Tender ID
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹6.9 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹7.0 L+₹10,237.90 (1.47%)Admitted-Finance | L2 | Admitted-Finance |
Tender Value
₹8.2 L
EMD Value
₹16,381
Closing Date
23 Mar 2026, 6:00 pmClosed
SE DC JODHPUR
SE DC OPH JODHPUR
Construction of New 33 KV Sub Station at Ketu Hama Erection of 33 KV Line 4.5 Km SC with ACSR Dog conductor Erection of 11 KV Inter Connection 2.8 Km from 33 KV GSS Ketu Hama under AEN Sekhala on LRC 2025
2026_JdVVN_540728_1
TNDC 59
Open Tender
Electrical Works
Percentage
90 days
SEKHALA
AS PER SPECS
3 documents required · 3 mandatory
₹2,950
AO DC MD RISL
₹16,381
Yes
27 May 2026
20 Feb 2026
24 Mar 2026
20 Feb 2026
23 Mar 2026
20 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | PART 'A" Construction of New 33/11 KV Sub Station at Ketu Hama under O&M, Sub-Division Sekhala | - | - | - | - |
| 2 | Levelling of ground | - | - | - | - |
| 3 | Levelling of ground up to 30 cm.depth. with tractor and T&P required as per condition of ground including removal of rubbish plants from ground & marking of boundary with lime powder.(Including all lead & lifting) | 1,000 | Sq. Mtr. | 1.92 | ₹1,920 |
| 4 | Excavation of pit in ordinary rock which does not require blasting/murrad (In Jodhpur Discom) to erect various supports and stay sets including stacking of excavated muck from the edge of excavation/pit. | - | - | - | - |
| 5 | (A) Height of poles/R.S.Joist/M.S. Rail Size of pit | - | - | - | - |
| 6 | 8 Mtr/R.S.Joist/M.S. Rail 1.2mx0.6mx1.35 m deep | 30 | Pit | 307.18 | ₹9,215.4 |
| 7 | 9 Mtr/ 1.2mx0.6mx1.50 m deep | 10 | Pit | 325.74 | ₹3,257.4 |
| 8 | Earth work excavation and foundation of platfrom of transformers and brakers including dressing of sides and ramming of bottoms .Liftup to 1.5 Meter including taking out the excavated soil and depositing and refilling of jhiri, watering and ramming and disposal of surplus excavated soil as directed with in a lead of 50 Meter. | - | - | - | - |
| 9 | Hard soil mixed with boulders | 35.86 | CUM | 137.41 | ₹4,927.52 |
| 10 | Providing and laying cement concrete including compaction etc, complete using stone aggregate 40 mm nominal size (hand broken ) in foundation plinth excluding the cost of shuttering using 1 cement:5 sand:10 aggregate mix. | 4.33 | CUM | 3,020.42 | ₹13,078.42 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.59 MB
SPECSTNDC59.pdf
Tender Documents • 1.24 MB
NITTNDC59.pdf
Other Document • 0.57 MB
BOQ_963914.xls
BOQ • 0.42 MB
DTEXT.pdf
PDF • 0.40 MB
DATEEXTTNDC59.pdf
PDF • 0.46 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .