| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.9 LAccepted-AOC | L1 | Accepted-AOC 18/AEE/MCS/TVM/2026-2027 | |
| 2 | Rejected-Technical | - | Rejected-Technical L4 Bidder | |
| 3 | Rejected-Technical | - | Rejected-Technical L2 bidder | |
| 4 | Rejected-Technical | - | Rejected-Technical L3 bidder |
| Sl No | Description | Qty | Unit | BINUKUMAR N L4 | BABU GEORGE L1 | TVPM UNEMPLOYED CONTRACT CO-OPERATIVE SOCIETY L3 | S SAJEEV L2 |
|---|---|---|---|---|---|---|---|
| 1.00Maintenance work | |||||||
| 1.00 | 15.56:Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | 373.53 | sqm | 60 ₹22,411.8 | 47.36 ₹17,690.38 Lowest | 57.76 ₹21,575.09 | 53.95 ₹20,151.94 |
| 1.00 | 26.28.2:Chipping of unsound/weak concrete material from slabs, beams, columns etc.
with manual Chisel and/ or by standard power driven percussion type or of
approved make including tapering of all edges, making square shoulders of
cavities including cleaning the exposed concrete surface and reinforcement
with wire brushes etc. and disposal of debris for all lead and lifts all complete
as per direction of Engineer-In-Charge50mm average thickness | 205.44 | sqm | 290 ₹59,578.18 | 222.4 ₹45,690.3 Lowest | 271.22 ₹55,719.98 | 253.32 ₹52,042.57 |
| 1.00 | 26.29.1:Cleaning of reinforcement from rust from the reinforcing bars to give it a total
rust free steel surface by using alkaline chemical rust remover of approved
make with paint brush and removing loose particles after 24 hours of its
application with wire brush and thoroughly washing with water and allowing
it to dry, all complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter | 1,369.61 | metre | 10 ₹13,696.1 | 6.99 ₹9,573.57 Lowest | 8.53 ₹11,682.77 | 7.97 ₹10,915.79 |
| 1.00 | 26.31.1:Providing, mixing and applying bonding coat of approved adhesive on chipped
portion of RCC as per specifications and direction of Engineer-In-charge
complete in all respect.SBR Polymer (@10% of cement weight) modified cementitious bond coat @2.2 kg cement per sqm of surface area mixed with specified proportion of approved polymer | 205.44 | sqm | 160 ₹32,870.72 | 123.75 ₹25,423.45 Lowest | 150.91 ₹31,003.25 | 140.95 ₹28,957.05 |
| 1.00 | 26.32.2:Providing, mixing and applying SBR polymer (of approved make) modified
Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with
polymer minimum 2% by wt. of cement used) as per specifications and
directions of Engineer-in-charge.
Note: Measurement and payment: The pre-measurement of thickness shall be
done just after the surface preparation is completed and Payment under this
item shall be made only after proper wet curing has been done and surface
has been satisfactorily evaluated by sounding / tapping with a blunt metal
instrument and/or the 75mm size cube crushing strength at the end of 28 days
to be not less than 30 N/Sqmm2).25 mm average thickness in 2 layers. | 205.44 | sqm | 680 ₹1,39,700.56 | 536.58 ₹1,10,236.07 Lowest | 654.37 ₹1,34,435.08 | 611.18 ₹1,25,562.04 |
| 1.01 | 13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand) | 373.53 | sqm | 350 ₹1,30,735.5 | 265.98 ₹99,351.51 Lowest | 324.36 ₹1,21,158.19 | 302.95 ₹1,13,160.91 |
| 1.01 | 13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer | 373.53 | sqm | 90 ₹33,617.7 | 67.77 ₹25,314.13 Lowest | 82.65 ₹30,872.25 | 77.2 ₹28,836.52 |
| 1.01 | 14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done . | 1,116.2 | sqm | 375 ₹4,18,575 | 299.57 ₹3,34,380.03 Lowest | 365.33 ₹4,07,781.35 | 341.22 ₹3,80,869.76 |
| 1.01 | 50.18.9.19.2:Providing and fixing PVC pipes including fixing the pipe with clamps/clips at 1.00 m spacing. This includes jointing of pipes with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 110 m dia 4 Kgf/cm2 - External work - Exposed on wall | 30 | metre | 375 ₹11,250 | 293.6 ₹8,808 Lowest | 358.05 ₹10,741.5 | 334.42 ₹10,032.6 |
Tender Value
₹8.5 L
EMD Value
₹21,178
Closing Date
6 Jun 2026, 11:00 amClosed
Asst Exe Engineer Medical College Sub division TV
Asst Exe Engineer Medical College Sub division PMG ,TVM
Civilworks
2026_PWD_852231_2
PWD/BLDG/TR/1514/2025_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
240 days
Medical College TVPM
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,870
Yes
₹21,178
Yes
8 Jul 2026
30 May 2026
8 Jun 2026
30 May 2026
6 Jun 2026
30 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Maintenance work | |||||
| 1.001 | 15.56:Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | 1 | sqm | - | - |
| 1.002 | 26.28.2:Chipping of unsound/weak concrete material from slabs, beams, columns etc.
with manual Chisel and/ or by standard power driven percussion type or of
approved make including tapering of all edges, making square shoulders of
cavities including cleaning the exposed concrete surface and reinforcement
with wire brushes etc. and disposal of debris for all lead and lifts all complete
as per direction of Engineer-In-Charge50mm average thickness | 0.8 | sqm | - | - |
| 1.003 | 26.29.1:Cleaning of reinforcement from rust from the reinforcing bars to give it a total
rust free steel surface by using alkaline chemical rust remover of approved
make with paint brush and removing loose particles after 24 hours of its
application with wire brush and thoroughly washing with water and allowing
it to dry, all complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter | 1 | metre | - | - |
| 1.004 | 26.31.1:Providing, mixing and applying bonding coat of approved adhesive on chipped
portion of RCC as per specifications and direction of Engineer-In-charge
complete in all respect.SBR Polymer (@10% of cement weight) modified cementitious bond coat @2.2 kg cement per sqm of surface area mixed with specified proportion of approved polymer | 0.8 | sqm | - | - |
| 1.005 | 26.32.2:Providing, mixing and applying SBR polymer (of approved make) modified
Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with
polymer minimum 2% by wt. of cement used) as per specifications and
directions of Engineer-in-charge.
Note: Measurement and payment: The pre-measurement of thickness shall be
done just after the surface preparation is completed and Payment under this
item shall be made only after proper wet curing has been done and surface
has been satisfactorily evaluated by sounding / tapping with a blunt metal
instrument and/or the 75mm size cube crushing strength at the end of 28 days
to be not less than 30 N/Sqmm2).25 mm average thickness in 2 layers. | 0.8 | sqm | - | - |
| 1.006 | 13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand) | 1 | sqm | - | - |
| 1.007 | 13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer | 1 | sqm | - | - |
| 1.008 | 14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done . | - | sqm | - | - |
| 1.009 | 50.18.9.19.2:Providing and fixing PVC pipes including fixing the pipe with clamps/clips at 1.00 m spacing. This includes jointing of pipes with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 110 m dia 4 Kgf/cm2 - External work - Exposed on wall | - | metre | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1442286.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
epaymentform.pdf
Tender Documents • 0.06 MB
SBD.pdf
Tender Documents • 1.64 MB
BOQ_1442286.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .