| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.0 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹3.0 L+₹5,222.39 (1.76%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹3.0 L+₹7,447.85 (2.51%)Admitted-Finance 36 1 A MASHID HATI ROAD MADHUMURALI BARASAT NORTH 24 PGS KOL 124 | BARASAT | NORTH 24 PARGANAS | WEST BENGAL | 700124 | L3 | Admitted-Finance |
Tender Value
₹3.0 L
EMD Value
₹6,000
Closing Date
17 Aug 2026, 1:00 pmClosed
EE/IGWTP
IGWTP,MANIRAMPUR,BARRACKPORE
REBUILDING OF THE SUBSIDED FLOOR WITH CRACKED WALL AND ROOF WITH DISPLACE DOORS WINDOWS OF THE LABOUR HUT QTR NO-C1 45C AT IGWTP
2026_KMC_1036106_1
KMC/IGWTP/030/26-27, DT-27/07/2026
Open Tender
CIVIL WORKS
Percentage
30 days
IGWTP, MANIRAMPUR, BARRACKPORE
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹6,000
IGWTP,MANIRAMPUR,BARRACKPORE
9 Oct 2026
4 Aug 2026
19 Aug 2026
4 Aug 2026
17 Aug 2026
10 Aug 2026
8 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . C. REPAIR & REHABILITATION FOR WATERPROOFING 1. Taking out old damaged tarfelt from the roof, parapet etc. preparing the roof surfaces by removing all spoils, blisters,moss etc. from the working site and disposal of the same beyond the compound and cleaning the site in all respect as per direction of Engineer-in-Charge. All floor | 90 | SQUARE METER | 12 | ₹1,080 |
| 2 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 8. Taking out carefully G.C.I. or C.I. or asbestos sheets (including ridges etc.) from roof or wall after unscrewing bolts, nuts, screws etc.and stacking the material at site as directed. (Payment to be made on measurement of portion of roof or wall removed.) | 25 | SQUARE METER | 41 | ₹1,025 |
| 3 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 10. Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. | 75 | SQUARE METER | 19 | ₹1,425 |
| 4 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC. 1. Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. (a) In ground floor including roof. | 4.9 | CUBIC METER | 447 | ₹2,190.3 |
| 5 | BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . A. ROOFING & SHEETWALLING 7. Asbestos corrugated (Trafford or similar approved quality) sheet (6 mm thick) work (excluding the supporting framework) fitted and fixed with 9.5mm. dia. J or L hook-bolt and nuts, limpet and bitumen washers and putty with 150 mm end lap & one corrugation minimum side lap complete. (Payment should be made on area of finished work) (a) In Roof | 25 | SQUARE METER | 471 | ₹11,775 |
| 6 | BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . B. WATERPROOF TREATMENT 2. Supplying and laying standard four course bituminous water proofing treatment as per specification laid down in I.S. 1346 - 1991 to be finished with pea size gravel including necessary preparatory works such as shaping mouth of outlets, cutting as and where necessary and refilling with sand and Cement mortar (4:1) or Cement Concrete (1:2:4) with graded stone chips before undertaking the treatment including cutting grooves in parapet and inserting edge of felt and mendinggood damage complete in all respect as per direction of Engineer - in - Charge including cost of all materials and labours and incidental charges but excluding the cost of Cement Mortar or concrete required for levelling and grading. (In sloped roof Course sand of approved varieties is to be used in place of Pea size gravels as fourth and final course.) i) 1st and 3rd Course with bonding materials of hot applied industrial blown type bitumen of grade 85/25 or 90/15conforming to I.S.702 - 1988 @ 12Kg/10Sqm on each layer. ii) 2nd course with Hessian base self finished bitumen type- 3 Gr.-I conforming to I.S. 1322-1993 (weighing 23kg/10Sqm gross with bitumen content 12.10kg/10Sqm ) tested under the provision of I.S. 13826 - 1993 part VII iii) 4th course with washed and clean pea sized gravel or grit @ 0.006 cum/Sqm. B. Over Sloped Roof. | 50 | SQUARE METER | 318 | ₹15,900 |
| 7 | BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 8. M.S. works in brackets made from flats, angles, tees etc. to sizes specialy bent, twisted, forged; making holes drilled and fitted to rafter of trusses with necessary bolts, nuts, washer or screws etc. (length of straight not less than 230 mm) (To be used for repair works only) | 0.95 | QUINTAL | 7,335 | ₹6,968.25 |
| 8 | BUILDING WORKS (G) WOOD AND PVC WORKS A. DOOR WINDOW FRAME 1. Wood work in door and window frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame exluding cost of concrete, Iron Butt Hinges and M.S clamps. (The quantum should be correted upto three decimals). (c) Sal : Siliguri Note: Extra for Lifting Charges for each additional floor, i) Rs. 200/- per Cu.m (upto 4th floor) ii) Rs.250/-(above 4th floor) 1A. Extra rate for Curved wood works in doors and window frame fitted and fixed complete over corresponding Items of Item No. 1. (In measuring such average length and average breadth to be taken into consideration, Thickness remaining constant). (The quantum should be corrected upto three decimals) | 0.39 | CUBIC METER | 1,07,923.2 | ₹42,090.05 |
| 9 | BUILDING WORKS (G) WOOD AND PVC WORKS B. DOOR WINDOW SHUTTER 1. Panel shutters of door and window, as per design (each panel consisting of single plank without joint), including fitting and fixing the same in position but excluding the cost of hinge and other fittings.In ground floor. (In case of non-supply of single plank, penal rate of reduction of 20% will be made) (iv) 25mm thick shutters with 12mm thick panel of size 30 to 45 cm. (b) Sishu, Gamar, Champ,Badam,Bhola, Mogra, Hallak. Note: i) Lifting Charges for upper floors refer item H (2). (ii) In case of panel with Rly. Type batton the rates will be reduced by Rs.20.00 /Sq.m.) | 18.5 | SQUARE METER | 2,259 | ₹41,791.5 |
| 10 | BUILDING WORKS (G) WOOD AND PVC WORKS E. REPAIR WORKS 30.Labour for taking out door and window frame including shutter for repair orreplacement of different parts of the frame & refixing the same including mending good all damaes complete. (Concrete and brick work for mending damage will be paid separately)(a) Upto area 2.5 Sq.m | 20 | SQUARE METER | 119 | ₹2,380 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.23 MB
TECHBID030.pdf
Tender Documents • 1.30 MB
BOQ_2545278.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .