| 3 | Not Admitted-Fee/PreQual/Technical MOHALLA SUBHASHNAGAR DEOKALI ROAD DISTT LAKHIMPUR KHERI | LAKHIMPUR KHERI | LAKHIMPUR KHERI | UTTAR PRADESH | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹1.5 Cr
EMD Value
₹9.7 L
Closing Date
11 May 2026, 5:00 pmClosed
Office at Deputy Director (Construction)
NAVEEN MANDI STHAL JANGI ROAD MIRZAPUR
Construction work of 10 nos B category and 10 nos C category shops at the New mandi Yard Gopiganj
2026_RKUMP_1142034_1
2026/40
Open Tender
Civil Works
Percentage
273 days
Mandi Samiti Gopiganj
Construction work of 10 nos B category and 10 nos C category shops at the New mandi Yard Gopiganj
3 documents required · 3 mandatory
₹27,800
Deputy Director (Construction)
₹9.7 L
Yes
20 May 2026
28 Apr 2026
12 May 2026
28 Apr 2026
11 May 2026
28 Apr 2026
28 Apr 2026 - 11 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Excavation in Foundation in ordinary soil (loam, clay or sand) including lift up to 1.5M and lead up to 50M. and including filling, watering and ramming of the excavated earth into the trenches or into the space between the building and the sides of the foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the E/I upto a distance of 50M. from the foundation trenches.(SI NO 251) | 1 | CUM | 110 | ₹109.89 |
| 1.02 | Providing and laying concrete 1:6:12 (1 cement, 4 fine sand and 8 stone agregate 40 mm size) curing complete, including cost of all T&P complete (S.I. No. 273) | 221.5 | CUM | 3,500 | ₹7,75,250 |
| 1.03 | R.C.C work with cement approved coarse sand and 2 cm. (3/4") gauge approved stone grit in the proportion 1:1.5:3 (1 cement: 2 coarse sand: 4 aggregate) in raft excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 BWG binding wire and necessary centering and shuttering etc. and also including supply of all materials labour and tools and plants etc. required for proper completion of the work. Strength of the concrete shall not be less than M-150 as per direction of Engineer-in-charge.(S.I,.No.287 A) | 40.86 | CUM | 6,300 | ₹2,57,418 |
| 1.04 | R.C.C work with cement, approved coarse sand and 2cm (3/4") gauge approved stone grit in the proportion of 1:1.5:3 in column excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all meterials labour and T&P etc. required for proper completion of the work. . (SI NO 288 A) | 1 | CUM | 9,600 | ₹9,599.9 |
| 1.05 | M-150 brick work in 1:6 cement and coarse sand in super structure avobe plinth level including necessasary cutting and moulding of bricks works as required and also including honey combed brick in thickness of wall more than12cm with all materials labourT&P required for proper completetion of work as per direction of E/I | 1 | CUM | 5,060 | ₹5,059.95 |
| 1.06 | R.C.C work with cement, approved coarse sand and 2cm (3/4") gauge approved stone grit in the proportion of 1:2:4 in lintels of doors & windows excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials labour and T&P etc. required for proper completion of the work. . (SI NO 283) | 24.74 | CUM | 8,200 | ₹2,02,868 |
| 1.07 | R.C.C work with cement, approved coarse sand and 2cm (3/4") gauge approved stone grit in the proportion of 1:1.5:3 in column excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all meterials labour and T&P etc. required for proper completion of the work. . (SI NO 288 A) | 43.26 | CUM | 9,600 | ₹4,15,296 |
| 1.08 | M-150 brick work in 1:4 cement and fine sand of 1.25fm in foundation and plinth including supply of all materialT&P complete for proper completion of work as per direction of E/I (SI NO305) | 237.18 | CUM | 5,738 | ₹13,60,938.84 |
| 1.09 | R.C.C work with cement, approved coarse sand and 2cm (3/4") gauge approved stone grit in the proportion of 1:1.5:3 in BEAM excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials labour and T&P etc. required for proper completion of the work. . | 1 | CUM | 9,319 | ₹9,309.68 |
| 1.1 | R.C.C work with cement, approved coarse sand and 2cm (3/4") gauge approved stone grit in the proportion of 1:1.5:3 in lintels of doors & windows excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials labour and T&P etc. required for proper completion of the work.. | 1.56 | CUM | 8,610 | ₹13,431.6 |
stage.html
html • 0.02 MB
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 8.75 MB
Tendernotice_2.pdf
PDF • 3.22 MB
BOQ_2134556.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .