS 456 (Plain and Reinforced Concrete - Code of Practice) and NBC
guidelines and test them using Contractor’s core cutting equipment.
3.10 Develop standard form and procedures to ensure a proper quality Control System to be
implemented for materials and workmanship.
3.12 Assist the R & BD on technical supervision of the works to ensure the quality and in conformity
with the standards and specifications prescribed in the contract and review the frequency of quality
3.13 Assist R & BD during inspection about the contractor’s equipment/machinery employed for
Building construction works so as to determine their suitability for work at site. Assistance shall
also be provided during periodic inspection for machines / laboratory equipment. Also review the
suitability of source of materials and their quality on the basis of inspection, laboratory equipment
certifications, test results, manufacturers certificate etc.
3.14 If the consultant considers any items of work substandard or unacceptable, he will inform the
contractor as well as R & BD of any rectification required in writing, providing full justification
thereof with all necessary supporting data.
3.15 Inspect the works on substantial completion before take over all indicate to the contractor / R &
BD any rectification required and any outstanding work to be carried by the contractor during the
Defects Liability Period.
3.16 Assist the R & BD in monitoring progress of the works at regular intervals through modern aids
such as computer aided project management techniques. Also review and assist R&B staff in
effective implementation of Quality control / Assurance system.
3.17 Prepare monthly reports and final audit report ( in Four copies) fully describing the progress of the
works and the assistance given by the consultant during the month under review, indicating also
the problem areas and actions required to overcome them by the relevant authority. Monthly
progress report shall consist the progress of work done in detail, planning of the work for the next
month, quality observed during MPR month with photographs, profiles for line level and
highlight the problem areas and actions taken by consultant against the problem areas, physical,
financial and timely progress in percentage.
3.18 Recommendations regarding the methods and procedures for the evaluation and the system for
monitoring of the conditions of the Building and road after the project completion.
3.20 Consultant shall recommend to R & BD to grant the permission to start the work on the basis of
quality check of materials on plant site, Plant and machinery, laboratory facility, weigh bridge and
any other requirements related to tender.
3.21 More over for complete work OR completed items check for building, RCC work, plaster,
masonry work and all other finishing work shall be performed as per IS code Guidelines. Also
inspect the work on completion / substantial completion before taking over in order to identify the
balance work and rectification of defects to be carried out by contractor during defect liability
period. After completion of each and every item, the report shall be submitted to concern officer
for verification and after the grant of permission, the next item shall only be started at site.
3.22 Also other item like concrete work, foot path, side drains, gutter, structure works etc. shall be
checked in accordance with standard specification and design and as per tender provisions.
3.23 Each quality aspects shall be reported building wise and item wise as summary report periodically
to R & BD. Also consultant shall furnish the summary of QC test results conducted in each
activity of work and furnish a QC certificate (regarding Quality of material and workmanship and
performance) along with contractors each invoice (RA BILLS)
3.24 Final report shall have concluding remarks (Building wise – Item wise) about overall quality of
building also consultant shall recommend the methods and procedures for evaluation and system
for monitoring the condition of road.
3.25 The consultant shall conduct technical audit of work. In addition to regular audit activities of
works the auditor shall also examine the following:
(A) The description, procedure, and quality to works executed accurately reflect the requirements
as per prevailing site condition. (B) R & BD site staff has followed correctly or not the system for
monitoring of work progress and supervision of works. (C) System followed for maintenance and
documentation of site instruction book, reports, minute of meetings and other documents are being
followed correctly and in accordance with the procedures acceptable to R & BD or not.
3.27 Consultant Responsibility for Building Works.
To verify the line out of road in accordance with approved drawing and site situation and to
suggest modifications wherever necessary as per technical requirement.
The consultant shall check and approve the design and procedure of staging and form work for
building work and also check reinforcement, form work and concrete to be casted first time in
each component of the building work and guide the R&B.D. Staff for good workmanship and
quality and record to be maintained.
The consultants shall verify the actual foundation level along with strata and approve the same as
well as also verify and approve the tilt and shift in well sinking / pile foundation and suggests
modifications or remedies when it is beyond permissible limits. The consultant shall verify the
records of well sinking / pile to be maintained.
The consultants shall witness first time pre stressing / post stressing of girders / slab in pre-
stressed superstructure and also check and verify the results of pre-stressing.
The testing of all material & C.C. cubes etc. shall be tested as per norms & as shown for road
3.28 To check measurements and keep measurement records as per direction of R&B.
3.29 To assist R&B to order the removal improper / substandard work.
3.30 To assist R&B in co-ordination work with different agencies and hold meetings for proper and
timely implementation of the works.
3.31 To carry out periodic review of contractor's resources vis-a-vis work program.
3.32 To check building inventory item wise incorporating all basic data and details of road;
3.33 To carryout existing building condition survey and listing all defects on Concrete surfacing.
3.34 To carryout a Safety Audit of the project reach through a qualified & experienced Building Safety
Auditor as per manual on building Safety Audit. Review and maintain the work zone as per IS
code and tender specifications for concrete during construction work. After construction is
completed, review and verify building safety criteria at site, certify the same and submit building
safety audit report survey.
3.35 Whenever required provide remedial designs.
3.36 Any other assignments given by the 'Employer'. The scope shall however remain restricted to such
services as necessary for fulfilling the stipulated obligations of the Engineer.
3.37 The executive engineer has right to use consultant services during the assigned period for the
other works under the jurisdiction of Surat (R&B) Division No.1, Surat for which no extra
remuneration will be paid.
OFFICE ACCOMODATION
The office of consultant’s team leader shall be maintained at Surat having approximate area of
to 60 Smt. The consultant shall make available suitable office accommodation for team leaders &
associated staff including office furniture, office equipment, and other relevant requirements as
per necessity of a T.L. and associated staff. It shall be maintained & managed by consultant at his
own cost. The consultant shall bear the cost of electricity telephone bill and water consumer etc. at
office accommodation including all taxes.
It is expected that the consultant will set up field office for construction engineer, A.R.E. &
Lab Technician as indicated below. Office accommodation space at District Place as per client
discretion including, laptop, computer with necessary networking system and furniture shall be
procured by consultant at his own cost. The Team leader is accepted to attend review meeting at
Gandhinagar and Surat once in a week or as required.
Sr. NOS. OF PROPOSED LOCATION
POSITION / PERSON
No. PERSON OF OFFICES
1 Team Leader 1 Surat
2 Quality Control Engineer 1 Site
3 Site Engineer 1 Site
4.01 Laboratories of CONTRACTOR / GERI / Polytechnic / Engineering Collages SVNIT / MSU
recognized Pvt. Labs shall be used. Also according to contract conditions the contractor shall
provided a fully equipped field testing laboratory. The consultant will have full access to witness /
supervise the tests in contractor’s laboratories during contract implementation. The testing results
shall be signed by consultant, contractor and departmental engineer.
4.02 Contractor shall make available free of cost core cutting machine in working order along with
operator and fuel at each site of work core sample is contempt.
4.03 At Laboratories of GERI / Polytechnic / Engineering colleges / R & B GOG recognized NABL
labs shall be used. All the day to day testing shall be carried out at contractor laboratory and
another test carried out as independent laboratory. Tests should be carried out as per prevailing
rules and relevant IRC / IS codes. And frequency of test given in MoRT&H specification
5thRevision. Tests on site in presence of representatives of consultant, contractor and same shall be
reported to authority engineer / representatives of authority engineer. The sample taken on the site
for sending above laboratories should be done in the in presence of Team leader, contractor and
same shall be reported to authority engineer / representatives of authority engineer
6.01 Consultancy services are required for a period of 24Months or original work extended time limit
of work whichever is later and will start on issuing work order
6.02 During monsoon from 01/07 to 30/09 (July to September) the staff shall be curtailed to
requirements of site or as directed by engineer in charge.
7.0 REPORTING REQUIREMENTS
7.01 Reports required to be submitted in Four copies (on CD/USB/Email and typed – hard copy) to R
& B include the following.
• Monthly reports on the activities progress and major issues and the observations by the Field
Engineer.(as per 3.17)
• Quarterly report covering summary of progress and quality checks (item wise) with remedial
measures and penalty measures.
• Final audit report containing building and road detailed report of quality and other relevant information.
• Building and road quality – certificate covering overall view of quality and all items with contractors each
R.A. bill and Final bill.
• Safety audit through a qualified and experienced Building and Road Safety Auditor as per
NBC / IS code and IRC / MORTH guidelines and submission of report with cost effective
measures and its estimate
• Code guidelines and submission of report with cost effective measures and its estimate
The Proposed schedules for submission of various reports are as follows.
No. Report Time of Submission
Quality Assurance Manual for the entire project
covering type and nature of QC tests to be conducted, Within 15 days from
acceptance criteria, frequency of tests, Standard commencement of services.
observation sheets and documentation.
Safety audit through a qualified and experienced
Building / Road Safety Auditor as per IS Code/ IRC / Within 15 days from
MORTH / NBC guidelines and submission of report commencement of services.
with cost effective measures and its estimate.
Monthly Reports on the activities in progress and
For every month by 20th date
3 major issues and the observations of the consultant’s
in following month.
Quarterly reports covering summary of progress and
By the end of every quarter of
quality checks (Activity wise) results of
4 assignment within 20 days
audit notes including remedial measures if suggested
after the expiry of quarter
and non conformance reports and their disposal.
Final completion report including status of audit notes,
Within one month after
NCR and its disposal and status of Quality control
5 completion of consultancy
Tests conducted along with required frequency and
results of QC tests.
Within one month after
Certificate regarding Quality of work executed for each
6 completion of work and with
activity of work.
Recommendations regarding methods and procedures Within one month after
7 for evaluation and the system for monitoring the completion of consultancy
condition of concrete after completion. assignment
Before starting of execution of
8 Design drawings
particular activity.
Note : Reports shall be submitted month wise individually.
DATA AND ASSISTANCE TO BE PROVIDED BY THE CLIENT
8.01 The following will be provided by R & BD:
• Copies of network maps of roads.
• Copies of estimated and contract agreements, work orders and tenders between R&B and contractors.
• Access to all other necessary data and facilitation of consultations required for the performance of the
consultant’s duties.
9.0 CONSULTANT’S RESPONSIBILITY
In addition to what is specified under the scope of services the consultant shall be responsible for –
9.01 The consultant will be responsible for providing all other necessary facilities and logistical support
for him/her self and supporting staff, including office and residential accommodation,
transportation, office equipment, communications, utilities, office supplies, and other support
requirements. The consultant shall also purchase/hire different types of vehicles as per need.
9.02 For the entire work consultant shall have to purchase 3 nos. of computer (P IV type, 40 GB HDD,
256 Ram, with CD Writer and CD ROM, 1.44 Floppy Drive, Pen Drive etc.) along with laser
printers of known brand (10-12 ppm, B/w, A-4).
9.03 Consultant shall also purchase necessary office furniture at the office of regional team leader, and
team leaders and at District Places for staff.
9.04 Consultant shall have to inform & submit register of activities carried out on site in pursuance of
9.05 To provide adequate staff with required tools, plants& equipment needed & convenience to field
staff perform their duties efficiently and to submit presence register regularly to engineer-in-
9.06 Offices / staff accommodation to be arranged & all related cost will be borned by consultant.
9.07 Office supplies communication, utilities and other supporting requirement.
9.08 To carry out every type of measure for qualities & technical audit and thus assure the client for
quality of the work as specified and reporting to be done to concerned Executive Engineer /
Superintending Engineer.
9.09 Consultant shall be totally responsible for the quality of the work. He shall be held responsible for
any type of defects or adverse query in the respect of quality of work noticed in future. He will be
liable for legal action for these defects or adverse query.
9.10 Consultant’s services include consultancy, supervision, Project supervision service like third part
inspection and quality assurance and rectification of works with methodology of R & B
department or as directed by concern Engineer-in-charge / Superintending Engineer.
9.11 The material collected at site of works shall be cross checked by consultant, if required to satisfy
the quality of material as per prevailing norms of Roads & Buildings Department in the presence
of contractor. The samples of Materials shall be sealed and sent to Government approved
laboratory for tests. The payment of additional checks shall be borned by the Roads & Buildings
9.12 If any rectification in work is asked to the contractor, then consultant have to get the work rectified
and certificate regarding rectification shall be produced to Roads & Buildings Department before
payment of R.A. bill to contractor. The consultant will be totally held responsible for satisfactory
rectification work.
9.13 Consultant shall provided quality assurance certificate with every running bill of the main work, as
specified / or ask by Engineer – in – charge. Final quality assurance certificate shall also be
provided with final bill of main work.
9.14 Consultant shall check and measure all measurements on site and sign on respective measurement
sheet like Request For Inspection (RFI) in EPC work/ measurement book given by R&B
9.15 Consultant shall assist by visiting site the above work during defect liability period in each quarter
and report for condition / damages occurred of building shall be reported with all colour
photographs / necessary documents unit wise / Strip Plan to authority engineer with rectification
treatment. Joint visit with contractor shall also be planned by authority if required. The decision of
Authority Engineer will be final in case of any discrepancy or doubt.
9.16 Material consumption certificate and testing schedule. as per frequency instructed by the
engineer in charge to be maintained by TPI. No additional cost will be paid separately.
10.0 CONTRACTUAL ARRANGEMENT
10.01 The consultant’s contract will be with R & B D and will be Consultancy services contracts.
11.0 PAYMENT SCHEDULE
11.01 The consultancy fee shall be paid for in Indian Rupees only.
11.02 The running bills shall be claimed as percentage of running Bill of work done limited to tender
amount of TPI/Tender.
➢ The consultancy running bills shall be paid simultaneously with payment of R.A. bills of
Contractor from time to time or as per grant availability.
➢ Income tax / service tax and any other taxes arise from time to time shall be deducted from
➢ Advance payment shall not be made.
➢ Final payment shall be made only after the final report and final statement, have been
submitted by the consultants and approved as satisfactory by the client.
11.03 Consultant will have to submit the certificate from concern DEE’s showing satisfactory work is
carried out by consultant as per T.O.R with every bill and presence of consultant shall be got
registered from the departmental engineer.
The running bills shall be claimed as percentage of running Bill of work done limited to tender
amount of TPI/Tender.
11.04 Consultant will have to submit the certificate of attendance / presence of their staff from
concerned Dy. Executive Engineer with every running bill, otherwise payment will not be done.
Specifically the separate daily attendance of every staff members (duly signed by them) have to be
submitted with the running bill and payment will be made as per actual presence of the staff. The
attendance register of staff should be counter signed by concerned Deputy Executive Engineer or
Executive Engineer of R&B Department.
11.05 Payment shall be made on pro-rate basis as per the original work progress, limited to the tender
amount of this work.
Amount of Original work
R.A. Bill = X Tender amount of this work.
Total tender value of original work
*And Payment on man month whichever is least.
12.01 Penalty action for delay
In case of delay in completion of services, a penalty equal to 0.1% of the contract price per day
subject to a maximum 10 % of the contract value will be imposed and shall be recovered from
payments due/performance security. However in case of delay due to reasons beyond the control
of the consultant, suitable extension of time will be granted.
12.02 Consultant liability towards the client
Consultant shall be liable to indemnify the Client for any loss or damage accrued or likely to
accrue due to deficiency ion service rendered by him which shall include any or all cost and
expenses incurred by the Client in removing the deficiency in service including engaging any
other consultant.
12.03 Warning/Debarring
In addition to the penalty as mentioned in above para, warning may be issued to the erring
Consultant for minor deficiencies. In the case of major deficiencies causing adverse effect on
reputation of the Client, other penal action including debarring the consultant for one to three
years period may also be initiated.
12.04 The Authority expects all the key personnel specified in the proposal to be available during
implementation of the Agreement. The Authority will not consider any substitution of key
personnel except under compelling circumstances beyond the control of the consultant and the
concerned key personnel. Such substitution shall be limited to not more than two key personnel
subject to equally or better qualified and experienced personnel being provided to the satisfaction
of the Authority. Replacement of the team leader will not normally be considered and may lead to
disqualification of the applicant or termination of the agreement. Replacement of two key personal
shall be permitted subject to reduction equal to 3% (Three percent) of total Fee payment of
consultant after replacement. In case of second replacement, reduction in fee payment shall be 6%
(Six percent) thereafter.
13.0 PERFORMANCE SECURITY
The amount of Security Deposit shall be 10 % of estimated consultancy amount. Consultant shall
be required to submit 5% of Security at the time of agreement in the form of FDR/NSC pledged in
favour of Executive Engineer, Surat (R&B) Division No.1, Surat FDR of Nationalized /
Commercial Bank Remaining 5% will be recovered from R.A. Bills. The validity of NSC / FDR
shall cover entire duration of consultancy period plus 3 months. The NSC / FDR will be return
after satisfactory completion of the agreement duly recommended by concern Exe. Engineer and
remaining 5% shall be refunded after Defect liability period of original work.
Deputy Executive Engineer
Surat (R&B) Sub Division No.
Executive Engineer
Surat (R&B) Division No.1,
I. FORM OF CONTRACT
COMPLEX TIME-BASED ASSIGNMENTS
THIS CONTRACT (hereinafter called the “Contract”) is made on the day of the month of
2021 between, on the one hand, Government of Gujarat, Roads and Buildings Department
(hereinafter called the “Client”) and, on the other hand, under this Contract, namely
(hereinafter called the “Consultants”).
(a) The Clients has requested the Consultants to provide certain consulting services as defined in the
General Conditions attached to this Contract (hereinafter called the “Services”).
(b) the Consultants, having represented to the Client that they have the required professional skills,
personnel and technical resources, have agreed to provide the Services on the terms and conditions
set forth in this Contract; and
(c) the Client has received the fund from the Government towards the cost of the Services and intends
to apply to eligible payments under this Contract, it being understood (i) that payments will be
made only at the request of the consultant and, (ii) that such payments will be subject, in all
respects, to the terms and conditions of the agreement, and (iii) that no party other than the Client
shall derive any rights from the agreement proceeds.
NOW THEREFORE the parties hereto hereby agree as follows:
1. The following documents attached hereto shall be deemed to form an integral part of this Contract:
(a) The General Conditions of Contract (hereinafter called “GC”);
(b) The Special Conditions of Contract (hereinafter called “SC”);
2. The mutual rights and obligations of the Client and the Consultants shall be as set forth in the
Contract; in particular;
(a) The Consultants shall carry out the Services in accordance with the provisions of the
(b) The Client shall made payments to the Consultants in accordance with the provisions of
IN WITNESS WHEREOF, the Partivadoes here to have caused this Contract to be signed in their
respective names as of the day and year first above written.
FOR AND ON BEHALF OF
Government of Gujarat, Roads and Buildings Department
Executive Engineer
Authorized Representative
FOR AND ON BEHALF OF
Consultant’s Name
Authorized Signatory
ABSTRACT OF THE WORKS
Sr No of No. of Bridge
Name of District Length
Say Total (A) 1 -
Executive Engineer
Surat (R&B) Division No.1,
ABSTRACT OF THE WORKS
Name of Name of Work
No Rs. in Crore
Consultancy Service for Quality Assurance of Construction of Categary-E type 32 Units
Residential Quarters for the Judicial Officers at Nanpura, Surat.
Surat (R&B) Construction of Categary-E type 32 Units
1 Division No.1, Residential Quarters for the Judicial Officers at
Surat Nanpura, Surat.
Executive Engineer
Surat (R&B) Division No.1,
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Details About Tender(1)(1).pdf
General Conditions.pdf
SBD part 1_compressed.pdf
SBD Part 2.pdf
Special Conditions(1)(1).pdf
TPI Tender Document.pdf
special condition 2.pdf
Pledge letter (1).pdf
sch-B.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .