| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.7 LAccepted-AOC | L1 | Accepted-AOC Submitted necessary documents |
Tender Value
Refer Docs
EMD Value
₹20,100
Closing Date
17 Feb 2021, 5:00 pmClosed
Assistant Executive Engineer
Assistant Executive Engineer, M.I.Subdivison, Chalakudy
Canal work
2021_Irrig_413823_1
08/Re-ET/AEE/MI-CKY/2020-21 dtd. 10/02/2021
Open Tender
Civil Works - Canal
Item Rate
180 days
Kuzhur
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹20,100
Yes
19 Jul 2021
10 Feb 2021
22 Feb 2021
10 Feb 2021
17 Feb 2021
10 Feb 2021
Amount
Maintenance of Vattakulam canal
15.3 : Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
2.28.1 : Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil etc.complete as per the direction and specification of deptl. officers at site
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soiletc.complete as per the direction and specification of deptl. officers at site
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.1.3 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)etc.complete as per the direction and specification of deptl. officers at site
5.22.4 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelHot rolled deformed bars etc.complete as per the direction and specification of deptl. officers at site
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.complete as per the direction and specification of deptl. officers at site
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)etc.complete as per the direction and specification of deptl. officers at site
4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)etc.complete as per the direction and specification of deptl. officers at site
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columnsetc.complete as per the direction and specification of deptl. officers at site
10.25.2 : Item Shifted to head 14 as item 14.74Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar worksetc.complete as per the direction and specification of deptl. officers at site
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)etc.complete as per the direction and specification of deptl. officers at site
50.13.1 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete as per the direction and specification of deptl. officers at site
od14551/2020_2021/IA : Supplying 200 mm dia PVC pipes with working pressure of 6 Kg /cm? with ISI specification including pipes for hydraulic pressure testing at laboratoryetc.complete as per the direction and specification of deptl. officers at site
od28109/2020_2021/IA : Laying and joining PVC pipes with required specials such as couplings, bends, tee, reducers, etc. with required quantity of cement solvent, including the cost for conveying to trenches, laying, laying, joining, testing, washing etc.etc.complete as per the direction and specification of deptl. officers at site
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.etc.complete as per the direction and specification of deptl. officers at site
Bidder Name
Anson Thomas
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_587943.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .