Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.4 CrAdmitted-Finance | -2.25% | ₹1.4 Cr | L1 | Admitted-Finance |
| 2 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Others-Hard Copies not submitted within the stipulated date and time |
Tender Value
₹1.4 Cr
EMD Value
₹2.8 L
Closing Date
21 May 2026, 5:00 pmClosed
Superintending Engineer
OFFICE OF THE SUPERINTENDING ENGINEER, PR CIRCLE, Z.P.COMPOUND, VISAKHAPATNAM
Package No AP26PVTLSB005 Construction of High Level Bridge on road from Laxmipuram to Merakallu in Chinthapalli Mandal of ASR District Est. Cost Rs. 218.27Lakhs Mtc. Cost Rs. 5.46 Lakhs
2026_ENCPR_147516_1
12/2026-27, PMGSY-PM JANMAN Batch-I (2025-26)Bridges/SE,PR,VSP dt 02.05.2026 of SE,PR,VSP(2nd call)
Open Tender
Civil - Roads and Bridges
365 days
Laxmipuram to Merakallu in Chinthapalli Mandal
AS PER SBD
3 documents required · 3 mandatory
₹0
₹2.8 L
OFFICE OF THE SUPERINTENDING ENGINEER, PR CIRCLE,
20 Jun 2026
8 May 2026
25 May 2026
8 May 2026
21 May 2026
8 May 2026
8 May 2026 - 21 May 2026
12 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Package No AP26PVTLSB005-Construction of High Level Bridge on road from Laxmipuram to Merakallu in Chinthapalli of ASR District | - | - | - | - |
Const .of 4V- 10.37 m span Bridge | - | - | - | - | |
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including contractors profit & Over head charges, but excluding GST etc., complete- For Foundations | 418 | Cum | 133 | ₹55,594 | |
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including dewatering, contractors profit & Over head charges, but excluding GST and seigniorage etc., complete-----Ordinary rock - SDR (not requiring blasting) including dewatering | 280 | Cum | 177 | ₹49,560 | |
Providing concrete for plain concrete M 10 grade in open foundations using 40 mm nominal size hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH ,including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete For levelling course | 32 | Cum | 7,000 | ₹2,24,000 | |
Plain cement concrete M 20 grade (Design mix) using 40,20 & 10mm metal (HBG) mechanically mixed in foundations complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1203 MORD and 1500, 1700 & 2200 MORTH ,including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete- ----- For Footings of Abutments, Piers & Return walls | 204 | Cum | 8,960 | ₹18,27,840 | |
Plain cement concrete M 20 grade (Design mix) using 40,20 & 10mm metal (HBG) mechanically mixed in Sub structure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH ,including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete- ----- For Sub structure of Abutments, Piers & Return Walls | 279 | Cum | 9,480 | ₹26,44,920 | |
Reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in substructure complete excluding reinforcement as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH, including contractors profit & Over head charges, but excluding Steel ,GST and seigniorage etc., complete -- For Bed Blocks | 16 | Cum | 10,000 | ₹1,60,000 | |
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in superstructure as per drawing and technical specifications Clauses 800, 1401.4.1 and 1401.4.2 MORD / Sections 1500, 1600 & 1700 MORTH ,including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete upto 5m height. - For Super Structure (Deck slab) | 282 | Cum | 10,890 | ₹30,70,980 | |
P.C.C. M 15 ordinary grade (1:2.5:5) using 40,20 & 10mm metal (HBG) mechanically mixed leveling course below approach slab complete as per drawing and technical specifications Clauses 800 and 1211 MORD & 2700 MORTH ,including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete ----- For Approach Slab | 8 | Cum | 8,290 | ₹66,320 |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.76 MB
Tendernotice_2.pdf
PDF • 5.16 MB
12SBD.pdf
Tender Documents • 1.06 MB
BOQ_230201.xls
BOQ • 0.30 MB