Loading…
Loading…
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
24 Jul 2026, 5:00 pm
Circle Officer
RURAL WORKS CIRCLE, SUNDARGARH
Refurbuising of Khatkurbahal PHC under AMA Hospita building (Phase-2) Scheme under DMF for the year 2025-26
2026_CERWI_135413_1
RWCCESNG-12 of 2026-27
National Competitive Bid
Civil Works - Buildings
365 days
Sundergarh
3 documents required · 3 mandatory
₹10,000
₹1.1 L
Yes
10 Jul 2026
10 Jul 2026
27 Jul 2026
10 Jul 2026
24 Jul 2026
10 Jul 2026
10 Jul 2026 - 23 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling and removing doors, windows and ventilators including removal of frame, hinges, fastening and stacking the same for reuse and removing the debris within 50m lead as per direction of Engineer-in-charge. | 120.65 | sqm | 465.1 | ₹56,114.32 |
| 2 | Dismantling and removing R.C.C. Chajja, Shelves, fins and parapet including stacking the useful materials for reuse and removing the debris within 50m lead as per direction of Engineer-in-charge. | 37.32 | sqm | 206.3 | ₹7,699.12 |
| 3 | Dismantling and removing 2.5 cm. thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead as per direction of Engineer-in-charge. | 414.61 | sqm | 132.6 | ₹54,977.29 |
| 4 | Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead as per direction of Engineer-in-charge. | 106.17 | sqm | 117.9 | ₹12,517.44 |
| 5 | Dismantling and removing old tiled wall including racking out joints 12mm deep and stacking the useful materials for reuse and removing the debris within 50m lead as per direction of Engineer-in-charge. | 326.4 | sqm | 76.6 | ₹25,002.24 |
| 6 | Dismantling and removing old tiled flooring including removing the base coarse and stacking the useful materials for reuse and removing the debris within 50m lead as per direction of Engineer-in-charge. | 162.87 | sqm | 147.4 | ₹24,007.04 |
| 7 | Removing cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead as per direction of Engineer-in-charge. | 1,414.14 | sqm | 58.9 | ₹83,292.85 |
| 8 | Dismantling brick or stone masonary in cement mortar upto 3.00m height including all costs complete. Stacking the useful materials for reuse and removing the debris 50 mtr lead as per direction of Engineer-in-charge. | 18.41 | cum | 1,646.6 | ₹30,313.91 |
| 9 | Scraping old paint with scrapers, sand papering and washing with soap water or soda including scaffolding charges up to 5mtr height as per direction of Engineer-in-charge. | 1,372.54 | sqm | 5.2 | ₹7,137.21 |
| 10 | 4cm thick grading concrete (1:2:4) on roof slab with 12mm & down graded size hard crusher broken granite chips on new work including cost of all materials, water-proofing compounds, T&P. required for the works complete as per the direction of Engineer-in-charge. | 414.61 | sqm | 905.4 | ₹3,75,387.89 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 4.32 MB
Tendernotice_1.pdf
PDF • 0.45 MB
BOQ_601018.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid