| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.0 LAccepted-AOC KERALA KL KERALA | L1 | Accepted-AOC L1 | |
| 2 | L2₹10.3 L+₹29,694 (2.96%)Rejected-AOC MIHAD HOUSE PURAKKAD POST PAYYOLI KOZHIKODE | L2 | Rejected-AOC L2 | |
| 3 | L3₹11.9 L+₹1.9 L (18.5%)Rejected-AOC KANNADIKKUZHI HOUSE RAMANATTUKARA VAZHAYUR EAST PO | L3 | Rejected-AOC L3 | |
| 4 | L4₹12.0 L+₹2.0 L (19.8%)Rejected-AOC | L4 | Rejected-AOC L4 | |
| 5 | L5₹13.0 L+₹3.0 L (29.5%)Rejected-AOC BALUSSERY GRAMA PANCHAYATH | L5 | Rejected-AOC L5 |
Tender Value
₹11.9 L
EMD Value
₹29,699
Closing Date
29 Jan 2025, 6:55 pmClosed
Assistant Executive Engineer
o/oAssistant Executive EngineerKyIP Canal Sub division Vatakara
GENERAL-KyIP-CADA 2024-25-Renovation and mordernisation works to Vellarakkad distributary canal between ch 0/000 km and ch 1/300 km-General Civil Work
2025_Irrig_729089_1
IRR/PI/TR/5261/2024_5_2_1/1
Open Tender
Civil Works - Canal
Item Rate
180 days
Maralur
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹29,699
Yes
21 Feb 2025
22 Jan 2025
31 Jan 2025
22 Jan 2025
29 Jan 2025
22 Jan 2025
22 Jan 2025 - 29 Jan 2025
Amount
Rectification
2.33.3:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyond 120 cm girth up to and including 240 cm girth
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
Canal lining
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
P.T.USMAN (BID ID -2081562)
HAREESH KUMAR V K (BID ID -2074797)
Rahul p (BID ID -2077940)
SUMESH (BID ID -2078624)
AMARNATH K (BID ID -2079006)
Bidder Name
VK BALAN
P.T.USMAN
HAREESH KUMAR V K
SUMESH
Rahul p
AMARNATH K
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1161933.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .