Tender Value
₹38.4 L
EMD Value
₹76,744
Closing Date
15 Jun 2026, 3:00 pm
CHIEF ENGINEER
NAGAR NIGAM BAREILLY
In ward 36, in Joharpur, from Pappu to Sajid, link street Naeem, street Gajendra Singh, from Chhatrapal to Omkar, from Mangalsen Sahu to Yadaram Sahu, from Baburam to Kailash Gupta, street Mohan Swaroop, from Prempal Sahu to Devidas Maurya, from Tota
2026_DOLBU_1153014_1
39/CE/CD/NNB/26-27 (41 To 60) Sr No 41 Tender List 73 Date-21.05.2026
Open Tender
Civil Works
180 days
BAREILLY
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,484
Bareillye-tender.com
₹76,744
25 May 2026
25 May 2026
15 Jun 2026
25 May 2026
15 Jun 2026
25 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1.01 | Dismantling of old damage brick work and stone work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M. (S.I.No.692) | 24.62 | CUM | 660 | ₹16,249.2 | BI01010001010000000000000515BI0100001117 |
| 1.02 | Dismantling of old damaged B.O.E. soling/ interlocking tiles and stacking of dismantlled materials as directed by E/I.within a distance of 60.00M.(Non Schedule Item No.3 | - | SQM | 12 | - | BI01010001010000000000000515BI0100001118 |
| 1.03 | Earth work in cutting or embankment in ordinary soil to be in 20 cm layers, including ,watering ,Dressing ,compacting ,ramming the soil to achive 95% proctor density ,and dressing the surface to be required levels and slope and also including 1.50m lift and 30 m lead . The earth from cutting to be used in making embankment or to be deposited as spoil banks within 30m distance as directed by the Engineer-in-charge. (Excluding Royalty) Analysis rate | 0.6 | CUM | 178 | ₹106.8 | BI01010001010000000000000515BI0100001119 |
| 1.04 | Excavation in foundation in ordinary soil foul requiring the use of special T&P such as pickaxe, subbles etc. (Loam, Clay or sand) including, lift upto 1.50 M and lead Upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30.0m from the foundation trencches. (Excluding Royalty)( S.I. No.251) | - | CUM | - | - | BI01010001010000000000000515BI0100001120 |
| 1.05 | Disposal of Debris upto 5 km including loading & unloadind lift 1.50mtr and lead up to 30.00 mtr | 0.8 | CUM | 183.5 | ₹146.8 | BI01010001010000000000000515BI0100001121 |
| 1.06 | Providing and layingConcrete with 4cm gauge brick ballast, fine sand of 1.25 fineness modulous and cement in prportion of 1:6:12 in foundation in under floor , including supply of all material labour and T&P etc rfequired of proper completetion of the work . | 0.2 | CUM | 3,705 | ₹737.3 | BI01010001010000000000000515BI0100001122 |
| 1.07 | First class B/w in 1:4 Cement C'sand mortor in F/P including supply of all meterial labour T&P etc required for proper completion of work. | 1 | CUM | 5,500 | ₹5,494.5 | BI01010001010000000000000515BI0100001123 |
| 1.08 | 12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimum thickness not less then 10 mm including all supply of meterial , Labour T&P etc required for proper completetion of the work. | 0.6 | SQM | 217 | ₹129.98 | BI01010001010000000000000515BI0100001124 |
| 1.09 | Providing laying C.C with 2cm gauge approved stone ballast, approved coarse sand and cement in praportion of 1:2:4 including supply of all materials, labour and T&P etc required for proper completetion of the work. | 26.77 | CUM | 7,833 | ₹2,09,689.41 | BI01010001010000000000000515BI0100001125 |
| 1.1 | RCC 1:1.50:3 with cement c'sand stone grit of 20 mm gauge in Slabs excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. | - | CUM | 8,881 | - | BI01010001010000000000000515BI0100001126 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 16.05 MB
BOQ_2159952.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid