Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹5.6 Cr
EMD Value
₹5.6 L
Closing Date
3 Dec 2026, 5:30 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Er. Bijay Kumar Sethy,ACE,RRIC,Dhenkanal
O/o the Addl. Chief Engineer AT-MAHISAPAT,PO-MAHISAPAT,DIST-DHENKANAL
Earthwork,Concrete,Grading-II and III,RCC work.
2026_CEBMD_146581_3
ACERRICD-06/2026-27
Open Tender
Civil Works - Canal
Percentage
Baulpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹5.6 L
Yes
18 Nov 2026
18 Nov 2026
4 Dec 2026
18 Nov 2026
3 Dec 2026
18 Nov 2026
18 Nov 2026 - 24 Nov 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing shrub jungle including uprooting stumps and small bushes and trees below 1m girth on pre-measurement including cost of labour, machinaries required for the work & all taxes etc. complete as per the direction of the Engineer-in-charge. | 51,495 | Sqm. | 0.27 | ₹13,903.65 |
| 2 | Labour for Soiling road surface with soiling stones including conveying ,spreading of filler material and filling the interstices with moorum, watering and consolidation with PRR including all costs, conveyance, royalty, cess, hire and running charges of PRR etc. complete as per the direction of the Engineer-in-Charge. | 348.1 | cum | 2,273.4 | ₹7,91,370.54 |
| 3 | Excavation, loading, unloading & carriage by mechanical means of all kinds of soil including stoney earth, gravel & moorum etc. interspread with boulders up to 1/2 cum size with all lifts & de-lifts including including trimming of slopes & bed to design section & depositing the excavated materials away from the work site as per specification & as directed by the Engineer-In-Charge within an initial lead of 1 km from the place of excavation complete. | 4,663.2 | cum | 81.9 | ₹3,81,916.08 |
| 4 | Filling foundation and plinth with sand by mechanical/ manual means and laying in layers duly compacted including watering ramming with all leads, lifts and delifts including, royalties, T&P etc. and all cost incidental to the work complete as per specification and direction of the Engineer-in-Charge. | 489 | cum | 597.2 | ₹2,92,030.8 |
| 5 | Plain cement concrete of M15 grade using 20mm and down grade black hard granite crusher broken stone aggregates including hoisting and laying including cost, carriage, royalty of all materials and cess etc, complete as per direction of the Engineer-in-charge. | 489 | cum | 5,715.9 | ₹27,95,075.1 |
| 6 | R.C.C. work of M-20 grade using 20mm and down grade black hard granite crusher broken stone aggregates including hoisting and laying including cost, carriage, royalty of all materials and cess etc, complete as per direction of the Engineer-in-charge. | 1,450.9 | cum | 6,171.9 | ₹89,54,809.71 |
| 7 | Providing formwork for concrete with F1 finish for upstream faces of dam, spillway, glacis of barrages, unexposed surfaces of foundation, block joints etc.with steel shutters rigidly fixed and removal of forms and making good to the surfaces where necessary complete with all labour, materials, T&P and cess etc.complete as per direction of the Engineer-in-charge. | 900 | Sqm. | 923.7 | ₹8,31,330 |
| 8 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor as per the direction of the Engineer-in-Charge. | 11,647.8 | Sqm. | 250.7 | ₹29,20,103.46 |
| 9 | Supplying, providing and straightening the coiled or bent up MS/HYSD/TMT bars cutting, bending and placing the grills in position with ties and chairs, spacers and binding wire 18 to 20 gauge, lapping, splicing, welding the joints where ever necessary for R.C.C works as per approved design, drawing with all costs and conveyance, royalty of the reinforcement bars, binding wire, cess and all costs incidental to the work and as per specification & direction of the Engineer-in-charge. | 622.28 | Qntl | 9,553.9 | ₹59,45,200.89 |
| 10 | Supplying, Providing and laying moorum in sub-base in layers not exceeding 100mm watering and compacting with PRR including cost and conveyance, royalty & all taxes of sub base materials as per direction of the Engineer-In-Charge. | 9,338 | cum | 1,322 | ₹1,23,44,836 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.37 MB
correctedrbccoverI.pdf
Tender Documents • 2.74 MB
BOQ_621910.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .