Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.6 LAccepted-AOC | L1 | Accepted-AOC LOWEST |
Tender Value
₹4.0 L
EMD Value
₹8,000
Closing Date
15 Feb 2021, 5:00 pmClosed
Raj Kumar EE
Executive Engineer,Jag Provincial Division PWD B and R Br Yamuna Nagar
Providing 30mm Thick Bituminous Concrete in (Km 0.00 to 0.60) in link road from Khizrabad Bilaspur road to Hafizpur (ID 693) in Yamuna Nagar District
2021_HRY_156130_2
PWD/CHD/YNGAR/1081
Open Tender
Construction Works
Works
30 days
Yamuna Nagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹500
₹8,000
Yamuna Nagar
11 Dec 2023
2 Feb 2021
17 Feb 2021
3 Feb 2021
15 Feb 2021
3 Feb 2021
10 Feb 2021
Amount
Milling of distress bituminous layer upto 20mm depth in a single pass with suitable milling machine (capable of milling @ 200-300 sqm area per Hr.) fitted with loading conveyor for loading the milled material directly on the trucks i/c hauling and stock piling the reclaimed material near the central recycling plant or reclaiming to bring to required specification to reuse with the approval of Engineer-in-Charge for safe disposal with all leads and lifts complete in all respects. Note :- 1. The unutilized quantity of reclaimed bituminous mix material shall be a recovery item as mention in BOQ item No. 5. 2. The quantity of reclaimed material shall be considered minimum 80% of theoretical volume. The reclaimed material shall be used 30% of total quantity as per clause No. 519 of MoRT&H specifications.
Providing and laying tack coat with bitumen VG-10 grade pressure distributor at the rate of 0.30 kg. per sqm. On the prepared bitumen/granular surface cleaned with mechanical broom including cost of bitumen as per clause No.503 (5th edition) 2013 as per MoRT&H specification (N.S.)
Providing & Laying 30mm thick compacted Bituminous Concrete (BC) in one layer with 100-120 TPH batch type hot mix plant and with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with appropriate rollers to achieve the desired compaction as per clause No. 507 MoRT&H specification (5th Revision) 2013 for road and bridge works (5th Revision)2013 using minimum 5.4% to bitumen grade VG-30 as binder content by weight of total mix, complete in all respects including cost of bitumen instruction issued from time to time by MoRT&H regarding machinery & bitumen will be followed strictly. The use of self propelled mechanical paver fitted with electronic sensor device conforming to MoRT&H specification in mandatory. If bitumen required more than 5.4% as per job mix formula no extra payment will be made, extra bitumen required will be considered as incidental to work.
Preparation of berms including filling or excavation and cutting of earth in all kind of soils including dressing the bank, side slope to given levels and templates after breaking of clouds, including the cost of rolling and watering all allowances for labour hardness wetness irrespective of all lead and lift and including Compensation for earth taken from private land, fields etc. and compacted to meet requirement of table 300-2 of MoRT&H specification clause No. 305 and to the entire satisfaction of the Engineer of the work conforming to PWD specification No. 6.2 and 6.3 and 3.2 and the other specification 1990 Ist edition. As per X-section attached at DNIT at Section -9. Note:- No earth work will be allowed to be taken from PWD B&R/ ROW except for surplus earth after approval from Engineer.
Recovery items: The rates quoted against recovery items will not be included in the total amount rather it will be deducted while calculating financial statement of the agency. Material obtained from dismantling of existing brick work, bituminous layer have been calculated taking assumption that 80% of theoretical material will be retrieved. The dismantled material can used in any of the item for the work after modification (bringing it to required specifications) after approval from employer. In case it is not possible to use this material on the work, the agency can take away this material. This material can be taken away by the agency at the price quoted by the agency but minimum price to be quoted is limited to reserve price as fixed and mentioned as under :- Scarified material @ Rs. 881.00 Per Cum
Note: All quantities of the above materials have been worked out on the basis of theoretical quantities laid on this road. However, agency may visit site before quoting rates and assess the extent of retrieved material. There shall be no measurement after actual dismantling and if material after dismantling is found on lesser side, no claim of agency on this score will be entertained and full recovery on the basis of quoted rate and quantity exhibited in the BOQ shall be made. The reserve rates are minimum rates to be used as base for quoting purchase rate by the agency. No rates below the reserve price will be entertained and reserve price will be considered for all purposes in case the agency quotes lesser than reserve price. 1. In case of any difference in the unit & nomenclature of any of the HSR items depicted in this DNIT and the given in HSR, the unit of nomenclature given in HSR shall be applicable. 2. In case of any difference in the unit of any non schedule item depicted in this DNIT and the conventional unit of that N.S. item as per practice in this department, the conventional unit as per practice shall be applicable
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .