Tender Value
Refer Docs
Closing Date
22 Sept 2026, 6:30 pmClosed
HOD (Procurement)
Pre-Qualification of Contractors for Small Connectivity Pipeline Projects.
340579
GTL/PROC/2026/08/O/502
Open
Pipe Laying Work
Works
Gandhinagar
7 Sept 2026
7 Sept 2026
7 Sept 2026
22 Sept 2026
7 Sept 2026
ANNEXURE-B Pre-bid Queries form for the tender "Pre-Qualification of Contractors for Small Connectivity Pipeline Projects". GTL Tender no.: GTL/PROC/2026/08/O/502 (n)Procure Tender ID: 340579
Sr. No. Bid Reference Bidder’s Queries/ Observation/Comments GTL's Response
Section Clause No. Clause heading Page no. Original Clause as per Tender doc.
Name of Bidder:
For ex. Section-II 10.0 Language of bid 16 The Bid, as well as all correspondence and documents relating to the bid exchanged by the Bidder and Owner, shall be English Only. abc xyz
Note: Queries must be submitted in this format only through e-mail on GTL's contact details before deadline of query submission date as provided in RFP/ Amendments/ updated during pre-bid meeting.
Annexure-C Unit Base Rate/ SCHEDULE OF RATES (Tender no.: GTL/PROC/2026/08/O/502; (n)Procure Tender ID: 340579)
HIRING OF CONTRACTOR FOR CUSTOMER CONNECTIVITY PIPELINE PROJECTS ACROSS GUJARAT
TOTAL COST OF SCHEDULE:A,B,C,D & E
DOCUMENT NO.: GTL-ARC-DOC-SOR-060-04-01
Rev. -0 dated 06.07.2026
Category of Registration in GST(Tick whichever is applicable)
Registered (Normal)
Registered (Composition Levy)
Type of Supply Under this Contract (Tick whichever is applicable)
Normal Supply of goods and services
Composite supply
Sr No Schedule No. SOR Description Quoted Amount
1 A PIPELINE WORKS ₹7,760,636
2 B STATION MECHANICAL AND ASSOCIATED WORKS ₹16,727,577
3 C CIVIL AND ASSOCIATED WORKS ₹3,769,300
4 D ELECTRICAL INCLUDING CATHODIC PROTECTION AND ASSOCIATED WORKS ₹16,548,049
5 E INSTRUMENTATION AND ASSOCIATED WORKS ₹27,042,206
TOTAL OF SCHEDULE A+B+C+D+E IN INR Including GST ₹71,847,768
Amount in WORDS:
1 The bidder shall quote the prices strictly as per the price bid format. Any bid not conforming to the price bid format shall be rejected.
2 The bidder shall have to quote the rates for each item. The bidder who fails to comply against requirement shall be rejected.
3 The quantity mentioned for each line item is indicative only and actual quantity may vary up to any extent without altering unit price. Payment shall be made against the GSPL certified quantity only
4 Withholding tax shall be applicable on the entire contract value as per the prevailing rate.
5 Given Schedule of Rates (SOR) to be treated in conjunction with scope of work/services/supply & terms and conditions given along with RFP documents.
6 The above prices are for the complete scope of wok /services/ supplies as defined in the bid/enquiry document.Any materials, works/services required for completion of the work as per scope but not defined in the SOR (schedule of rates), the same is deemed to be included in the quoted price as above.
7 GTL reserves the right to reject any or all bid without giving any reason whatsoever.
Sign & Stamp of Bidder:
Annexure-C Unit Base Rate/ SCHEDULE OF RATES (Tender no.: GTL/PROC/2026/08/O/502; (n)Procure Tender ID: 340579)
HIRING OF CONSTRUCTION CONTRACTOR FOR CUSTOMER CONNECTIVITY PIPELINE PROJECTS ACROSS GUJARAT
PIPELINE AND ASSOCIATED WORKS
DOCUMENT NO.:GTL-ARC-DOC-SOR-060-04-01
Rev 0 dated 06.07.2026
BIDDER'S NAME :
S. No. Description of Items Unit Quantity HSN/SAC Unit Rate Total Basic Amount GST Total Amount with GST
(Basic) % Amount
A B C D E F G = D x F H I J = G + I
A PIPELINE LAYING / INSTALLATION
1.1.2 PIPELINE LAYING/ INSTALLATION : Laying/ installation of coated line pipe, associated fittings and accessories, etc. as per specifications, drawings, other provisions of Contract and instructions of Owner / Consultant, including but not limited to carrying out the following: "Receiving and taking-over", handling, loading, transportation and unloading of Owner supplied externally and Internally coated and bare line pipes from designated place(s) of issue / dump site(s) to Contractor's own stock-yard(s)/ workshop(s)/ work-site(s) including Revalidation of pipeline route based on alignment sheets and crossings drawings, stringing on the pipeline Right-of-Use (ROU)/ Right of way (ROW).
"Receiving and taking over", handling, including loading and unloading, transportation of Owner supplied materials from Owner's designated place(s) of issue to worksite(s); Arrangement of all additional land required for Contractor's storage, fabrication, access for construction (other than Owner provided ROU/ROW); supply of all materials (except Owner supplied materials), consumables, equipment, labour, etc.; Staking and installation of construction markers, clearing, grubbing, grading (as required) of Right of Use/ Right of Way. Including Delivery and Transportation of free issued material to site; and reconciliation & transportation of surplus material, removed material, spares to owner’s designated store from site. Storage of materials including preservation as required as per suppliers/manufacturer’s recommendation and loading, unloading & transportation from Owner store (Refer Annexure – IV) to work site is included in the scope of Contractor.
Counting the number and type of trees cut in presence of DFO/concerned authorities and keeping record thereof; Trenching to all depths and to a width to accommodate the pipeline and/or 2 nos of HDPE Duct along with optical fibre cable/cable conduit as specified in scope document and as per the relevant standards, specifications, etc. by excavation in all types of soils (including soft/hard rock), including blasting, chiselling or otherwise cutting etc.; providing trench padding as required with sand/ graded earth approved by Owner / Consultant; Carrying out repairs of pipe and coating defects not attributable to Owner (i.e. defects occurring after "taking over" of pipes from Owner); Thorough internal cleaning of all pipes by suitable methods to remove
debris, shots, grits etc. to the satisfaction of Owner / Consultant ; Stringing of line pipes along ROU/ROW including providing straw bags, soft padding/sand padding; Aligning, bending, cutting and bevelling (as required) of pipes for welding and field adjustments, NDT of re- bevelled area, welding, carrying out destructive/ non- destructive testing of welds as
required including radiography and providing all requisite equipment, labour, supervision, materials, films, consumables, all facilities and personnel to process, develop, examine and interpret radiographs and other tests, as required; carrying out repairs of weld joints found defective by Owner / Consultant, carrying out re-radiography and other
non- destructive tests as required on repaired joints, etc.; Installation of carrier pipe including concrete coated pipes (wherever required) at all crossings including Pipelines /roads/ canals/ nala/ water crossings etc. (except at major water and other crossings that are specifically covered separately in this document) by open cut or boring method including pre-testing and post hydro-testing of crossing section.
as required; Carrying out installation of carrier pipe in the casing pipe at cased crossings (excluding supply and installation of casing pipes covered separately); Epoxy coating of casing pipe,bentonite filling, Coating of all field weld joints, warning mat/TAP, buried fittings, valves etc.; Lowering the pipelines in trench including providing sand bag separators for parallel pipelines at the specified spacing (when
applicable), providing required padding over and around the pipeline with sand/graded material approved by Owner / Consultant (in rocky areas), backfilling with available, approved excavated material and/or other suitable soil approved by Owner / Consultant; Supply and installation of slope breaker as per specifications and drawings in steep slope areas,
wherever required; Carrying out hydrostatic testing including air cleaning, flushing, filling, gauging, pressurization of complete pipeline in various test sections as approved by Owner / Consultant to the specified test pressure, providing all equipment, pumps, fittings, instruments, dead weight tester, all types of pigs etc., and services, supervision, labour, consumables,
water including supply of corrosion inhibitor, air, etc. as required, locating of leaks and rectification of defects attributable to Contractor, re- testing after rectification, successful completion of hydro- testing of pipeline including De-watering and swabbing, . All tie-ins, including the tie-in(s) with the pipeline / piping installed by others including cutting of test header
, re-bevelling as required; Carrying out all temporary, ancillary, auxiliary works and all incidental works required to make the pipeline ready for pre-commissioning; Repair of defects recorded during EGP/gauge plate run or otherwise including cutting, bevelling, welding, radiography, field joint coating etc.; as applicable, , Final clean-up and restoration of right of way/right
of use including obtaining NOC from respective statutory authorities as required and disposal of debris and returning all surplus material to designated disposal areas/storage yard, as directed by Owner / Consultant; Restoration of land, facilities and boundary wall etc. at associated facilities dismantled/damaged by the Contractor during construction; Obtaining
work permits/ NOC from various statutory authorities having jurisdiction, before execution of the work, and complying with all stipulation/ conditions/ recommendation of the said authorities; Preparation of as-built drawings, pipe-book and other records. SOR shall be read in conjunction with scope of work, job specific requirements, specifications, standards, drawings and
other provision of contract document. All above works for buried pipeline as per following details.
Development & Maintenance of Contractor Storage Yard adequate to store the line pipes including arrangement of all Lifting & Handling equipment at Contractor's Storage Yard shall be done by the Contractor. Rate for the same shall be quoted in applicable items.
1.1 Installation of Coated Line Pipes in all type of soil except hard rock (with OFC/OFC conduit i.e. 2 nos of HDPE Duct) as per following details:
1.1.1 Size in Inch ( mm) Wall Thickness in mm Line Pipe Grade
1.2 Installation of Coated Line Pipes in hard rocky area (with OFC/OFC conduit i.e. HDPE Duct) as per following details: 0.00
1.2.1 Size in Inch ( mm) Wall Thickness in mm Line Pipe Grade 0.00
1.3 For Seismic Areas in all type of Soil except hard rock as per Standard Drawing .(with OFC/OFC conduit i.e. 2 nos of HDPE Duct) as per following details: Unit rate for additional work over and above item no. 1.0 for supply of specified and approved quality of Back Filled materials including required soil testing as defined in contract document at seismic zone along pipeline route in place of available excavated material and/ or other suitable soil including additional excavation as per standard drawing Specification, including backfilling of excavated trench for specified length after laying of pipeline, including transportation of backfill material over all distances and disposal of surplus excavated soil, complete. Note : Bidder shall be paid for supply of selected back filled materials, addition excavation etc. apart from rate over and above item no.: 1.1 0.00 0 0.00
1.3.1 Size in Inch ( mm) Wall Thickness in mm Line Pipe Grade 0.00 0 0.00
1.4 For Seismic Areas in Hard Rock as per Standard Drawing (with OFC/OFC conduit i.e. 2 nos of HDPE Duct) as per following details: Unit rate for additional work over and above item no. 1.0 for supply of specified and approved quality of Back Filled materials including required soil testing as defined in contract document at seismic zone along pipeline route in place of available excavated material and/ or other suitable soil including additional excavation as per standard drawing, Specification, including backfilling of excavated trench for specified length after laying of pipeline, including transportation of backfill material over all distances and disposal of surplus excavated soil, complete. Note : Bidder shall be paid for supply of selected back filled materials, addition excavation etc. apart from rate over and above item no.: 1.2 0.00 0 0.00
1.4.1 Size in in Inch ( mm) Wall Thickness in mm Line Pipe Grade 0.00 0 0.00
Note:-Rate of laying of OFC & conduit shall be quoted in relevant Schedule of Rates (SOR) of Telecom Works, hence not to be included in Pipeline Laying works. 0.00 0 0.00
2.0 MECHANICAL PROTECTION 0.00 0 0.00
2.1 CONTINUOUS CONCRETE COATING 0.00 0 0.00
Unit rate for additional work over and above item no. 1.0 for supply of all consumables and materials and application of continuous concrete weight coating on pipes of all wall thicknesses in all areas of work except minor/ major river crossings covered separately, and performing all works as per specifications and instructions of Owner / Consultant and other provisions of Contract document. 0.00 0 0.00
Pipes as per following details : 0.00 0 0.00
Size in Inch ( mm) Wall Thickness in mm Concrete Coating Thickness in mm 0.00 0 0.00
2.2 CONCRETE SLAB 0.00 0 0.00
2.2.1 Unit rate for additional work over and above item no. 1.0 for Supply, fabrication and installation of reinforced concrete weights. Reinforced steel size should be 10 & 12 mm. top and bottom at a rate of 200 mm c/c of precasted RCC M 20 Grade on pipeline of wall thickness of 100 mm thick and size as per specifications & Standard drawings and instructions of Owner/ Owner’s representative including supply of consumables, materials, equipment, labour, supervision, all associated civil works. 0.00 0 0.00
3.0 SOIL STABILIZATION 0.00 0 0.00
3.1 BANK STABILIZATION 0.00 0 0.00
3.1.1 Unit rate for additional works over and above item no. 1.0 for supply, transportation, fabrication and installation for protection and stabilization of banks of water crossings including supply of all materials, consumables, manpower and performing works as per drawings, specifications, instructions of Owner / Consultant and provisions of Contract documents SQ M 1 7,920.00 7,920.00 18% 1425.60 9345.60
3.2 SLOPE STABALIZATION (Hilly areas) 0.00 0 0.00
3.2.1 Additional works over and above item no. 1.0 for supply, transportation, fabrication and installation for protection and stabilisation of soil in hilly areas including supply of all materials, equipment, consumables, manpower and performing works as per drawings, specification, instruction of Owner / Consultant and provisions of Contract documents. SQ M 1 6,600.00 6,600.00 18% 1188.00 7788.00
4.0 BACKFILLING WITH SELECT SOIL 0.00 0 0.00
4.1 BACKFILLING WITH SELECT SOIL (WITH IN STATION) 0.00 0 0.00
4.1.1 Unit rate for supply and transportation, of specified and approved quality of sand in place of available excavated material and/ or other suitable soil as per applicable standards/ specifications, including backfilling of excavated trench for specified length after laying of pipeline or SV installation, including transportation of backfill material over all distances and disposal of surplus excavated soil, complete. 0.00 0 0.00
5.0 OPEN CUT CROSSING WITH CASING 0.00 0 0.00
supply, transportation, and Installation of casing pipe by open cut trench for road or canal crossings wherever required in all types of soil and terrain and all other materials viz. casing insulators and casing end seals, materials for casing vent and drains, etc. including supply of all other materials equipments, consumables, manpower, welding including visual inspection of all weld joints, installation of casing insulators, end seals, pipeline laying/installation with casing 0.00 0 0.00
Backfilling, Bentonite filling, surface preparation and painting ( External and Internal, if asked by Authorities) and restoration as original of the facility crossed and performing all works as per drawings, specifications and instructions of Owner / Consultant and provision of Contract document. 0.00 0 0.00
Casing Pipe size in Dia ( mm) Casing Pipe Material Wall Thickness of Casing Pipes in mm Pipeline Size in Inch ( mm) 0.00 0 0.00
6.0 CASED CROSSING 0.00 0 0.00
supply, transportation and Installation of casing pipe by boring for rail, road or canal crossings wherever required in all types of soil and terrain and all other materials viz. casing insulators and casing end seals, materials for casing vent and drains, etc. including supply of all other materials equipments, consumables, manpower, welding including visual inspection of all weld joints, installation of casing insulators, end seals, pipeline laying/installation with casing 0.00 0 0.00
vents and drain-off pipes, Bentonite filling, surface preparation and painting / Coating (External and Internal, if asked by Authorities) backfilling and restoration as original of the facility crossed and performing all works as per drawings, specifications and instructions of Owner / Consultant and provision of Contract document. 0.00 0 0.00
Casing Pipe size in Dia (mm) Casing Pipe Material Wall Thickness of Casing Pipes in mm Pipeline Size in Inch ( mm) 0.00 0 0.00
7.0 CS CONDUIT FOR HDPE / OFC 0.00 0 0.00
Supply, transportation, and Installation of casing pipe by Open cut / boring or any other method for rail, road or canal crossings wherever required in all types of soil and terrain and all other materials as per enclosed drawing with the bid including supply of all other materials equipments, consumables, manpower, welding including visual inspection of all weld joints, surface preparation and painting (External and Internal, if asked by Authorities), backfilling and restoration as original of the facility crossed and performing all works as per drawings, specifications and instructions of Owner / Consultant and provision of Contract document. 0.00 0 0.00
7.1 BY OPEN CUT 0.00 0 0.00
7.1.1 Casing Pipe size in Dia ( mm) Casing Pipe Material Wall Thickness of casing in mm Pipeline Size in Inch ( mm) 0.00 0 0.00
7.2 BORING OR ANY OTHER METHODS 0.00 0 0.00
7.2.1 Casing Pipe size in Dia ( mm) Casing Pipe Material Wall Thickness of casing in mm Pipeline Size in Inch ( mm) 0.00 0 0.00
8.0 PIPELINE AND CS CONDUIT INSTALLATION BY HDD TECHNIQUE AT LOCATION AS PER IFC DRAWING OR AS INSTRUCTED BY OWNER / CONSULTANT 0.00 0 0.00
Receiving, transportation, and taking over of owner supplied free issue 3 Layer PE coated line pipes of all sizes, type and wall thickness and API 5L Gr. X-52 / 65 grade from owner's designated point of issue. For complete works for the major canal/NH/RLY by horizontal drilling method (HDD) including all additional drilled lengths necessitated by Contractor's design of water crossings, carring out all topographical, hydrological and geo-technical surveys required for calculation of scour level for design and construction of crossing, preparation of all 0.00 0 0.00
necessary design Calculation & Profile drawings along with design document, procedure (i.e. scour level calculation & installation design) for Owner's / Consultant's approval, mobilization and demobilization at site(s), supply of all materials as per "Contractor's Scope of Supply" including 1 Nos. of 6" NB size, 6.4 mm, API 5L Gr. B CS conduit pipe and 6"CS Pipe which includes Strings preparation, welding etc. for 2 nos of HDPE duct (1 Nos of OFC inside 1 HDPE duct and other duct will be in spare) in required length, all consumables, equipments, manpower and other 0.00 0 0.00
resources, and acquiring the required land for site preparations as per the provisions of the Contractor document, Preparation of detailed construction method statement and execution of, but not limited to, the following works in accordance with specifications, drawings and as per provisions of the Contract document and instructions of the Owner/Consultant; Work for pipeline which includes Strings preparation, pipeline laying/installation with casing welding, NDT of welds and rebevelled areas, radiography, weld repair and retesting, pretesting of complete string, corrosion coating of field joints with DIRAX or equivalent, inspection of corrosion coating and repair of defects 0.00 0 0.00
Pre-construction surveys and collection of all necessary data, Installation of pipeline and CS conduit/optical fibre cable conduit by horizontal directional drilling to the correct profile or below the river bed / crossing i.e. minimum 5.0 m below calculated scour level between the banks or Minimum Cover 1.5 M to 5.0 M in place of cased crossing as per approved drawings and specification. Separate CS conduit, Pulling / Blowing optical fibre cable in interduct of flexible HDPE Duct in the conduit mentioned above, Post- 0.00 0 0.00
installation, Cleaning, Gauging, Pre and Post Hydrotest including leaks and repair of defects and reseting, coating check, etc. for defects attributed to Contractor's faulty work. Supply, fabrication and construction of protective fencing as required, Supply, fabrication and erection of pipeline markers, bentonite disposal, Restoration and clean-up etc., Preparation of as built drawings and other records etc.; All other works not specifically listed herein, but required as per specifications, drawings, provision of contract document, calculations, and construction method statements , leading to successful completion of works. 0.00 0 0.00
8.1 Horizontal Directional Drilling to the correct profile or below the river bed crossing etc. wherever the minimum 5.0 m below calculated scour level between the banks as per approved drawings and specification. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness in mm Line Pipe Grade 0.00 0 0.00
Note: 1. Rates quoted shall be applicable for multiple crossings at different locations i.e. all over Gujarat & shall be paid in Running Meter. 2. Contractor shall be paid based on distance between tie-in points at two ends of crossing and not between points at entry and exit of HDD 3. No separate payment shall be paid to the contractor for Receiving and taking over of owner supplied free issue externally and internally coated line pipes of all sizes, type and wall thickness from owner's designated point of issue. 4. Contractor shall not be entitled for any extra payment for any extra depth beside the above necessitated due to location/ area constraint, capacity of rig etc. 5.Bidder shall not be paid for HDD work of above item no.: 8.1.1 to 8.1.3 without prior written approval from Owner in place of cased Crossing or any change in methodology. 6. 1 nos of separate 6" NB size, 6.4 mm, API 5L Gr. B CS conduit pipe shall be installed which includes Strings preparation, welding etc. for 2 nos of HDPE duct (1 Nos of OFC inside 1 HDPE duct and other duct will be in spare) in required length. 0.00 0 0.00
8.2 Horizontal Directional Drilling to the correct profile or below the crossing in place of cased crossing etc. wherever the minimum Covered 1.5 m to 5.0 M in between the ROU width as per approved drawings and specification with prior approval from Owner. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness in mm Line Pipe Grade 0.00 0 0.00
Note: 1. Rates quoted shall be applicable for multiple crossings at different locations i.e. all over Gujarat 2. Contractor shall be paid based on distance between tie-in points at two ends of crossing and not between points at entry and exit of HDD 3. No separate payment shall be paid to the contractor for Receiving and taking over of owner supplied free issue externally and internally coated line pipes of all sizes, type and wall thickness from owner's designated point of issue. 4. Contractor shall not be entitled for any extra payment for any extra depth beside the above necessitated due to location/ area constraint, capacity of rig etc. 5.Bidder shall not be paid for HDD work of above item no.: 8.2.1 to 8.2.3 without prior written approval from Owner in place of cased Crossing or any change in methodology. 6. 1 nos of separate 6" NB size, 6.4 mm, API 5L Gr. B CS conduit pipe shall be installed which includes Strings preparation, welding etc. for 2 nos of HDPE duct (1 Nos of OFC inside 1 HDPE duct and other duct will be in spare) in required length. 0.00 0 0.00
9.0 PERMANENT MARKERS 0.00 0 0.00
Supply, transportation, fabrication and installation of following types of permanent markers along the route including all associated civil works such as excavation in all types of soil, construction of pedestals and grouting with concrete, clearing, supply and application of approved colour and quality of primer and paint, stencil letter cutting for numbers, direction, Chainage, etc., restoration of area to original condition and performing all works as per drawings, specifications 0.00 0 0.00
and instructions of Owner / Consultant Note: The painting of all markers shall conform to the painting Specification, Standard Drawing irrespective of whatever shown on respective standards 0.00 0 0.00
9.2 Pipeline Warning Signs NOS 1 16,500.00 16,500.00 18% 2970.00 19470.00
9.3 Right of use Boundary Markers NOS 1 4,400.00 4,400.00 18% 792.00 5192.00
Note: 1. The painting of all markers shall conform to highly Marine/ Coastal environment for above ground piping and equipments (Above Ground) of spec. irrespective of whatever shown on respective Standards. 2. All Exterior paints indicating for the required service conditions. 3. Primer and finish coats shall be of Class-I quality and shall conform to paint system C5.08 in accordance with Table C.5 of ISO 12944-5. 0.00 0 0.00
10.0 LEAKS/BURSTS (ATTRIBUTABLE TO OWNER) 0.00 0 0.00
10.1 MAJOR LEAK (DETECTED BY VISUAL METHOD): 0.00 0 0.00
All works for locating major leak/burst (occurred during PRE,POST OR MAINLINE hydrostatic testing) including necessary repairing/replacing defective pipe length, including cutting and removing out defective pipes, pretesting of replacement pipe and welding into mainline, NDT of welds and re-bevelled area, repair and re-testing of defective welds, coating of welded joints, clean-up, retesting the pipeline including providing all necessary equipments, 0.00 0 0.00
labour, materials, consumables and inputs other than Owner supplied materials and performing all works as per drawings, specifications enclosed with the Contract and directions of Owner / Consultant. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
Note : This rate is applicable for manufacturing defects in Owner supplied material only 0.00 0 0.00
10.2 MINOR LEAK (DETECTED BY SECTIONALISING): 0.00 0 0.00
All works for locating leak by sectionalising or any other methods which cannot be located by visual means, including necessary repairing/replacing defective pipe length, including cutting and removing out defective pipes, pretesting of replacement pipe and welding into mainline, NDT of welds and re-bevelled area, repair and re-testing of defective welds, coating of welded joints, clean-up, retesting the pipeline including providing all necessary 0.00 0 0.00
equipments, labour, materials, consumables and inputs other than Owner supplied materials and performing all works as per drawings, specifications enclosed with the Contract and directions of Owner / Consultant. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
Note : This rate is applicable for manufacturing defects in Owner supplied material only 0.00 0 0.00
10.3 LEAKS/ BURSTS (ATTRIBUTABLE TO OWNER FOR TERMINAL PIPING FREE ISSUED MATERIALS) 0.00 0 0.00
All works for leak/burst (occurring during hydrostatic testing) including necessary repair/replacement of defective pipe length or any other items supplied by Owner including cutting and removing out defective, welding, NDT of welds, repair and re-testing of defective welds, painting of welded joints, clean-up, re hydro testing of the pipe segment including providing all necessary equipments, labour, materials, consumables and inputs other than 0.00 0 0.00
Owner supplied materials and performing all works as per drawings, specifications enclosed with the Contract and directions of Owner / Consultant. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
10.3.1 6" NB ( 168.3) All Wall Thickness API 5L X 52, PSL-2 / LTCS Materials NOS 1 11,000.00 11,000.00 18% 1980.00 12980.00
10.3.2 8" NB ( 219.1) All Wall Thickness API 5L X 52, PSL-2 / LTCS Materials NOS 1 11,000.00 11,000.00 18% 1980.00 12980.00
10.3.3 12" NB ( 323.9) All Wall Thickness API 5L X 65, PSL-2 / LTCS Materials NOS 1 11,000.00 11,000.00 18% 1980.00 12980.00
Note : This rate shall be applicable for manufacturing defects in Owner supplied materials only . 0.00 0 0.00
11.0 INDUCTION / LONG RADIUS (R=3D and 6D) BENDS: 0.00 0 0.00
Supply, transportation, and Fabrication of Long Radius (R=3D and 6D) Bends as defined in scope of work and technical specifications of bid documents. 0.00 0 0.00
Note : 1 : The rates are supply of seamless pipes with required testing. 2. Surface preparation and coating of Long radius bend by field joint coating after manufacturing bend shall included in above rate. 3. The rates are included with all testing as per bid documents including Procedure Qualification Test and transportation of bend at site. 0.00 0 0.00
11.1 3D INDUCTION / LR BENDS 0.00 0 0.00
11.1.1 ANGLE OF 15 TO 30 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.1.2 ANGLE OF 31 TO 45 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.1.3 ANGLE OF 46 TO 60 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.1.4 ANGLE OF 60 TO 90 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.2 6D INDUCTION / LR BENDS 0.00 0 0.00
11.2.1 ANGLE OF 15 TO 30 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.2.2 ANGLE OF 31 TO 45 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.2.3 ANGLE OF 46 TO 60 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
11.2.4 ANGLE OF 60 TO 90 DEGREE. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness to be used for fabricating of Bend in mm Min. wall Thickness after fabricating of Bend in mm Line Pipe Grade, Seamless 0.00 0 0.00
12 MAGNETIC CLEANING 0.00 0 0.00
12.1 MAGNETIC CLEANING OF PIPELINE 0.00 0 0.00
Mobilization/demobilization of magnet pigs with tools, tackles, consumables, accessories and personnel by contractor at work site including but not limited to magnet pigs and pig tracking device, temporary launcher and receiver as per specification and other provision of the bid document including supply of material, equipment, manpower, etc. as required material, equipment, manpower, etc. as required for magnet cleaning. Running of adequate no of magnet pigs for pipeline including pig tracking for each segment, preparation of site report as per specification and provisions of bid documents. 0.00 0 0.00
NOTE: Bidder should considere the rate for MOB and DEMOB in SOR Item No.: 12.1.1 to 12.1.3 for Magnet pigging. No separate rate shall be paid for MOB and DEMOB for Magnetic pigging activities. 0.00 0 0.00
13.0 DRYING, PRE-COMMISSIONING AND COMMISSIONING ASSISTANCE 0.00 0 0.00
Drying at Dew point temperature, Pre-commissioning activities and pre-commissioning checks to the specified acceptance criteria, making the entire pipeline system ready for commissioning, providing assistance during the complete duration of Drying, Pre Commissioning including supply of all equipment, man- power, consumables (including pigs and required quantity of nitrogen for pipeline commissioning and valve operations) materials for all temporary works and performing all associated works, complete as per the relevant specifications, other provisions of Contract document and instructions of Owner / Consultant. 0.00 0 0.00
13.1 DRYING OF PIPELINE 0.00 0 0.00
13.1.1 Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
13.2 PRECOMMISSIONING ( Pre - commissioning Check and Activities) 0.00 0 0.00
13.2.1 Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
13.3 COMMISSIONING ASSISTANCE (Applicable if pigging is involved ) 0.00 0 0.00
13.3.1 Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
14.0 OVERALL COMMISSIONING OF ENTIRE PIPELINE SYSTEM 0.00 0 0.00
Overall commissioning including system checks, inertisation and charging of entire pipeline system including stations and all associated facilities including but not limited to the following: Notifying the Owner that the pipeline system is ready for commissioning; Review of status jointly with the Company and obtaining final clearance for start of commissioning; Development and submission of commissioning procedures including detailed calculations for lengths, obtaining Owner approval, 0.00 0 0.00
carrying out overall commissioning of the total pipeline system including all facilities and all necessary co-ordination/ liaison with other Contractor(s) / OEM / Owner Project and O & M team / Consultant; Carrying out commissioning; Supply of all equipment like Nitrogen vapourisers, along with all piping and instruments, temporary venting/ flaring facilities, man- power, consumables including pigs and required quantity of Nitrogen; Performing all associated works, complete as per applicable specification, other provisions of Contract document and instructions of Owner / Consultant. 0.00 0 0.00
Size in in Inch ( mm) Wall Thickness in mm Materials Specification / Grade 0.00 0 0.00
15.0 REPAIR OF DEFECTS IN PIPE COATING ( ATTRIBUTABLE TO OWNER) 0.00 0 0.00
15.1 Repair of line Pipe Coating. 0.00 0 0.00
15.1.1 Supply of all coating repair materials as per the requirements of the relevant specifications, supply of all consumables, utilities, equipment, and all manpower required, pipe cleaning and surface preparation, repairing of coating defects (resulting in holiday in coating) and testing including all handling, transportation, etc. for line pipes, performing all works necessary for the completion of the works strictly in accordance with the relevant specifications and instructions of OWNER, recorded at the time of taking-over by CONTRACTOR at all places of work. 0.00 0 0.00
15.1.1.1 Repair of Holidays in Coating NOS 1 715.00 715.00 18% 128.70 843.70
15.1.1.2 Repair of Cosmetic Defects in Coating: Description of same as in “15.1.1.” above, but for repair of cosmetic defects in coating. SQ M 1 770.00 770.00 18% 138.60 908.60
Note : 1.Rates for repairing of defects in line pipe identified and recorded at the time of receiving & taking over i.e. defects attributable to Owner shall be paid. 2. Bidder should refer attached ANNEXURE – VII: CRITERIA FOR REPAIR OF LINE PIPE COATING AT OWNER’S STORAGE along with OVERALL SCOPE OF WORK FOR CONTRACTOR OF PIPELINE & ASSOCIATED FACILITIES 0.00 0 0.00
15.2 Repair of Defects in Line pipe 0.00 0 0.00
15.2.1 Repair of OWNER supplied pipes of all wall thicknesses, recorded at the time of taking-over by CONTRACTOR at all places of work 0.00 0 0.00
15.2.1.1 Cutting and rebevelling NOS 1 935.00 935.00 18% 168.30 1103.30
Note : Rates for repairing of defects in line pipe identified and recorded at the time of receiving & taking over i.e. defects attributable to Owner shall be paid. 0.00 0 0.00
16.0 HOOK UP FROM EXISTING UNDER GROUND PIPLINE OR IDLE TIME PRESERVATION 0.00 0 0.00
16.0 Nitrogen purging for hook up with existing pipeline ( before and after the cutting of exisitng pipeline and welding of new branch). Preservation, if required, of complete pipeline including station sections, associated facilities and terminal facilities (installed by contractor) and its maintenance by filling and pressurizing with nitrogen to a positive pressure of Min. 2 bar(g). Supply and maintenance of nitrogen at required pressure, including supply of all consumables, nitrogen, all equipment, manpower, etc., complete as per requirement of specifications, other provisions of contract document and instruction of Owner / Consultant. Cu. Mtrs 1 160.00 160.00 18% 28.80 188.80
NOTE : Bidder shall be paid only, in case of Hookup with Existing Under Ground line wher tee or flow tee or HOT tap will be done by cutting of existing pipeline. Hook up with existing above ground / under ground Tap Off Point within station for new connectivity shall not be paid under this line item and the same shall be considered in appropiate line item of Station Mechanical and associated SOR. 0.00 0 0.00
17 INTELLIGENT PIGGING INCLUDING XYZ MAPPING as defined in scope of work and specification of bid document 0.00 0 0.00
Mobilization/demobilization of Required pigs with tools, tackles, consumables, accessories and personnel by contractor at work site including but not limited to ILI and XYZ tool and pig tracking device, temporary or parment launcher and receiver as per specification and other provision of the bid document including supply of material, equipment, manpower, etc. as required material, equipment, manpower, etc. as required for ILI and XYZ Mapping. Running of different type and adequate no of pigs for pipeline including pig tracking for each segment, preparation of site report as per specification and provisions of bid documents. 0.00 0 0.00
NOTE: Bidder should considere the rate for MOB and DEMOB in SOR Item No.: 17.1 to 17.3 for ILI pigging. No separate rate shall be paid for MOB and DEMOB for ILI and XYZ Mapping pigging activities.
Total of Pipeline Laying and associated work in schedule A (In Rs.) 6,576,810.00 1,183,825.80 7,760,635.80
1 The rates are in INR excluding GST. GST shall be payable extra at actual.
2 The quantity indicated above are Tentative.
3 All Above works shall be executed in accordance with SCOPE OF WORK, Technical Specification , Data Sheets, QAP, Drawings and other provision of bid documents and instruction of Owner/ Owner's Representative.
4 Bidder to confirm full complience to spec. Deviations are not allowed and shall make liable for rejection
5 Item/Service mentioned in Clause No./Serial No. 5.0, 6.0, and 8.0 shall be settled sperately and shall not be inculded in Clause no./Serial No. 1.0
6 The above total prices shall be inclusive of all TPI, packing, forwarding, handling, storage, stacking, Transportation, spares , special tools , tackles,loading and unloading charges up to final destination site but does not include taxes
7 All the items required to complete the work shall be the scope of supply of contractor only.
8 Rate of laying of OFC & conduit shall be quoted in relevant Schedule of Rates (SOR) of Instrumentation Works, hence not to be included in Pipeline Laying works.
9 This work is exclusive of all works associated with main pipeline only.
10 All other works pertaining to Station Mechanical, Station Architecture/civil/Structural/Electrical & TCP/Instrumentation works shall be as per rates indicated elsewhere in the tender document.
11 Work is inclusive of receiving, transporting, taking over, loading & unloading, storage of company supplied material and return of surplus material to Company's designated stockyard/store.
12 Prices quoted shall include the following
a) a) All handling , transportation including marine transportation( if applicable) , liason , port fee, ware house , handling , all fees customs duty etc.
b) b) All design , engineering, supply, installation, tech support and guarantee
13 Owner supplied Material as per Scope Of Work for OVERALL SCOPE OF WORK FOR CONTRACTOR OF PIPELINE & ASSOCIATED FACILITIES are free issued supply by Owner. However, Transportation, Erection, Installation and integration of these free issue materials is in Contractor's scope. Receiving, taking over, transporting, loading & unloading, storage of company supplied material Free issue Materials from Owner's storage to Site is in Contractor's Scope.
14 Preparation of all As-Built drawings will be in contractor's scope.
Annexure-C Unit Base Rate/ SCHEDULE OF RATES (Tender no.: GTL/PROC/2026/08/O/502; (n)Procure Tender ID: 340579)
HIRING OF CONTRACTOR FOR CUSTOMER CONNECTIVITY PIPELINE PROJECTS ACROSS GUJARAT
STATION MECHANICAL AND ASSOCIATED WORKS
DOCUMENT NO.: GTL-ARC-DOC-SOR-060-04-01
Rev 0 dated 06.07.2026
S. No. Description of Items Unit Quantity HSN/SAC Unit Rate Total Basic Amount GST Total Amount with GST
(Basic) % Amount
A B C D E F G = D x F H I J = G + I
1.0 SUPPLY AND TRANSPORTATION OF PIPING MATERIALS / ITEMS AS PER SPECIFICATION, QUALITY ASSURANCE PLAN AND DATA SHEET ENCLOSED WITH THE TENDER
1.1 LOW TEMPERATURE CARBON STEEL PIPES
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.3 UNEQUAL / REDUCING TEE 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.8 WNRF FLANGE 0.00 0.00 0.00
Size in in Inch Rating /Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.9 BLIND FLANGE 0.00 0.00 0.00
Size in in Inch Rating /Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.10 SPECTACLE FLANGE 0.00 0.00 0.00
Size in in Inch Rating /Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.11 CONCENTRIC REDUCER 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.12.1 12 600# / Connecting Pipe Thickness ASTM A 694 WPHY 65 / ASTM A860 WPHY 65 / ASTM A 420 WPL 6 NOS 1 23,100.00 23,100.00 18% 4,158.00 27,258.00
1.12.2 10 600# / Connecting Pipe Thickness ASTM A 694 WPHY 52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 17,325.00 17,325.00 18% 3,118.50 20,443.50
1.12.3 8 600# / Connecting Pipe Thickness ASTM A 694 Gr.F52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 10,725.00 10,725.00 18% 1,930.50 12,655.50
1.12.4 6 600# / Connecting Pipe Thickness ASTM A 694 Gr.F52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 6,600.00 6,600.00 18% 1,188.00 7,788.00
1.12.5 3 600# / Connecting Pipe Thickness ASTM A 694 Gr.F52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 2,585.00 2,585.00 18% 465.30 3,050.30
1.12.6 2 600# / Connecting Pipe Thickness ASTM A 694 Gr.F52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 2,145.00 2,145.00 18% 386.10 2,531.10
1.12.7 6 300# / Connecting Pipe Thickness ASTM A 694 Gr.F52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 6,600.00 6,600.00 18% 1,188.00 7,788.00
1.12.8 4 300# / Connecting Pipe Thickness ASTM A 694 Gr.F52 / ASTM A860 WPHY 52 / ASTM A 420 WPL 6 NOS 1 2,805.00 2,805.00 18% 504.90 3,309.90
1.13 TRANSITION PIECE ( Min. 1 MTR LENGTH) 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.13.1 24 Sch 80 / As per Matching Pipe / items ASTM A 694 WPHY 65 / ASTM A860 WPHY 65 / ASTM A 420 WPL 6 NOS 1 264,000.00 264,000.00 18% 47,520.00 311,520.00
1.13.2 18 Sch 80 / As per Matching Pipe / items ASTM A 694 WPHY 65 / ASTM A860 WPHY 65 / ASTM A 420 WPL 6 NOS 1 214,500.00 214,500.00 18% 38,610.00 253,110.00
1.13.3 12 Sch 80 / As per Matching Pipe / items ASTM A 694 Gr.F65 SEAMLESS NOS 1 192,500.00 192,500.00 18% 34,650.00 227,150.00
1.13.4 10 Sch 80 / As per Matching Pipe / items ASTM A 694 Gr.F52 SEAMLESS NOS 1 154,000.00 154,000.00 18% 27,720.00 181,720.00
1.13.5 8 Sch 80 / As per Matching Pipe / items ASTM A 694 Gr.F52 SEAMLESS NOS 1 148,500.00 148,500.00 18% 26,730.00 175,230.00
1.13.6 6 Sch 80 / As per Matching Pipe / items ASTM A 694 Gr.F52 SEAMLESS NOS 1 137,808.00 137,808.00 18% 24,805.44 162,613.44
1.14 WELDED TYPE RAIN CAP (FLAPPER BRASS TYPE) FOR VENT 0.00 0.00 0.00
Size in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
1.14.1 1 Sch 160 / As per Matching Pipe / items BRASS NOS 1 1,650.00 1,650.00 18% 297.00 1,947.00
1.14.2 2 Sch 160 / As per Matching Pipe / items BRASS NOS 1 1,650.00 1,650.00 18% 297.00 1,947.00
1.14.3 3 Sch 80/ As per Matching Pipe / items BRASS NOS 1 2,200.00 2,200.00 18% 396.00 2,596.00
1.14.4 4 Sch 80/ As per Matching Pipe / items BRASS NOS 1 2,338.00 2,338.00 18% 420.84 2,758.84
1.14.5 6 Sch 80/ As per Matching Pipe / items BRASS NOS 1 5,500.00 5,500.00 18% 990.00 6,490.00
1.14.6 8 Sch 80/ As per Matching Pipe / items BRASS NOS 1 8,938.00 8,938.00 18% 1,608.84 10,546.84
2.0 PIPING (ABOVE GROUND): FABRICATION, ERECTION, INSTALLATION AND TESTING OF PIPING: 0.00 0.00 0.00
Receiving of all Owner supplied materials from Owner's designated place(s) of issue, transportation including loading, unloading, handling from Owner's designated place(s) of issue to Contractor's own stock yard(s)/ worksite(s) /work shop(s) including arranging all necessary intermediate storage area(s) thereof, as required; supply and Transportation of all materials (except those specified subsequently in SOR), equipment, consumables as defined in Contractor's scope of supply including studs & nuts & gaskets, their transportation to the work site(s); performing all 0.00 0.00 0.00
Above ground/buried piping fabrication works including cutting, edge preparation (inclusive of grinding the edges of pipes, fittings flanges etc. to match with the matching edges of uneven/ different thickness wherever required), fit up, pre-heating wherever required, welding, threading etc.; erection of pipes of all types and thickness over sleepers at all elevations; hook-up to all sizes, all types of inline and online instruments such as pressure safety valves(other than those covered separately), fittings of all sizes i.e. flow tees, insulating joints, LR bends, pig signallers, elbows, 0.00 0.00 0.00
reducers, tees, 'o' lets, flanges, blind flanges, spectacle blinds, tappings for pressure gauges, thermowells, hoses and hose couplings of all sizes, if applicable, sample connections, flame arrestors as applicable , vents and drains required for process and hydrotesting purposes etc. including fixing of all types of gaskets, bolts, studs and nuts of all sizes; carrying out non-destructive testing (excluding radiography covered subsequently in item of 0.00 0.00 0.00
SOR) such as Ultrasonic testing , magnetic particle/ liquid penetration, Hardness Testing etc. as required; hook up with existing piping/pipeline installed by others as per drawings wherever required; and Hard Baricadding to make seperation of existing process area cleaning and flushing by water/compressed air, carrying out hydrostatic test, pneumatic test, valve functional test and any other type of testing as specified, de-pressurising, card board blasting, dewatering, drying by compressed air; cutting/ rebevelling (as required), pre-commissioning and providing commissioning assistance to commissioning Contractor/Agency for process piping and 0.00 0.00 0.00
commissioning of non- process piping if applicable; clean up-and restoration of site, preparation of as built drawings, documents and project records; transportation of surplus free issue materials to Owner's designated places; completing all works in all respects as per the AFC drawings, specifications, standards, and other provisions of Contract and instruction of OWNER / Consultant. 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
Note:- 1. Installation of items such as valves, Pig Trap, equipments will be paid separately as per rates covered elsewhere. 2. Supply and installation of studs & Bolts with washer and Gaskets shall be included in above rates. No seperate rates shall be paid for such items. 3. Bidder should also inculde the cost of supply & application of rust prevent material i.e moly coat on studs and bolts. 0.00 0.00 0.00
3.0 Performance of radiographic inspection of piping of all types, sizes, thickness including providing or hiring of all necessary equipment, supply of all consumables including radiographic films and whatever else even though not expressly mentioned but required to perform the work as per specification and instructions of Owner / Consultant 0.00 0.00 0.00
Size in in Inch Schedule / Wall Thickness in mm Materials Specification / Grade 0.00 0.00 0.00
4.0 INSTALLATION OF VALVES 0.00 0.00 0.00
Receiving and taking over of all Owner supplied materials, equipments from Owner's designated place(s) of issue, transportation including loading, unloading, handling from Owner's designated place(s) of issue to Contractor's own stock yard(s)/ work site(s)/ work shop(s) including arranging all necessary intermediate storage area(s) thereof, as required; supply of all materials, equipment, consumables as defined in Contractor's scope of supply and its transportation to the work site(s);installation of valves,equipments including fixing of gaskets, bolts, studs, nuts wherever required, levelling, aligning, installation and assembly of accessories including accessories for actuators including making electrical connections for such actuators, if any, by bolting/threading or welding of pipes at all elevations, testing, completing all works in all respects as per drawings, specification, other provisions of Contract and directions of the OWNER / Consultant. 0.00 0.00 0.00
Installation / Erection of above ground / Under Ground / Flanged / Butt welded Valves (Ball/Check//Globe ) as per details given below: 0.00 0.00 0.00
Size in in Inch Rating /Schedule / End Connection Materials Specification / Grade 0.00 0.00 0.00
4.4 2 and below 150# / BW or FLG / MANUAL As per Bid NOS 1 7,150.00 7,150.00 18% 1,287.00 8,437.00
4.26 2 & below 600# / BW or FLG / MANUAL As per Bid NOS 1 3,674.00 3,674.00 18% 661.32 4,335.32
5.0 PIPE SUPPORTS 0.00 0.00 0.00
Supply Transportation of pipe support to site, fabrication and erection of pipe/ equipment supports (for all sizes/ thickness) including shoes, Guide, T-posts, Safety & Caution Board for Station for all types of guides, anchors, special supports etc. if applicable, all necessary equipment, consumables, labour etc. for completing all works including supply of Studs,bolts, nuts, washers, U-clamps, wooden blocks etc. as required for supporting, 0.00 0.00 0.00
SUPPLY, transportation to site and application of Paints and primers suitable for highly corrosive/ normal corrosive painting environment including identification, lettering/ numbering, colour coding as defined in contract document and as per standard specification for Shop and Field painting, Drawings, Specification, Standards, other provisions of Contract and instruction of Owner / Consultant. 0.00 0.00 0.00
Note : Welds, bolts, nuts, washers etc. shall not be measured. Rates for structural steel work shall be deemed to include the same 0.00 0.00 0.00
5.2 Dismantling & removing the existing installed equipment such as DG Set, Metering skid, Filter, Filteration skid, PRS skid, Pig Barrel, Pig Trolly, Jib Crane, Piping spools,electrical/ instrumentation panel, valves, structural steel etc. carefully including handling, loosing the nuts, bolt cutting etc(if required) and stacking the equipments/ material within a radius of 250 Mts. and as directed by Owner. Manpower, Machinery required, transportation is in contractor's scope. Including tranportation of dismantled equipments to owners store. 0.00 0.00 0.00
5.2.2 Item weight more than 50 Kg and upto 150 kg Item weight upto 51-150 kg Item weight upto 51-150 kg Item weight upto 51-150 kg Lumsum 1 4,400.00 4,400.00 18% 792.00 5,192.00
5.2.3 Item weight more than 150 Kg and upto 250 kg Item weight upto 151-250 kg Item weight upto 151-250 kg Item weight upto 151-250 kg Lumsum 1 7,150.00 7,150.00 18% 1,287.00 8,437.00
5.2.4 Item weight more than 250 kg and upto 500 kg Item weight upto 251-500 kg Item weight upto 251-500 kg Item weight upto 251-500 kg Lumsum 1 13,200.00 13,200.00 18% 2,376.00 15,576.00
5.2.5 Item weight more than 500 Kg and upto 1000 kg Item weight upto 501-1000 kg Item weight upto 501-1000 kg Item weight upto 501-1000 kg Lumsum 1 15,400.00 15,400.00 18% 2,772.00 18,172.00
5.2.6 Item weight more than 1 Ton and upto 2 Tonnes Item weight upto 1 Ton - 2 Tonnes Item weight upto 1 Ton - 2 Tonnes Item weight upto 1 Ton - 2 Tonnes Lumsum 1 16,500.00 16,500.00 18% 2,970.00 19,470.00
5.2.7 Item weight more than 2 Tonnes and upto 3 Tonnes Item weight upto 2-Tonnes- 3 Tonnes Item weight upto 2-Tonnes- 3 Tonnes Item weight upto 2-Tonnes- 3 Tonnes Lumsum 1 17,050.00 17,050.00 18% 3,069.00 20,119.00
Supply of paints, solvents and primers, preparation of surfaces and application of primer and finish paints suitable for highly corrosive painting environment as defined in contract document and on pipes as per standard specification for field and shop painting , identification, lettering/ numbering, colour coding etc. as specified 0.00 0.00 0.00
including rub down and touch up of shop primer or scrapping of shop primer wherever required and providing of surface prepration up to SA 2 1/2, scaffolding for all heights, labour, materials, tools and tackles, consumables, supervision etc. to complete the work in all respect as per Specification, Drawings, Standards and instruction of OWNER / Consultant. 0.00 0.00 0.00
Note: 1. The painting of all markers shall conform to highly Marine/ Coastal environment for above ground piping and equipments (Above Ground) of spec. irrespective of whatever shown on respective Standards. 2. All Exterior paints indicating for the required service conditions. 3. Primer and finish coats shall be of Class-I quality and shall conform to paint system C5.08 in accordance with Table C.5 of ISO 12944-5. 0.00 0.00 0.00
6.1 HIGHLY CORROSIVE PAINTING ENVIRONMENT 0.00 0.00 0.00
6.1.1 Painting of all above ground piping including all fittings, valves, Insulating Joint, flanges etc. including colour bands and line marking / stenciling with Surface preparation 0.00 0.00 0.00
6.2 HIGHLY CORROSIVE PAINTING ENVIRONMENT 0.00 0.00 0.00
6.2.1 Painting of all above ground piping including all fittings, valves, Insulating Joint, flanges etc. including colour bands and line marking / stenciling with Surface preparation 0.00 0.00 0.00
6.2.1.3 For Cold Tap (including 50% overlapping) 0.00 0.00 0.00
7.0 SCRAPER TRAP,QOEC, JIB CRANE, PIG HANDLING SYSTEM 0.00 0.00 0.00
Design, engineering, manufacturing, procurement of materials and bought out components, Fabrication, assembly at shop, inspection, testing at manufacturer's works, supply, packing, transportation, delivery of the following, including supply of all commissioning spares & special tools and tackles and documentation as per enclosed general notes, standard specifications, addendums, instruction to bidders / suppliers, data sheets, drawings etc. and other codes and standards attached with bid. 0.00 0.00 0.00
Size in in Inch (mm) Wall Thickness for Minor Barrel in mm Wall Thickness for Major Barrel in mm Materials Specification / Grade 0.00 0.00 0.00
Note : 1. Rate of PIG SIGNALLER (INTRUSIVE AND NON INTRUSIVE TYPE) for engineeing, Designing, supply, Transportation, Installation / Erection, testing and commissioning shall be quoted in relevant Schedule of Rates (SOR) of Instrumentation Works, hence not to be included in Station Mechanical works. 2. Wall thickness shall be finalised based on Calculation with Corrosion allowance 3 mm and design factor - 0.5 ( for location class 1,2 & 3). 0.00 0.00 0.00
8.0 ERECTION OF MECHANICAL EQUIPMENT 0.00 0.00 0.00
Erection of Equipment with assemblies placing the equipment on foundations, levelling, aligning, fixing of foundation bolts including chipping and dressing of foundations grouting (incluing supply and applications of grout material), drying with compressed air, erection of inter- connecting piping whereever required. Purging the line with NITROGEN providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of Owner / Consultant for each equipmen including accessories. 0.00 0.00 0.00
Contractor Shall engage independent HAZOP Chairman/ Agency for HAZOP study of all As-built P&ID of connectivity / project in consultation with PMC/Owner. Note : Cost/expense for HAZOP study shall included for appointment of HAZOP Agency/chairman’s fees, documentation, Travelling, boarding, lodging, administration of the HAZOP study and miscellaneous expense including preparation & submission of HAZOP report.
Total of Station Mechanical and associated work in schedule B (In Rs.) 14,175,913.00 2,551,664.34 16,727,577.34
1. The rates are in INR excluding GST. GST shall be payable extra at actual.
2. The quantity indicated above are Tentative.
3. All Above works shall be executed in accordance with SCOPE OF WORK, Technical Specification ,Data Sheets, QAP, Drawings and other provision of bid documents and instruction of Owner/ Owner's Representative.
4. Cost mentoined for alll the item supply will be inclusive of transportation cost. No extra cost shall be paid for transporation.
5. Bidder to confirm full complience to spec. Deviations are not allowed and shall make liable for rejection
6. The above total prices shall be inclusive of all TPI, packing, forwarding, handling, storage, stacking, Transportation, spares , special tools , tackles,loading and unloading charges up to final destination site but does not include taxes
7. All the items required to complete the work shall be the scope of supply of contractor only.
8. Rate of pig signaller (Intrusive and Non Intrusive type) shall be quoted in relevant Schedule of Rates (SOR) of Instrumentation Works, hence not to be included in Station Mechanical works.
9. This work is exclusive of all works associated with Station Mechanical only.
10. All other works pertaining to pipeline, Station Architecture/civil/Structural/Electrical & TCP/Instrumentation works shall be as per rates indicated elsewhere in the tender document.
11. Work is inclusive of receiving, Transporting, taking over, loading & unloading, storage of company supplied material and return of surplus material to Company's designated stockyard/store.
12. Prices quoted shall include the following
a) All handling , transportation including marine transportation( if applicable) , liason , port fee, ware house , handling , all fees customs duty etc.
b) All design , engineering, supply, installation,, tech support and guarantee
13. Owner supplied Material as per Scope Of Work for OVERALL SCOPE OF WORK FOR CONTRACTOR OF PIPELINE & ASSOCIATED FACILITIES are free issued supply by Owner. However, Transportation, Erection, Installation and integration of these free issue materials is in Contractor's scope. Receiving, taking over, transporting, loading & unloading, storage of company supplied material Free issue Materials from Owner's storage to Site is in Contractor's Scope including reconciliation & transportation of surplus material, removed material, spares to owner’s designated store from site. Storage of materials including preservation as required as per suppliers/manufacturer’s recommendation and loading, unloading & transportation from Owner store (Refer Annexure – IV) to work site is included in the scope of Contractor.
14. Preparation of all As-Built drawings shall be in contractor's scope.
Annexure-C Unit Base Rate/ SCHEDULE OF RATES (Tender no.: GTL/PROC/2026/08/O/502; (n)Procure Tender ID: 340579)
HIRING OF CONTRACTOR FOR CUSTOMER CONNECTIVITY PIPELINE PROJECTS ACROSS GUJARAT
CIVIL AND ASSOCIATED WORKS
DOCUMENT NO.: GTL-ARC-DOC-SOR-060-04-01
Rev. -0 Dated 06.07.2026 JCS
S. No. Description of Items Unit Quantity HSN/SAC Unit Rate Total Basic Amount GST Total Amount with GST
(Basic) % Amount
A B C D E F G = D x F H I J = G + I
1 C CIVIL , STRUCTURAL & ARCHITECTURAL
2 C.1 SURVEY WORK
3 C.1.1 Conducting topographical ground/land survey in the specified area as shown in the tender drawings by conventional/GPS or any other standard method, covering details of physical features like Rivers, Nallahs, Lakes, Ponds, wells, pits, Forest, Trees, Roads, culverts, transmission lines, telegraph/ telephone and electric poles, underground or any other services, cross drainage works including cross sectional details of nallah etc. including establishing high flood level with source of information, identification of any monument, historical structure, wild life sanctuary in the vicinity, storm water disposal point with levels, cross-section details of nallah, recording spot levels, including providing in tabulation girth wise no. of trees etc as specified, plotting and developing topographical contour maps, showing true north including establishing survey reference stations, key plan etc. including all equipment's, instruments, personnel's, clearing of bushes as per requirement for intervisibility to carry out survey work etc. , complete work in all respects as per drawings, specifications and directions of Engineer-in-Charge including submitting hard copies of drawings/map and supply of electronic files. Note: Survey work shall be carried out by survey agency approved by Contractor and shall be submitted to PMC for review. SQ.M 1 22.00 22.00 18% 3.96 25.96 0.00
4 C.2 GEO TECHNICAL INVESTIGATION (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
5 C.2.1 Conducting soil investigation with boring including all field tests and laboratory tests, mobilization and demobilization of equipments & personnel etc. for soil investigation for each borehole location . complete work in all respects as per drawings, specifications and directions of Engineer-in-Charge including submitting hard copies of Reports & recommendations and supply of electronic files. 0.00 0.00 0.00
8 C.3 SITE GRADING & ROCK CUTTING FOR SITE GRADING (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
9 C.3.1 Cutting down trees having a girth above 30cms and upto and including of 120 cms (girth measured at a height of one metre above ground level) including cutting of trunk and branches, digging and grubbing of roots upto all depth below ground level, filling the hollows produced by removal of roots with approved available earth for all leads and lifts, watering, ramming and compacting the filled earth to obtain 95% of maximum laboratory dry density, disposing the unserviceable materials beyond plant boundary at suitable location to be decided by the Contractor and stacking the serviceable materials within plant boundary etc. complete as per specifications and directions of Engineer-in-Charge. SQ.M 1 118.00 118.00 18% 21.24 139.24 0.00
10 C.4 EARTHWORK EXCAVATION IN SOIL (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
11 C.4.1 Earth work in EXCAVATION below ground level for all kinds of works in ALL TYPES OF SOILS EXCEPT SOFT ROCK AND HARD ROCK as classified in specification for a depth upto 1.5m including removal of vegetation, shrubs and debris, cutting and dressing of sides in slopes, levelling, grading and ramming of bottoms, dewatering of accumulated water from any source and keeping the surface dry for subsequent works and disposal or stacking of excavated material WITHIN A LEAD OF 100M, as directed including providing temporary supports to existing service lines like water pipes, sewage pipes, electric overhead and underground cables etc. all complete, but excluding shoring and strutting.Quoted rate includes removal of gravel filling along with HDPE sheet, paver block and other misc. items in the existing process area. CUM 1 226.00 226.00 18% 40.68 266.68 0.00
12 C.4.2 Earth work in EXCAVATION below ground level for all kinds of works in ALL TYPES OF SOILS EXCEPT SOFT ROCK AND HARD ROCK as classified in specification for a depth beyond 1.5m and upto and inclusive of 3.0m including Removal of vegetation, shrubs and debris, cutting and dressing of sides in slopes, levelling, grading and ramming of bottoms, dewatering of accumulated water from any source and keeping the surface dry for subsequent works and disposal or stacking of excavated material within a lead of 100m, as directed including providing temporary supports to existing service lines like water pipes, sewage pipes, electric overhead and underground cables etc. all complete, but excluding shoring and strutting. CUM. 1 248.00 248.00 18% 44.64 292.64 0.00
13 C.5 EARTHWORK EXCAVATION IN SOFT ROCK (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
14 C.5.1 Earth work in EXCAVATION below ground level for all kinds of works in SOFT ROCK as classified in specification for a depth upto 1.5m including removal of vegetation, shrubs and debris, cutting and dressing of sides in slopes, levelling, grading and ramming of bottoms, dewatering of accumulated water from any source and keeping the surface dry for subsequent works and disposal or stacking of excavated material within a lead of 100m, as irected including providing temporary supports to existing service lines like water pipes, sewage pipes, electric overhead and underground cables etc. all complete, but excluding shoring and strutting. CUM 1 455.00 455.00 18% 81.90 536.90 0.00
15 C.6 BACKFILLING AFTER EXECUTION OF WORK (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
16 C.6.1 BACKFILLING after execution of the WORK to proper grade and level with selected materials from available excavated soil from spoil heaps ,including re- excavating the deposited soil excavated earlier, breaking clods, laying at all depths and heights in layers of thickness not exceeding 15 cms. watering, rolling and ramming by manual methods/ mechanical compactors to achieve 95% laboratory maximum dry density, dressing, trimming etc. in foundations, plinths, trenches, pits etc. all complete. Quoted rate includes backfilling of earth, gravel along with HDPE sheet, paver block and other misc. items in the existing process area and restoration at found condition. CUM 1 280.00 280.00 18% 50.40 330.40 0.00
17 C.7 TRANSPORTING & DISPOSING THE SURPLUS EARTH AND DEBRIS 0.00 0.00 0.00
18 C.7.1 Transporting and disposing the SURPLUS EARTH AND DEBRIS including shrubs and vegetations from construction areas to areas ANYWHERE OUTSIDE THE PLANT BOUNDARY, including re-excavating the deposited soil excavated earlier, loading, transportation, unloading, laying at all depths and heights, stacking,levelling and dressing both the area (viz. from where the earth is transported and where it is deposited) to required levels and slopes complete with all lifts as directed. For carting on the basis of truck measurements (volume of truck reduced by 30% for voids). DISPOSAL AREAS OUTSIDE PLANT BOUNDARY TO BE ARRANGED BY THE CONTRACTOR. Royalty as applicable for disposal outside plant limits to be borne by the Contractor. CUM 1 152.00 152.00 18% 27.36 179.36 0.00
19 C.8 EARTH WORK IN FILLING (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
20 C.8.1 EARTHWORK IN FILLING by excavating the earth from BORROW AREAS arranged by CONTRACTOR for material available at any leads, transporting the earth from borrow area including cleaning & stripping the earth at borrow areas, breaking clods, loading, unloading and laying at all depths and heights in layers of thickness not exceeding 15 cms., watering, rolling and ramming by manual methods/mechanical compactors to achieve 95% of the maximum laboratory dry density, ressing, trimming, levelling the top surface etc. in Plot filling, Filling under Approach road, etc. all complete. CUM 1 407.00 407.00 18% 73.26 480.26 0.00
21 C.9 PLAIN & REINFORCED CEMENT CONCRETE: (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
22 C.9.1 PLAIN CEMENT CONCRETE - PCC 0.00 0.00 0.00
23 C.9.1.1 Providing and laying PLAIN CEMENT CONCRETE for all depths below and upto plinth level in foundations, drains, fillings, non-suspended floors, pavements & ramps or any other works etc. including shuttering, tamping, ramming, vibrating, curing, etc. all as specified in any shape, position, thickness and finishing the top surface rough or smooth as specified and directed all complete for concrete grade M20 with 20mm and down size graded crushed stone aggregates/Gravels. ALL MATERIALS INCLUDING CEMENT SUPPLIED BY THE CONTRACTOR. CUM 1 6,959.00 6,959.00 18% 1,252.62 8,211.62 0.00
24 C.9.2 RCC (SUBSTRUCTURE- BELOW PLINTH BEAM LEVEL) - CONTROL ROOM BUILDING, GUARD ROOM & BOUNDARY WALL 0.00 0.00 0.00
25 C.9.2.1 Providing and laying REINFORCED CEMENT CONCRETE OF M-30 GRADE with 20 mm and down size graded crushed stone aggregates/ gravel in SUBSTRUCTURE INCLUDING CENTERING & SHUTTERING ) e.g. foundations, raft, pile caps, columns, etc., (including single pour concreting as specified on the drawing), applying cement wash on concrete surface (wherever no other surface application is specified), providing pockets, openings, recesses, chamfering, etc., wherever required, vibrating, tamping, curing and rendering if required to give a smooth and even surface etc. (EXCLUDING THE COST OF REINFORCEMENT) for all depths below plinth level in any shape, position and thickness etc. all complete as specified, shown and directed. ALL MATERIALS INCLUDING CEMENT SUPPLIED BY THE CONTRACTOR. CUM 1 9,460.00 9,460.00 18% 1,702.80 11,162.80 0.00
26 C.9.2.2 Providing and laying REINFORCED CEMENT CONCRETE OF M-25 GRADE with 20 mm and down size graded crushed stone aggregates/ gravel in SUBSTRUCTURE INCLUDING CENTERING & SHUTTERING ) e.g. foundations, raft, pile caps, columns, etc., (including single pour concreting as specified on the drawing), applying cement wash on concrete surface (wherever no other surface application is specified), providing pockets, openings, recesses, chamfering, etc., wherever required, vibrating, tamping, curing and rendering if required to give a smooth and even surface etc. (EXCLUDING THE COST OF REINFORCEMENT) for all depths below plinth level in any shape, position and thickness etc. all complete as specified, shown and directed. ALL MATERIALS INCLUDING CEMENT SUPPLIED BY THE CONTRACTOR. CUM 1 8,798.00 8,798.00 18% 1,583.64 10,381.64 0.00
27 C.9.3 RCC WORKS - EXCLUDING CONTROL ROOM BUILDING, GUARD ROOM & BOUNDARY WALL 0.00 0.00 0.00
28 C.9.3.1 Providing and laying REINFORCED CEMENT CONCRETE OF M-30 GRADE with 20 mm and down size graded crushed stone aggregates/ gravel in SUBSTRUCTURE & SUPERSTRUCTURE UPTO AND INCLUSIVE OF 3M ABOVE PLINTH LEVEL AND FOR ALL DEPTHS INCLUDING CENTERING & SHUTTERING ) e.g. foundations, raft, beams, pile caps, Retaining walls, counterforts, buttresses, pedestals, pipe sleepers, pipe support (in all respect), columns, U/G water tank etc., including equipment/ machine foundations & pedestals viz. metering skid, Diesel generators, etc. (including single pour concreting as specified on the drawing), applying cement wash on concrete surface (wherever no other surface application is specified), providing pockets, openings, recesses, chamfering, etc., wherever required, vibrating, tamping, curing and rendering if required to give a smooth and even surface etc. (EXCLUDING THE COST OF REINFORCEMENT) in any shape, position and thickness etc. all complete as specified, shown and directed. ALL MATERIALS INCLUDING CEMENT SUPPLIED BY THE CONTRACTOR. CUM 1 9,460.00 9,460.00 18% 1,702.80 11,162.80 0.00
29 C.9.3.2 Providing and laying REINFORCED CEMENT CONCRETE OF M-25 GRADE with 20 mm and down size graded crushed stone aggregates/ gravel in SUBSTRUCTURE & SUPERSTRUCTURE UPTO AND INCLUSIVE OF 3M ABOVE PLINTH LEVEL AND FOR ALL DEPTHS INCLUDING CENTERING & SHUTTERING ) e.g. foundations, raft, beams, pile caps, Retaining walls, counterforts, buttresses, pedestals, pipe sleepers, pipe support (in all respect), columns, U/G water tank etc., including equipment/ machine foundations & pedestals viz. generators, etc. (including single pour concreting as specified on the drawing), applying cement wash on concrete surface (wherever no other surface application is specified), providing pockets, openings, recesses, chamfering, etc., wherever required, vibrating, tamping, curing and rendering if required to give a smooth and even surface etc. (EXCLUDING THE COST OF REINFORCEMENT) in any shape, position and thickness etc. all complete as specified, shown and directed. ALL MATERIALS INCLUDING CEMENT SUPPLIED BY THE CONTRACTOR. CUM 1 8,798.00 8,798.00 18% 1,583.64 10,381.64 0.00
30 C.9.3.3 DG set foundation as per Dwg attached in bid documents and other relvant dwgs., design basis and specs including but not limited to well compacted earth, supply and filling of rubble soling, sand supply and filling as per SOR clause no. C.20.10, PCC works as per SOR clause no. C.9.1 , RCC works as per SOR Clause no. C.9.2.1, Reinforcement works as per SOR clause no. C.11. This includes associated works like RCC ramp, brick masonry works,RCC Pavement, 150 mm Dia PVC Pipes as per 4985_ Heavy Duty etc. complete in all respect as per the above referred drawing. SQ.M 1 20,350.00 20,350.00 18% 3,663.00 24,013.00 0.00
31 C.9.3.4 Metering skid foundation as per Dwg attached in bid documents and other relvant dwgs., design basis and specs including but not limited to well compacted earth, supply and filling of rubble soling, sand supply and filling as per SOR clause no. C.20.10, PCC works as per SOR clause no. C.9.1 , RCC works as per SOR Clause no. C.9.2.1, Reinforcement works as per SOR clause no. C.11. etc. complete in all respect as per the above referred drawing. SQ.M 1 20,900.00 20,900.00 18% 3,762.00 24,662.00 0.00
32 C.9.3.5 Valve pit chamber (Depth upto 1.5m) as per Dwg attached in bid documents and other relvant dwgs., design basis and specs including but not limited to well compacted earth, supply and filling of rubble soling, sand supply and filling as per SOR clause no. C.20.10, PCC works as per SOR clause no. C.9.1 , RCC works as per SOR Clause no. C.9.2.1, Reinforcement works as per SOR clause no. C.11. etc. complete in all respect as per the above referred drawing.This includes associated works like RCC walls, Pre-cast cover slab with hook, structural steel works, MS Rungs, Polysulphide sealent,casing pipe, Locking arrangement, pipe support inside chamber etc. complete in all respect as per the above referred drawing. SQ.M 1 33,000.00 33,000.00 18% 5,940.00 38,940.00 0.00
33 C.9.3.6 Valve pit chamber (Depth upto 1.5m to 3m) as per Dwg attached in bid documents and other relvant dwgs., design basis and specs including but not limited to well compacted earth, supply and filling of rubble soling, sand supply and filling as per SOR clause no. C.20.10, PCC works as per SOR clause no. C.9.1 , RCC works as per SOR Clause no. C.9.2.1, Reinforcement works as per SOR clause no. C.11. etc. complete in all respect as per the above referred drawing.This includes associated works like RCC walls, Pre-cast cover slab with hook, structural steel works, MS Rungs, Polysulphide sealent,casing pipe, Locking arrangement, pipe support inside chamber etc. complete in all respect as per the above referred drawing. SQ.M 1 34,925.00 34,925.00 18% 6,286.50 41,211.50 0.00
34 C.9.3.7 PILING WORK :- Providing and building up pile of below diameter in RCC of grade M30 with 20 mm down size graded crush stone aggregates / gravel including all shuttering but excluding the cost of reinforcement (to be measured under respective item ) all complete as directed. 0.00 0.00 0.00
40 C.9.3.8 Under Ground Water tank for ALL depth and Size as per dwgs attached in bid documents & relvant dwgs. , design basis and specs including but not limited to well compacted earth, supply and filling of rubble soling, sand supply and filling as per SOR clause no. C.20.10, PCC works as per SOR clause no. C.9.1, RCC works as per SOR Clause no. C.9.2.1, Reinforcement works as per SOR clause no. C.11. etc. complete in all respect as per the above referred drawing.This includes associated works like RCC top and bottom slabs, side walls, on all sides, glazed tiles from inside, vent pipe, inlet pipe, overflow pipe, PVC stopper, Manhole with CI Cover, Rungs, Level Switch, Corrugated GI shed, motor and self priming centrifugal pump (Capacity of 2m3/hr. for head of 20m) for pumping water to over head tank etc. complete in all respect as per the above referred drawing. SQ.M 1 23,925.00 23,925.00 18% 4,306.50 28,231.50 0.00
41 C.9.3.8.1 Constructing brick masonry Septic Tank with brickwork in cement mortar 1:6 including R.C.C. 1:2:4 (1 cement : 2 sand : 4 graded coarse aggregate) top slab, C.I. cover all as per standard drawing, etc. complete in all respects inclusive of cost of all materials, labour, tools, tackles etc. as per drawings, specifications and directions of the Engineer-in-Charge. LS 1 173,000.00 173,000.00 18% 31,140.00 204,140.00 0.00
42 C.9.3.8.2 Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with bricks and S.W. drain pipe 100 mm diameter, 1.8 m long, Brick bats of size 80 mm to 40 mm complete as per standard design/drawing. : LS 1 117,000.00 117,000.00 18% 21,060.00 138,060.00 0.00
43 C.10 CONTROL ROOM BUILDING - SUPERSTRUCTURE (INCLUDING OTHER ASSOCIATED FACILITIES) 0.00 0.00 0.00
44 C10.1 Construction of Control Room Building as per drawings, design basis and specification. Building work for all Superstructure works (excluding Staircase. Payment of staircase shall be made against individual line items like excavation, concrete,reinforcement etc. available in this SOR) INCLUDING CENTERING & SHUTTERING , Reinforcement , Beams at all levels, columns, Stub columns,slab & other structural elements, plinth protection, all ramps,AAC masonry work, all RCC trenches and its associated facilties, partition wall, Plastering & pointing, flooring, Floor finishes, Door & windows, rolling shutter, false ceiling, all internal and external finishes, painting, roof treatment, False Ceiling, False Flooring and Underdeck insulation,steps,Flooring works, painting and colouring, Anti-termite treatment, painting & Stencling of each rooms and For Parapet wall, furniture, HDPE drinking water tank, soakpit & septic tank, U/G sewerage system, Cable Pull Pit and its associated hume pipes, Plumbing & building drainage, water supply and sanitary works , RO machine,wind soak,table (1 No.),chair (4 No.), cat ladder, miscellaneous works as per relevant specs complete in all respect as per Architecture and other relvant structural drawings and specifications etc.) All the items/works shown in this architecture drawings shall be formed as part of scope. Superstructure shall be considered from bottom of plinth level beam (including cable trench) to the highest point of roof. No extra payment shall be made on account of height/extra projections of structure. FOR MODE OF MEASREUMENT REFER CIVIL SOW documents attached in bid documents 0.00 0.00 0.00
45 C10.1.1 Seismic zone V (Refer Drawings attached in bid documents) SQ.M 1 30,800.00 30,800.00 18% 5,544.00 36,344.00 0.00
46 C10.1.2 Seismic zone IV, III & II (Refer Drawings attached in bid documents) SQ.M 1 29,700.00 29,700.00 18% 5,346.00 35,046.00 0.00
47 C.10.2 GUARD ROOM - SUPERSTRUCTURE (INCLUDING OTHER ASSOCIATED FACILITIES)(Refer attached Drawing in bid documents) 0.00 0.00 0.00
48 C.10.2.1 Construction of Guard Room Building as per drawings, design basis and specification. Building work for all Superstructure works including INCLUDING CENTERING & SHUTTERING , Reinforcement , Beams at all levels, columns, slab & other structural elements, plinth protection, all ramps,AAC masonry work, partition wall, Plastering & pointing, flooring, Floor finishes, Door & windows, all internal and external finishes, painting, painting & Stencling of each rooms and For Parapet wall roof treatment, steps, Flooring works, paiting and colouring, Anti-termite treatment, furniture, miscellaneous works as per relevant specs complete in all respect as per Architecture and other relvant structural drawings and specifications etc.) All the items/works shown in this architecture drawings shall be formed as part of scope. Superstructure shall be considered from bottom of plinth level beam to the highest point of roof. No extra payment shall be made on account of height/extra projections of structure. SQ.M 1 22,330.00 22,330.00 18% 4,019.40 26,349.40 0.00
49 C.11 HYSD BARS (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
50 C.11.1 Supplying and placing in position HIGH YIELD STRENGTH DEFORMED STEEL BARS REINFORCEMENT of Grade Fe500D TMT conforming to IS:1786, for RCC work (excluding control room building & Guard room & boundary wall superstructure) including transporting the Steel, straightening, cleaning, decoiling, cutting, bending to required shapes and lengths as per details, binding with 18 SWG black soft annealed binding wire at every intersection, supplying and placing with proper cover blocks, supports, chairs, overlaps, welding, spacers, fanhooks etc. for all heights and depths etc. all complete as directed. SUPPLY OF ALL MATERIAL IN CONTRACTOR'S SCOPE MT 1 83,600.00 83,600.00 18% 15,048.00 98,648.00 0.00
51 C.11.2 Supplying and placing in position HIGH YIELD STRENGTH DEFORMED STEEL BARS REINFORCEMENT of Grade Fe 550D TMT conforming to IS:1786, for RCC work (excluding control room building & Guard room & boundary wall superstructure ) including transporting the Steel, straightening, cleaning, decoiling, cutting, bending to required shapes and lengths as per details, binding with 18 SWG black soft annealed binding wire at every intersection, supplying and placing with proper cover blocks, supports, chairs, overlaps, welding, spacers, fanhooks etc. for all heights and depths etc. all complete as directed. SUPPLY OF ALL MATERIAL IN CONTRACTOR'S SCOPE MT 1 83,600.00 83,600.00 18% 15,048.00 98,648.00 0.00
52 C.12 BOUNDARY WALL WORKS (REFER ATTACHED SPECIFICATION AND DRAWING IN BID DOCUMENTS) 0.00 0.00 0.00
53 C.12.1 Compound wall with Footings, RCC columns, beams at all level, Retaining wall, brick works at all level, coping and Brick masonry (3.0m high) including 0.6m high barbed wire & concertina coil (dia. 600mm) including earthwork in excavation in all types of soil including hard rock and soft rock, laying of PCC and RCC, overhead on ‘Y’ shape structural steel frame. SUPERSTRUCTURE & SUBSTRUCUTRE works including (reinforcement, masonry work, Plastering ,painting, CENTERING & SHUTTERING complete in all respect etc.) and supplying, fixing and tensioning in position , GI Barbed wire conforming to IS:278 in horizontal rows and cross diagonals for compound wall "Y" shaped overhang etc. with necessary GI staples, clips and pins, GI straining bolts and binding wire, expansion joints, weep holes, stone pitching outside, well compacted earth with all labour and materials etc. complete as per drawings, specifications and directions of Engineer-in-Charge.(The barbed wire shall be measured in linear length of the barbed wire actually fixed) Supplying, fabricating and fixing in position structural steel line posts, straining posts, struts for 'Y' shaped overhang etc. conforming to IS:2062 over brick/stone Masonry/ RCC compound walls/ columns, cutting to required size as per drawings and specifications, welding where necessary, embedding in position, holding to correct level and line, any auxiliary structure for dummy supports, drilling holes and painting as per painting specification attached with tender, cutting brick/rubble/concrete surfaces if necessary, grouting with M20 grade concrete including cost of grout with all labour and material, including backfilling ,disposal of surplus earth outside the station boundary for all lift and leads etc. complete as per drawings, specifications and directions of Engineer-in-Charge.( All materials including cement shall be supplied by contractor). For Meaurement in Running Metre, Centre line length of Boundary wall shall be considered. NO extra payment on account of structural projections etc. shall be considered.(Note: Rates are excluding Sand filling. If Sand filling is required shall be paid as per SOR item no. C.20.10.1) 0.00 0.00 0.00
54 C12.1.1 TYPE-A (DIFFERENCE BETWEEN FGL AND NGL IS ≤ 0.8 MTR.) RM 1 39,050.00 39,050.00 18% 7,029.00 46,079.00 0.00
55 C12.1.2 TYPE-B (DIFFERENCE BETWEEN FGL AND NGL IS > 0.8 MTR. BUT ≤ 1.3 MTR.) RM 1 44,880.00 44,880.00 18% 8,078.40 52,958.40 0.00
56 C12.1.3 TYPE-C (DIFFERENCE BETWEEN FGL AND NGL IS > 1.3 MTR. BUT ≤ 1.8 MTR.) RM 1 51,150.00 51,150.00 18% 9,207.00 60,357.00 0.00
57 C.12.2 Compound wall with Footings, RCC columns, beams at all level, RCC Retaining wall, brick works at all level, coping and Brick masonry above FGL (3.0m high) and additional 0.85m high barbed wire & concertina coil (dia. 610mm) including earthwork in excavation in all types of soil including hard rock and soft rock, earthwork in backfilling , sand padding of required thickness below foundation, laying of PCC as shown in drawing, overhead on ‘Y’ shape structural steel frame. SUPERSTRUCTURE & SUBSTRUCUTRE works including (reinforcement, masonry work, Plastering ,painting, CENTERING & SHUTTERING complete in all respect etc.) and supplying, fixing and tensioning in position , GI Barbed wire conforming to IS:278 in horizontal rows and cross diagonals for compound wall "Y" shaped overhang etc. with necessary GI staples, clips and pins, GI straining bolts and binding wire, expansion joints, weep holes, stone pitching outside (Type-1 or Type-2 as per dwg. attached in the bid documents and as per IFC drawing ), well compacted earth with all labour and materials etc. complete as per Tender and IFC drawings, specifications and directions of Engineer-in-Charge.(The barbed wire shall be measured in linear length of the barbed wire actually fixed) Supplying, fabricating and fixing in position structural steel line posts, straining posts, struts for 'Y' shaped overhang etc. conforming to IS:2062 over brick/stone Masonry/ RCC compound walls/ columns, cutting to required size as per drawings and specifications, welding where necessary, embedding in position, holding to correct level and line, any auxiliary structure for dummy supports, drilling holes and painting as per painting specification attached with tender, cutting brick/rubble/concrete surfaces if necessary, grouting with M20 grade concrete including cost of grout with all labour and material, including backfilling ,disposal of surplus earth outside the station boundary for all lift and leads etc. complete as per drawings, specifications and directions of Engineer-in-Charge. All The works shown in the IFC drawing issued shall be covered as part of the scope in this line item. ( All materials including cement shall be supplied by contractor). For Meaurement in Running Metre, Centre line length of Boundary wall shall be considered. NO extra payment on account of structural projections etc. shall be considered.(Note: Rates are excluding Sand filling along the perimeter of boundary wall , however sand padding below foundation is already covered as part of this SOR line item. If Sand filling is required along the perimeter of boundary wall shall be paid as per SOR item no. C.20.10.1) 0.00 0.00 0.00
58 C 12.2.1 TYPE-A (DIFFERENCE BETWEEN FGL AND NGL IS ≤ 0.8 MTR.) RM 1 41,250.00 41,250.00 18% 7,425.00 48,675.00 0.00
59 C 12.2.2 TYPE-B (DIFFERENCE BETWEEN FGL AND NGL IS > 0.8 MTR. BUT ≤ 1.3 MTR.) RM 1 47,080.00 47,080.00 18% 8,474.40 55,554.40 0.00
60 C 12.2.3 TYPE-C (DIFFERENCE BETWEEN FGL AND NGL IS > 1.3 MTR. BUT ≤ 1.8 MTR.) RM 1 55,330.00 55,330.00 18% 9,959.40 65,289.40 0.00
61 C.12.3 DEMOLITION, DISMANTLING, REMOVAL,TRANSPORTATION,DISPOSING OF EXISTING Compound wall elements which briefly covers Footings, RCC columns, beams at all level, RCC Retaining wall, brick works at all level, coping and Brick masonry above FGL (3.0m high) and additional 0.85m high barbed wire & concertina coil (dia. 610mm) including earthwork in excavation in all types of soil including hard rock and soft rock, earthwork in backfilling and compaction , PCC , coping,grouting etc. overhead on ‘Y’ shape structural steel frame. SUPERSTRUCTURE & SUBSTRUCUTRE works including (reinforcement, masonry work, Plastering ,painting, CENTERING & SHUTTERING complete in all respect etc.) , GI Barbed wire conforming to IS:278 in horizontal rows and cross diagonals for compound wall "Y" shaped overhang etc. with necessary GI staples, clips and pins, GI straining bolts and binding wire, expansion joints, weep holes, stone pitching outside (as per site condition ), backfilling and well compacted earth , with all labour and materials etc. completely cleaned as per site condition, specifications and directions of Engineer-in-Charge. This includes Transporting and disposing the ALL THE DEBRIS including RCC, brick masonry and structural items,barbed wire etc. complete in all respect from construction areas to areas ANYWHERE OUTSIDE THE PLANT BOUNDARY. DISPOSAL AREAS OUTSIDE PLANT BOUNDARY TO BE ARRANGED BY THE CONTRACTOR. Royalty as applicable for disposal outside plant limits to be borne by the Contractor. For Meaurement in Running Metre, Centre line length of Boundary wall shall be considered. NO extra payment on account of structural projections etc. shall be considered. All works related for boundary wall demolishing and disposing shall be covered under this line item only and NO additional SOR line item shall be operable for boundary wall demolishing and disposing. 0.00 0.00 0.00
62 C 12.3.1 TYPE-A (DIFFERENCE BETWEEN FGL AND NGL IS ≤ 0.8 MTR.) RM 1 11,000.00 11,000.00 18% 1,980.00 12,980.00 0.00
63 C 12.3.2 TYPE-B (DIFFERENCE BETWEEN FGL AND NGL IS > 0.8 MTR. BUT ≤ 1.3 MTR.) RM 1 14,300.00 14,300.00 18% 2,574.00 16,874.00 0.00
64 C 12.3.3 TYPE-C (DIFFERENCE BETWEEN FGL AND NGL IS > 1.3 MTR. BUT ≤ 1.8 MTR.) RM 1 16,500.00 16,500.00 18% 2,970.00 19,470.00 0.00
65 C.13 STRUCTURAL STEEL WORKS (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
66 C.13.1 Supplying, transporting, storing, fabricating in position and testing/examining bolted and/or welded STRUCTURAL STEEL WORKS at all levels and locations including all built-up sections/compound sections made out of rolled sections, I-Beam and/or plates/bent plates in platforms, crossover (excluding chequered plates,hand railing and gratings), ladders, channel section,Structural Supports, Safety Sign Board & Emergency Contact Sign Board (including Letter Writing) as per dwg. attached in bid documents , I-Beams for pipe support & equipment and process piping, posts etc. cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/welding of joints, (including sealing the joints of box sections with continuous welding), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, preparing the surface for painting and applying shop primer as per relevant specifications, design basis and other tender drawings Specification after fabrication etc. all complete (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). KG 1 102.00 102.00 18% 18.36 120.36 0.00
67 C.13.1.1 Structural steel gate (3.0 m wide )- Openable type with 2 panel as per dwg. Attached in bid documents and other relevant specifications, design basis and other tender drawings wherever applicable NO 1 110,000.00 110,000.00 18% 19,800.00 129,800.00 0.00
68 C.13.1.2 Structural steel gate (4.0 m wide ) -Openable type with 2 panel as per dwg. Attached in bid documents and other relevant specifications, design basis and other tender drawings wherever applicable NO 1 121,000.00 121,000.00 18% 21,780.00 142,780.00 0.00
69 C.13.1.3 Structural steel gate (4.50 m wide ) - Sliding type as per dwg. Attached in bid documents and other relevant specifications, design basis and other tender drawings wherever applicable NO 1 132,000.00 132,000.00 18% 23,760.00 155,760.00 0.00
70 C.13.1.4 Structural steel wicket gate (1.2 m wide ) as per dwg. Attached in bid documents and other relevant specifications, design basis and other tender drawings wherever applicable NO 1 77,000.00 77,000.00 18% 13,860.00 90,860.00 0.00
71 C.14 CHAIN LINK FENCING (REFER ATTACHED DWG. IN BID DOCUMENTS) 0.00 0.00 0.00
72 C.14.1 Supplying, fabricating and fixing G.I. chain link fencing fabric, 1.8 mtr height, conforming to IS:2721 fixed to steel/RCC posts/struts above ground level, including supply of chain link fencing fabric in 1.8 metre wide rolls, stretcher bars, staples, etc. required for fixing the fencing, fixing of chain link fencing between straining posts, 230 thk & 450 high brick fixing of bottom of fencing in cement concrete 1:2:4 blocks and painting with synthetic enamel etc. , including supply and fixing line wires, supply and laying of Rubble soling complete as per drawings, specifications and directions of Engineer -in-Charge (All materials shall be supplied by Contractor). (The measurement of chain link fencing shall be on linear basis for 1.8 m wide fencing fabric) RM 1 7,535.00 7,535.00 18% 1,356.30 8,891.30 0.00
73 C.14.2 Supplying, fabricating and fixing G.I. chain link fencing fabric, 3.0 mtr height, conforming to IS:2721 fixed to steel/RCC posts/struts above ground level, including supply of chain link fencing fabric in 3.0 metre wide rolls, stretcher bars, staples, etc. required for fixing the fencing, fixing of chain link fencing between straining posts, 230 thk & 450 high brick fixing of bottom of fencing in cement concrete 1:2:4 blocks and painting with synthetic enamel etc. , including supply and fixing line wires, supply and laying of Rubble soling complete as per drawings, specifications and directions of Engineer -in-Charge (All materials shall be supplied by Contractor). (The measurement of chain link fencing shall be on linear basis for 3.0 m wide fencing fabric) RM 1 10,675.00 10,675.00 18% 1,921.50 12,596.50 0.00
74 C.15 ROADS & FLEXIBLE PAVEMENT (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
75 C.15.1 Bituminous Road (All layers complete in all respect as per relevant standard drawing) SQ.M 1 2,750.00 2,750.00 18% 495.00 3,245.00 0.00
76 C.15.2 RCC Road (All layers complete in all respect as per relevant standard drawing) SQ.M 1 3,135.00 3,135.00 18% 564.30 3,699.30 0.00
77 C.16 CONCRETE PAVEMENTS (REFER ATTACHED DWG. IN BID DOCUMENTS) 0.00 0.00 0.00
78 C.16.1 Providing and laying Reinforced Cement Concrete with 20mm and down size graded crushed stone aggregates in flooring, pavements,roads etc. including leaving pockets, if necessary, making recess/drains, laying in alternate panels, etc. for all depths including shuttering, tamping, curing, etc. as specified in any shape, thickness, position and finishing the top surface smooth etc. all complete as per drawings, specifications and directions of Engineer-in-Charge. For RCC of M-25/M-30 grade concrete (all materials including cement but excluding cost of providing & fixing reinforcement ). Providing 20mm wide Expansion Joints in pavement slabs as per general technical specification including cleaning the joints of all loose material, filling with 20mm thick impregnated fibre boards for the full depth of slab except for 25mm depth from top and sealing the top 25mm with approved Joint Sealing Compound as per IS:1834 Type-B etc. Sealing joint around pedestal and column etc. 20mm wide x 150 mm deep including filling with 20mm thick impregnated fire board for the full depth of slab except for 25mm depth from top and sealing the top 25mm with approved joint sealing compound as per IS:1834 Type-B. all complete as per drawings, specifications and directions of Engineer-in-Charge. 0.00 0.00 0.00
83 C.17 RCC HUME PIPE CULVERTS & ELECTRICAL ROAD CROSSINGS ETC. (REFER ATTACHED DWG. IN BID DOCUMENTS) 0.00 0.00 0.00
84 C.17.1 Providing, laying, jointing and testing RCC hume pipes of following dia. and NP3 class for culverts, road crossing, incl. excavation in all strata up to an average depth of 1 m cutting, collars jointing in 1:2 cement mortar etc. complete as per specifications and as directed by the engineer-in charge. Supplying and laying in position of RCC NP3 class pipes with collars, confirming to IS: 458 for pipe culverts, cable crossing, road crossing etc. including cutting the hume pipe if necessary, lowering, laying in position to proper levels, slopes etc. caulking the joints with spun yarn soaked in neat cement slurry and finishing with cement mortar 1: 2 (1 Cement: 2 Sand) curing etc. all complete as per drawings / specifications and directions of Owner/Owner’s Representative. Rate is included the cost of excavation up to 1.2-meter cover and backfilling of earth. Providing bedding concrete of PCC (1:4:8) 75 mm thick and backfilling with good earth. 0.00 0.00 0.00
91 C.18.0 BOX CULVERT (REFER ATTACHED DWG. IN BID DOCUMENTS) 0.00 0.00 0.00
92 C.18.1 Construction of RCC Box culvert of following type including wing wall and parapet wall all complete as per technical specifications and drawings. 0.00 0.00 0.00
97 C.19 U/G AND A/G G.I. PIPELINE SYSTEM - WATER SERVICES (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
98 C.19.1 Supplying and laying mild steel galvanised pipes conforming to IS:1239 (heavy grade) and fittings conforming to IS:1239/ ASTM A105 (Galvanized) and as per piping materials specification Class including supply of teflon tapes, white lead, etc. cutting the pipes to required lengths, making threads, earthwork in excavation for trenches, valve pits, etc. in all types of soil excluding soft and hard rock including laying of pipes in trenches, joining the pipes and fittings with threaded connections, hydrostatic testing of the piping, backfilling the trenches with selected/approved earth fill material, cutting of roads wherever required, making good the road surface after laying, disposal of surplus earth within a lead of 500 m, etc. including supply of necessary fittings etc. complete as per specifications, drawings and directions of Engineer-in-Charge. For ( Nom. Dia - 50 mm, Pipe class - J2A ) Excluding piping system in control room and guard room. RM 1 660.00 660.00 18% 118.80 778.80 0.00
99 C.20 MISC. CIVIL AND STRUCTURAL WORKS 0.00 0.00 0.00
100 C.20.1 Providing and laying brick masonry with locally available bricks of specified class (Brick of class lower than specified shall not be accepted) in cement mortar 1:4 (1 cement : 4 Coarse sand) in one or more brick thickness and in any shape in foundation and plinth for valve pits, drains, valve chamber,earthing pit, cable pull pit, circular/square manholes, wing walls, etc. including providing recesses, openings, etc. including curing, finishing the joints flush below ground level and raking out joints in plinth with all labour and material, etc. complete as per drawings, specifications and direction of Engineering-Charge. All materials including cement supplied by the Contractor and. ( Brick Class - 5 ) CUM 1 6,320.00 6,320.00 18% 1,137.60 7,457.60 0.00
101 C.20.2 Providing 13mm thick average cement plaster in cement mortar 1:3 (1 cement: 3 sand) on brick walls/stone masonry/pitching or on concrete surfaces for manholes, valve chamber, cable pull pit, earthing pit , valves pits, culverts, wing walls, etc. including cleaning and preparation of the surface, scaffolding, curing etc. for all depths and heights complete as per drawings specifications and direction of Engineer-in-Charge.All materials including cement supplied by the Contractor. SQ.M 1 358.00 358.00 18% 64.44 422.44 0.00
102 C.20.3 STORM WATER DRAIN - BRICK DRAIN (REFER ATTACHED DWG. IN BID DOCUMENTS) Providing and laying brick drain including 13mm thick average cement plaster in cement mortar 1:3 (1 cement: 3 sand) on brick drain walls including cleaning and preparation of the surface,curing etc. for all depths and heights complete as per drawings specifications and direction of Engineer-in-Charge. 0.00 0.00 0.00
106 C.20.4 MS CHEQUERED PLATES 0.00 0.00 0.00
107 C.20.4.1 Supplying, fabricating and erecting in position at all levels and locations bolted, screwed and/or welded M.S. CHEQUERED PLATES of any thickness in walkways, platforms, stairtreads or any other place as directed, etc. cutting to required size, shape, making holes, notches, openings of required size, nosing, straightening if required, making the edges smooth, removing the burrs, fixing, welding, preparation and submission of fabrication drawings and preparing the surfaces for painting and applying shop primer as per TE Specification after fabrication and return of unused/ scrap/ unserviceable chequered plates to Owner's store and material reconciliation etc. all complete as specified and directed KG 1 121.00 121.00 18% 21.78 142.78 0.00
108 C.20.5 ANCHOR BOLTS 0.00 0.00 0.00
109 C.20.5.1 Supplying, fabricating, fixing and keeping in position at all levels and locations THREADED ANCHOR BOLTS of all diameters and nomenclature including nuts, washers, anchor plates, pipe sleeves etc. in foundations, columns, pedestals, pipe supports, slabs, beams, walls etc. or any other place as directed including handling & transporting, straightening if required, turning from relevant size M.S. rounds to required diameter, threading, welding, providing necessary templates and auxiliary dummy structures, if any, necessary tying and welding with reinforcement, adjustment of shuttering & reinforcement/any other fixture, greasing exposed metal surfaces, covering bolts and packing the sleeves with jute cloth etc. all complete as specified and directed.(SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). KG 1 121.00 121.00 18% 21.78 142.78 0.00
110 C.20.6 MS METAL INSERTS 0.00 0.00 0.00
111 C.20.6.1 Supplying, transporting, storing, fabricating and fixing in position M.S. METAL INSERT (with lugs and Teflon sheet) of any shape made out of flats, plates, rolled sections, pipes etc. providing necessary templates, staging, cutting, straightening, if required, bolting, welding as required and embedding in position on both Plain and Reinforced Cement concrete members inclusive of adjusting shuttering & reinforcement/ any other fixture, welding where necessary, tying and holding to correct level, line and position, any auxiliary dummy structures to support the heavy inserts, painting exposed surfaces with a coat of primer as per TE Specification all complete for all depths and heights as specified and directed. (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). KG 1 149.00 149.00 18% 26.82 175.82 0.00
113 C.20.7.1 Supplying, fabricating and erecting in position at all levels and locations ELECTROFORGED GALVANISED GRATING (purchased from approved manufacturer by the Contractor) conforming to GTL/Consultant STANDARD (in walkways, platforms, stair treads etc.) including cutting to required size, shape, making holes, notches, openings of required size, nosing, straightening if required, making the edges smooth, removing the burrs, fixing with manufacturer's supplied galvanised clamps, preparation and submission of fabrication drawings, all complete as specified and directed (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). KG 1 156.00 156.00 18% 28.08 184.08 0.00
114 C.20.8 HAND RAILING 1000mm 0.00 0.00 0.00
115 C.20.8.1 Supplying, fabricating and fixing in position at all locations 1000mm high INCLINED & HORIZONTAL HAND RAILING (for staircases/platform/crossover ) consisting of top rail, mid rail and vertical posts (as per drawing) with 32mm nominal diameter medium grade M.S. Tubes conforming to IS:1239 including straightening if required, cutting, bending, welding, bolting, grouting with ordinary grout, cleaning, surface preparation, hot-dip galvanising (80-85 micron as per IS:4759, IS:2629, IS: 4736, IS:2633), shop primer (1 coat of P6 of 40 micron) as per TE SPEC. preparation and submission of fabrication drawings etc. all complete as specified, shown and directed. (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). (Complete handrail work shall be measured as length of top rail only and not length of each element fixed). RM 1 1,430.00 1,430.00 18% 257.40 1,687.40 0.00
116 C.20.9 Supplying & Laying interlocking Paver Blocks for roads, footpaths and any other place etc. including providing 50 mm thick sand filling below Paver Blocks including compaction of sand layer, filling the joints by dry sand, providing precast kerb stone of PCC M-20 at edges, including preparation of compacted sub-grade etc. all complete as per drawing, standard and directions of Engineer-in-Charge. (All material including cement supplied by contractor, paver blocks shall confirm to IS: 15658. cloour and shape of paver block shall be as per owner requirements for 60mm thick paver blocks. SQ.M 1 1,111.00 1,111.00 18% 199.98 1,310.98 0.00
117 C.20.10 SAND FILLING 0.00 0.00 0.00
118 C.20.10.1 Supplying and filling approved SAND of specified quality under floors, in foundations, plinths, tank foundations etc. for all depths and heights including cost of sand,royalties,transportation to site for all leads and lifts, including loading, unloading, spreading in layers of loose thickness not exceeding 150 mm,watering,ramming,compacting with mechanical compactors and/or other equipment to the specified levels to achieve 85% relative density as per IS:2720 Part XIV,including preparation of subgrade to the required slope, providing testing apparatus and testing the degree of consolidation all complete as per drawings, specifications and direction of Engineer-in-charge. The rates shall be inclusive of the cost of all labour,material,equipments etc. all complete . CUM 1 990.00 990.00 18% 178.20 1,168.20 0.00
119 C.20.11 Gravel Filling (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
120 C.20.11.1 Supply and laying of gravel/ crush stone of size ranging between 20 mm to 40 mm in compacted thickness of 100mm including 1000 micron HDPE sheet in process area development ,valve pit, open area within the unit battery limit or at any other place as directed, etc. complete as per drawings, specifications, design basis and direction of Engineer-in-Charge SQ.M 1 880.00 880.00 18% 158.40 1,038.40 0.00
121 C.20.12 SAND GRAVEL MIX 0.00 0.00 0.00
122 C.20.12.1 Supplying and filling sand gravel mix (1:1) with approved aggregate below road, RCC pavement, manholes, pits, foundations, bedding of UG piping etc. in layers of 150 mm loose thickness (maximum) including watering, ramming, rolling, compacting to achieve 85% relative density as per IS 2720 Part-XIV, quarrying, royalties, transportation, handling, etc. all complete as per drawings, specifications, design basis and directions of Engineer-in- Charge. (The rate shall be inclusive of the cost of all labour, material, equipment etc. all complete) CUM 1 1,650.00 1,650.00 18% 297.00 1,947.00 0.00
123 C.20.13 RANDOM RUBBLE PITCHING (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
124 C.20.13.1 Supplying & laying random rubble pitching 225 mm thick in 1:6 cement mortar (1 cement: 6 coarse sand) in one layer for embankments, road side slopes,holding ponds bunds, drains, channels or at any other place as directed including cost of stones, all royalties & taxes, transportation to site with all leads and lifts, dressing, preparation of sub grade for pitching, flush pointing in 1:4 cement mortar (1 cement: 4 sand), curing etc. complete as per drawings, specifications, design basis and directions of Engineer-in-Charge. SQ.M 1 903.00 903.00 18% 162.54 1,065.54 0.00
125 C.20.14 BORE WELL (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
126 C.20.14.1 Providing bore well with sufficient yield for all depth and seasoned use in all type of soil including soft & hard rock with supply Erection, /Installation , Testing and Commissioning of Submersible pump (Single Phase with Dual starter including cables and accessories) of good quality, IS marked (C.I body) including providing floor drainage system around tube well and upto nearest storm water drain including drilling for tube well, providing casing pipes, cleaning, testing and commissioning of tube well system all complete as per specification, design basis, standard, codes and direction of Engineer- in-Charge. Note : Contractor shall arrange required NOC for bore well from concern authority at no extra cost. NO 1 275,000.00 275,000.00 18% 49,500.00 324,500.00 0.00
127 C.20.14.2 Supply, Erection, /Installation , Testing and Commissioning of Submersible pump (1 HP_ Single Phase with Dual starter incluing cable and accessories) of good quality, IS marked (C.I body) including providing floor drainage system around tube well and upto nearest storm water drain for tube well as per specification, design basis, standard, codes and direction of Engineer- in-Charge. Note : Item rate shall be applicable and paid in case only 1 HP _Submersible pump supplied by Contracor where existing bore well is available without Submersible pump. NO 1 11,000.00 11,000.00 18% 1,980.00 12,980.00 0.00
128 C.20.15 RUBBLE SOLING 0.00 0.00 0.00
129 C.20.15.1 Supply & filling Rubble Soiling (250-300 mm thick) in trench, bottom of foundations for piping supports and other facilities as per the drawings etc. up to required level complete as per drawings, specifications and as directed by EIC . No separate charges shall be paid for manpower, consumables, equipments, handling, tools & tackles used during execution of this activity.The rubble stone shall be of best variety of black trap / granite / basalt or other approved-variety of stone available locally. The stone shall be hard, durable free from defects and of required size and shall be approved by the Engineer-in-charge. The scope for work covers supply and laying in foundations, trenches, pits and over areas, in all sorts of soil, soft and hard rock, correct to dimensions given in the drawing including shoring, protections of existing underground utilities of any, such as water lines, electric cables etc. dewatering and shoring if necessary, stacking the useful materials as directed within the lead specified, refilling around the foundation and into the plinth with selected useful excavated earth and disposing off the surplus earth / materials within specified lead and finishing the surface to proper levels, slopes and camber etc. all complete. SQM 1 1,045.00 1,045.00 18% 188.10 1,233.10 0.00
130 C.20.16 FRP SHEET CANOPY 0.00 0.00 0.00
131 C 20.16.1 Supply, Fabrication and Installation of FRP Sheet Canopy with all accessories like studs & washers for any instruments,GEB meter, CO2 Cylinder, UG tank etc.Dimensions of the canopy to suit at site condition and instruction as per EIC. No separate charges shall be paid for manpower, consumables, equipments, tools & tackles used during execution of this activity. KG 1 145.00 145.00 18% 26.10 171.10 0.00
133 C20.17.1 Painting of Above Ground Civil Supports/Foundations/Earth Pits etc. (Existing/Newly Constructed) including Paint (Terra cotta), equipments for application & its accessories, manpower, material etc. upto required surface finish. 2500 Sq. Mtr. SQM 1 154.00 154.00 18% 27.72 181.72 0.00
134 C.21 DEMOLISHING AND DISMANTLING (REFER ATTACHED SPECIFICATION IN BID DOCUMENTS) 0.00 0.00 0.00
135 C.21.1 Demolishing BRICKWORK (taking all necessary safety precautions) for all depths below plinth level including supply of all tools and tackles, necessary scaffolding, propping, underpinning, cleaning and stacking of serviceable material, disposal of unserviceable material to spoil heaps anywhere within the plant boundary, all complete as specified and directed. (Excavation & backfilling shall be paid separately under relevant items). CUM 1 1,868.00 1,868.00 18% 336.24 2,204.24 0.00
136 C.21.2 Demolishing BRICKWORK (taking all necessary safety precautions) for all heights above plinth level including supply of all tools and tackles, necessary scaffolding, propping, underpinning, cleaning and stacking of serviceable material, disposal of unserviceable material to spoil heaps anywhere within the plant boundary, all complete as specified and directed. CUM 1 1,868.00 1,868.00 18% 336.24 2,204.24 0.00
138 C.21.3.1 Demolishing RCC WORK (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning etc., cutting, straightening, scraping and cleaning of reinforcement bars, stacking of serviceable materials, disposal of unserviceable material to spoil heaps anywhere within the plant boundary, all complete as specified and directed. (Excavation & backfilling shall be paid separately under relevant items). CUM 1 3,221.00 3,221.00 18% 579.78 3,800.78 0.00
139 C.21.3.2 Demolishing RCC WORK (taking all necessary safety precautions) for all heights above plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning etc., cutting, straightening, scraping and cleaning of reinforcement bars, stacking of serviceable materials, disposal of unserviceable material to spoil heaps anywhere within the plant boundary, all complete as specified and directed. CUM 1 3,221.00 3,221.00 18% 579.78 3,800.78 0.00
141 C.21.4.1 Demolishing PLAIN CEMENT CONCRETE work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning etc. disposal of unserviceable material to spoil heaps anywhere within the plant boundary, all complete as specified and directed. (Excavation and backfilling shall be paid separately under relevant items) CUM 1 2,208.00 2,208.00 18% 397.44 2,605.44 0.00
142 C.21.5 INTERLOCKING PAVER BLOCK 0.00 0.00 0.00
143 C.21.5.1 Taking out existing CC interlocking paver blocks including removal of rubbish etc., disposal of unserviceable material to the dumping ground and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. SQM 1 119.00 119.00 18% 21.42 140.42 0.00
144 C.22 GROUTING WITH NON-SHRINKABLE COMPOUND 0.00 0.00 0.00
145 C.22.1 Providing and laying manually or by pumping at all positions a ready mix non-shrink cementitious grout of compressive strength specified below for specified works e.g. pipe support, base grouting of rotating equipment and other installation complete in all respects as per scope of work, detailed construction drawings , technical specifications and directions of the Engineer-In-Charge. 0.00 0.00 0.00
146 C.22.1.1 Having compressive strength of 30 N/mm2 Per bag of 25 Kg 1 1,485.00 1,485.00 18% 267.30 1,752.30 0.00
147 C.22.1.2 Having compressive strength 45 N/mm2 Per bag of 25 Kg 1 1,650.00 1,650.00 18% 297.00 1,947.00 0.00
148 1) Minimum coverage as per manufacturers recommendations shall be applied in absence of actual field consumption data.] 0.00 0.00 0.00
149 C.23 PORTA CABIN WITH WIND SOCK (REFER ATTACHED DWG. IN BID DOCUMENTS) 0.00 0.00 0.00
150 C.23.1 Supplying, transporting, storing, fabricating in position and testing/examining bolted and/or welded including all built-up sections/compound sections made out plates/bent plates,plywood painting etc. in PORTA CABIN WITH WIND SOCK.etc.( for Control Room or Guard Room) cutting to required size, straightening/ bending if required, edge preparation, cleaning, finishing edges, fixing in line and level as Specification and standard drawings etc. all complete (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). SQ.M 1 49,500.00 49,500.00 18% 8,910.00 58,410.00 0.00
151 C.24 GREEN BELT DEVELOPMENT 0.00 0.00 0.00
152 C.24.1 Development of Green belt (approx. 20% of the plot area), 2 rows of trees @ 3m c/c shall be planted along boundary wall of the plot & available open space. Locally available tree and suitable for local condition shall be used. The top 300 mm of soil shall be filled/removed and backfilled with good earth soil for landscaping, if required. Decision on removal & refilling shall be based on soil conditions at site.Brick curbing, if required, shall be provided with single line brick work embedded 100mm inside the earth. SQ.M 1 121.00 121.00 18% 21.78 142.78 0.00
153 C.25 RECHARGE WELL (REFER ATTACHED DWG. IN BID DOCUMENTS) 0.00 0.00 0.00
154 C.25.1 Providing and laying brick masonry with locally available bricks of specified class (Brick of class lower than specified shall not be accepted) in cement mortar 1:4 (1 cement : 4 Coarse sand) in one or more brick thickness and in any shape in Recharge well including curing, finishing with all labour and material, etc. complete as per drawings, specifications and direction of Engineering-Charge. All materials including cement supplied by the Contractor. NOS 1 275,000.00 275,000.00 18% 49,500.00 324,500.00 0.00
155 C.26 RE-INSTALLATION OF EXISTING ITEM 0.00 0.00 0.00
156 C.26.1 Installation of equipment such as DG Set, Metering skid, Filter, Filteration skid, PRS skid, Pig Barrel, Pig Trolly, Jib Crane, Piping,electrical/ instrumentation panel, valves, structural steel etc. carefully including handling, erection and proper installtion of the equipments/ material within a radius of 250 Mts. and as directed by EIC. Manpower, Machinery required, transportation is in contractor's scope . 0.00 0.00 0.00
158 C.26.1.2 Item weight more than 50 Kg and upto 150 kg NO 1 4,400.00 4,400.00 18% 792.00 5,192.00 0.00
162 C.26.1.6 Item weight more than 1 Ton and upto 2 Tonnes NO 1 16,500.00 16,500.00 18% 2,970.00 19,470.00 0.00
163 C.26.1.7 Item weight more than 2 Tonnes and upto 3 Tonnes NO 1 17,050.00 17,050.00 18% 3,069.00 20,119.00 0.00
1. The rates are in INR excluding GST. GST shall be payable extra at actual.
2. The quantity indicated above are Tentative.
3. All Above works shall be executed in accordance with ISSUED FOR CONSTRUCTION DRAWINGS (IFC), SCOPE OF WORK, Design Basis, Technical Specifications ,Standard drawings, Project drawings, Data Sheets, QAP, Drawings and other provision of bid documents and instruction of Owner/ Owner's Representative.
4. Bidder to confirm full compliance to spec. Deviations are not allowed and shall make liable for rejection
5. The above total prices shall be inclusive of all TPI, packing, forwarding, handling, storage, stacking, Transportation, spares , special tools , tackles,loading and unloading charges up to final destination site but does not include taxes
6. All the items required to complete the work shall be the scope of supply of contractor only.
7. This work is exclusive of all works associated with Station Architecture/civil/Structural only.
8. All other works pertaining to Station Mechanical/Electrical & TCP/Instrumentation works shall be as per rates indicated elsewhere in the tender document.
9. Prices quoted shall include the following
a) All handling , transportation including marine transportation( if applicable) , liason , port fee, ware house , handling , all fees customs duty etc.
b) All design , engineering, supply, installation,, tech support and guarantee
10. For all line items, referred Spec./drawing is tentative only. All the applicable IFC DRAWINGS, SOW, Design Basis, Specifications, Project drawings, Standrd drawings etc. shall be referred for better understanding of scope of contract.
11.If any items are not covered in SOR and required to execute the work which is a part of scope of contract. The contractor shall be paid as per Delhi Schedule of rates (DSR).
12. In case of using CRS reinforcement, Sulphate resistant cement (SRC), 10 % additional rate may be considered on reinforcement and concrete works line items of above SOR.
13. Preparation of all As-Built drawings for each project will be in contractor's scope.
Annexure-C Unit Base Rate/ SCHEDULE OF RATES (Tender no.: GTL/PROC/2026/08/O/502; (n)Procure Tender ID: 340579)
HIRING OF CONTRACTOR FOR CUSTOMER CONNECTIVITY PIPELINE PROJECTS ACROSS GUJARAT
ELECTRICAL INCLUDING CATHODIC PROTECTION AND ASSOCIATED WORKS
DOCUMENT NO.: GTL-ARC-DOC-SOR-060-04-01
Rev 0 dated 06.07.2026
S. No. Description of Items Unit Quantity HSN/SAC Unit Rate Total Basic Amount GST Total Amount with GST
(Basic) % Amount
A B C D E F G = D x F H I J = G + I
1.0 SWITCH BOARDS / AC UPS SYSTEM / PANEL/STABILIZER /DG SET
1.1 Design & Engineering, supply , Installation, testing and commissioning of MEDB/SWITCH BOARD, DG, AC UPS system with battery bank /battery rack installation,FLP wall mounted battery Isolators or Junction box & ups distribution board and ,cubicles with electrical equipment, misc. electrical panels etc., including transportation up to site at the place of installation, unpacking, assembly, including mounting and wiring of loose parts supplied by equipment vendor, interconnection of shipping sections and requisite inter-panel wiring between shipping sections, including supply of all wiring materials, installation on foundations or fixing to wall or steel structures, aligning, levelling, grouting, including all labour and materials, as per approved drawings, specifications of this tender and directions of OWNER / CONULTANT.
1.1.1 Design, Engineering, Supply , erection , termination , earthing (as per SLD) and commissioning of floor mounted 415V,3phase MEDB as per single line diagram of SV station attached in the bid documents . Nos. 1 319,000.00 319,000.00 18% 57,420.00 376,420.00
1.1.2 Design, Engineering, Supply , erection , termination , earthing and commissioning of wall mounted 415V,3phase OLDB as per single line diagram of SV station attached in the bid documents . Nos. 1 62,700.00 62,700.00 18% 11,286.00 73,986.00
1.1.3 Design, Engineering, Supply , erection , termination , earthing and commissioning of wall mounted 415V,3phase ILDB as per Single line diagram of of SV station attached in the bid documents Nos. 1 49,500.00 49,500.00 18% 8,910.00 58,410.00
1.1.4 Design, Engineering, Supply , erection , termination, earthing ,Testing & commissioning of wall mounted 415V,3phase SSDB as per Single line diagram of SV station attached in the bid documents . Nos. 1 49,500.00 49,500.00 18% 8,910.00 58,410.00
1.1.5 Design, Engineering, Supply , erection , termination, earthing ,Testing &commissioning of wall mounted 415V,3phase ACDB with change over circuit & timer as per Single line diagram of SV station attached in the bid documents . Nos. 1 53,900.00 53,900.00 18% 9,702.00 63,602.00
1.1.6 Design, Engineering, Supply , erection , termination , earthing ,Testing & commissioning of wall mounted 415V,3phase , PDB as per Single line diagram of Dispatch station with power supply & Receiving station/customer end with power supply according to drawing attached in the bid documents. Nos. 1 104,500.00 104,500.00 18% 18,810.00 123,310.00
1.1.7 Design, Engineering, Supply , erection , termination , earthing ,Testing & commissioning of wall mounted/structral mountes 415V,3phase , FLP type PDB/Lighting distribution board as per Single line diagram of Dispatch station with power supply & Receiving station/customer end with power supply according to drawing attached in the bid documents. Nos. 1 114,400.00 114,400.00 18% 20,592.00 134,992.00
1.1.8 Design, Engineering, Supply , erection , termination , earthing (as per SLD) Testing &Commissioningof Min size of 2x5 KVA floor mounted AC supply UPS system, Parallel redundant ,with auxiliary bsupply and three phase charger and with NI-Cd battery bank with rack,with 12 hours backup, (6 hrs. each) (2 x50% load) as per the Tender specification.General Specification of-UPS System. Nos. 1 6,600,000.00 6,600,000.00 18% 1,188,000.00 7,788,000.00
1.1.9 Design, Engineering, Supply , erection , termination , earthing (as per SLD) Testing & and commissioning of floor mounted, having min.75 kva capacity,415V,3phase Stabilizer with microprocessor based display,having manual bypass and energy efficient Isolation Transformer as per General specification of Servo stabilizer. Nos. 1 550,000.00 550,000.00 18% 99,000.00 649,000.00
1.1.10 Design, Engineering, Supply , erection , Testing & commissioning of wall mounted SFU as per Single line diagram of SV station attached in bid documents including liasioning with SEB as per Tender specification and direction of OWNER / CONSULTANT. Nos. 1 55,000.00 55,000.00 18% 9,900.00 64,900.00
1.1.11 Design, Engineering, Supply , erection , termination , earthing ,Testing & and commissioning of lighting inverter with VRLA battery,distribution board,stand structure and other required material like cable/cord/link etc as per TS-Electrical package and Typical single line diagram of SV station attached in the bid documents. Nos. 1 44,000.00 44,000.00 18% 7,920.00 51,920.00
1.1.12 Design, Engineering, Supply , erection , termination , earthing (as per SLD) Testing & commissioning of prime rated DG Set, min.40kva capacity,415V,3ph+N,with inbuilt control panel as per TS-DG set and Typical single line diagram of SV station attached in the bid documents. Nos. 1 621,500.00 621,500.00 18% 111,870.00 733,370.00
1.1.13 Design, Engineering, Supply , erection , termination , earthing and commissioning of UPS Distribution board , 230 V AC,with copper busbar, refer TS Electrical package & SLD of typical sv station for outgoing feeders. Nos. 1 49,500.00 49,500.00 18% 8,910.00 58,410.00
1.1.14 Design, Engineering, Supply , Installation, testing and commissioning of Minimum 18KW ON Grid Solar system complete with solar modules, MPPT Solar inverter, ACDB, DCDB, DC Cables, earthing and lightning protection complete in all respects. Nos. 1 1,100,000.00 1,100,000.00 18% 198,000.00 1,298,000.00
2 POWER AND CONTROL CABLE 0.00 0.00 0.00
2.1 Supply, laying with excavation and backfilling of cable trench/tray as specified in General specification of Erection, Installation, Testing & commisioning of Electrical Equipments / Cable route layout , termination , erection and testing of 1.1 KV Power FRLS XLPE Cables . Outdoor cable will be laid in buried cable trench and via HDPE duct laying and in Indoor application it will be in Cable trench by provision of Cable tray and supports inside the trench as per cable and Accessories . 0.00 0.00 0.00
2.1.14 3C x 2.5 sqmm CU FRLS Unarmoured Cable M 1 132.00 132.00 18% 23.76 155.76
3 Earthing & Lightning 0.00 0.00 0.00
3.1 Supply , Installation , testing and commissioning of GI Earth electrodes & Cu plate type earth electrode complete with earth pit as per General specification of Erection, Installation, Testing & commisioning of Electrical Equipments ,General specification for Earthing and Lightning Potection & Indoor and Outdoor earthing layouts of various station as described in specification Electrical package and all necessary material including excavation of earth pit , filling with charcol and salt , back filling, brick work ,pit cover, Lightning rod/spike/hollow sphire and all necessary civil work,connections including all labour and materials as approved drawing and specification of this tender, IS 3043 & IEC 62305 and direction of OWNER / CONSULTANT. 0.00 0.00 0.00
3.1.1 GI Earth Electrodes 0.00 0.00 0.00
3.1.1.1 65 dia x 3000 mm Long GI pipe electrode type Earth pit Nos. 1 24,750.00 24,750.00 18% 4,455.00 29,205.00
3.1.2 Cu plate Earth Pit 0.00 0.00 0.00
3.1.3 Earth strip and wire 0.00 0.00 0.00
3.1.3.3 25x 6 mm GI Flat strip for Pole Earthing M 1 350.00 350.00 18% 63.00 413.00
3.1.3.5 Single core stranded 2.5 Sqmm Cu green earthing wire M 1 61.00 61.00 18% 10.98 71.98
3.1.3.6 Single core stranded 16 Sqmm Cu green earthing wire M 1 248.00 248.00 18% 44.64 292.64
3.1.3.7 Single core stranded 25 Sqmm Cu green earthing wire M 1 325.00 325.00 18% 58.50 383.50
3.1.3.8 Single core stranded 10 Sqmm Cu green earthing cable M 1 209.00 209.00 18% 37.62 246.62
3.1.3.9 300mm long 25x6 copper earth busbar with rigid insulator Nos. 1 2,475.00 2,475.00 18% 445.50 2,920.50
3.1.3.10 20mm dia 1500mm long copper vertical airterminal for lightning protection . Refer typical drawing attached in the bid documents for Lightning protection system. Nos. 1 5,720.00 5,720.00 18% 1,029.60 6,749.60
3.1.3.11 25x6mm GI strip for building roof & down conductor for lightning protection.Refer typical drawing attached in the bid documents for Lightning protection system. M 1 220.00 220.00 18% 39.60 259.60
3.1.3.12 200 x 200 x6 mm MS plate with anchor fastner as mentioned in typical drawing attached in the bid documents for Lightning protection system. Nos. 1 2,475.00 2,475.00 18% 445.50 2,920.50
4 OUTDOOR Lighting 0.00 0.00 0.00
4.1 Supply , Erection , Testing & commissioning of Outdoor area lighting system including with supply of flameproof / weather proof LED light fixture,hot dip galvanized lighting pole , junction box and earthing including supply of all necessary hardware , transportation at the place , un packing and all labour and materials as per approved drawings and General specification of Erection, Installation, Testing & commisioning of Electrical Equipments General specification for Lighting of this Tender and directions of OWNER / CONSULTANT. Refer TS Electrical package. 0.00 0.00 0.00
4.1.1 100W FLP LED Fixture (min.IP-65) high illumination level with exd type Junction box (min.IP-65), 4.5 mtr high pole for hazardeous /process area Nos. 1 27,500.00 27,500.00 18% 4,950.00 32,450.00
4.1.2 160W LED Fixture with 11mtr high pole with whether proof Junction box, for open area Nos. 1 30,910.00 30,910.00 18% 5,563.80 36,473.80
4.1.3 70 W Street LED Fixture with 9 mtr long pole with whether proof Junction box for street area lighting Nos. 1 21,450.00 21,450.00 18% 3,861.00 25,311.00
4.1.4 27 W Lantran LED Fixturewith whether proof Junction box for Gate for Gate lamp Nos. 1 13,750.00 13,750.00 18% 2,475.00 16,225.00
4.1.5 White LED Solar Light system with 6 mtr long hot dip galvanized steel tubular pole with with high efficiency multi crystaline cell ,VRLA battery/controller box, and with solar panel and other hardwares,cables ,connectors for Outdoor critical lighting Refer Electrical Design Basis, General Specification for Lighting & Technical data sheet of solar street light for further details. Nos. 1 132,000.00 132,000.00 18% 23,760.00 155,760.00
5 INDOOR Lighting 0.00 0.00 0.00
5.1 Supply , erection , Testing & commissioning of Indoor building area lighting system including with supply of LED light fixture with all assesories, point wiring,PVC conduit laying including supply of all necessary hardware , transportation at the place , un packing and all labour and materials as per approved drawings and General specification of Erection, Installation, Testing & commisioning of Electrical Equipments ,General specification for Lighting of this Tender and directions of OWNER / CONSULTANT. Refer TS Electrical package. 0.00 0.00 0.00
5.1.1 2x36 W LED decorative fixture for control room & Electrical room Nos. 1 4,015.00 4,015.00 18% 722.70 4,737.70
5.1.2 1x50W LED FLP, Industrial Fixture with FLP Junction box for battery room Nos. 1 15,950.00 15,950.00 18% 2,871.00 18,821.00
5.1.3 2x36W LED fixture for Store room/ Guard Room Nos. 1 2,915.00 2,915.00 18% 524.70 3,439.70
5.1.4 2x18W LED Industrial Fixture for Toilet /Varandah/Co2 area Nos. 1 2,695.00 2,695.00 18% 485.10 3,180.10
5.1.5 PVC Conduit including bend,tee, clamps,JB and other required assesories M 1 83.00 83.00 18% 14.94 97.94
5.1.6 Supply and installation of 150mm heavy duty pvc pipe should meet the latest IS 4985. M 1 300.00 300.00 18% 54.00 354.00
6 Switch socket 0.00 0.00 0.00
6.1 Supply , Installation ,testing of single phase Switch socket,regulators and MCB as per General specification of Erection, Installation, Testing & commisioning of Electrical Equipments and Indoor illumination layout for SV and Indoor illumination layout for Typical SV station and direction of OWNER / CONSULTANT. 0.00 0.00 0.00
6.1.1 5/15A surface type switch socket Nos. 1 935.00 935.00 18% 168.30 1,103.30
6.1.2 5A flush type socket OUTLET FOR EXHAUST FAN Nos. 1 715.00 715.00 18% 128.70 843.70
6.1.4 Flame proof Junction box for Exhaust fan in Battery room Nos. 1 1,705.00 1,705.00 18% 306.90 2,011.90
6.1.6 Modular switch board Nos. 1 935.00 935.00 18% 168.30 1,103.30
6.1.7 Supply ,Installation,testing of 50Amp / 63Amp ,4 pole MCB in existing OLDB Nos. 1 2,695.00 2,695.00 18% 485.10 3,180.10
7 FANS and Exhaust FAN 0.00 0.00 0.00
7.1 Supply ,Installation and testing of energy efficient Ceiling Fan and Exhaust fan with louvers including all labours and materials as per Indoor Illumination layout for SV and General specification of Erection, Installation, Testing & commisioning of Electrical Equipments , Electrical Design Basis and directions of OWNER / CONSULTANT. 0.00 0.00 0.00
7.1.2 450 mm FLP Exhaust Fan for battery room Nos. 1 23,650.00 23,650.00 18% 4,257.00 27,907.00
7.1.3 200 mm Exhaust Fan for toilet Nos. 1 4,730.00 4,730.00 18% 851.40 5,581.40
7.1.4 300 mm Exhaust Fan for Electrical room Nos. 1 9,350.00 9,350.00 18% 1,683.00 11,033.00
8 Air conditioning unit 0.00 0.00 0.00
8.1 Supply ,Installation and testing of Indoor & Outdoor unit of split AC including all labours and materials for Typical SV station refer specification of Erection, Installation, Testing & commisioning of Electrical Equipments and General Specification fo Air conditioningSystem and directions of OWNER / CONSULTANT. 0.00 0.00 0.00
8.1.1 1.5 Ton ,Five star Air condition INVERTER base unit Nos. 1 74,250.00 74,250.00 18% 13,365.00 87,615.00
9 Hardware and other Accessories 0.00 0.00 0.00
9.1 Supply and Installation of Hardware and other accessories including all labours and materials as per General specification of Erection, Installation, Testing & commisioning of Electrical Equipments , Electrical Design Basis , General Specification for Cable and accessories and directions of OWNER / CONSULTANT. 0.00 0.00 0.00
9.1.4 Aluminium tags for Cable Nos. 1 17.00 17.00 18% 3.06 20.06
9.1.5 Electrical hand gloves Pair 1 1,980.00 1,980.00 18% 356.40 2,336.40
9.1.6 Cable route marker as per Standard drawing Nos. 1 2,530.00 2,530.00 18% 455.40 2,985.40
9.1.7 Ladder type Cable tray - Galvanized steel fabricated out of hot rolled sheet steel with rigid welded ladder type 450 mm wide straight run M 1 715.00 715.00 18% 128.70 843.70
9.1.8 Ladder type Cable tray - Galvanized steel fabricated out of hot rolled sheet steel with rigid welded ladder type 300 mm wide straight run M 1 913.00 913.00 18% 164.34 1,077.34
10 Cable Glands 0.00 0.00 0.00
10.1 Cable Glands (Ex-d) : Flame proof IIA/IIB double compression type brass for out door termination of overall diameter including all labour and material as per approved drawings , specifications of this tender and direction of OWNER / CONSULTANT. 0.00 0.00 0.00
10.1.1 Cables with upto OD 20 mm Nos. 1 396.00 396.00 18% 71.28 467.28
10.1.2 Cables with above OD 20 mm Nos. 1 770.00 770.00 18% 138.60 908.60
10.2 Cable Glands : Weather proof double compression type brass for out door termination of overall diameter including all labour and material as per approved drawings , specifications of this tender and direction of OWNER / CONSULTANT. 0.00 0.00 0.00
10.2.1 Cables with upto OD 20 mm Nos. 1 369.00 369.00 18% 66.42 435.42
10.2.2 Cables with above OD 20 mm Nos. 1 468.00 468.00 18% 84.24 552.24
10.2.3 Cables with upto OD 30 mm upto 40 mm Nos. 1 699.00 699.00 18% 125.82 824.82
10.3 Supply and fixing of cable lugs of the following types and sizes as per Electrical package & Typical Single line diagram of this tender and direction of OWNER / CONSULTANT. 0.00 0.00 0.00
10.3.2 95 Sq mm aluminium lugs. Nos. 1 72.00 72.00 18% 12.96 84.96
10.3.3 70 Sq mm aluminium lugs. Nos. 1 66.00 66.00 18% 11.88 77.88
10.3.4 50 Sq mm aluminium lugs. Nos. 1 55.00 55.00 18% 9.90 64.90
10.3.5 35 Sq mm aluminium lugs. Nos. 1 44.00 44.00 18% 7.92 51.92
10.3.6 25 Sq mm aluminium lugs. Nos. 1 33.00 33.00 18% 5.94 38.94
10.3.7 16 Sq mm tinned copper lugs. Nos. 1 44.00 44.00 18% 7.92 51.92
10.3.8 10 Sq mm tinned copper lugs Nos. 1 33.00 33.00 18% 5.94 38.94
10.3.9 4 Sq mm tinned copper lugs Nos. 1 20.00 20.00 18% 3.60 23.60
10.3.10 6 Sq mm tinned copper lugs Nos. 1 28.00 28.00 18% 5.04 33.04
10.3.11 2.5 sq.mm tinned copper lugs Nos. 1 13.00 13.00 18% 2.34 15.34
11.00 Supply and Installation of Bolt on/Din-Rail Industrial type Fabricated Finished Enclosure (MCB Distribution Box)of Aproved Make Legrand, Hawells(4P MCB 8-Way Bolt on Type/Din Rail Type) Nos. 1 9,075.00 9,075.00 18% 1,633.50 10,708.50
12.00 Supply & installation of MCB, 10 KA of Aproved Make as per the GSPL Vendor list attached with this tender 0.00 0.00 0.00
13.0 Dismantling and stacking of damaged lighting pole / Solar lighting Ploe of sizes upto15M including excavation, cutting etc.& backfilling if required, completion of job in totality to the satisfaction of EIC within a lead of 100Mtr. The safe removal of existing luminaire, JBs, Earthing connection, cable connection etc. from the pole and handing over of same to GSPL is in contractor's scope. No separate charges shall be paid for manpower, consumables,lifting equipments, handling, tools & tackles used during execution of this activity. Nos 1 49,500.00 49,500.00 18% 8,910.00 58,410.00
14.0 Relocation of Lighting / Solar pole within the terminal which includes removal with or without RCC foundation & re-installation with proper foudation , concrete support etc. complete in all respect. This also includes leveling of old foundation location & backfilling if required, with all tools/tackles/labour/machinery/Hydra etc. Removal of fixtures, JB, earthing connections, Cable connections from pole at old location & reconnection and testing of all the system at new location is included in the scope. Nos 1 49,500.00 49,500.00 18% 8,910.00 58,410.00
15.0 Dismantling of cables including excavation and backfilling after removing the cables from cable trench/tray as specified in General specification. completion of job in totality to the satisfaction of EIC, the safe removal of existing cable, route marker etc. No separate charges shall be paid for manpower, consumables,lifting equipments, handling, tools & tackles used during execution of this activity. 0.00 0.00 0.00
16.0 Relaying of cables including excavation and backfilling of cable trench/tray as specified in TS- Erection, Installation, Testing & commisioning of Electrical Equipments / Cable route layout , termination , erection and testing of 1.1 KV Power FRLS XLPE Cables. completion of job in totality to the satisfaction of EIC, The safe laying of existing cable, route marker etc. No separate charges shall be paid for manpower, consumables,lifting equipments, handling, tools & tackles used during execution of this activity. 0.00 0.00 0.00
17.0 Dismantling and ReInstallation to other safe place of single phase 5/15 A Switch socket outlet, Switch boards as per TS- Erection, Installation, Testing & commisioning of Electrical Equipments and Indoor illumination layout for SV and Indoor illumination layout for Typical SV station and direction of OWNER / CONSULTANT. completion of job in totality to the satisfaction of EIC. The safe dismentling and reinstallation to other safe place of existing S/S outlet, wiring, conduiting etc. No separate charges shall be paid for manpower, consumables,lifting equipments, handling, tools & tackles used during execution of this activity. No. 1 979.00 979.00 18% 176.22 1,155.22
18.0 Dismantling of GI Pipe / Cu plate type earth electrode including GI/Cu strip complete in all respects.completion of job in totality to the satisfaction of EIC. The safe dismentling of GI Pipe / Cu Plate earth electrode etc. No separate charges shall be paid for manpower, consumables,lifting equipments, handling, tools & tackles used during execution of this activity. No. 1 16,500.00 16,500.00 18% 2,970.00 19,470.00
19.0 ReInstallation on safe place of GI Pipe / Cu plate type earth electrode complete with earth pit as per TS- Erection, Installation, Testing & commisioning of Electrical Equipments ,General specification for Earthing and Lightning Protection & Indoor and Outdoor earthing layouts of various station as described in Electrical package and all necessary material including excavation of earth pit , filling with charcol and salt , back filling, brick work ,pit cover, Earthing electrode and all necessary civil work,connections including all labour and materials as approved drawing and specification of this tender, IS 3043 & IEC 62305 and direction of OWNER / CONSULTANT. No. 1 25,300.00 25,300.00 18% 4,554.00 29,854.00
20.0 Dismantling of 40 kva DG set complete with Control panel, Exhaust pipe, L.T Cables, earthing etc.complete in all respects.completion of job in totality to the satisfaction of EIC. The safe removal of existing DG, Control panel, LT Cables connections, Exhaust pipe and earthings etc. from the existing location. No separate charges shall be paid for manpower, consumables,lifting equipments, handling, tools & tackles used during execution of this activity. No. 1 27,500.00 27,500.00 18% 4,950.00 32,450.00
21.0 ReInstallation on safe place of 40 KVA DG Set complete in all respect. This also includes leveling of old foundation location & backfilling if required, with all tools/tackles/labour/machinery/Hydra etc. Installation of control panel, earthing connections, Cable connections, Exhaust pipe from existing location & reconnection and testing of all the system at proposed location is included in the scope. No. 1 22,000.00 22,000.00 18% 3,960.00 25,960.00
22 TEMPORARY CATHODIC PROTECTION SYSTEM 0.00 0.00 0.00
22.1 Soil Resistivity Measurement, Soil Chemical analysis , Bonding from existing PCP system/existing pipeline ,Testing and commissioning & Monitoring of the temporary cathodic protection [TCP] system using galvanic anodes to protect the external surface of the entire steel grid network from, against soil-side corrosion for minimum 2 year or till commissioning of permanent CP system whichever is later . All work shall be carried out conforming to the Scope of work, Design Basis, Data Sheets, specification, standard and vendor list attached and provisions of TENDER including TS-TCP system OWNER/CONSULTANT approved survey report/design package, including all materials, equipments, consumables, start up/commissioning etc. including transportation, storage of materials at site, manpower, in line with direction of OWNER / CONSULTANT.Refere detail SOW and specification. TCP design shall include adequacy check of existing CP system(TR unit/Anodes) for bonding with exisitng PCP system. 0.00 0.00 0.00
22.2 Design engineering,all calculation of complete sacrificial anode cathodic protection system (Only Design) 0.00 0.00 0.00
22.2.1 6” NB 3LPE coated under ground gas pipeline Mtr 1 17.00 17.00 18% 3.06 20.06
22.2.2 8” NB 3LPE coated under ground gas pipeline Mtr 1 17.00 17.00 18% 3.06 20.06
22.2.3 12” NB 3LPE coated under ground gas pipeline Mtr 1 17.00 17.00 18% 3.06 20.06
22.3 Supply, Installation with civil foundation work for Normal size test station (IP 55) as per spec - Temporary cathodic protection Nos. 1 24,200.00 24,200.00 18% 4,356.00 28,556.00
22.4 Supply Installation with civil foundation work for Big size test station (IP 55) for HT crossing as per specification -Temporary cathodic protection Nos. 1 24,200.00 24,200.00 18% 4,356.00 28,556.00
22.5 Supply, Installation and testing Permanent Reference Cell with cotton bag & backfill material Nos. 1 24,200.00 24,200.00 18% 4,356.00 28,556.00
22.6 Supply, Installation and testing of MG Anode with all civil works Nos. 1 11,880.00 11,880.00 18% 2,138.40 14,018.40
22.7 Supply, Installation and testing of Zn Anode with all civil work Nos. 1 23,100.00 23,100.00 18% 4,158.00 27,258.00
22.8 Supply of pin including Installation and testing of pipe to cable connection by Pin Brazing Encapsulation method Nos. 1 6,380.00 6,380.00 18% 1,148.40 7,528.40
22.9 Supply, Installation and testing of Polarisation Coupons Nos. 1 8,250.00 8,250.00 18% 1,485.00 9,735.00
22.10 Supply Installation and testing of ER probe & reader for external corrosion monitoring Nos. 1 632,500.00 632,500.00 18% 113,850.00 746,350.00
22.11 Supply, Installation and testing of Solid State decoupling device and zinc grounding cell at the High tension pipelines locations as indicated in specification Nos. 1 276,100.00 276,100.00 18% 49,698.00 325,798.00
22.12 Supply, Installation and testing of isolating spark gap or surge divertor on isolation joint with connections on both side of IJ in the installed test station Nos. 1 35,200.00 35,200.00 18% 6,336.00 41,536.00
22.13 Supply & Installation of cables – Annealed high conductivity, tinned, stranded copper conductor, XLPE insulated, 650/1100 V grade, PVC,FRLS sheathed or as per specification and Miscellaneous such as termination, tagging, excavating the trench for cable laying, backfilling, etc., including the cost of all labour, materials, tools and tackles. 0.00 0.00 0.00
22.14 1C x 4 sqmm armoured - Anneled high conductivity tinned stranded copper conductor ,xlpe insulated,pvc sheathed,650V grade Mtr 1 319.00 319.00 18% 57.42 376.42
22.15 1C x 6 sqmm armoured - Anneled high conductivity tinned stranded copper conductor ,xlpe insulated,pvc sheathed,650V grade Mtr 1 385.00 385.00 18% 69.30 454.30
22.16 1C x 10sqmm armoured - Anneled high conductivity tinned stranded copper conductor ,xlpe insulated,pvc sheathed,650V grade Mtr 1 495.00 495.00 18% 89.10 584.10
22.17 1C x 25 sqmm armoured - Anneled high conductivity tinned stranded copper conductor ,xlpe insulated,pvc sheathed,650V grade Mtr 1 550.00 550.00 18% 99.00 649.00
22.18 1C x 35 sqmm armoured - Anneled high conductivity tinned stranded copper conductor ,xlpe insulated,pvc sheathed,650V grade Mtr 1 600.00 600.00 18% 108.00 708.00
22.19 Supply and installation of 6 mm thick HDPE sheet under the HT Line crossing or Foreign pipeline SQ. Mtr 1 1,021.00 1,021.00 18% 183.78 1,204.78
22.20 Dismentaling ,Relocation & "fit to use " of Reference cell including cabling and all other accessories, including cable laying, trenching, routing, marking and retermination complete in all respects. Nos. 1 16,500.00 16,500.00 18% 2,970.00 19,470.00
22.21 Dismantling of TLP including excavation, cutting etc.& backfilling if required, completion of job in totality to the satisfaction of EIC. The safe removal of existing TLP, cables, cable connection, removal of foundation etc. and handing over of same(TLP, cables & cable terminations etc.) to GSPL is in contractor's scope. No separate charges shall be paid for manpower, consumables, lifting equipments, handling, tools & tackles used during execution of this activity. No. 1 16,500.00 16,500.00 18% 2,970.00 19,470.00
22.22 Relocation of existing test station as per enclosed drawings and technical specifications. Work shall include all related civil works including foundation, termination of cables inside the test stations along with lugs & ferules sealing of cable entry space with bitumen compound supply of all materials, consumables, tools, tackles, etc. for satisfactory completion of work and as per directions of EIC. No. 1 22,000.00 22,000.00 18% 3,960.00 25,960.00
23 PERMANENT CATHODIC PROTECTION SYSTEM 0.00 0.00 0.00
23.1 Design, engineering,supply,installation,testing ,commissioning with all post commissioning surveys,preparation/submission & approvals of documents & Asbuilts drawings/documents of complete permanent cathodic protection system having life of 40 years.The scope shall include acquisition of land for anode ground bed and anode junction box and for laying of cables. The scope shall also include disconnection of temporary cathodic protection system wherever it is not the part of PCP before commissioning and reconnect it after commissioning, installation of independent sacrificial type CP System, laying and termination of all the cables of CP system, including all the CP cables . Supply, Installation, testing and commissioning of CPTR unit ,CTSU & reader,Permanent Cu/CuSO4 Reference cell,cp cables,cable route markers, Deepwell/shallow type anode ground bed as per soil resistivity with MMO lida tubular anode,coke breeze,anode & cathode tail cable. The scope shall also include any civil & fabrication works like pcc foundation ,tenching,backfilling,drilling for installation of anode ,chanlink & fencing . The scope shall also include three months cp monitoring after commissioning of pcp system. Refere detail SOW and specification. 0.00 0.00 0.00
23.1.1 Design,Engineering,Attenuaction calculation for Permanent Cathodic Protection system of proposed section /pipeline as per TS -Permanent cathodic protection system. Per Package 1 204,600.00 204,600.00 18% 36,828.00 241,428.00
23.1.2 Supply, Installation with civil foundation work for Anode Junction Box (IP 55) as per tender specification & drawing. Nos. 1 46,200.00 46,200.00 18% 8,316.00 54,516.00
23.1.3 Supply, Installation with civil foundation work for Cathode Junction Box (IP 55)as per tender specification & drawing. Nos. 1 33,000.00 33,000.00 18% 5,940.00 38,940.00
23.1.4 supply,Installation and testing of Floor mounted CPTR unit ,suitable to 230 V ac supply having Min capacity of 25A/25V,IP-52,with remote montioring and control through SCADA facility as per TS -Permanent cathodic protection system. Nos. 1 448,800.00 448,800.00 18% 80,784.00 529,584.00
23.1.5 supply,Installation and testing of Deep well type Anode bed using MMO lida tubular anodes (size & quantity a per attenuciation calculation) with all civil & fabrication associated acivites and required materials like vent pipe,MS pipe,pvc pipe as per TS -Permanent cathodic protection system & SOW for PCP system attached in the bid documents for further details work . (Note : Cables required from Anode bed to TR unit or any where shall be paid seperately in respective line item of SOR) Nos. 1 957,000.00 957,000.00 18% 172,260.00 1,129,260.00
23.1.6 supply,Installation and testing of Shallow type Anode bed using MMO LIDA tubular anode (size & quantity as per attenuciation calculation) with all civil & fabrication associated acivites and required materials like including GI cannister ,PVC pipe with end cap,sand ,bricks etc. as per TS -Permanent cathodic protection system & SOW for PCP system attached in the bid documents for further details work . (Note : Cables required from Anode bed to TR unit or any where shall be paid seperately in respective line item of SOR.) Nos. 1 627,000.00 627,000.00 18% 112,860.00 739,860.00
23.1.7 Supply, Installation and testing Permanent Reference Cell with Special Backfill in Cotton bag Nos. 1 42,240.00 42,240.00 18% 7,603.20 49,843.20
23.1.8 Supply, Installation and testing of Anode tail cable 1CX16 sq.mm HMWPE sheathed & PVDF 1100 V ,un armoured cable Mtr 1 317.00 317.00 18% 57.06 374.06
23.1.9 Supply, Installation and testing of Anode & Cathode header cable 1CX35 sq.mm Annealed,high conductivity,copper conductor, xlpe insulated,pvc sheathed FRLS armoured cable Mtr 1 726.00 726.00 18% 130.68 856.68
23.1.10 Supply, Installation and testing of reference cell & monitoring cable 1CX4 sq.mm Annealed,high conductivity,copper conductor, xlpe insulated,pvc sheathed FRLS armoured cable Mtr 1 343.00 343.00 18% 61.74 404.74
23.1.11 Supply and installation of 8 pair, 1.5 mm2, copper conductor PVC insulated screened cable for sending analogue signals between CPTR & SCADA system I/O rack Mtr 1 343.00 343.00 18% 61.74 404.74
23.1.12 Supply, Installation and testing of CTSU & Reader at selected location by Engineer Incharge Nos. 1 72,600.00 72,600.00 18% 13,068.00 85,668.00
23.2 Post Commissioning surveys as per TS -Cathodic protection system 0.00 0.00 0.00
23.2.1 Closed Interval potential logging Survey (CIPL) Mtr 1 11.00 11.00 18% 1.98 12.98
23.2.2 AC-DC Interference Survey & Mitigation measure Mtr 1 11.00 11.00 18% 1.98 12.98
23.2.3 Coating conductance survey Mtr 1 5.00 5.00 18% 0.90 5.90
23.2.4 Current Attenuation Survey (CAT) Survey Mtr 1 5.00 5.00 18% 0.90 5.90
23.2.5 Direct Current Voltage Gradient Survey (DCVG) Survey Mtr 1 5.00 5.00 18% 0.90 5.90
23.3 CP monitoring for three months after pcp commissioning from the date of commissioning with monthly progress reports & mitigation of any anomaly required to tune up the functioning of PCP system Mtr 1 3.00 3.00 18% 0.54 3.54
24.0 Total of Electrical and Temporary cathodic Protection and Permanent Cathodic protection system associated work in schedule D (In Rs.) 14023770.00 14023770.00 2524278.6 16548048.6
1 The rates are in INR excluding GST. GST shall be payable extra at actual.
2 The quantity indicated above are Tentative.
3 All Above works shall be executed in accordance with SCOPE OF WORK, Specification, Data Sheets, QAP, Drawings and other provision of bid documents and instruction of Owner/ Owner's Representative.
4 Bidder to confirm full complience to spec. Deviations are not allowed and shall make liable for rejection
5 The above total prices shall be inclusive of all TPI, packing, forwarding, handling, storage, stacking, Transportation, spares , special tools , tackles,loading and unloading charges up to final destination site but does not include taxes
6 All the items required to complete the work shall be the scope of supply of contractor only.
7 This work is exclusive of all works associated with Station Mechanical only.
8 All other works pertaining to pipeline, Station Architecture/civil/Structural/Instrumentation works shall be as per rates indicated elsewhere in the tender document.
9 Work is inclusive of receiving, taking over, loading & unloading, storage of company supplied material and return of surplus material to Company's designated stockyard/store.
10 Prices quoted shall include the following
a) All handling , transportation including marine transportation( if applicable) , liason , port fee, ware house , handling , all fees customs duty etc.
b) All design , engineering, supply, installation,, tech support and guarantee
11 Owner supplied Material as per Scope Of Work, are free issued supply by Owner. However, Erection, Installation and integration of these free issue materials is in Contractor's scope.
12 Receiving, taking over, loading & unloading, storage of company supplied material Free issue Materials from Owner's storage to Site is in Contractor's Scope.
13 Preparation of all As-Built drawings will be in contractor's scope.
Annexure-C Unit Base Rate/ SCHEDULE OF RATES (Tender no.: GTL/PROC/2026/08/O/502; (n)Procure Tender ID: 340579)
HIRING OF CONTRACTOR FOR CUSTOMER CONNECTIVITY PIPELINE PROJECTS ACROSS GUJARAT
INSTRUMENTATION AND ASSOCIATED WORKS
DOCUMENT NO.: GTL-ARC-DOC-SOR-060-04-01
Rev. -0 dated 06.07.2026
S. No. Description of Items Unit Quantity HSN/SAC Unit Rate Total Basic Amount GST Total Amount with GST
(Basic) % Amount
A B C D E F G = D x F H I J = G + I
1.1 Instrument Supply & Installation in Field :
1.1.1 a) Engineering , Design, ,Supply, Installation, Calibration, Testing & Commissioning of Pressure Gauges (0-100 Barg) inclusive of supply of necessary piping materials/tubings along with all necessary valves & fittings, fabrication and installation of impulse lines/manifolds , supports & testing. as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 26,400.00 26,400.00 18% 4,752.00 31,152.00
b) Engineering , Design, ,Supply, Installation, Calibration, Testing & Commissioning of Pressure Gauges (0-60 Barg) inclusive of supply of necessary piping materials/tubings along with all necessary valves & fittings, fabrication and installation of impulse lines/manifolds , supports & testing. as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 26,400.00 26,400.00 18% 4,752.00 31,152.00
c) Engineering , Design, Supply, Installation, Calibration, Testing & Commissioning of Pressure Gauges (0-1 Barg) inclusive of supply of necessary Gauge saver along with all necessary valves & fittings, fabrication and installation of impulse lines/manifolds , supports & testing. as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 30,800.00 30,800.00 18% 5,544.00 36,344.00
d) Engineering , Design, Supply, Installation, Sizing, Testing & Commissioning of Pressure Safety valve as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 192,500.00 192,500.00 18% 34,650.00 227,150.00
1.1.2 Transmitter
a) Engineering , Design, Supply, Installation, Calibration, Testing & Commissioning of Pressure Transmitters including mounting of Instrument on yoke, canopy , supply of yoke, supply and erection of supports for impulse lines wherever required, supply, fabrication & installation of SS manifolds/ SS impulse lines & SS valves & fittings with supports, testing and painting of supports. as per Specification , QAP and Technical datasheet of RFP Technical document. Nos. 1 143,000.00 143,000.00 18% 25,740.00 168,740.00
b) Engineering , Design, Supply, Installation, Calibration, Testing & Commissioning of Temperature Transmitters including mounting of Instrument on yoke, supply of yoke, supply and erection of supports for impulse lines wherever required, supply, fabrication & installation of SS manifolds/ SS impulse lines & SS valves & fittings with supports, testing and painting of supports as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 69,300.00 69,300.00 18% 12,474.00 81,774.00
c) Engineering , Design with wake frequency calculation, Supply , Installation, Calibration, Testing & Commissioning of RTD welded type thermowell (as per approved Piping GAD & Hook-up drawings) inclusive of installation of thermowell on the piping nozzle and installation of instruments as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Set 1 25,300.00 25,300.00 18% 4,554.00 29,854.00
d) Engineering , Design with wake frequency calculation, Supply , Installation, Calibration, Testing & Commissioning of RTD Skin type (as per approved Piping GAD & Hook-up drawings) and installation of instruments as per General Specification-Instrumentation ,SOW, Technical datasheet of RFP Technical document. Set 1 22,550.00 22,550.00 18% 4,059.00 26,609.00
e) Engineering , Design with wake frequency calculation, Supply , Installation, Calibration, wake frequency calculation , Testing & Commissioning of Temp. Gauge with welded type thermowell (as per approved Piping GAD & Hook-up drawings) inclusive of installation of thermowell on the piping nozzle and installation of instruments as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Set 1 13,750.00 13,750.00 18% 2,475.00 16,225.00
f) Engineering , Design, Supply of Universal Hand Held Communicator / HART Configurator as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 852,500.00 852,500.00 18% 153,450.00 1,005,950.00
1.1.3 a) Engineering , Design, Supply, Installation, Testing & Commissioning of Intrusive Pig Signaller as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 676,500.00 676,500.00 18% 121,770.00 798,270.00
b) Engineering , Design, Supply, Installation, Testing & Commissioning of Non Intrusive Pig Signaller as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document. Nos. 1 770,000.00 770,000.00 18% 138,600.00 908,600.00
1.1.4 a) Design , Engineering , Volume calculation ,Power consumption Calculation, Supply, Installation, Testing and commissioning of Fire alarm system and CO2 Flooding system including common Fire alarm cum suppression panel with Detector , cylinder , directional valve , NRV , PSV , Pressure switch , Actuation hose , cylinder stand , Electrically glow type EXIT board, Hooter/Flasher , Siren , MCP , Cables ( LHS, Power and Signal) and Manual release switches( as per final approved Bill of material and GA drawing ) inclusive of Battery & Battery box as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document and in accordance with latest NFPA. Set 1 2,420,000.00 2,420,000.00 18% 435,600.00 2,855,600.00
b) Supply, Installation, Testing and commissioning of Optical detector as per approved data sheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis` Nos. 1 2,888.00 2,888.00 18% 519.84 3,407.84
c) Supply, Installation, Testing and commissioning of Multicriteria detector as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 3,465.00 3,465.00 18% 623.70 4,088.70
d) Supply, Installation, Testing and commissioning of Directional valve as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 36,850.00 36,850.00 18% 6,633.00 43,483.00
e) Supply, Installation, Testing and commissioning of Actuation hose as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 4,043.00 4,043.00 18% 727.74 4,770.74
f) Supply, Installation, Testing and commissioning of NRV for cylinder bank as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 3,696.00 3,696.00 18% 665.28 4,361.28
g) Supply, Installation, Testing and commissioning of weight monitoring system for cylinder bank as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 11,550.00 11,550.00 18% 2,079.00 13,629.00
h) Supply, Installation, Testing and commissioning of Electrically glow type EXIT sign board as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 3,465.00 3,465.00 18% 623.70 4,088.70
i) Supply, Installation, Testing and commissioning of Manual call point as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 3,465.00 3,465.00 18% 623.70 4,088.70
j) Supply, Installation, Testing and commissioning of Pressure switch as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 5,280.00 5,280.00 18% 950.40 6,230.40
k) Supply, Installation, Testing and commissioning of Hooter with Flasher as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 9,240.00 9,240.00 18% 1,663.20 10,903.20
l) Supply ,Installation , Testing and commissioning of OEM Electronic Cards/Microprocessor cards suitable to new/existing Fire Alarm Cum Release Panel Nos. 1 135,850.00 135,850.00 18% 24,453.00 160,303.00
NOTE : Loose supply of above item of Sr No.: 1.1.4 b) to 1.1.4 l) shall be paid separately. The same shall not be paid separately in case of Fire alarm system and CO2 Flooding system supplied in set as per approved documents. i.e. in item no.: 1.1.4 a).
1.1.5 a) Design , Engineering , Volume calculation ,Power consumption Calculation, Supply, Installation, Testing and commissioning of Fire alarm system and clean agent flooding system [ Inert Gas ] including common Fire alarm cum suppression panel with Detector , cylinder , directional valve , NRV , PSV , Pressure switch , Actuation hose , cylinder stand , Electrically glow type EXIT board, Hooter/Flasher , Siren , MCP , Manual abort switch ,Cable ( LHS, Power and Signal), Manual Abort Switch and Manual release switches( as per final approved Bill of material and GA drawing ) inclusive of Battery & Battery box as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis of RFP Technical document and in accordance with latest NFPA . Set 1 2,750,000.00 2,750,000.00 18% 495,000.00 3,245,000.00
b) Supply, Installation, Testing and commissioning of Optical detector as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 3,080.00 3,080.00 18% 554.40 3,634.40
c) Supply, Installation, Testing and commissioning of Multicriteria detector as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 3,465.00 3,465.00 18% 623.70 4,088.70
d) Supply, Installation, Testing and commissioning of Directional valve as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 46,200.00 46,200.00 18% 8,316.00 54,516.00
e) Supply, Installation, Testing and commissioning of Actuation hose as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 11,550.00 11,550.00 18% 2,079.00 13,629.00
f) Supply, Installation, Testing and commissioning of NRV for cylinder bank as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis Nos. 1 12,870.00 12,870.00 18% 2,316.60 15,186.60
g) Supply, Installation, Testing and commissioning of Electrically glow type EXIT sign board as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 3,465.00 3,465.00 18% 623.70 4,088.70
h) Supply, Installation, Testing and commissioning of Manual call point as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 3,465.00 3,465.00 18% 623.70 4,088.70
i) Supply, Installation, Testing and commissioning of Pressure switch as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 5,060.00 5,060.00 18% 910.80 5,970.80
j) Supply, Installation, Testing and commissioning of Hooter with Flasher As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 9,240.00 9,240.00 18% 1,663.20 10,903.20
k) Supply, Installation, Testing and commissioning of Manual abort switch as per approved datasheet & General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 4,070.00 4,070.00 18% 732.60 4,802.60
l) Supply ,Installation , Testing and commissioning of OEM Electronic Cards/Microprocessor cards suitable to new/existing Fire Alarm Cum Release Panel Nos. 1 135,850.00 135,850.00 18% 24,453.00 160,303.00
NOTE : Loose supply of above item of Sr No.: 1.1.5 b) to1.1.5 l) shall be paid separately. The same shall not be paid separately in case of Fire alarm system and CLEAN AGENT system [ Inert Gas ] supplied in set as per approved documents. i.e. in item no.: 1.1.5 a).
1.1.6 a) Design, Engineering, Power consumption , Supply, Installation, Testing & Commissioning of LEL GAS Detection System including Controller Unit in Control Panel , FLP Junction box , Cable ,Glands & Sensors . Please note following item for the quantification as "Set" • 1 set ( TX & RX) OPGD with Pole and accessories • 1 Nos of PGD with stand and accessories • 1 No of wall mounted panel ( with 16 Channel Control Card, Power supply, Channel card for detector etc.) • 1 No of Hooter • 1 No of Beacon • 1 no of junction box (This shall be as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents attached in the Bid Document . Set 1 1,650,000.00 1,650,000.00 18% 297,000.00 1,947,000.00
b) Supply, Installation, Testing and commissioning of Open Path Gas detector as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 587,400.00 587,400.00 18% 105,732.00 693,132.00
c) Supply, Installation, Testing and commissioning of Point Gas detector as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 178,200.00 178,200.00 18% 32,076.00 210,276.00
d) Supply, Installation, Testing and commissioning of Portable Gas detector as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 189,750.00 189,750.00 18% 34,155.00 223,905.00
e) Supply, Installation, Testing and commissioning of Monitor/controller as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 433,400.00 433,400.00 18% 78,012.00 511,412.00
f) Supply, Installation, Testing and commissioning of Hooter and Beacon as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 66,440.00 66,440.00 18% 11,959.20 78,399.20
g) Supply, Installation, Testing and commissioning of FLP Junction box as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 29,700.00 29,700.00 18% 5,346.00 35,046.00
h) Dismantling ,Relocation & "fit to use " of existing OPGD detector along with pole & all accessories including cable laying ,trenching, routing ,marking ,retermination and loop checking Nos. 1 26,070.00 26,070.00 18% 4,692.60 30,762.60
i) Dismantling ,Relocation & "fit to use " of existing PGD detector along with pole & all accessories including cable laying ,trenching, routing ,marking ,retermination and loop checking Nos. 1 17,820.00 17,820.00 18% 3,207.60 21,027.60
j) Dismantling ,Relocation & "fit to use " of Junction Box with stand detector along with pole & all accessories including cable laying ,trenching, routing ,marking ,retermination and loop checking Nos. 1 14,850.00 14,850.00 18% 2,673.00 17,523.00
k) Dismantling ,Relocation & "fit to use " of Hooter/Beacon with stand detector along with pole & all accessories including cable laying ,trenching, routing ,marking ,retermination and loop checking Nos. 1 14,850.00 14,850.00 18% 2,673.00 17,523.00
l) Supply, Installation, testing and commissioning of controller cards for existing Gas Detector Panel including all accessories such as prefab cable, terminal block, barriers/isolators, relays, relay board, C-channel, PVC conduit with cover, MCB fuse etc. complete in all respects. No. 1 55,000.00 55,000.00 18% 9,900.00 64,900.00
NOTE : Loose supply of above item of Sr No.: 1.1.6 b) to1.1.6 l) shall be paid separately. The same shall not be paid separately in case of LEL GAS Detection System supplied in set as per approved documents. i.e. in item no.: 1.1.6 a).
1.1.7 Optical Fibre Cable & HDPE Duct
a) Design, Engineering, Manufacturing and testing, Supply, Transportation, Erection /Installation by using blowing techniques in HDPE lubricated duct, Splicing and field testing by OTDR of Optical Fibre Cable. OFC armoured cable shall be 24 Nos.single mode fibres in accordance to ITU-T-G-655 suitable to 1550/1625 nm wavelength & Telecordia GR-20 core compliant as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents mtr 1 160.00 160.00 18% 28.80 188.80
b) Design, Engineering, Manufacturing, testing, Supply, Testing, Inspection, Transportation, Erection/Installation / Laying of 50mm Outer Diameter PLB HDPE Duct for OFC in common trench along with pipeline as per Specification mtr 1 127.00 127.00 18% 22.86 149.86
c) Design, Engineering, Manufacturing, testing, Supply, Testing, Inspection, Transportation, Erection /Installation / Laying of 50mm Outer Diameter PLB HDPE Duct for OFC in separate trench with excavation and backfilling of the trench as per Specification mtr 1 451.00 451.00 18% 81.18 532.18
d) Engineering, Manufacturing, Supply, Inspection, Transportation, Erection, Installation of OFC distance marker (on pipeline) as per specification Nos. 1 22,550.00 22,550.00 18% 4,059.00 26,609.00
e) Engineering, Manufacturing, Inspection & Testing, Supply, , Transportation, Erection, Installation of any type of jointing closure as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 16,913.00 16,913.00 18% 3,044.34 19,957.34
f) Supply , Engineering, Manufacturing, Inspection, Transportation, Erection, Installation of joint pit , electronic route marker and connection of OFC in jointing pit with cover as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents Nos. 1 16,913.00 16,913.00 18% 3,044.34 19,957.34
Miscellaneous Items 0.00
1.1.7.1 OFC Splicing Joint : OFC-24 Fiber Jointing at pit location / FTC including pigtails by preparation of fiber, removal of the sheath, cleaning of the fiber, fixing the fiber to the LIU with proper clamping / ties. Numbering of the fiber using ferrules, splicing the fiber to the pigtail, proper routing of the fiber in the cassette. Proper closure of the cassette, connecting the pigtail to the adapter, and marking the same, for 1-24 fibers joints. Job Include Supply of Jointing Enclosure for 24 core Fiber Cable, Weather proof, as per Standard Specification and approved make ( Raychem, 3 M make ) and Fault finding & identification using OTDR. End to end testing of fibres after jointing and submission of report. In case of unacceptable dB loss at repair joint same needs to be rectified with-out any cost implication to GSPL. Final end to end OTDR test shall be carried-out for all 24 Fibres & submit the report without any cost implication to GSPL. No separate charges shall be paid for manpower, instruments, transportation used during this activity. Visit for fault finding & final testing shall be considered as one visit only. Complete Link Testing End to End with Power Source, Laser Source, OTDR meter working with 1310 nm and 1550 nm from both end including Pigtails, Patch cord for testing. Submission of all 24 core OTDR traces between two terminals or across the joints No separate charges will be paid for Pit Excavation & back-filling for particular joint location. Nos. 1 17,325.00 17,325.00 18% 3,118.50 20,443.50
1.1.7.2 6" HDPE Duct - between pull pit to control room/electrical room for the cable insertion Nos. 1 2,860.00 2,860.00 18% 514.80 3,374.80
1.1.8 Signal Cable , Cable Gland , Cable tray, Junction box and MCT Block
Supply and Laying of control, signal, multipair, single triad cables onfield to respective Junction box (Installation of JB with RCC support as per the hook-up drawing) and on main cable trays, perforated trays, trenches including supply of all required cable glands(Explosion proof double compression type) and consumables like ferrules, clamps, PVC tubes, aluminium/SS tag plates etc., clamping , ferruling, glanding of the cables, termination at both ends, including shield/drain/ communication wire, providing/fixing of identifying tags and megger testing and loop testing inclusive of supply & erection of GI Perforated tray in Process area and buried cable for outdoor area with RCC hume pipe for road crossing and laying the cables in cable trench on tray in control room. Scope and supply shall be as per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents. Note - RCC support and RCC hume pipe shall be paid shall be paid in Civil SOR.
m) - 2P x 1.5 mm² - Quad Cable for RTD Mtr. 1 319.00 319.00 18% 57.42 376.42
o) RS-232/485 Serial interface Cable Mtr. 1 264.00 264.00 18% 47.52 311.52
p) Flameproof double compression Cable Gland 1/2" NPT Nos. 1 303.00 303.00 18% 54.54 357.54
q) Flameproof double compression Cable Gland 3/4" NPT Nos. 1 413.00 413.00 18% 74.34 487.34
r) Flameproof double compression Cable Gland 1/2"ET Nos. 1 248.00 248.00 18% 44.64 292.64
s) Flameproof double compression Cable Gland 3/4"ET Nos. 1 325.00 325.00 18% 58.50 383.50
t) Flameproof double compression Cable Gland 11/2"ET Nos. 1 660.00 660.00 18% 118.80 778.80
u) Flameproof double compression Cable Gland 1 " ET Nos. 1 451.00 451.00 18% 81.18 532.18
v) Perforated Cable tray ( 60 mm wide x 30 mm hight) Mtr. 1 451.00 451.00 18% 81.18 532.18
w) Perforated Cable tray ( 100 mm wide x 30 mm hight) Mtr. 1 616.00 616.00 18% 110.88 726.88
x) Ladder type Cable tray ( 300 mm wide x 30 mm hight) Mtr. 1 891.00 891.00 18% 160.38 1,051.38
y) Flameproof Junction box as per specification with Plug and suitable for cable entries of single pair and multi pair cable as per the Instrument cable schedule Nos. 1 24,200.00 24,200.00 18% 4,356.00 28,556.00
z) Multi cable Transit (MCT) block with stay plate and module as per the approved datasheet Nos. 1 137,500.00 137,500.00 18% 24,750.00 162,250.00
2.0 CONTROL PANEL AND PANEL MOUNTED INSTRUMENTS IN CONTROL ROOMS
2.1 Design, Engineering, Procurement, Manufacture, Testing, Inspection, Supply, Transportation, Erection, Calibration / Simulation, Loop checking & Commissioning of Local Control Panels (Free Standing type floor mounted) along with all accessories and Panel Mounted Instruments as indicated below, including supply of commissioning spares with special tools and tackles as required, as per Data Sheets / Specification in the Bid Document Set 1 671,000.00 671,000.00 18% 120,780.00 791,780.00
Control Panel (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents)
a) Supply and installation of Indicators (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 23,650.00 23,650.00 18% 4,257.00 27,907.00
b) Supply and installation of Signal Repeater / Multiplier (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 15,400.00 15,400.00 18% 2,772.00 18,172.00
c) Supply and installation of Barriers (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 15,400.00 15,400.00 18% 2,772.00 18,172.00
d) Supply and installation of Annunciator (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 49,500.00 49,500.00 18% 8,910.00 58,410.00
e) Supply and installation of Process Indicator (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 35,200.00 35,200.00 18% 6,336.00 41,536.00
f) Supply and installation of AC power to DC power Converter ( Power Module) (As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) Nos. 1 13,200.00 13,200.00 18% 2,376.00 15,576.00
g) Supply & Replacement of GSPL approved make Selector switch in Instrument local control panel. The job shall be carried out by qualified instrument technician /electrician. Nos. 1 4,950.00 4,950.00 18% 891.00 5,841.00
h) Supply, installation , Testing and commission of relays and relay boards, for existing LCP Panel including all accessories such as prefab cable, terminal block, C-channel, PVC conduit with cover, MCB, fuse etc. complete in all respects. Nos. 1 16,500.00 16,500.00 18% 2,970.00 19,470.00
NOTE : Loose supply of above item of Sr No.: 2.1 a) to h) shall be paid separately. The same shall not be paid separately in case of Local Control Panels supplied in set as per approved documents. i.e. in item no.: 2.1.
3.0 Start up and commissioning
3.1 Start up & Commissioning of complete terminal Field instruments, Loop checking including all labour, test equipments and other auxiliaries as required, etc., complete in all respects as per specifications/ drawings/ directions of Engineer-in-Charge. All necessary Testing and commissioning reports, as-built drawings etc., shall also be prepared and to be submitted to the client /consultant
3.2 Metering skid (Free Issue material) such as cable laying & termination from Field JB to Control room mounted Panel with necessary accessories etc., installation of Metering Panel within control room and interfacing with RTU panel as per As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents). Contractor's Scope will also include Receiving, taking over, loading & unloading, transportation ,storage of supplied this Free issue Materials from Owner's storage/designated store to Site NOTE : Any supply of materials by contractor for erection / installation, testing of skid other than free issue shall be paid extra. Lumpsum per skid 1 258,500.00 258,500.00 18% 46,530.00 305,030.00
3.3 Metering skid cable laying & termination from Field JB to Field mounted Panel and Installation of Solar Power system as per instruction of Client/PMC instruction as per As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis documents) . Contractor's Scope will also include Receiving, taking over, loading & unloading, transportation ,storage of supplied this Free issue Materials from Owner's storage/designated store to Site NOTE : Any supply of materials by contractor for erection / installation, testing of skid other than free issue shall be paid extra. Lumpsum per skid 1 203,500.00 203,500.00 18% 36,630.00 240,130.00
4.0 Supply and installation of Fire Fighting Equipment All fire extinguishers shall bear ISI or equivalent mark. Manuals of each fire extinguisher shall be provided at every location. NOTE : The quantity and size of fire extinguishers required shall be provided based on the nature of occupancy and class of fire/risk to be protected with prior approval of Owner.
g) 6 Nos of Sand buckets with stand Nos. 1 11,770.00 11,770.00 18% 2,118.60 13,888.60
h) 4 Nos of Sand buckets with stand Nos. 1 11,880.00 11,880.00 18% 2,138.40 14,018.40
5.0 Calibration of secondary instruments such as Pressure Transmitter, Diff Pressure Transmitter, Level Transmitter (DP Type),Temperature Transmitter, Pressure Gauge, Diff Pressure Gauge, Temperature Gauge, RTD at respective locations. (Trained manpower as well as master calibrator along with all tools and tackles, consumables, etc. required for removal, calibration and reinstallation of field instruments is in the scope of contractor).
a) PT of Calibration Range (0-100 barg) Nos. 1 3,850.00 3,850.00 18% 693.00 4,543.00
b) TT of Calibration Range (-30 to + 70 deg. C) Nos. 1 2,750.00 2,750.00 18% 495.00 3,245.00
c) LT (Type Differential Pressure) of Calibration Range (0-500 mmH2O) Nos. 1 3,850.00 3,850.00 18% 693.00 4,543.00
d) PG of Calibration Range (0-100 barg) Nos. 1 1,375.00 1,375.00 18% 247.50 1,622.50
e) PG of Calibration Range (0-60 barg) Nos. 1 1,375.00 1,375.00 18% 247.50 1,622.50
f) TG of Calibration Range (0-100 deg.C) Nos. 1 2,750.00 2,750.00 18% 495.00 3,245.00
g) DPG of Calibration Range (0-2 barg) Nos. 1 3,850.00 3,850.00 18% 693.00 4,543.00
h) DPT of Calibration Range(0-2 barg) Nos. 1 3,850.00 3,850.00 18% 693.00 4,543.00
6.0 Testing and Calibration of PSV/CRV: Calibration of PSV/CRV sizes as given below with men, materials tools & tackles, consumables. The job including dismantling of PSV/CRV from the filter equipment/Pipeline/ Launcher/Receiver/Actuator Valve cylinders/PRS skid at height of maximum 3 meter, blinding of one upstream side of line flange of removed space of valve, Cleaning of all components by kerosene if required, Lapping of nozzle & disc if required, assembly of valve with repaired component, Calibration and Testing as found as left set pressure of valve at spot with all required materials tools & tackles. seat tightness required at 90% of test pressure & calibration of PG is required. Re-installation/errection of PSV/CRV on Filter equipment/Pipeline/ Launcher/Receiver/Actuator Valve cylinders/PRS skid in position after testing/calibration. Consumable such as nitrogen, grease, testing gaskets & painting of Valves etc. shall be arranged at site by the contractor for the above job. Gasket for the pipes / joint flanges shall be provided by contractor. Issuing a certificate of calibration by a competent person as per SMPV latest rules. The job shall be done by the competent person who has certificate possessing by issued Factory Inspector. All type of transportation is included in the job
7.0 Supply & Installation of 12V SMF Battery of Approved make. No separate charges shall be paid for manpower, consumables, equipments, tools & tackles used during execution of this activity. Contractor shall buyback the old battery.F140:P140
8.0 Modification of Local Control Panel (LCP) and Gas Detection Panel (GDP)
8.1 a) Modification of Local Control Panel (LCP) covers the minimum below ; Provision of the necessary panel cutout (If spare not available ) in existing panel for process indicator for PT and TT , Provision of additional lamp or selector switch or push button with necessary wiring (If spare not available) for GOOV and it's wiring for new field instrument signals with existing spare of the panel. Provision of Process indicator (Bar graph) with wiring for new PT and TT if spare not available Provision of barrier and repeater with necessary wiring as per the loop scheme for new PT, TT and GOV if spare are not available. Provision of Terminal block module with wiring if spare terminals are not available in AITB , DITB and SCADA TB. Provision of delay timer and relay with wiring for new GOOV logic if spare not available SET 1 291,500.00 291,500.00 18% 52,470.00 343,970.00
NOTE : Either one or more spares/modification / changes executed in existing LCP shall be completely payment paid as per above 8.1 based on approved documents. Further, All necessary hardware required for modification of panel shall be provided by contractor.
8.2 Modification of GAS Detection System (GDP)
a) Modification of GAS Detection System (GDP) The existing Gas detection panel modification involve to use existing card in 16 channel rack for OPGD and PGD. Wiring of detector signal to existing TB of panel as per the approved document/drawing and Interfacing , loop checking , calibration ,testing and commissioning of the new Gas detectors. Provision of new detector control card with wiring in existing GDP for new detectors if spare card not available Provision of Terminal block module with wiring if spare terminals are not available in existing TB . SET 1 247,500.00 247,500.00 18% 44,550.00 292,050.00
9.0 Supply, Installation, testing and commissioning of SS 316 Tubes (0.065" thk) for GOOA Valve from the tapping point to GOOA Valve including all labour, accessories, connectors, SS Valves, and other auxiliaries as required, etc., complete in all respects as per specifications/ drawings/ directions of Engineer-in-Charge. Mtrs 1 2,035.00 2,035.00 18% 366.30 2,401.30
10.0 Dismantling of Existing GDP 'Dismantling, Re-location, Re-installation, termination, Testing and commissioning of Existing GDP Job includes , Re-routing of cables (on cable trays) to the new location, dismantling, Re-routing, Re-installation of cable trays, Glanding and termination of cables at ends etc., complete in all respects as per specifications/ drawings/ directions of Engineer-in-Charge. SET 1 38,500.00 38,500.00 18% 6,930.00 45,430.00
11.0 In case of RTU panel is in scope of bidder : Design, Engineering, Manufacturing, testing, Supply, Inspection, FAT, Transportation, Erection/Installation, SAT, Integration with existing system of GTL etc. of RTU/SCADA System as per scope and Specification attached in tender. SET 1 2,525,964.00 2,525,964.00 18% 454,673.52 2,980,637.52
12.0 In case of RTU panel is free issue material : Installation of RTU panel in the control room building with panel earthing connection to earthing pit, RTU panel base frame, all Interfacing signals and power cables between RTU and Local Control Panel ,GDP,FAP, UPS etc., RS485 cable required for SCADA & Telecom connectivity As per General Specification-Instrumentation ,QAP ,SOW, Technical datasheet & Design Basis System architecture/cable block diagram documents. Contractor's Scope will also include Receiving, taking over, loading & unloading, transportation ,storage of supplied this Free issue Materials from Owner's storage/designated store to Site. Note : In case of RTU Panel issued as a free issue material, Commissioning and integration of RTU panel with existing GTL's SCADA system shall be in scope of Owner / RTU panel suppler. Nos. 1 38,500.00 38,500.00 18% 6,930.00 45,430.00
13.0 In case of Telecom System (includes MPLS-TP, IP Phones, CCTV Cameras etc.) is in scope of bidder : Design, Engineering, Manufacturing, testing, Supply, Inspection, FAT, Transportation, Erection/Installation, SAT, Integration with existing system of GTL etc. of Telecom System as per scope and Specification attached in tender. SET 1 5,688,300.00 5,688,300.00 18% 1,023,894.00 6,712,194.00
14.0 In case of Telecom panel (MPLS-TP) & IP phones are free issue material : Installation of Telecom Panel (MPLS-TP) in the control room building with panel earthing connection to earthing pit, Telecom panel base frame, Telecom panel battery stand, charger rack & Stand and all Interfacing signals, power and communication cables with RTU As per General Specification-Instrumentation , QAP ,SOW, Technical datasheet & Design Basis System architecture/cable block diagram documents).Contractor's Scope will also include Receiving, taking over, loading & unloading, transportation ,storage of supplied this Free issue Materials from Owner's storage/designated store to Site Note : In case of Telecom Panel (MPLS-TP) & IP phones are issued as a free issue material, Commissioning and integration of Telecom panel (MPLS-TP) and IP phones with existing GTL's Telecom Network and EPABX system shall be in scope of Owner / Telecom Panel suppler. Nos. 1 38,500.00 38,500.00 18% 6,930.00 45,430.00
15.0 Suppy , Mounting, Install ,testing & Commissioning of IP Based CCTV Camera [PTZ Type ] with 1 no. PTZ camera with IR Illuminators,required accessories including 1 no Pole with structure & associated canopy , integration & Configuration with existing CCTV server. SET 1 286,000.00 286,000.00 18% 51,480.00 337,480.00 New. Rate based on Tracteble
16.0 Suppy , Mounting, Install ,testing & Commissioning of IP Based CCTV Camera [Fixed Type ] with - 1 No of Fixed Type Camera .required accessories including 1 no Pole with structure & associated canopy , integration & Configuration with existing CCTV server . SET 1 112,200.00 112,200.00 18% 20,196.00 132,396.00 New. Rate based on Tracteble
17.0 Total of Instrumentation and associated work schedule - E in Rs. 22,917,124.00 22,917,124.00 4,125,082.32 27,042,206.32
1. The rates are in INR excluding GST. GST shall be payable extra at actual.
2. The quantity indicated above are Tentative and for the bid evaluation purpose only.
3. All Above works shall be executed in accordance with SCOPE OF WORK, Technical Specification, Data Sheets, QAP, Drawings and other provision of bid documents and instruction of Owner/ Owner's Representative.
4. Bidder to confirm full compliance to spec. Deviations are not allowed and shall make liable for rejection
5. The above total prices shall be inclusive of all TPI, packing, forwarding, handling, storage, stacking, Transportation, spares , special tools , tackles, loading and unloading charges up to final destination site but does not include taxes
6. All the items required to complete the work shall be the scope of supply of contractor only.
7. Rate of RCC Foundation, RCC Hume pipe, Power cable, earthing etc. work shall be quoted in relevant Schedule of Rates (SOR) of Civil / Electrical and TCP Works, hence not to be included in Instrumentation works.
8. All other works pertaining to Station Mechanical, Station Architecture/civil/Structural/Electrical and TCP works shall be as per rates indicated elsewhere in the tender document.
9. Work is inclusive of receiving, taking over, loading & unloading, storage of company supplied material and return of surplus material to Company's designated stockyard/store.
10. Prices quoted shall include the following
a) All handling , transportation including marine transportation( if applicable) , liaison , port fee, ware house , handling , all fees customs duty etc.
b) All design , engineering, supply, installation,, tech support and guarantee
11. Owner supplied Material as Scope Of Work for OVERALL SCOPE OF WORK FOR CONTRACTOR OF PIPELINE & ASSOCIATED FACILITIES are free issued supply by Owner. However, Erection, Installation and integration of these free issue materials is in Contractor's scope. Receiving, taking over, loading & unloading, storage of company supplied material Free issue Materials from Owner's storage to Site is in Contractor's Scope.
12. Preparation of all As-Built drawings will be in contractor's scope.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Tech. Vol - Table of Content.pdf
8.1 GTL AVL.pdf
2.3 SOW Civil.pdf
3.3 Design Basis Civil.pdf
5.1 Technical Spec Civil.pdf
5.2.1 Civil DWG.pdf
5.2.2 Civil DWG.pdf
5.3 Civil DWG Typical _part-1.pdf
5.3 Civil DWG Typical _part-2.pdf
5.3 Civil DWG Typical _part-3.pdf
2.4 SOW Electrical.pdf
2.5 SOW CP.pdf
3.4 Design Basis Electrical.pdf
3.5 Design Basis CP.pdf
6.1 Technical Spec Electrical including CP_Part-1.pdf
6.1 Technical Spec Electrical including CP_Part-2.pdf
6.2 DS Electrical including CP_Part-1.pdf
6.2 DS Electrical including CP_Part-2.pdf
6.3 QAP Electrical including CP.pdf
6.4 Dwg Electrical_Part-1.pdf
6.4 Dwg Electrical_Part-2.pdf
6.4 Dwg Electrical_Part-3.pdf
2.6 SOW_ Instrumentation _ R2.pdf
3.6 Design Basis-Instrumentation_080526.pdf
7.1.1 TS Instrumentation with Appendix.pdf
7.1.2 TS OFC with Appendix.pdf
7.1.3 GTL-ARC-DOC-IN-TS-060-04-03 PLB-HDPE DUCTS R-1.pdf
7.2 DS Instrumentation_Part-1.pdf
7.2 DS Instrumentation_Part-2.pdf
7.3 QAP Instrumentation.pdf
7.4 Drawings Inst.pdf
2.1 SOW Overall.pdf
2.2 SOW Pipeline and Mech.pdf
3.1 Design Basis Process.pdf
3.2 Design Basis Piping and Pipeline.pdf
4.1.1 Technical Spec Pipeline_Part-1.pdf
4.1.1 Technical Spec Pipeline_Part-2.pdf
4.2.1 Technical Spec Piping.pdf
4.3 Data Sheet Mechanical.pdf
4.4 QAP Mechanical.pdf
4.5.1 P and ID.pdf
4.5.2 GAD.pdf
4.5.3 Typical_Part-1.pdf
4.5.3 Typical_Part-2.pdf
RFP PQ SCPL Total.pdf
Annexure-B Pre bid queries form.xlsx
XLSX
Annexure-C Unit Base Rate.xlsx
XLSX
Annexure-D1 Guideline for HSE Planning at site P1.pdf
Annexure-D1 Guideline for HSE Planning at site P2.pdf
Annexure-D2 Guideline for HSE Violation recovery.PDF
Addendum 1.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .