superintending Engineer, PH Circle Idukki, Painavu
superintending Engineer, PH Circle Idukki, Kerala Water Authority, Painavu
Jal Jeevan Mission (JJM)-JJM-CWSS to Idukki- Kanjikuzhi, Vazhathope, Mariyapuram, Kamakshi, Vathikudy and Vannapuram (Part) Panchayaths in Idukki District-Supply and erection of clear water pumpsets- Electrical works
2026_KWA_826277_1
29/2024-25/SE/PHC/IDK/7067
Open Tender
Civil Works - Water Works
Item Rate
Idukki- Kanjikuzhi, Vazhathope
Please refer Tender documents.
10 documents required · 10 mandatory
₹16,540
₹5 L
Yes
7 Jan 2026
7 Jan 2026
6 Jun 2026
7 Jan 2026
4 Jun 2026
7 Jan 2026
7 Jan 2026 - 28 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Pumpsets at WTP | |||||
| 1.001 | OD79939/2024-2025:Supply, erection, testing and commissioning of KWA pre qualified reputed make Centrifugal pump sets - 1. Pump with bronze/SS impeller, SS shaft and CI pump casing with suitable type base plate with coupling, coupling guard foundation bolts & nuts etc. complete suitable for coupling the pump and motor above the base plate etc. complete including providing suitable foundation including cost of cement, sand and metal etc. complete. The duty condition is as follows Discharge –63.25 lps Suction Head – 6 m Length of suction pipe - 6.5 m, Total head-110.0 m, Pumping main - 400mm DI K9, 6971.0 m.
2. Motor- Supply, erection , testing and commissioning of KWA pre qualified reputed make horizontal solid shaft foot mounted TEFC squirrel cage induction motor with 6 poles suitable for the above pump working 3 phase 50 Hz AC supply, working voltage 415 V. The motor shall conform to EEFI/IS 325 including providing suitable concrete foundation including cost of cement, sand and metal etc. complete. Flexible coupling shall be used for coupling of pumps and motors.
3. Starter- Supply, erection , testing and commissioning of suitable rating fully automatic soft starter with air break contact suitable for the above motor with over voltage and under voltage protection, single phase preventer, over load relay with motor protection relay with main contactor and bypass contactor as per IE rules and code of practice etc. complete.
4. Panel board-(Suitable for operating two pump sets but one pump set at a time) Supply, Design, fabrication, erection, testing and commissioning of Cubicle type, floor mounted MS fabricated dust and vermin proof common control panel board consisting of 1 No. suitable capacity MCCB as incomer and 2 Nos. of suitable capacity MCCB as out going(the two MCCBs are interlocking with each other) providing suitable size aluminum bus bar to interconnect the above MCCBs and fitted with 3 Nos. of indicator lamps, 1 No. volt meter with selector switch etc. complete and provided with a common earth bus for the entire panel and interconnect with the MCCBs as per IE rules and code of practice. The panel shall be fitted on a common base frame on suitable foundation.
5. Cabling work- Supply, erection , testing and commissioning of suitable size XLPE cables for the above pump set panel board to starter and from starter to motor, considering energy conservation
6. Earthing- Supply of all materials and providing suitable earthing by using suitable size pipe or plate earthing GI/copper strip buried in ground and giving double earthing to motor, starter, panel board etc. as per IE standards.
7. Capacitor -Supply, erection , testing and commissioning of heavy duty APP capacitor for the motor to get a power factor above 0.95. The capacitor shall conform to IS 2834
8. Valves- Supply of suitable size best quality heavy duty ISI marked CI double flanged sluice valve and non - return valve with suitable pressure rating. Fitting of valves shall include proper RCC support especially for non - return valves.IN case of positive suction pump set, sluice valve should be in suction as well as delivery sides for easy repair works
9. Suction and delivery pipe connections- Supply and fitting of suitable size best quality GI/M.S pipe of thickness not less than 8mm for a total length of 10.00m suitable for the above pump set and connecting the suction pipe and valve with suitable flanges nut & bolts IR sheets etc. complete and connecting the delivery side of pump with the valves and suitable specials to connect with the pumping main. If the dia. of suction pipe is above 80mm, CI pipes and specials shall be provided. ( rate include pump, motor, panel board, stater,10 m cable , capacitor,10 m suction pipe, foot valve, NRV, sluice valve, pipe connection upto valve, earthing , erection , trial run and commissioning, 2 year maintenance, factory inspection above 100 HP.) | 3 | no | - | - |
| 1.002 | OD79940/2024-2025:Supply, erection, testing and commissioning of KWA pre qualified reputed make Centrifugal pump set - 1. Pump - Pump with bronze/SS impeller, SS shaft and CI pump casing with suitable type base plate with coupling, coupling guard foundation bolts& nuts etc. complete suitable for coupling the pump and motor above the base plate etc. complete including providing suitable foundation including cost of cement, sand and metal etc. complete. The duty condition is as follows Discharge –111.0 lps Suction Head – 6 m Length of suction pipe - 6.5 m, Total head-85.0 m, Pumping main - 350mm DI K9, 16220.0 m.
2. Motor- Supply, erection , testing and commissioning of KWA pre qualified reputed make horizontal solid shaft foot mounted TEFC squirrel cage induction motor 6 pole suitable for the above pump working 3 phase 50 Hz AC supply, working voltage 415 V. The motor shall conform to EEFI/IS 325 including providing suitable concrete foundation including cost of cement, sand and metal etc. complete. Flexible coupling shall be used for coupling of pumps and motors.
3. Starter- Supply, erection , testing and commissioning of suitable rating fully automatic starter with air break contact suitable for the above motor with over voltage and under voltage protection, single phase preventer, over load relay with motor protection relay with main contactor and bypass contactor as per IE rules and code of practice etc. complete.
4. Panel board-(Suitable for operating two pump sets but one pump set at a time) Supply, Design, fabrication, erection, testing and commissioning of Cubicle type, floor mounted MS fabricated dust and vermin proof common control panel board consisting of 1 No. suitable capacity MCCB as incomer and 2 Nos. of suitable capacity MCCB as out going(the two MCCBs are interlocking with each other) providing suitable size aluminum bus bar to interconnect the above MCCBs and fitted with 3 Nos. of indicator lamps, 1 No. volt meter with selector switch etc. complete and provided with a common earth bus for the entire panel and interconnect with the MCCBs as per IE rules and code of practice. The panel shall be fitted on a common base frame on suitable foundation.
5. Cabling work- Supply, erection , testing and commissioning of suitable size XLPE cables for the above pump set panel board to starter and from starter to motor, considering energy conservation
6. Earthing- Supply of all materials and providing suitable earthing by using suitable size pipe or plate earthing GI/copper strip buried in ground and giving double earthing to motor, starter, panel board etc. as per IE standards.
7. Capacitor -Supply, erection , testing and commissioning of heavy duty APP capacitor for the motor to get a power factor above 0.95. The capacitor shall conform to IS 2834
8. Valves- Supply of suitable size best quality heavy duty ISI marked CI double flanged sluice valve and non - return valve with suitable pressure rating. Fitting of valves shall include proper RCC support especially for non - return valves.IN case of positive suction pump set, sluice valve should be in suction as well as delivery sides for easy repair works
9. Suction and delivery pipe connections- Supply and fitting of suitable size best quality GI/M.S pipe of thickness not less than 8mm for a total length of 10.00m suitable for the above pump set and connecting the suction pipe and valve with suitable flanges nut & bolts IR sheets etc. complete and connecting the delivery side of pump with the valves and suitable specials to connect with the pumping main. If the dia. of suction pipe is above 80mm, CI pipes and specials shall be provided. ( rate include pump,motor,panel board, stater,10 m cable , capacitor,10 m suction pipe,foot valve, NRV, sluice valve, pipe connection upto valve, earthing , erection , trial run and commistioning, 2 year maintanence, factory inspection above 100 HP.) | 2 | no | - | - |
| 2Pumpsets at Calvary church | |||||
| 2.001 | OD79866/2024-2025:Supply, erection, testing and commissioning of KWA pre qualified reputed make Centrifugal pump set - 1. Pump - pump with bronze/SS impeller, SS shaft and CI pump casing with suitable type base plate with coupling, coupling guard foundation bolts& nuts etc. complete suitable for coupling the pump and motor above the base plate etc. complete including providing suitable foundation including cost of cement, sand and metal etc. complete. The duty condition is as follows Discharge –15 lps Suction Head – 6 m Length of suction pipe - 6.5 m, Total head-225.0 m, Pumping main - 150mm DI K9, 3555.0 m.
2. Motor- Supply, erection , testing and commissioning of KWA pre qualified reputed make horizontal solid shaft foot mounted TEFC squirrel cage induction motor with 4 poles (1500 rpm) suitable for the above pump working 3 phase 50 Hz AC supply, working voltage 415 V. The motor shall conform to EEFI/IS 325 including providing suitable concrete foundation including cost of cement, sand and metal etc. complete. Flexible coupling shall be used for coupling of pumps and motors.
3. Starter- Supply, erection , testing and commissioning of suitable rating fully automatic soft starter with air break contact suitable for the above motor with over voltage and under voltage protection, single phase preventer, over load relay with motor protection relay with main contactor and bypass contactor as per IE rules and code of practice etc. complete.
4. Panel board-(Suitable for operating two pump sets but one pump set at a time) Supply, Design, fabrication, erection, testing and commissioning of Cubicle type, floor mounted MS fabricated dust and vermin proof common control panel board consisting of 1 No. suitable capacity MCCB as incomer and 2 Nos. of suitable capacity MCCB as out going(the two MCCBs are interlocking with each other) providing suitable size aluminum bus bar to interconnect the above MCCBs and fitted with 3 Nos. of indicator lamps, 1 No. volt meter with selector switch etc. complete and provided with a common earth bus for the entire panel and interconnect with the MCCBs as per IE rules and code of practice. The panel shall be fitted on a common base frame on suitable foundation.
5. Cabling work- Supply, erection , testing and commissioning of suitable size XLPE cables for the above pump set panel board to starter and from starter to motor, considering energy conservation
6. Earthing- Supply of all materials and providing suitable earthing by using suitable size pipe or plate earthing GI/copper strip buried in ground and giving double earthing to motor, starter, panel board etc. as per IE standards.
7. Capacitor -Supply, erection , testing and commissioning of heavy duty APP capacitor for the motor to get a power factor above 0.95. The capacitor shall conform to IS 2834
8. Valves- Supply of suitable size best quality heavy duty ISI marked CI double flanged sluice valve and non - return valve with suitable pressure rating. Fitting of valves shall include proper RCC support especially for non - return valves.IN case of positive suction pump set, sluice valve should be in suction as well as delivery sides for easy repair works
9. Suction and delivery pipe connections- Supply and fitting of suitable size best quality GI/M.S pipe of thickness not less than 8mm for a total length of 10.00m suitable for the above pump set and connecting the suction pipe and valve with suitable flanges nut & bolts IR sheets etc. complete and connecting the delivery side of pump with the valves and suitable specials to connect with the pumping main. If the dia. of suction pipe is above 80mm, CI pipes and specials shall be provided. ( rate include pump,motor,panel board, stater,10 m cable , capacitor,10 m suction pipe,foot valve, NRV, sluice valve, pipe connection upto valve, earthing , erection , trial run and commistioning, 2 year maintanence, factory inspection above 100 HP.) | 2 | no | - | - |
| 3Pumpsets at Double cutting | |||||
| 3.001 | OD79868/2024-2025:Supply, erection, testing and commissioning of KWA pre qualified reputed make Centrifugal pump set - 1. Pump - pump with bronze/SS impeller, SS shaft and CI pump casing with suitable type base plate with coupling, coupling guard foundation bolts& nuts etc. complete suitable for coupling the pump and motor above the base plate etc. complete including providing suitable foundation including cost of cement, sand and metal etc. complete. The duty condition is as follows Discharge –17lps Suction Head – 6 m Length of suction pipe - 6.5 m, Total head-145.0 m, Pumping main - 150mm DI K9, 4534 m.
2. Motor- Supply, erection , testing and commissioning of KWA pre qualified reputed make horizontal solid shaft foot mounted TEFC squirrel cage induction motor with 4 poles (1500rpm) suitable for the above pump working 3 phase 50 Hz AC supply, working voltage 415 V. The motor shall conform to EEFI/IS 325 including providing suitable concrete foundation including cost of cement, sand and metal etc. complete. Flexible coupling shall be used for coupling of pumps and motors.
3. Starter- Supply, erection , testing and commissioning of suitable rating fully automatic soft starter with air break contact suitable for the above motor with over voltage and under voltage protection, single phase preventer, over load relay with motor protection relay with main contactor and bypass contactor as per IE rules and code of practice etc. complete.
4. Panel board-(Suitable for operating two pump sets but one pump set at a time) Supply, Design, fabrication, erection, testing and commissioning of Cubicle type, floor mounted MS fabricated dust and vermin proof common control panel board consisting of 1 No. suitable capacity MCCB as incomer and 2 Nos. of suitable capacity MCCB as out going(the two MCCBs are interlocking with each other) providing suitable size aluminum bus bar to interconnect the above MCCBs and fitted with 3 Nos. of indicator lamps, 1 No. volt meter with selector switch etc. complete and provided with a common earth bus for the entire panel and interconnect with the MCCBs as per IE rules and code of practice. The panel shall be fitted on a common base frame on suitable foundation.
5. Cabling work- Supply, erection , testing and commissioning of suitable size XLPE cables for the above pump set panel board to starter and from starter to motor, considering energy conservation
6. Earthing- Supply of all materials and providing suitable earthing by using suitable size pipe or plate earthing GI/copper strip buried in ground and giving double earthing to motor, starter, panel board etc. as per IE standards.
7. Capacitor -Supply, erection , testing and commissioning of heavy duty APP capacitor for the motor to get a power factor above 0.95. The capacitor shall conform to IS 2834
8. Valves- Supply of suitable size best quality heavy duty ISI marked CI double flanged sluice valve and non - return valve with suitable pressure rating. Fitting of valves shall include proper RCC support especially for non - return valves.IN case of positive suction pump set, sluice valve should be in suction as well as delivery sides for easy repair works
9. Suction and delivery pipe connections- Supply and fitting of suitable size best quality GI/M.S pipe of thickness not less than 8mm for a total length of 10.00m suitable for the above pump set and connecting the suction pipe and valve with suitable flanges nut & bolts IR sheets etc. complete and connecting the delivery side of pump with the valves and suitable specials to connect with the pumping main. If the dia. of suction pipe is above 80mm, CI pipes and specials shall be provided. ( rate include pump,motor,panel board, stater,10 m cable , capacitor,10 m suction pipe,foot valve, NRV, sluice valve, pipe connection upto valve, earthing , erection , trial run and commistioning, 2 year maintanence, factory inspection above 100 HP.) | 2 | no | - | - |
| 3.002 | OD79869/2024-2025:Supply, erection, testing and commissioning of KWA pre qualified reputed make Centrifugal pump set - 1. Pump - pump with bronze/SS impeller, SS shaft and CI pump casing with suitable type base plate with coupling, coupling guard foundation bolts& nuts etc. complete suitable for coupling the pump and motor above the base plate etc. complete including providing suitable foundation including cost of cement, sand and metal etc. complete. The duty condition is as follows Discharge –108.0 lps Suction Head – 6 m Length of suction pipe - 6.5 m, Total head-70.0 m, Pumping main - 400mm DI K9, 7934.0 m. 2. Motor- Supply, erection , testing and commissioning of KWA pre qualified reputed make horizontal solid shaft foot mounted TEFC squirrel cage induction motor with 4 poles (1500rpm) suitable for the above pump working 3 phase 50 Hz AC supply, working voltage 415 V. The motor shall conform to EEFI/IS 325 including providing suitable concrete foundation including cost of cement, sand and metal etc. complete. Flexible coupling shall be used for coupling of pumps and motors. 3. Starter- Supply, erection , testing and commissioning of suitable rating fully automatic soft starter with air break contact suitable for the above motor with over voltage and under voltage protection, single phase preventer, over load relay with motor protection relay with main contactor and bypass contactor as per IE rules and code of practice etc. complete. 4. Panel board-(Suitable for operating two pump sets but one pump set at a time) Supply, Design, fabrication, erection, testing and commissioning of Cubicle type, floor mounted MS fabricated dust and vermin proof common control panel board consisting of 1 No. suitable capacity MCCB as incomer and 2 Nos. of suitable capacity MCCB as out going(the two MCCBs are interlocking with each other) providing suitable size aluminum bus bar to interconnect the above MCCBs and fitted with 3 Nos. of indicator lamps, 1 No. volt meter with selector switch etc. complete and provided with a common earth bus for the entire panel and interconnect with the MCCBs as per IE rules and code of practice. The panel shall be fitted on a common base frame on suitable foundation. 5. Cabling work- Supply, erection , testing and commissioning of suitable size XLPE cables for the above pump set panel board to starter and from starter to motor, considering energy conservation 6. Earthing- Supply of all materials and providing suitable earthing by using suitable size pipe or plate earthing GI/copper strip buried in ground and giving double earthing to motor, starter, panel board etc. as per IE standards. 7. Capacitor -Supply, erection , testing and commissioning of heavy duty APP capacitor for the motor to get a power factor above 0.95. The capacitor shall conform to IS 2834 8. Valves- Supply of suitable size best quality heavy duty ISI marked CI double flanged sluice valve and non - return valve with suitable pressure rating. Fitting of valves shall include proper RCC support especially for non - return valves.IN case of positive suction pump set, sluice valve should be in suction as well as delivery sides for easy repair works 9. Suction and delivery pipe connections- Supply and fitting of suitable size best quality GI/M.S pipe of thickness not less than 8mm for a total length of 10.00m suitable for the above pump set and connecting the suction pipe and valve with suitable flanges nut & bolts IR sheets etc. complete and connecting the delivery side of pump with the valves and suitable specials to connect with the pumping main. If the dia. of suction pipe is above 80mm, CI pipes and specials shall be provided. ( rate include pump,motor,panel board, stater,10 m cable , capacitor,10 m suction pipe,foot valve, NRV, sluice valve, pipe connection upto valve, earthing , erection , trial run and commistioning, 2 year maintanence, factory inspection above 100 HP.) | 2 | no | - | - |
| 4Pumpsets at Kanjikuzhi | |||||
| 4.001 | OD79867/2024-2025:Supply, erection, testing and commissioning of KWA pre qualified reputed make Centrifugal pump set - 1. Pump - pump with bronze/SS impeller, SS shaft and CI pump casing with suitable type base plate with coupling, coupling guard foundation bolts& nuts etc. complete suitable for coupling the pump and motor above the base plate etc. complete including providing suitable foundation including cost of cement, sand and metal etc. complete. The duty condition is as follows Discharge –54.5.0 lps Suction Head – 6 m Length of suction pipe - 6.5 m, Total head-50.0 m, Pumping main - 350mm DI K9, 2008.0 m.
2. Motor- Supply, erection , testing and commissioning of KWA pre qualified reputed make horizontal solid shaft foot mounted TEFC squirrel cage induction motor 4 poles (1500rpm) suitable for the above pump working 3 phase 50 Hz AC supply, working voltage 415 V. The motor shall conform to EEFI/IS 325 including providing suitable concrete foundation including cost of cement, sand and metal etc. complete. Flexible coupling shall be used for coupling of pumps and motors.
3. Starter- Supply, erection , testing and commissioning of suitable rating fully automatic STAR DELTA starter with air break contact suitable for the above motor with over voltage and under voltage protection, single phase preventer, over load relay with motor protection relay with main contactor and bypass contactor as per IE rules and code of practice etc. complete.
4. Panel board-(Suitable for operating two pump sets but one pump set at a time) Supply, Design, fabrication, erection, testing and commissioning of Cubicle type, floor mounted MS fabricated dust and vermin proof common control panel board consisting of 1 No. suitable capacity MCCB as incomer and 2 Nos. of suitable capacity MCCB as out going(the two MCCBs are interlocking with each other) providing suitable size aluminum bus bar to interconnect the above MCCBs and fitted with 3 Nos. of indicator lamps, 1 No. volt meter with selector switch etc. complete and provided with a common earth bus for the entire panel and interconnect with the MCCBs as per IE rules and code of practice. The panel shall be fitted on a common base frame on suitable foundation.
5. Cabling work- Supply, erection , testing and commissioning of suitable size XLPE cables for the above pump set panel board to starter and from starter to motor, considering energy conservation
6. Earthing- Supply of all materials and providing suitable earthing by using suitable size pipe or plate earthing GI/copper strip buried in ground and giving double earthing to motor, starter, panel board etc. as per IE standards.
7. Capacitor -Supply, erection , testing and commissioning of heavy duty APP capacitor for the motor to get a power factor above 0.95. The capacitor shall conform to IS 2834
8. Valves- Supply of suitable size best quality heavy duty ISI marked CI double flanged sluice valve and non - return valve with suitable pressure rating. Fitting of valves shall include proper RCC support especially for non - return valves.IN case of positive suction pump set, sluice valve should be in suction as well as delivery sides for easy repair works
9. Suction and delivery pipe connections- Supply and fitting of suitable size best quality GI/M.S pipe of thickness not less than 8mm for a total length of 10.00m suitable for the above pump set and connecting the suction pipe and valve with suitable flanges nut & bolts IR sheets etc. complete and connecting the delivery side of pump with the valves and suitable specials to connect with the pumping main. If the dia. of suction pipe is above 80mm, CI pipes and specials shall be provided. ( rate include pump,motor,panel board, stater,10 m cable , capacitor,10 m suction pipe,foot valve, NRV, sluice valve, pipe connection upto valve, earthing , erection , trial run and commistioning, 2 year maintanence, factory inspection above 100 HP.) | 2 | no | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
KWAGeneralConditionsforeTenderingV5.pdf
PDF • 0.69 MB
Tendernotice_1.pdf
PDF • 0.15 MB
BOQ_1386014.xls
BOQ • 0.44 MB
29NITVOl1oders.pdf
Tender Documents • 18.38 MB
29tenderQ1Q8n.xls
Other Document • 0.03 MB
29NITVol2.pdf
Tender Documents • 0.82 MB
Date_extension.pdf
PDF • 0.10 MB
datecorrigendum23.pdf
PDF • 0.24 MB
datecorrigendun26b.pdf
PDF • 0.24 MB
datecorrigendum52.pdf
PDF • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .