| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.0 LAdmitted-Fee/PreQual/Technical/Finance THEKKEKARA MAKKAPPALLIL PUTHENCHANTHA P O | KERALA | ₹4.0 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹4.0 L+₹1,345.58 (0.34%)Admitted-Fee/PreQual/Technical/Finance | ₹4.0 L+₹1,345.58 (0.34%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L3₹4.3 L+₹24,491.83 (6.11%)Admitted-Fee/PreQual/Technical/Finance CHOCHUPARAMBIL ERATTUPETTA | IDUKKI | KERALA | 685501 | ₹4.3 L+₹24,491.83 (6.11%) | L3 | Admitted-Fee/PreQual/Technical/Finance |
| Sl No | Description | Qty | Unit | Shaji Andrews L1 | SHAHUL HAMEED L3 | JITHIN THOMAS L2 |
|---|---|---|---|---|---|---|
| 1.00Wall construction | ||||||
| 1.00 | 15.7.1:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In mud mortar | 4 | cum | 690 ₹2,761.38 Lowest | 730 ₹2,921.46 | 691 ₹2,765.38 |
| 1.00 | OD61448/2026-2027:DISMANTLING DR -dismantling, clearing away and carefully stacking materials useful for
reuse for any thickness of walls in DR masonry including disposal of debris within a distance of
150 m | 13.92 | cum | 718 ₹9,994.56 Lowest | 760 ₹10,579.2 | 719 ₹10,008.48 |
| 1.00 | 2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil | 18.36 | sqm | 127 ₹2,331.72 Lowest | 135 ₹2,478.6 | 127 ₹2,331.72 Lowest |
| 1.00 | OD61439/2026-2027:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site | 11.14 | cum | 1,626 ₹18,107.14 Lowest | 1,720 ₹19,153.92 | 1,629 ₹18,140.54 |
| 1.00 | OD60978/2026-2027:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | 28.45 | cum | 3,785 ₹1,07,698.39 Lowest | 3,995 ₹1,13,673.73 | 3,793 ₹1,07,926.02 |
| 1.01 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 5.41 | cum | 9,943 ₹53,791.63 Lowest | 10,490 ₹56,750.9 | 9,963 ₹53,899.83 |
| 1.01 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 19.4 | sqm | 366 ₹7,100.4 Lowest | 390 ₹7,566 | 366 ₹7,100.4 Lowest |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 351.65 | kilogram | 106 ₹37,274.9 Lowest | 113 ₹39,736.45 | 107 ₹37,626.55 |
| 1.01 | 50.6.2.1:Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x15 cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15cm in: CM 1:6 ( 1 cement :6 coarse sand) etc complete | 11.31 | cum | 6,476 ₹73,243.56 Lowest | 6,835 ₹77,303.85 | 6,489 ₹73,390.59 |
Tender Value
₹4.2 L
EMD Value
₹10,582
Closing Date
13 Aug 2026, 2:00 pmClosed
Assistant Executive Engineer
Assistant Executive Engineer LID and EW Division Kottayam
Annual Plan-DPK180/27 Thrikkodithanam GHS Wall Constructions-General Civil Work Work
2026_LSGD_863774_24
2/2026-27/AEE/LID and EW
Open Tender
Civil Works - Others
Item Rate
Kottayam
Please refer Tender documents.
7 documents required · 7 mandatory
₹935
Yes
₹10,582
Yes
15 Aug 2026
3 Aug 2026
14 Aug 2026
3 Aug 2026
13 Aug 2026
3 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Wall construction | |||||
| 1.001 | 15.7.1:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In mud mortar | 1 | cum | - | - |
| 1.002 | OD61448/2026-2027:DISMANTLING DR -dismantling, clearing away and carefully stacking materials useful for
reuse for any thickness of walls in DR masonry including disposal of debris within a distance of
150 m | - | cum | - | - |
| 1.003 | 2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil | 1 | sqm | - | - |
| 1.004 | OD61439/2026-2027:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site | 1 | cum | - | - |
| 1.005 | OD60978/2026-2027:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | - | cum | - | - |
| 1.006 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | - | cum | - | - |
| 1.007 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 1 | sqm | - | - |
| 1.008 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 1 | kilogram | - | - |
| 1.009 | 50.6.2.1:Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x15 cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15cm in: CM 1:6 ( 1 cement :6 coarse sand) etc complete | - | cum | - | - |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.23 MB
affida.pdf
Tender Documents • 0.23 MB
BOQ_1461274.xls
BOQ • 0.30 MB
epay.pdf
Tender Documents • 0.24 MB
feere.pdf
Tender Documents • 0.33 MB
fot.pdf
Tender Documents • 0.24 MB
ip.pdf
Tender Documents • 0.24 MB
pa.pdf
Tender Documents • 0.25 MB
viewsbd.pdf
Tender Documents • 2.65 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .