Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹2.6 Cr
EMD Value
₹5.2 L
Closing Date
30 Nov 2026, 1:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Revenue
ELECT.G
17 conditions · 5 needing a document upload
Financial Eligibility Criteria: (Ref: RB letter No. 2022/CE- I/CT/GCC2022/POLICY : Advance Correction Slip No.-1 dt 14.07.2022) The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The intending tenderers should possess a valid electrical contractor license at the time of opening of tender, issued by any state government & same should be submitted along with tender documents by all bidders including working contractors of this unit otherwise offer shall be summarily rejected....... IT SHOULD BE NOTED BY THE TENDERER THAT ELECTRICAL LICENSE UNDER RENEWAL AT THE TIME OF TENDER OPENING WILL NOT BE CONSIDERED AND OFFER WILL BE SUMMARILY REJECTED. IT IS THE RESPONSIBILITY OF TENDERER TO UPLOAD VALID ELECTRICAL CONTRACTOR LICENSE ON THE DATE OF TENDER OPENING.
All requisite documents mentioned in clause 3.7 of tender document attached pertaining to constitution of firm/concern. (As applicable).
47 conditions · 4 needing a document upload
The rate to be quoted by tenderer shall be inclusive of all state/central taxes including GST. THE TENDERER SHOULD UPLOAD VALID GST REGISTRATION CERTIFICATE ALONG WITH THE OFFER.
The tender shall comply with General Condition of contract (GCC),2022 of Indian Railways (file attached). and its latest amendment, if any. The tenderer shall submit the offer after duly satisfying himself/herself with the GCC,2022 in general.
Tenderers are required to upload the Bank details as per Annexure-XII (Real Time Gross Saving (RTGS)/National Electronic Fund Transfer (NEFT) Model Mandate Form)of tender document.
Tenderers are required to upload requisite details as per Annexure-VIIB (DETAILS OF CONTRACTUAL PAYMENT RECEIVED IN LAST THREE FINANCIAL YEARS AND CURRENT FINANCIAL YEAR) without which the offer is liable to be rejected.
Tenderers are compulsorily required to upload Affidavit as per Annexure-XXIV along with tender document, without which the offer will be considered incomplete and will be rejected summarily.
All requisite documents/credentials mentioned in clause 3.5 of tender document attached pertaining to his/their technical and financial eligibility. (As applicable).
All requisite documents mentioned in clause 3.7 of tender document attached pertaining to constitution of firm/concern. (As applicable).
The tender includes the design, supply, fixing, testing and commissioning of LT Panels/Front operated double door type weather proof LT Panels/Feeder Pillars/LT Distribution Boards conforming to IS/IEC61439-1: 2020, IS/IEC 61439-2: 2020 or the latest applicable edition/amendment in force as specified in the NIT Schedule. Contractors are advised to carefully examine and familiarize themselves with the relevant provisions of the applicable IS/IEC standards, codes and specifications before participating in the tender.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Tender involves rewiring of mainly occupied staff quarters. Therefore, availability of quarters for re-wiring will be limited in numbers and in gradual manner. Contractor cannot demand availability of all staff quarters (proportional to tendered qty) simultaneously and cannot claim any type of relaxation on this account.
The plastering work after cutting of grooves shall be finished properly in the level of original wall with painting/white wash to the satisfaction of Railways.
The contractor has to submit drawing/plan showing route diagram to consignee for signature of concerned SSEs of other departments. It required geological survey to be conducted at his own cost to avoid damage of any other cable/Pipe etc.
No post tender correspondence for submission of additional documents shall be entertained after opening of the Technical & Commercial offers. Even suo-moto post tender letters of the tenderer/s shall be treated as Null & Void.
The rate to be quoted by tenderer shall be inclusive of all state/central taxes including GST. tenderer shall submit GST certificate along with the offer.
This tender complies with Public Procurement Policy (Make in India) Order 2017, dated 15/06/2017, issued by Department of Industrial Promotion and Policy, Ministry of Commerce, circulated vide Railway Board letter no. 2015/RS(G)/779/5 dated 03/08/2017 and 27/12/2017.
IF ANY DISCREPANCY IS FOUND IN THE TENDER DOCUMENT, NAMELY SOR ITEM DESCRIPTION, SPECIAL TENDER CONDITION ETC., CLARIFICATION CAN BE SOUGHT FROM THE OFFICE OF SRDEE/G/DLI, DRM OFFICE, STATE ENTRY ROAD, NEW DELHI.
This tender complies with Railway Board instructions for Startups (recognized by Department of Industrial Policy and Promotion, Ministry of Commerce and Industry) for exemption from payment of Bid Security as detailed in GCC 2022 as amended from time to time. Such Startup firms may note that no other exemption is applicable to them in this particular tender.
On account payment, contractor shall submitted indemnity bond with validity up to the completion/extended period in the prescribed format (please refer Annexure-XXVIII) at the contractor's cost, vesting the ownership of such material with the railways.
This tender shall also complies with "Indian Railways Standard General Conditions of Contract, April 2022 (Advance Correction Slip No. 11)" vide Railway Board letter No. 2022/CE-I/CT/GCC- 2022/POLICY/Pt.I (E-3320424), dated:13.03.2026 (attached)
All disputes or differences of any kind whatsoever arising out of or in connection with this contract, whether during its execution or after completion, termination, or breach thereof, shall be subject to the exclusive jurisdiction of the competent courts at New Delhi only.
The issues not covered under the tender document shall be governed by General conditions of Contract (GCC) 2022 or its latest amendments if any during entire period of contract. If any contradiction in Tender Document and GCC is observed then GCC shall prevail.
Before energization /commissioning, the contractor shall carry out all pre-commissioning tests (like, Continuity resistance of conductors, Insulation resistance test, Polarity test, Verification of automatic disconnection of supply (ADS), Phase sequence test, Functional tests, Voltage drop verification, Earth electrode resistance test, Earth Continuity test, Load test, Verification of additional protection (RCDs/RCCBs/RCBOs) etc.) and submit the corresponding test reports as specified in the Chapter 16 (Verification of Installation) of CPWD General Specifications for Electrical Works, Part-I (Internal), 2023 or latest. The rates quoted in the NIT schedule are inclusive of all the afore- mentioned tests and no additional payment will be made and contractor shall submit the required test report for the same.
All test instruments used for carrying out the pre-commissioning tests shall be of reputed make (like Megger, Fluke etc. ) and shall be properly calibrated, with valid calibration certificates available for verification whenever required.
This tender shall also complies with "Indian Railways Standard General Conditions of Contract, April 2022 (Advance Correction Slip No. 12)" vide Railway Board letter No. 2022/CE-I/CT/GCC- 2022/POLICY (3389822), dated: 12.08.2026(attached)
Contractor has to depute sufficient number of efficient manpower to carry out the work in parallel at different sites under scope of instant tender. No any excuses regarding non- availability of material and manpower for carrying out the work concurrently/parallelly at various sites shall be admissible.
The Contractor shall comply with all applicable provisions of IS 732:2019 (Code of Practice for Electrical Wiring Installations) for every relevant item mentioned in the NIT Schedule.
The NIT Schedule includes the supply, fixing of RCCBs and RCBOs of the specified ratings, voltage independent Type A (sensitive to alternating current and DC component), conforming to IS 12640 (Part 1 or 2 as mentioned) and applicable IS/IEC standards. Bidders shall carefully examine and comply with all relevant provisions, codes, standards and technical specifications before participating in the tender.
The DOC of 12 months is because of the limited availability of quarters at any given time. But contractor has to start the procurement and the work immediately after issuance of LOA and he/she shall maintain uniform progress of the work over DOC period of 12 months.
Electrical Improvement of Staff Amenities including Rewiring of Railway Quarters and Allied Electrical Works in the jurisdiction of SSE/PS/PHG.
119-SRDEE-G-DLI-2026-27~NR
119-SRDEE-G-DLI-2026-27
Open
Works - General
12 Months
Delhi
₹0
₹5.2 L
6 Nov 2026
6 Nov 2026
16 Nov 2026
117 items across 2 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 2,58,89,940 | ||
| — | 1648.00 | — | — | ||
| Wiring for light point/ fan point/ exhaust fan point/ call bell point with1.5 sq.mm FRLSH/HFFR PVC insulated copper conductor single core cable in surface/recessed medium class PVC conduit, with modular switch, modular plate, suitable GI box and earthing the point with 1.5 sq.mm FRLS PVC insulated copper conductor single core cable etc. as required conforming to CPWD General Specifications for Electrical Works Part-I Internal - 2023 and CPWD DSR (E&M) 2025 & IS 732:2019(reviewed 2024 or latest) & as per explanatory note. Group A | — | — | — | 11,66,784 | |
| — | 1860.00 | — | — | ||
| Wiring for light point/ fan point/ exhaust fan point/ call bell point with1.5 sq.mm FRLSH/HFFR PVC insulated copper conductor single core cable in surface/recessed medium class PVC conduit, with modular switch, modular plate, suitable GI box and earthing the point with 1.5 sq.mm FRLS PVC insulated copper conductor single core cable etc. as required conforming to CPWD General Specifications for Electrical Works Part-I Internal - 2023 and CPWD DSR (E&M) 2025 & IS 732:2019(reviewed 2024 or latest) & as per explanatory note. Group B | — | — | — | 14,39,640 | |
| — | 19060.00 | — | — | ||
| Supply and recessing/fixing of medium-class, FRLS PVC conduit pipe of 25 mm size conforming to IS 9537 Part-III 1983/IEC 60614-2-2 (or Latest version) with accessories junction box, bends etc. including cutting the wall, making chase, plastering/clamping etc. as per site requirement & as per explanatory Note . | — | — | — | 35,26,100 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC-2022-ACS10_merged.pdf
ATTACHMENT
GCCAdvanceCorrectionSlipNo.11.pdf
ATTACHMENT
TECHSPEC-I.pdf
ATTACHMENT
TECHSPEC-II.pdf
ATTACHMENT
Chapter-16CPWDGeneralSpecforElectWorkPart-IInternal2023.pdf
ATTACHMENT
GCC-2022-ACS-12compressed.pdf
ATTACHMENT
TenderDocument.pdf
ATTACHMENT
SpecialConditionsofContract.pdf
ATTACHMENT
ExplanatoryNote.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .