Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.0 LAccepted-AOC | L1 | Accepted-AOC Being first lowest | |
| 2 | L2₹12.6 L+₹58,906.86 (4.90%)Rejected-AOC | L2 | Rejected-AOC Being second lowest | |
| 3 | L3₹12.9 L+₹88,383.75 (7.35%)Rejected-AOC | L3 | Rejected-AOC Being third lowest | |
| 4 | L4₹13.0 L+₹94,613.74 (7.87%)Rejected-Finance | L4 | Rejected-Finance Being 4th lowest | |
| 5 | L5₹13.3 L+₹1.3 L (10.8%)Rejected-Finance | L5 | Rejected-Finance Being 5th lowest |
Tender Value
₹13.7 L
EMD Value
₹34,350
Closing Date
10 Jul 2024, 5:00 pmClosed
The Managing Director
Kerala State Warehousing Corporation, Head Office Ernakulam, P.B.No.1727, Warehousing Corporation Road, Kochi-682016
Construction of compound wall at State Warehouse Thrippunithura in Ernakulam District.
2024_KSWC_677782_1
KSWC/Constn/RM/SW/ Thripunithura/2024-25
Open Tender
Repair and Maintenance Works
Item Rate
90 days
State Warehouse Thripunithura
Please refer Tender documents
9 documents required · 9 mandatory
₹2,950
₹34,350
Yes
11 Sept 2024
27 Jun 2024
12 Jul 2024
27 Jun 2024
10 Jul 2024
27 Jun 2024
27 Jun 2024 - 10 Jul 2024
Amount
Compound wall & Gate
Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 500 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock/hard soil
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size
Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Random rubble masonry with hard stone in foundation and plinth up to plinth level with:<br>Cement mortar 1:6 (1 cement : 6 coarse sand)
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Solid block masonry using pre cast solid blocks ( Factory made) of size 30x20x20cm or nearest available size confirming to IS 2185 Part I of 1979 for super structure up to floor two level thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) including cost of all materials, conveyance, labour charge, scaffolding etc complete as required.
Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) after preparing the surface by using wirebrush or emery paper,all works including cost and conveyance of all materials,labour charges, scaffolding etc. complete as required.
Steel work in built up tubular (round, square or rectangular hollow tubes etc.-minimum thickness 2.00 mm) etc., including cutting, hoisting, fixing position and applying a priming coat of approved steel primer after preparing the surface by using wirebrush or emery paper, including welding and bolted with special shaped washers etc. complete.Hot finished welded type tubes.All works including cost and conveyance of all materials,labour charges, scaffolding etc. complete for 2 nos M.S.sliding Gate (both ways sliding)of size 7.00M X 1.80M as per the direction of Engineer-in-Charge..
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat after preparing the surface by using wirebrush or emery paper,all works including cost and conveyance of all materials,labour charges, scaffolding etc. complete as required. complete.On steel work
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Lettering with black Japan pint of approved brand and manufacture. All works including cost and conveyance of all materials,labour charges, scaffolding etc. complete as required.
MUHAMMED NAJEEB
SAMU P V
govind
QUBE CONSTRUCTION
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .