Loading…
Loading…
Tender Value
₹29.0 L
EMD Value
₹57,924
Closing Date
24 Aug 2026, 6:00 pmDue today
EE WR NAVNERA PROJECT DIV. I KOTA
EE WR NAVNERA PROJECT DIV. I KOTA
Shifting of Public asset Chabutra (Indradev, Kala ji, gora ji, Tajiya rest platform) at Baldara Village which is affected due to Submergence of Navnera Barrage Project across River Kalisindh Dist-Kota.
2026_WRDAS_587561_7
EE WR NAVNERA PROJECT DIV. I KOTA NITNO-06/2026-27
Open Tender
Civil Works
Percentage
90 days
KOTA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
1000 EE WR NAVNERA PROJECT DIV. I KOTA
₹57,924
Yes
24 Aug 2026
14 Aug 2026
25 Aug 2026
14 Aug 2026
24 Aug 2026
14 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cutting & clearance of jungle, bushes, shrubs Ankra/Ipomoea, Juliflora typna etc. on canal and bunds in dry/moist/slushy conditions including disposal as per instructions of the Engineer-in-charge. Cost of wood has been deducted from rates and thus will be property of contractor after cutting. | 3,200 | Sqm | 2.5 | ₹8,000 |
| 2 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect | 5,261.44 | Cum | 95 | ₹4,99,836.8 |
| 3 | Preparation of foundation of structure including removal of all loose stones, silt and final washing. | 89.6 | Sqm | 23 | ₹2,060.8 |
| 4 | Refilling the excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including cost of water. loading and unloading wherever required with cost of dewatering wherever require. | 3,683.01 | Cum | 91 | ₹3,35,153.91 |
| 5 | Providing and Laying in position of Cement concrete Nominal mix (1:2:4) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20mm | 98.66 | Cum | 5,703 | ₹5,62,657.98 |
| 6 | Random rubble stone masonry (using R. R. stones where 75 % stones to be not less than 15 cm in size in any direction and weighing not less than 23 kg.) for foundation including curing all leads of all construction materials including curing etc. complete.In cement sand mortar 1:5 | 80.72 | Cum | 4,377 | ₹3,53,311.44 |
| 7 | Brick work with clay flyash F.P.S. brick (IS 13757- 1993 ) of class designation 75 in superstructure above plinth level upto floor five level in : Cement mortar 1 : 4 (1 cement : 4 coarse sand) | 21.92 | Cum | 5,038 | ₹1,10,432.96 |
| 8 | Supplying of M.S. reinforcement including labour charges for bending binding and placing in position all reinforcement as per drawing including cost of binding wire and all leads and lifts using. Tor or Rib bar | 843.56 | kg | 89 | ₹75,076.84 |
| 9 | Centering and shuttering for slabs, beams, lintels Columns, trough with or without caps and base including propping and removing | 20.16 | sqm | 225 | ₹4,536 |
| 10 | Random rubble dry stone Kharanja under floor. | 19.2 | Cum | 932 | ₹17,894.4 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.37 MB
BOQ_1043439.xls
BOQ • 0.26 MB
DATE-CORRIGENDUM.pdf
PDF • 0.50 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].