| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.9 LAccepted-AOC ABC OF VIJAYPUR SECTION UNDER EDD BAGESHWAR | L1 | Accepted-AOC Awarded | |
| 2 | L2₹2.9 L+₹1,057.52 (0.37%)Rejected-AOC SHEESHMAHAL KATHGODAM ALMORA | L2 | Rejected-AOC Rejected | |
| 3 | L3₹3.0 L+₹11,422.28 (3.95%)Rejected-AOC | L3 | Rejected-AOC Rejected |
Tender Value
Refer Docs
EMD Value
₹11,700
Closing Date
15 Mar 2023, 3:00 pmClosed
EE,EDD,Almora
EDD Almora, Laxmeshwar, Almora
Repair of electricity lines and transformers damaged in natural disaster in between 07.10.2022 to 10.10.2022 at Lamgara Section of EDSD 2nd, Almora
2023_UPCL9_54929_1
61/2022-23/EDD(A)
Open Tender
Electrical Works
Item Wise
365 days
Lamgara
As per tender document
2 documents required · 2 mandatory
₹295
EE,EDD,Almora
₹11,700
26 Sept 2023
14 Feb 2023
16 Mar 2023
14 Feb 2023
15 Mar 2023
20 Feb 2023
Amount
Supply of Top Channel Clamp SP23 with N&B
Supply of LT Shackle Insulator with N&B
Supply of LT Clamp for SP-21 with N&B
Supply of LT Clamp for SP-10 with N&B
Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km ST pole SP 23 (Galvenised)
Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km ST pole SP 21 (Galvenised)
Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km ST pole SP 10 (Galvenised)
Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km 11/0.4 KV 25 KVA New
Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km11/0.4 KV 63 KVA New
Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km Small materials
Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km ST pole SP 23 (Galvenised)
Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km ST pole SP 21 (Galvenised)
Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km ST pole SP 10 (Galvenised)
Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km 11/0.4 KV 25 KVA New (Upto 1 to 3 Km)
Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km 11/0.4 KV 63 KVA New (upto 1 Km)
Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km Small materials (upto 1 to 3 Km)
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor Single Pole SP 10
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor Single Pole SP 21
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor Single Pole SP 23
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor Double Pole Sp 23
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor 11 KV ACSR weasel
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor LT 3 PH 4 wire Weasel / AB cable
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor LT 1 PH 2 Wire Weasel / AB Cable
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor 11/0.4 KV 25 KVA New
Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor 11/0.4 KV 63 KVA New
Excavation of earth for pole pit for errection of pole in all type of soil in size 0.9X0.6X1/6 of pole lengh of Sp 23/21/10
Erection of Double Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-23.
Erection of Single Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-23.
Erection of Single Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-21
Erection of Single Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-10
Grouting of pole in CC ratio 1:4:8 including cost of Cement, sand, Stone ballast as per RESPO norms in size 0.45X0.45X1/9 of SP 23/21/10 Pole
Muffing of Pole With CC 1:3:6 Block 45cm Height from Ground level Including cost of Ballast,cement & sand Etc.
Fabrication of MS Channel/MS Angle making proper hole as per norms complete
Looping Chooping and cutting of tree which fallen on line
Laying & Resagging of 11 KV line in Weasel Conductor Complete including Fixing of all accessories as per RESPO (1ph or 3 Ph)
Laying & Resagging of LT Line with ACSR Weasel conductor including continuous earth wire complete work up to energizing LT 3 PH 4 wire Weasel / AB cable
Laying & Resagging of LT Line with ACSR Weasel conductor including continuous earth wire complete work up to energizing LT 1 PH 2 Wire Weasel / AB Cable
Installation/mounting of new T/F in DP structure and its complete comissioning as per RESPO 11/0.4 KV 25 KVA New
Installation/mounting of new T/F in DP structure and its complete comissioning as per RESPO 11/0.4 KV 63 KVA New
Back Head load cartage of materials from pit site to Dump store ava. Lead distance 3 Km 11/0.4 KV 25 KVA New (Upto 1 to 3 Km)
Back Head load cartage of materials from pit site to Dump store ava. Lead distance 3 Km 11/0.4 KV 63 KVA New (upto 1 Km)
Back Motarable cartage of Material from road side dump store to Almora Including Loading & Un-loading both End.Dist 65 Km 11/0.4 KV 25 KVA New
Back Motarable cartage of Material from road side dump store to Almora Including Loading & Un-loading both End.Dist 65 Km 11/0.4 KV 63 KVA New
Back Motarable cartage of Material from road side dump store to Almora Including Loading & Un-loading both End.Dist 65 KmSmall materials
J D M ENTERPRISES
BALAM SINGH MEHRA
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .