Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹57.7 LAccepted-AOC | ₹57.7 L | L1 | Accepted-AOC Lowest 1 |
| 2 | L2₹65.2 LRejected-AOC | ₹65.2 L | L2 | Rejected-AOC Lowest 2 |
| Sl No | Description | Qty | Unit | MAJO K J L1 | DIJO JOHNY L2 |
|---|---|---|---|---|---|
| 1.00Appendix A-Reactive Maintenance | |||||
| 1.00 | 3.24.B:Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil by Manual Means to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres) | 1,115 | metre | 229.33 ₹2.6 L | 259 ₹2.9 L |
| 1.00 | 55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement. | 11.46 | cum | 2,492.19 ₹28,555.51 | 2,815 ₹32,254.27 |
| 1.00 | 55.8.a:Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface. | 1.91 | cum | 5,443.21 ₹10,385.64 | 6,147 ₹11,728.48 |
| 1.00 | 55.7.a:Providing bitumen leveling coarse between 40mm and 150mm with 36mm deptl metal by spreading the metal to line and levels and rolling until the compacted coarse aggregate has a firm surface and applying hot bitumen with pressure sprayer at the rate of 20 Kg per M3 metal including all cost of bitumen conveyance heating mixing spreading in appropriate locations to proper levels compacting with power roler and other sundry stores. | 9.55 | cum | 3,012.33 ₹28,767.75 | 3,402 ₹32,489.10 |
| 1.00 | 10.5.1a:Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm. Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - For grading I Material | 2,595.5 | sqm | 468.11 ₹12.1 L | 529 ₹13.7 L |
| 1.01 | OD55988/2025-2026:Conducting and Reporting Routine Maintenance inspections for the entire length of the project road at a frequency of 7 days throughout the agreement period of the running contract as directed by the departmental officers at site.
Additional Routine Inspection may be required in response to reports or complaints from the police other authorities and the public as a result of major incidence, typhoon or flooding damages etc. and are not measurable/ payable. A portion of the routine inspection may be carried out either during or immediately following a period of wet weather. | 1,293.66 | km | 45.52 ₹58,887.59 | 51.41 ₹66,507.27 |
| 1.01 | OD55987/2025-2026:Engaging wood cutter | 40 | each | 1,119.61 ₹44,784.40 | 1,264 ₹50,560 |
| 1.01 | OD55985/2025-2026:Providing and fixing of non retro-reflectorised DLP board manufactured as per IRC :67 made of Type IV microprismatic grade sheeting fixed over aluminium sheeting 2mm thick/ aluminium composite material sheeting 4mm thick with area not exeeding .9 sqm with suitable back supporting frame of MS Angle 40x40x6 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete min size 45x45x60 cm ,60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc. | 1.49 | sqm | 8,629.62 ₹12,840.87 | 9,746 ₹14,502.05 |
| 1.01 | OD55990/2025-2026:Dry Rubble Masonry with Departmental stone including all cost of materials and labour charges, etc. | 22.5 | cum | 2,024.76 ₹45,557.10 | 2,287 ₹51,457.50 |
Tender Value
₹59.3 L
EMD Value
₹50,000
Closing Date
15 Oct 2025, 3:00 pmClosed
EXECUTIVE ENGINEER
EXECUTIVE ENGINEER PWD ROADS DIVISION THRISSUR
GENERAL RM 2025 26 RC2 Phase1 Cluster II Zone II One year Running Contract for various PWD Roads under Wadakkanchery Section in Thrissur District 7 Nos road stretches for a length of 24.81 km General Civil work
2025_PWD_807148_1
PWD/RB/9823/2025-2026
Open Tender
Civil Works - Roads
365 days
Thrissur
Please refer Tender documents.
9 documents required · 9 mandatory
₹2,760
Yes
₹50,000
Yes
6 Jun 2026
8 Oct 2025
17 Oct 2025
8 Oct 2025
15 Oct 2025
8 Oct 2025
Amount
Appendix A-Reactive Maintenance
3.24.B:Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil by Manual Means to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres)
55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.
55.8.a:Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.
55.7.a:Providing bitumen leveling coarse between 40mm and 150mm with 36mm deptl metal by spreading the metal to line and levels and rolling until the compacted coarse aggregate has a firm surface and applying hot bitumen with pressure sprayer at the rate of 20 Kg per M3 metal including all cost of bitumen conveyance heating mixing spreading in appropriate locations to proper levels compacting with power roler and other sundry stores.
10.5.1a:Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm. Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - For grading I Material
OD55988/2025-2026:Conducting and Reporting Routine Maintenance inspections for the entire length of the project road at a frequency of 7 days throughout the agreement period of the running contract as directed by the departmental officers at site. Additional Routine Inspection may be required in response to reports or complaints from the police other authorities and the public as a result of major incidence, typhoon or flooding damages etc. and are not measurable/ payable. A portion of the routine inspection may be carried out either during or immediately following a period of wet weather.
OD55987/2025-2026:Engaging wood cutter
OD55985/2025-2026:Providing and fixing of non retro-reflectorised DLP board manufactured as per IRC :67 made of Type IV microprismatic grade sheeting fixed over aluminium sheeting 2mm thick/ aluminium composite material sheeting 4mm thick with area not exeeding .9 sqm with suitable back supporting frame of MS Angle 40x40x6 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete min size 45x45x60 cm ,60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc.
OD55990/2025-2026:Dry Rubble Masonry with Departmental stone including all cost of materials and labour charges, etc.
OD55989/2025-2026:Providing and fixing vinyl sticker in existing DLP board including lettering and printing Removal of existing sticker plate from the DLP board by removing the rivet and accessories, transportation from site to factory, Removal of existing sticker from Sticker Plate, installation of new sticker, transporting back to site. installation of new sticker plate to the DLP board using rivets and accessories.
OD105916/2025-2026:Engaging Coolie for petty works
Appendix B- Premonsoon work
2.2:Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area
OD55979/2025-2026:Man engaged for clearing blocked up ventway ,Clearing of drains, pavement sweeping, where required,removal of debris from roads ,Clearing all type of waste from roads maintenance of sign boards ,clearing footpath pedestrian area etc.
OD55977/2025-2026:Filling up pot holes with readymix compound (25Kg bag) and compacting by ramming to get a compact surface including cost of materials, laying charges transportation to site etc complete Rate is derived for a bag of 25 Kg
55.16:Providing and fixing guard post Providing and fixing guard post of size 200mmx200mm, 1400mm long, 800mm above ground level and 600mm below GL. casted in M20 Grade concrete reinforced with 4 nos of 8mm dia longitudinal bars and 6mm dia stirrups @ 100mm c/c, firmly fixed in position by means of foundation of size 0.5mx0.5mx0.7m in M15 grade concrete below ground level including painting 2 coats on exposed surface with synthetic enamel paint in alternate white & black band 20cm wide
55.15:Refurbishment of existing signboardsRefurbishment of existing signboards of all size except gantry mounted ones to their original reflectivity & position by removing obstructions like overgrowth vegitation etc ,if any,washing the signboards with water & soap solution to remove all dirt, oil etc. , correcting any dislocations including minor repairs, replacement of lost nut and bolts etc complete.
OD55974/2025-2026:Lifting the existing precast RCC covering slabs from drain and culvert for removal of silt and placing the same slab on position after completion of clearing work including all labour charges and miscellaneous expenses etc. complete
OD55980/2025-2026:Hire charges of Hydraulic excavator including operation charges and fuel charges for clearing and removing waste materials clearing grassetc. along the sides of roads as per the direction of departmental officers at site.
OD55976/2025-2026:Hire charges of Tipper including operation charges and fuel charges for cleaning and removing dumped stons waste materials etc as per the direction of departmental officers at site etc.complete
OD55981/2025-2026:Engaging wood cutter
OD55975/2025-2026:Engaging Coolie for petty works
OD55978/2025-2026:Supplying and spreading quarry rubbish in the eroded portions of BT edge, deep pot holes and low level berms as per the direction of the departmental officers at site including cost of materials, conveyance and labour charges for spreading, ramming etc complete.
Appendix C- Preventive Maintenance
2.2:Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area
10.2:Maintenance of Earthen Shoulder (filling with fresh soil) Making up the loss of material/ irregularities on the shoulder to the design level by adding fresh approved soil and compacting it with appropriate equipment.
3.24.B:Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil by Manual Means to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres)
OD55973/2025-2026:Man engaged for clearing blocked up vent way, clearing of drains, pavement sweeping where required, removal of debris from roads, clearing all types of waste from roads, maintenance of sign board, clearing footpath/ pedestrian area etc.
4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.
55.7.a:Providing bitumen leveling coarse between 40mm and 150mm with 36mm deptl metal by spreading the metal to line and levels and rolling until the compacted coarse aggregate has a firm surface and applying hot bitumen with pressure sprayer at the rate of 20 Kg per M3 metal including all cost of bitumen conveyance heating mixing spreading in appropriate locations to proper levels compacting with power roler and other sundry stores.
55.8.a:Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.
10.5.1a:Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm. Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - For grading I Material
3.13.1.B:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil - Mechanical Means - (Depth upto 3 m)
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
12.8.A.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15
12.8.1.C:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer - (Without formwork)
12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer
12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
8.4.3:Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign with 7years warranty manufactured as per IRC :67 made of Type IV micro prismatic grade sheeting vide clause 801.3.3 fixed over aluminium sheeting, 2 mm thick/ aluminium composit material sheeting 4 mm thick with suitable back supporting frame of MS angle 25x25x3 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc. 60 cm circular
8.5:Providing and fixing of direction and place identification retro-reflectorised sign with 7 years warranty manufactured as per IRC :67 made of Type IV micro prismatic grade sheeting fixed over aluminium sheeting, 2 mm thick/ aluminium composit material sheeting 4 mm thick with area not exceeding 0.9 sqm, with suitable back supporting frame of MS angle 40x40x6 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc.
8.15:Supplying and installation of delineator (Roadway indicators) posts 80- 100cm high above ground level, pained black, and white in 15 cm wide strips, fitted with min. 80 x 100 mm rectangular or 75 mm dia circular retro reflectorized panels at the top with minimum visibility of 300m with provisions to prevent edge lifting and vandalisam, and conforming to clause 806 , IRC-79 and the drawings including fixing to ground (The deleniator shall be of approved type as per specification)
8.35:Providing and fixing reflective road studs (Raised Pavement Marker) of ' category A' made out of ASA/HIPS/ABS moulded body with shanks and conforming to ASTM D 4280, strong enough to support a load of more than 13.635 T when tested in accordance with ASTM D 4280, reflective panel confirming to ASTM D 788, and reflectivity conforming to clause 804.4. including installation, drilling, fixing with adhesive etc. with 2 years warranty for the road stud as well as for in field performance as per clause 804.7.3 Road Markers/Road Stud with Lense Reflector :-
8.13:Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads on Bituminous Surface @ 250 gms per sqm area, the thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform, and free from streaks and holes.
8.4.2:Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign with 7years warranty manufactured as per IRC :67 made of Type IV micro prismatic grade sheeting vide clause 801.3.3 fixed over aluminium sheeting, 2 mm thick/ aluminium composit material sheeting 4 mm thick with suitable back supporting frame of MS angle 25x25x3 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc. 60 cm equilateral triangle
55.10.1:Providing and erecting retro-reflectorised Object Hazard Marker 300mm x 900mm Providing and erecting retro-reflectorised Object Hazard Marker sign with 07 years warranty, manufactured as per IRC 67 USING Type IV ASTM D 4956-09 micro prismatic retro reflective sheeting fixed over aluminium sheetig, 2 mm thick / aluminium composit material sheeting 4 mm thick with suitable back support frame and supported on a mild steel angle iron post 75mmx75mmx6mm, firmly fixed 30cm above ground level by means of properly designed foundation with M 15 grade cement concrete 30cmx30x45cm, 45cm below ground level including painting all non-reflective faces with epoxy paint 2 coats over epoxy primer as per approved drawing and clause 801.300 mm x 900 mm
55.11.1:Flexible Hazard Marker 30cm x 30cm Hazard Marking on the surface of trees,concrete,Masonry etc using Aluminium backed flexible presmatic (AFP) SHEETING CONSISTING OF Yellow colored flexible presmatic sheeting non-metallic presmatic lens as recto reflective elements and conforming to ASTM D 4956-09 Type IV specification values for reboundable sheetig with printed arrow /Slant line pattern in black colour. AFP sheeting laminated at the back with a 50 micron thick Aluminium (AI) foil with pressure sensitive adhesive and liner and shall not crack when tested for flexibility as per section S2.2.2 of ASTM D 4956-09 including application on any surface with adhesive as recommended by manufacturer and ceiling the edges all around with epoxy based structural adhesive to resist any peel-off.
55.15:Refurbishment of existing signboardsRefurbishment of existing signboards of all size except gantry mounted ones to their original reflectivity & position by removing obstructions like overgrowth vegitation etc ,if any,washing the signboards with water & soap solution to remove all dirt, oil etc. , correcting any dislocations including minor repairs, replacement of lost nut and bolts etc complete.
OD55971/2025-2026:Filling up potholes with bituminous ready mix compound (25 kg bag )and compacting by ramming to get a compact surface including cost of materials, laying charges, transportation to site etc. complete. Rate is arrived for a bag of 25 kg
OD55970/2025-2026:Engaging wood cutter
OD55972/2025-2026:Providing Spring Post including all cost of materials etc. complete.
3.17:Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2.
OD105922/2025-2026:Engaging Coolie for petty works
Appendix D-Emergency works
OD55982/2025-2026:Hire charges of Hydraulic excavator including operation charges and fuel charges for clearing and removing waste materials clearing grassetc. along the sides of roads as per the direction of departmental officers at site.
OD55983/2025-2026:Hire charges of Tipper including operation charges and fuel charges for cleaning and removing dumped stons waste materials etc as per the direction of departmental officers at site etc.complete
OD55984/2025-2026:Engaging wood cutter
OD105926/2025-2026:Engaging Coolie for petty works
DIJO JOHNY (BID ID -2390061)
Bidder Name
MAJO K J
DIJO JOHNY
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1345103.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid