| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.6 LAdmitted-Finance | ₹14.6 L | L1 | Admitted-Finance |
| 2 | L2₹15.1 LAdmitted-Finance | ₹15.1 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | GOLAYYA C HIREMATH L1 | SHEKAR G L2 |
|---|---|---|---|---|---|
| 1.00Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m,as directed by Engineer-in-Charge. | |||||
| 1.01 | All kinds of soil | 46 | One Cubic Metre | 300 ₹13,800 | 450 ₹20,700 |
| 2.00Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50 m and lift up to 1.5m, as directed by Engineer-in-Charge. | |||||
| 2.01 | Ordinary rock | 44 | One Cubic Metre | 500 ₹22,000 | 500 ₹22,000 |
| 3.00Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. | |||||
| 3.01 | All kinds of soil. | 9 | One Cubic Metre | 500 ₹4,500 | 300 ₹2,700 |
| 4.00 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 68 | One Cubic Metre | 200 ₹13,600 | 200 ₹13,600 |
| 5.00Extra for every additional lift of 1.5 m or part thereof in excavation /banking excavated or stacked materials. | |||||
| 5.01 | All kinds of soil. | 44 | One Cubic Metre | 200 ₹8,800 | 128 ₹5,632 |
| 6.00Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : | |||||
Tender Value
₹12.9 L
EMD Value
₹25,762
Closing Date
22 Jan 2026, 6:00 pmClosed
The Executive Engineer Civil Tender KTK Circle
Room No 324 3rd Floor CGMT Doorasamparka Bhavana No 1 Swamy Vivekananda Road Bengaluru 560008
Construction of 40m GBT foundation including Erection, Painting, earthing arrangement, Cable tray along with DG set and BTS foundations and barbed wire Fencing, filling earth in low lying area at BSNL plot SIRWAR Tal- Manavi Dist- Raichur (4th call)
2026_BSNL_262875_1
11/NIT/BSNL/CD/HBL/2025-26
Open Tender
Civil Works - Buildings
60 days
Sirwar
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
The Accounts officer (Cash), BSNL, Hubballi
₹25,762
30 Jan 2026
13 Jan 2026
24 Jan 2026
14 Jan 2026
22 Jan 2026
14 Jan 2026
14 Jan 2026 - 21 Jan 2026
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m,as directed by Engineer-in-Charge.
All kinds of soil
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50 m and lift up to 1.5m, as directed by Engineer-in-Charge.
Ordinary rock
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
All kinds of soil.
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Extra for every additional lift of 1.5 m or part thereof in excavation /banking excavated or stacked materials.
All kinds of soil.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:2:4 (1 cement : 2 coarse sand(zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources).
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
Centering and shuttering including strutting, propping etc. and removal of form for :
Foundations, footings, bases of columns, etc. for mass concrete
Lintels, beams, plinth beams, girders, bressumers and cantilevers
Columns, Pillars, Piers, Abutments, Posts and Struts
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
Thermo-Mechanically Treated bars of grade Fe-500D or more.
Smooth finishing of the exposed surface of R.C.C. work with 6 mm thick cement mortar 1:3 (1 Cement : 3 fine sand).
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:
Cement mortar 1:6 (1 cement : 6 coarse sand)
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.
In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works.
12 mm cement plaster of mix :
1:6 (1 cement: 6 coarse sand)
Finishing walls with water proofing cement paint of required shade :
New work (Two or more coats applied @ 3.84 kg/10 sqm).
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :
Two or more coats on new work.
Labour charges for fixing anchor bolts of any dia in position during concreting including fixing necessary templates,making dimensional adjustments for centre line distances of tower legs and carriage of anchor bolts,templates from Telecom stores, Tumkur to site of work etc.as per the direction of Engineer in charge.
Transportation including insurance of four legged angular light weight communication tower material including anchor bolts, ladder, working platform, cable trays, antenna fixtures and similar materials etc., from the departmental stores/stacking yard Raichur to the site of work, including loading, unloading and stacking of materials all complete as per the direction of Engineer in Charge.
40 m high tower materials
Up to 05( Five) kms.
Beyond 05(five) Kms up to 10(ten) kms.
Beyond 10(ten) Kms up to 20(twenty) kms.
Beyond 20 kms. (From Raichur to Sirwar site= 40 km)
Erection of four legged light weight communication tower of 40 mts. height, including insurance, sorting and listing of tower materials as per chart/drawing supplied by the manufacturer/ BSNL and placing of anchor bolts and templates and fixing in the columns, beams, etc all complete. (Note 1: Necessary safety measures shall be adopted while erecting the tower to ensure the safety of men and materials and adjacent properties). (Note 2: The safe custody of tower materials will be the responsibility of the agency from the time of handing over by department till the handing over of tower to concerned authorities.) (Weight of tower materials may vary from 8.6 MT to 10 MT.)
Providing and applying high gloss synthetic enamel paint (two or more coats) of approved brand and colour ( International white and orange) over approved base coats of 'ETCH ' primer and zinc chromate primer for four legged galvanized ground based communication tower as per specifications enclosed as per the directions of the Engineer-in-charge, for 40 m GBT (Weight of tower materials may vary from 8.6 MT to 10 MT.)
Providing GI plate earthing including excavation of pit of size 2.00m x 2.00m x 3.00m depth in all kinds of soil including rocky strata and placing four numbers of GI plates of size 600 x 600 x 6.5 mm thick vertically in all the four corners of the excavated pit and inter connecting the plates with GI strips of size 50 x 3 mm with two nos of GI bolts and nuts of 10mm dia at each connection. To prevent ingress of moisture and soil, the joints are made water tight by covering with bitumen. A GI pipe of 50mm dia 3000mm long with holes at zigzag position at 100 mm interval with GI funnel at top shall be provided for watering the earth. 2nos of 50 x 3 mm GI strips shall be connected with any one of a GI plate electrode with GI bolts and nuts and a lead strip of 1mm thickness inbetween the joints. The GI strip will run vertically and be bent
with a radius of 1m at a depth of about 30cm. below ground level to interconnect with other pit earth. After the electrodes are placed in position and all the interconnections made, the pit should be filled up with finely sieved good quality soil which should be rammed in layers so that it is compact and cohesive. The surplus excavated earth shall be disposed off as directed within a lead of 50metre. A precast RCC slab of size 530 x 530 x 75mm with 75mm ida hole at the centre to pass GI pipe in it shall be placed and a half brick masonry chamber of size 280 x 280 x 280mm shall be constructed over it. The chamber will be covered with GI manhole cover and frame of 300 x 300mm (the weight of cover being not less than 4.5kg and the frame not less than 2.7kg.) etc. complete as directed by the Engineer - in - charge. (The rate is inclusive of supplying required quantity of finely sieved good quality soil at site).
Providing and laying ring earth including excavation of trench of size 300 width x1000 to 1500 mm depth ( in rock minimum depth shall be 600mm) and laying 50 x 3 mm GI flat (with zinc 610gm/sqm) at the bottom as per drawing and then refilling with finely sieved good quality soil. The ring earth shall be connected to all the tower legs with GI strips 50 X 3 mm and with GI bolts and nuts at ends. Provision for connecting ring earth to the lightening arrestor shall be made by providing 50 X 3 mm GI strip one end of which is connected to the ring earth by means of GI bolts and nuts and other end left free above earth with necessary bolt holes.
Providing and fixing G.I. strips of 50 x 3mm size of approved quality one end connected to the bottom of lightening arrester and the other end connected to the ring earth/plate earth with 2nos. 10mm dia. G.I. bolts and nuts at every connection. The G.I. strip shall be clamped to the tower at uniform intervals at 1.50 m using necessary Porcelean insulator clamps with bolts and nuts to aviod direct contact with the tower, as directed by the Engineer-in-charge.
Providing and fixing copper lightening arrester of 1500 mm length, 25mm dia. Hollow tube and of wall thickness not less than 1.60mm including tinning the bottom portion of the spike for a length of not less than 150mm and connecting to the G.I. strip of size 50 X 3 mm by means of clamps and 2 nos. 10 mm dia brass bolts and nuts all complete as directed by the Engineer-in- charge. The lightening spike shall be fixed to the tower with Teflon sheet to avoid direct contact with the tower.
Supplying and fixing LED double aviation obstruction lamp of Saraj, Binoy, Aviads, Litten or equivalent with light dependent resistance sensor (day and night automatic timer) with necessary MCB switches, 1.5 sqmm. armoured cables of required length, clamps etc. complete.
Making arrangement for A/T by providing all tools,necessary labours including providing theodolite, torque-wrench, Meggar, transportation of all tools & plants & A/T team to the tower site and back, providing insurance coverage to labours to complete the A/T etc. all as per the requirement of A/T & as directed by the Engineer in charge.
Excavating holes more than 0.10 cum & up to 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto1.5 m.
All kinds of soil.
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50m outside the periphery of the area cleared.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:3:6 (1 Cement : 3 coarse sand(zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources).
Providing and fixing ISI marked oxidised M.S. sliding door bolts with nuts and screws etc. complete (Copper oxidised as per IS 1378)
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.
Hot finished welded type tubes.
Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade:
Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture.
Supplying at site :
R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar nibs wherever required as per direction of Engineer-in-charge (cost of earth works in excavation, concrete works in foundation to be paid separately).
Supplying and fixing turn buckles and straining bolts for barbed wire fencing.
Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used.
With G.I. barbed wire
Providing and welding of box hinges 100 mm size by welding to the gate channels etc. all complete as directed by the engineer in charge.
Lettering on steel gate plate by white synthetic enamel paint in appropriate size and matter as directed by Engineer - in - charge.
Supplying, laying & spreading of red earth/soil (locally available) in low lying area of BSNL plot at Sirwar in dist. Raichur as per direction of Engineer in charge.
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.57 MB
BOQ_304679.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid