| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 LAccepted-AOC | L1 | Accepted-AOC Lowest | |
| 2 | L2₹3.0 L+₹55,313.33 (23.0%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹3.3 L+₹87,898.11 (36.5%)Rejected-AOC EDAMCHERYKUNNU HOUSE CHENGALA PO KASARGOD | KANNUR | KERALA | 670511 | L3 | Rejected-AOC L3 |
Tender Value
₹3.0 L
EMD Value
₹7,405
Closing Date
29 Sept 2023, 4:00 pmClosed
Assistant Executive Engineer
Head work Sub Division Malampuzha Irrigation
Clearing,Demolishing Erath Work ,PCC 1 4 8 ,centring and shuttering,PCC 1 3 6,PCC 1 2 4 PCC 1 1 5 3 RCC,Plastering,Earth Filling
2023_Irrig_605410_1
IRR/PI/TR/5413/2023_5_1_1/1
Open Tender
Civil Works - Canal
Item Rate
364 days
Mundur
please refer Tender Document
7 documents required · 7 mandatory
₹655
Yes
₹7,405
Yes
26 Oct 2023
21 Sept 2023
3 Oct 2023
21 Sept 2023
29 Sept 2023
21 Sept 2023
Amount
CADA WORK
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
50.2.26.1:Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
NOUFAL ALAMPADY
MOHAMMED KUNHI C A
Bidder Name
MOHAMMED KUNHI C A
RAMESH KUMAR T G
NOUFAL ALAMPADY
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_902259.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .