Loading…
Loading…
Tender ID
Tender Value
₹26.5 L
EMD Value
₹27,000
Closing Date
9 Feb 2026, 6:00 pmClosed
Executive Engineer, Ahmedabad Irrigation Division, Ahmedabad
Constructing Box Type ( 2m X 2m, 3 nos) VRB at Goraiya Drain at Village Goraiya Ta. Viramgam Dist. Ahmedabad.(Re-Invitation)
271317
18 of 2025-26
Open
Civil - All
Works
Ahmedabad
6 documents required · 5 mandatory · 1 optional
₹1,500
Executive Engineer, Ahmedabad Irrigation Division, Ahmedabad
₹27,000
30 Jan 2026
30 Jan 2026
30 Jan 2026
9 Feb 2026
30 Jan 2026
BILL OF QUANTITY
Name of Constructing Box Type ( 2m X 2m, 3 nos) VRB at Goraiya Drain at Village Goraiya Ta.
work: Viramgam Dist. Ahmedabad.
Item NO. DESCRIPTION QTY. UNIT RATE in AMOUNT
Dismentalling of RCC work viz. slab, beam, lintel,
barrel, staire case, etc. including removing the
steel from the dismentalled portion without
1 damage to reinforcement sorting and stacking of 29.26 Cmt 1494.00
usefule and unuseful material from the
dismentalled material as directed under detailed
specification etc. complete. upto lead 200 mt.
Dismentalling masonary in lime or cement &
stacking of useful and unuseful material from the
dismentalled materials as directed under detailed
specification etc. comp. (a) Brick
Excavation in all sorts of soil (including wet and
slushy condition of soil) with yellow, sandy, gravelly
soil including soft murrum & H.M. including sorting
& stacking and depositing the excavated stuff in
uniform layers as and where directed upto lead of
30 mt. and lift as shown below including clearing
the site etc. complete.(Including dewatering) (a)
Providing and laying foundation concrete of
proportion as under by using cement, sand and
machine crushed course aggregate laid in situ
4 including necessary temping, smooth finishing, 42.12 Cmt 3559.00
watering and curing as directed with all leads and
lifts etc complete.
(a) PCC 1:3:6 (MSA 40)
Providing and laying in position reinforce cement
concrete using crushed aggregate including
providing necessary form work, centering,
vibrating, smooth specified finishing, curring as
required for specified leads and all lifts etc
complete in M-25 grade.
For walls, including top and bottom slab of outlet
sluice etc complete.(20MSA)
Providing and laying H.Y.S.D. steel bar
reinforcement for R.C.C. works and anchor bars
with providing binding wires including cutting,
bending, welding, binding in position, hooking,
placing in position with all leads & lifts etc.
BILL OF QUANTITY
Name of Constructing Box Type ( 2m X 2m, 3 nos) VRB at Goraiya Drain at Village Goraiya Ta.
work: Viramgam Dist. Ahmedabad.
Item NO. DESCRIPTION QTY. UNIT RATE in AMOUNT
Providing weep holes 100 or 110 mm Dia pipe in
7 the retaining wall with required fixtures as directed 21.00 Rmt. 314.00
etc complete. (b) P.V.C. pipe (6 kg/cm^2, 110mm)
Providing galvanized iron/cast iron 100 mm dia
8 water spout including iron fitting as per desiga and 6.00 Nos. 689.00
drawing etc complete.as per Most Specification.
Backfill with selected earth including ramming
consolidation including watering with lead as
under and all lifts etc.complete. (Dumper capacity
10 Providing Rubble Apron as per drawing & design. 92.01 Cmt 2615.00
Quarrying transporting and depositing selected
materials from borrow area for raising of
11 embankment work in all zone of earthen dam for 700.00 Cmt 86.00
specified thickness as directed for lead upto 1 km
and all lifts etc.complete.
Compaction of embankment work at requisite
moisture content to the required dry density using
12 rollers O.M.C.standard spreading, dressing of 700.00 Cmt 24.00
suitable inclusive ,watering, of type at necessary
rolling directed with all leads and lifts etc.complete.
Care & Diversion of river as directed including
13 dewatering of earth dam foundation including 1% Lump sum from Item No. 1 to 12
C.O.T. during construction etc. completed.
In words Twenty Six Lakh Forty Eight Thousands Ninety Six Rupees Only)
I/We am/are willing to carry out the work at…… % above/below percent(Should be written in figures and words) of
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
The Contractor shall exhibit a board with detailed specification and details of work as directed by the
Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-
10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in R.C.C. items where
there is a change as per actual mix design the cost of difference of cement consumption have been deducted
from the rate of original item at the rate of input rate mentioned in all the tender.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Book Goraiya VRB.pdf
sch B Goraiya VRB.pdf
POL Goraiya VRB.pdf
Tender notice 18 of 2025-26.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .