| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.5 LAccepted-AOC | ₹12.5 L | L1 | Accepted-AOC L1 |
| 2 | L2₹13.3 LRejected-AOC | ₹13.3 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | V.RATHEESH L1 | P.T.MICHAEL L2 |
|---|---|---|---|---|---|
| 1.00Detailed Estimate | |||||
| 1.00 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 0.14 | cum | 211.26 ₹28.52 | 217.65 ₹29.38 |
| 1.00 | 4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 40 mm nominal size derived from natural sources) | 0.18 | cum | 6,858.95 ₹1,234.61 | 7,066.39 ₹1,271.95 |
| 1.00 | 4.2.5:Providing and laying cement concrete in retaining walls, return walls, walls ( any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor, etc. up to floor five level, excluding the cost of centering, shuttering and finishing:1:3:6 (1 cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 20 mm nominal size derived from natural sources) | 1.08 | cum | 9,093.63 ₹9,821.12 | 9,368.65 ₹10,118.14 |
| 1.00 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | 16.8 | sqm | 316.65 ₹5,319.72 | 326.23 ₹5,480.66 |
| 1.00 | 50.10.1:Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete | 1,341.25 | kg | 160 ₹2.1 L | 195.09 ₹2.6 L |
| 1.01 | 50.10.2:Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete | 2,506.01 | kg | 150 ₹3.8 L | 158.02 ₹4.0 L |
| 1.01 | OD266018/2025-2026:Finishing with epoxy paint(two or more coats) at all locations prepared and applied as per manufacturer's specifications, excluding priming coat, preparation of surface, etc, complete.On steel work | 309.79 | sqm | 135 ₹41,821.92 | 148.2 ₹45,911.17 |
| 1.01 | OD205220/2025-2026:Providing and fixing Aluminium powder coated profile sheets (Size ,shape and pitch of corrugation as approved by Engineer-in-charge)0.46mm (+0.05%),total coated thickness with zinc coating 120 grams per sqm as per IS:277,in 240 mpa steel grade,5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns.sheet should have protective guard film of 25 microns minimum to avoid sratches during transportation and should be supplied in single length up to 12 metre or as desired by Enginner -in-charge . The sheet shall be fixed using self drilling /self tapping screws of size (5.5x55 mm) with EPDM seal ,complete up to any pitch in horizontal/vertical or curved surfaces,excluding the cost of purlins,rafter and trusses and including cutting to size and shape wherever required. (As per approved TS estimate 1699/2023) | 577.36 | sqm | 780 ₹4.5 L | 789.67 ₹4.6 L |
| 1.01 | OD266020/2025-2026:providing and fixing precoated Aluminium plain sheet ridge caping roofing accessories 0.46 mm(0.050%)and necessary overlap total coated thickness,zinc coating 120 grams per sqm as per IS mm (9+0.05 mm%) | 76.7 | metre | 372.4 ₹28,563.08 | 383.67 ₹29,427.49 |
Tender Value
₹14.9 L
EMD Value
₹37,237
Closing Date
3 Feb 2026, 3:00 pmClosed
Executive Engineer
Office of the Executive Engineer PWD Buildings Division Alappuzha
GENERAL-GTDMCH Alappuzha - Construction of aluminium roof above the radiation oncology department-Civil workGeneral Civil Work
2026_PWD_831467_1
PWD/BLDG/TR/20655/2022_5_1_1/1
Open Tender
Civil Works - Buildings
180 days
Alappuzha
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
₹37,237
26 May 2026
28 Jan 2026
5 Feb 2026
28 Jan 2026
3 Feb 2026
28 Jan 2026
Detailed Estimate
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources)
4.2.5:Providing and laying cement concrete in retaining walls, return walls, walls ( any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor, etc. up to floor five level, excluding the cost of centering, shuttering and finishing:1:3:6 (1 cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
50.10.1:Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
50.10.2:Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
OD266018/2025-2026:Finishing with epoxy paint(two or more coats) at all locations prepared and applied as per manufacturer's specifications, excluding priming coat, preparation of surface, etc, complete.On steel work
OD205220/2025-2026:Providing and fixing Aluminium powder coated profile sheets (Size ,shape and pitch of corrugation as approved by Engineer-in-charge)0.46mm (+0.05%),total coated thickness with zinc coating 120 grams per sqm as per IS:277,in 240 mpa steel grade,5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns.sheet should have protective guard film of 25 microns minimum to avoid sratches during transportation and should be supplied in single length up to 12 metre or as desired by Enginner -in-charge . The sheet shall be fixed using self drilling /self tapping screws of size (5.5x55 mm) with EPDM seal ,complete up to any pitch in horizontal/vertical or curved surfaces,excluding the cost of purlins,rafter and trusses and including cutting to size and shape wherever required. (As per approved TS estimate 1699/2023)
OD266020/2025-2026:providing and fixing precoated Aluminium plain sheet ridge caping roofing accessories 0.46 mm(0.050%)and necessary overlap total coated thickness,zinc coating 120 grams per sqm as per IS mm (9+0.05 mm%)
OD175221/2022-2023:supplying and fitting 200mm PVC pathy 6Kg/cm2 for gutter including 25x6mm think M.S clamp at 75cm c/c including all cost and labour charges etc complete
50.18.9.19.2:Providing and fixing PVC pipes including fixing the pipe with clamps/clips at 1.00 m spacing. This includes jointing of pipes with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 110 m dia 4 Kgf/cm2 - External work - Exposed on wall
50.18.9.22.1:Providing and fixing PVC moulded fittings/ accessories for Rigid PVC pipes, including jointing with PVC solvent cement - 110 mm dia Elbow
50.18.9.22.2:Providing and fixing PVC moulded fittings / accessories for Rigid PVC pipes, including jointing with PVC solvent cement - 110 mm dia 45 degree Elbow
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
13.88:Removing white or colour wash by scrapping and sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete.
13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
13.109.2:Finishing walls with water proofing cement paint of required shade :Old work (one or more coats @ 2.20 kg/10 sqm) complete.
13.60.1:Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1397045.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
sbd.pdf
Tender Documents • 1.64 MB
BOQ_1397045.xls
BOQ • 0.31 MB
PRI.pdf
Other Document • 0.26 MB
affi.pdf
Other Document • 0.02 MB
epy.pdf
Other Document • 0.07 MB
bis.pdf
Other Document • 0.56 MB
Download all tender documents and submit your bid