| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹13.6 LAccepted-AOC | ₹13.6 L | 1 | Accepted-AOC L1 bidder |
| 2 | 2₹18.0 LRejected-AOC | ₹18.0 L | 2 | Rejected-AOC L2 bidder |
| 3 | 3₹19.0 LRejected-AOC | ₹19.0 L | 3 | Rejected-AOC L3 bidder |
| Sl No | Description | Qty | Unit | P.Damodaran, G.R.Industries L2 | MANAF V L1 | ASHIFUL HAK.C L3 |
|---|---|---|---|---|---|---|
| 1.00Painting and Overhauling the Sluice shutters | ||||||
| 1.00 | OD21975/2023-2024:Cleaning all the debris deposited, if any from shutters and its grooves including
cost of all material, labour charges,tools if any etc. complete. | 4 | each set | 6,897 ₹27,588 | 5,780.99 ₹23,123.96 | 8,070 ₹32,280 |
| 1.00 | OD53310/2025-2026:Painting all the exposed surfaces of the gate and embedded parts with two coats of epoxy coal tar black paint confirming to IS14948 with a minimum film thickness of 150+/-5 microns per each coat over two coats of priming coat applied with high build surface tolerant coating having low VOC primer with a film thickness of 70+/-5 microns , so that the total film thickness of all coats including priming coat at any rate is not less than 350 microns after cleaning the surface using hand and power tool cleaning including cost of all materials, labour charges , cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site | 1,991.4 | sqm | 480 ₹9.6 L | 353.01 ₹7.0 L | 492 ₹9.8 L |
| 1.00 | 85.103:Supply of MS checquered plates including cost of conveyance charges | 818.45 | kg | 100 ₹81,844.80 | 61.54 ₹50,367.29 | 85.91 ₹70,312.87 |
| 1.00 | 85.124:Fabrication and supply of Hoisting bride unit in structural steel confirming to IS2062 Gr including ladder, covers for hoisting unit etc as per approved specifications, drawings and directions of departmental officer at site including cost of labour, machinery, incidental and handling charges for fixing handrails and allied works etc complete but excluding material already supplied and weight of pipes for hand rails etc | 818.45 | kg | 86.82 ₹71,057.66 | 72.76 ₹59,550.28 | 101.57 ₹83,129.76 |
| 1.00 | 85.136:Erection of the hoisting bridge unit including handrails , ladder and platform etc. in correct alignment and anchoring it ; setting and aligning the covers of the hoisting unit etc complete including cost of all labour, machinery, incidental and conveyance , lead and lift charges etc complete but excluding cost of materials already supplied | 818.45 | kg | 5 ₹4,092.24 | 3.51 ₹2,872.75 | 4.9 ₹4,010.40 |
| 1.01 | 85.115:Cost of painting with 2 coats of enamel paint over 1 coat of zinchromate primer as per IS1477:1994 after hand and power tool cleaning including cost of all materials, labour charges, cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site | 1,198.47 | sqm | 290 ₹3.5 L | 211.28 ₹2.5 L | 295 ₹3.5 L |
| 1.01 | OD21280/2023-2024:Overhauling the spillway shutters such as worm reducer,gears,pinions,plummer
blocks,chain & sprockets,bearings etc of hoist mechanism and wire ropes, applying cardium compound,pivots of electromagnetic brackes,trunion bushes etc.twice in year including the cost of all materials,labour charges(including dismantling & refitting of hoist unit covers etc.) coveyance charges etc.complete as directed by thedeptl.official at site. | 5 | set | 21,080.75 ₹1.1 L | 17,667.78 ₹88,338.90 | 24,665 ₹1.2 L |
| 1.01 | OD25856/2024-2025:Trial run the shutter including cost of all labour ,materials etc complete | 5 | set | 3,711 ₹18,555 | 3,110.41 ₹15,552.05 | 4,345 ₹21,725 |
| 2.00Replacing the damaged rubber seal in Emergency shutter | ||||||
Tender Value
₹16.2 L
EMD Value
₹40,488
Closing Date
21 Mar 2026, 5:00 pmClosed
Jishakumar C B
Executive Engineer, Irrigation-Mechanical Division, Malampuzha
GENERAL-CHIMMONI-Overhauling and painting of Shutter and Hoisting mechanism.- General Mechanical Work-1
2026_Irrig_846449_1
IRR/MH/6002/2025-2026
Open Tender
Repair and Maintenance Works
120 days
Chimmoni Dam
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹40,488
Yes
9 Jun 2026
11 Mar 2026
24 Mar 2026
11 Mar 2026
21 Mar 2026
11 Mar 2026
11 Mar 2026 - 21 Mar 2026
Painting and Overhauling the Sluice shutters
OD21975/2023-2024:Cleaning all the debris deposited, if any from shutters and its grooves including cost of all material, labour charges,tools if any etc. complete.
OD53310/2025-2026:Painting all the exposed surfaces of the gate and embedded parts with two coats of epoxy coal tar black paint confirming to IS14948 with a minimum film thickness of 150+/-5 microns per each coat over two coats of priming coat applied with high build surface tolerant coating having low VOC primer with a film thickness of 70+/-5 microns , so that the total film thickness of all coats including priming coat at any rate is not less than 350 microns after cleaning the surface using hand and power tool cleaning including cost of all materials, labour charges , cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site
85.103:Supply of MS checquered plates including cost of conveyance charges
85.124:Fabrication and supply of Hoisting bride unit in structural steel confirming to IS2062 Gr including ladder, covers for hoisting unit etc as per approved specifications, drawings and directions of departmental officer at site including cost of labour, machinery, incidental and handling charges for fixing handrails and allied works etc complete but excluding material already supplied and weight of pipes for hand rails etc
85.136:Erection of the hoisting bridge unit including handrails , ladder and platform etc. in correct alignment and anchoring it ; setting and aligning the covers of the hoisting unit etc complete including cost of all labour, machinery, incidental and conveyance , lead and lift charges etc complete but excluding cost of materials already supplied
85.115:Cost of painting with 2 coats of enamel paint over 1 coat of zinchromate primer as per IS1477:1994 after hand and power tool cleaning including cost of all materials, labour charges, cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site
OD21280/2023-2024:Overhauling the spillway shutters such as worm reducer,gears,pinions,plummer blocks,chain & sprockets,bearings etc of hoist mechanism and wire ropes, applying cardium compound,pivots of electromagnetic brackes,trunion bushes etc.twice in year including the cost of all materials,labour charges(including dismantling & refitting of hoist unit covers etc.) coveyance charges etc.complete as directed by thedeptl.official at site.
OD25856/2024-2025:Trial run the shutter including cost of all labour ,materials etc complete
Replacing the damaged rubber seal in Emergency shutter
OD19195/2025-2026:Removing the damaged rubber seal from the Emergency shutter including cost of all labour ,machinery etc
OD19200/2025-2026:Supplying and fixing in correct position with specified initial interface P type rubber seal confirming to IS11855 to the gates including cost of SS bolts and nuts and all labour and machinery and incidental and conveyance charges complete as per approved specifications and drawings
OD19557/2025-2026:Supplying and fixing in correct position with Angular bulb nose rubber seal for corners to the gates including cost of SS bolts and nuts and all labour and machinery and incidental and conveyance charges complete including scaffolding and special appliances as per approved specifications and drawings
OD19592/2025-2026:Supply of MS plates confirming to IS 2062GrB including cost of conveyance charges
OD19594/2025-2026:Fabrication and supply of Structural Steel wheel gate and accessories as per approved specifications, drawings and directions of deptl officer at site including cost of labour , machinery , incidental and handling charge etc complete but exculding cost of materials already supplied
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1430055.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
BOQ_1430055.xls
BOQ • 0.31 MB
SBD.pdf
Tender Documents • 1.64 MB
Download all tender documents and submit your bid