Cess Repair under the jurisdiction of DEN/Central/Adra in Adra Division.
E-DRM-Engg-ADRA-52-26
E-DRM-Engg-ADRA-52-26
Open
9 Months
Ludhiana, Punjab
₹0
₹4.9 L
23 Jun 2026
23 Jun 2026
2 Jul 2026
Item- 1 Execution of works covered under USSOR-2021
S No. Item Description of Item Unit Qty Rate Amount
ADRA DIVISION-ENGG/SOUTH EASTERN RLY
Earthwork in filling in embankment, guide bunds,
around buried type abutments, bridge gaps,
trolley refuges, platforms etc. with contractor's
own earth conforming to Soil Quality Class
SQ1/SQ2/SQ3, after preparation of foundations
as applicable, benching in existing banks
wherever required, spreading in layers with
motor grader, bringing the moisture content to
OMC, mechanical compaction to specified
density and dressing of bank to final profile as
per RDSO Specifications: RDSO/2020/GE: IRS-
0004 with latest correction slips. Note: 1)
Foundation preparation, Benching including
additional earthwork on account of this,
wherever required, shall be paid extra under
relevant schedule item for benching. 2) Payment
for Earthwork under this item shall be made
based on the cross section measurements
calculated (i) with original ground profile of
existing bank based on initial ground levels
before doing benching and (ii) final profile of the
bank worked out with final levels as per
prevailing guidelines.
Earthwork in cutting in formation, trolley
refuges, side drains, level crossing approaches,
platforms, catch water drains, diversion of nallah
& finishing to required dimension and slopes to
obtain a neat appearance to standard profile
inclusive of all labour, materials, plant &
machinery, leading all cut spoils either to make
spoil dumps or for filling in embankment with
leads within 2 km on either side of edge of the
cutting(s) including all lifts, ascent, descent,
loading, unloading, bailing & pumping out water,
if required, clearance of site and all other works
incidental thereto for completing the work as per
RDSO Specification No. RDSO/2020/GE: IRS-0004
with latest updated correction slips and to the
satisfaction of the Engineer-in-Charge. Note: (i)
All usable earth arising from cut spoils shall be
led into bank formation and Unusable spoils shall
be dumped / stacked away from toe of
embankment. (ii) All hard rock /and boulders not
fit for filling will be stacked by the contractor
and will be property of the Railways. (iii)Cut
trees shall be property of Railways and to be
deposited in the railway godown unless specified
otherwise in the Conditions of Contract.
2 012011 In all conditions and classifications of soil except cum 891.00 106.59 94971.69
3 012020 Foundation preparation in cutting - ploughing 100 99000.00 279.20 276408.00
and pulverizing 15 cm of top of soil with tractor Sqm
trolley, mixing water to achieve OMC with water
sprinkler or allowing for natural drying, as
required, and compaction with vibratory roller of
suitable capacity to achieve 98% MDD for laying
blanketing layer.
Providing and laying in position Plain cement
concrete of specified Nominal Mix for
miscellaneous works like side drains, foundation
for OHE masts and other miscellaneous
structures excluding the cost of Cement,
centering and shuttering - All work up to plinth
graded stone aggregate 20 mm nominal size)
graded stone aggregate 20 mm nominal size)
ADRA DIVISION-ENGG/SOUTH EASTERN RLY
Centering and shuttering including strutting,
propping etc. and removal of form for :
6 025031 All types of bridge sub-structures, e.g. pier, Sqm 4405.50 674.52 2971597.86
abutment, wing wall, retaining wall, RCC box
type foundations, Abutment cap, Pier Cap,
Inspection Platform & Pedestal over Pier cap,
Fender wall, Diaphragm wall etc. up to 5m above
Supply and using Cement at Worksite
7 025073 Pozzolana Portland Cement approved MT 742.50 8429.01 6258539.93
8 051070 Providing and laying Pitching with Stone cum 1430.00 2369.16 3387898.80
Boulders, weighing not less than 35kg each with
voids filled with cement sand mortar 1:4 on
slopes laid over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing and
Technical Specifications (filter media to be paid
separately under the relevant item). Rate is
excluding cost of cement which shall be paid
extra under relevant item.
9 052040 Supply and laying of coarse sand including cum 792.00 973.10 770695.20
consolidation with all labour, lead, lift, tools,
plants, crossing of tracks as per drawing and
technical specification as directed by the
Engineer in charge in case loose slush is
encountered at site of foundation before casting
the foundation or laying the filtering media.
10 113010 Cess repair/widening work as per RDSO cum 15412.00 303.63 4679545.56
Specifications and guidelines RDSO/2020/GE:
IRS-0004 or latest in running line with suitable
soil to the designed profile The work shall include
uprooting and disposing of all the vegetation,
benching at every 30 Cm vertical height,
earthwork in benching portion and compaction
u s i n g suitable slope vibratory
Rollers/Compactors etc. to achieve prescribed
MDD. Note: 1. Payment of cess repairs shall be
based on the quantities worked out from the
cross sectional calculations only and worked out
from the initial ground levels before doing
benching and final levels as done for new
embankment. The earth work in benching
portion shall not be paid extra as the same has
been included in the rate. 2. The earth work shall
be started only after Completing of the benching
and certified. 3. The benching Work shall be
done for a maximum height of 1.50 m at any
time based on the progress of earthwork starting
from toe of the embankment.
making cess on other side of the track (when no
approaches available along track or no road
vehicles to work at site) by dumping contractor's
own earth, collected along toe of bank of any
height on to other side of track & side slope of
the existing bank by head load, duly crossing of
tracks with all contractor's materials, labour,
tools, plant including loading of earth in baskets,
lifting, leading to the non-cess side of bank
including crossing of tracks & dumping etc. and
as directed by the Engineer in-charge.
Schedule Schedule B-Execution of work covered under CPWD DSR-2023-Ver-1
Item- 1 CESS REPAIR
S No. Item Description of Item Unit Qty Rate Amount
13.0 FINISHING
ADRA DIVISION-ENGG/SOUTH EASTERN RLY
13.44S EXTERIOR FINISHING
Finishing walls with water proofing cement paint
of required shade :
13.44.1 New work (Two or more coats applied @ 3.84 Sqm 3465 116.9 405058.5
16.0 ROAD WORK
16.1S ROADS
16.3 Supplying and stacking at site.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Bidsecruitydocument.pdf
ATTACHMENT
JPOCABLE.pdf
ATTACHMENT
CorrectionSlip08.pdf
ATTACHMENT
ANNEXUREVIAforBIDSECURITY.pdf
ATTACHMENT
2018_CE-I_CT_9Date04_06_2018.pdf
ATTACHMENT
SpecialConditions_Contract_17102018.pdf
ATTACHMENT
JPOcabledamage.pdf
ATTACHMENT
ASC-2GCC-2022.pdf
ATTACHMENT
GCCACS.pdf
ATTACHMENT
CessrepairLocationcentral.pdf
ATTACHMENT
AnnexureVIBwithUDIN.pdf
ATTACHMENT
ACS-03OFGCC2022.pdf
ATTACHMENT
correctionslip.pdf
ATTACHMENT
GCC 2022
ATTACHMENT
ACS11GCC2022.pdf
ATTACHMENT
correctionslip-09.pdf
ATTACHMENT
CTIndianRailwaysStandardGeneralConditionsofContractApril- correction slip
ATTACHMENT
CTIndianRailwaysStandardGeneralConditionsofContractApril- Correction slip
ATTACHMENT
CorrectionSlipNo_7ACS-71.pdf
ATTACHMENT
GCC_April-2022_2022_CE-I_CT_GCC-2022_POLICY_27.04.22.pdf
ATTACHMENT
2023_10_20RBCE_CE-I-CTIndianRailwaysStandardGeneralConditionsofContractApril-2022AdvanceCorrectionSlipNo_5ACS-53.pdf
ATTACHMENT
2025_03_04RBCE_CE-I-CTIndianRailwaysStandardGeneralConditionsofContractApril-2022AdvanceCorrectionSlipNo_10ACS-10.pdf
ATTACHMENT
Download all tender documents and submit your bid