CHIEF ENGINEER (G)
Providing and fixing New GI Sheet in ESP 3 in place of corroded sheet and other Misc Civil Work of ESP at Gandhinagar TPS
288542
EW-270
Open
Miscellaneous Works
Works
Gandhinagar
2 documents required · 2 mandatory
₹2,950
Gujarat State Electricity Corporation Limited Payable at Gandhinagar
₹1.5 L
30 Mar 2026
30 Mar 2026
30 Mar 2026
20 Apr 2026
30 Mar 2026
1. SECTION-A:
ACKNOWLEDGEMENT OF TENDER FEE /EMD.
TENDER NOTICE.
2. SECTION-B:
DECLARATION FORM CUM UNDER TAKING TO
BE SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE TENDERER
3. SECTION-C:
GENERAL CONDITIONS OF CONTRACT
4. SECTION-D:
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES & LIST OF SAFETY
5. SECTION-E :
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE – I (DETAILS OF BANK FOR
SOLVEANCY & BG)
6. SECTION-F:
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF
STEEL / CEMENT
GENERAL GUIDELINES RELEVANT TO I.S.
7. SECTION-G:
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
DETAIL SPECIFICATION
8. SECTION-H:
SCHEDULE-B
Safe Maintenance Procedure
EW- 270 PUR-F-006 RFQ-75883
ACKNOWLEDGEMENT OF TENDER FEE
TENDER NOTICE
EW- 270 PUR-F-006 RFQ-75883
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
Ph. 91-79-23215663Fax: 91-79-23217673, e-mail:
[email protected] Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
ACKNOWLEDGMENT
e- Tender for the
“Providing and fixing New G.I Sheet in ESP 3 in place of corroded sheet and other
Misc. Civil Work of ESP at Gandhinagar TPS.”
TENDER FEE PAID VIDE DEMAND DRAFT NO.
_________________________________ DATED___________________________ RS.
EARNEST MONEY DEPOSIT PAID VIDE D.D. NO.
_______________________________ DATED ____________________ RS.
1. The undersigned reserves the right to reject any or all tenders
without assigning any reasons thereof.
2. The Tender fee will be accepted in form of Demand Draft and Earnest
Money Deposit will be accepted in form of Demand Draft or Bank
Guarantee of any bank as prescribe in ANNEXURE- I drawn in favour of
“GUJARAT STATE ELECTRICITY CORPORATION LTD.” payable at
Gandhinagar TPS
For & On behalf of
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 270 PUR-F-006 RFQ-75883
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
Ph. 91-79-23215663Fax: 91-79-23217673, e-mail:
[email protected] Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
Tender Notice No: GSECL/___/ __/ For Civil works
CE [Generation], Gandhinagar, TPS invites “On-line Tenders” (e-tendering) for the work of
“Providing and fixing New G.I Sheet in ESP 3 in place of corroded sheet and other
Misc. Civil Work of ESP at Gandhinagar TPS.”Tender Papers & Specifications may be
down loaded from Web site https://gsecl.nprocure.com(For view, down load and on line
submission) and GUVNL / GSECL web sites www.gsecl.in (For view only).All tender
documents are to be upload (Notarized / self-attested copies of original – as specified in
tender document) through online only (mandatory) on (n) procure portal excluding Tender
fee and EMD Tender fee and EMD are to be submitted physically by Registered Post A.D. or
Speed Post addressed to: CHIEF ENGINEER (GENERATION), GUJARAT STATE
ELECTRICITY CORPORATION LTD, THERMAL POWER STATION, GANDHINAGAR-
382041, GUJARAT. “NO COURIER SERVICE OR HAND DELIVERY” will be accepted.
Tender Estimated E.M.D.
No. Cost Rs. Rs.
EW- “Providing 11 (Eleven) Rs. 2500+
270 and fixing Months from 450 = Rs. Rs.
New G.I Sheet 2950.00/-
the date of
in ESP 3 in Rs. written
(Two (One Lakh
Thousand Forty Eight
place of
order to Nine Thousand Six
commence hundred Hundred Fifty
sheet and Fifty (Non Three Only)
other Misc. the work.
Refundable)
Civil Work of
Gandhinagar
180 Days [From the opening of
1 Validity of Tender
Technical Bid].
Last Date for Online tender / offer submission through
2 As per Tender Notice
(n)Procure only up to 18:00 Hrs(This is Mandatory)
Last Date for physical receipt of cover for DD / Bank
Guarantee / Online payment reference for Tender Fee and
3 As per Tender Notice
EMD only up to 15:00 Hrs Through RPAD or Speed Post
Date of opening of online Technical Bid, all relevant
documents submitted through online process, Cover for
4 Tender fee and EMD at 15:30 Hrs (Online technical bid As per Tender Notice
will be opened for Bidders who have submitted Cover for
Tender Fee and EMD)
Tentative date of on-line opening of price bid (if possible) Party has to be in touch with
at 15.30 hrs. website www.nprocure.com and
also with e-mail sent by above
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
EW- 270 PUR-F-006 RFQ-75883
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 270 PUR-F-006 RFQ-75883
1) Only following listed documents must be upload in n-process online only. No physical
documents are to be submitted except tender fee and EMD cover. Price Bid shall not be
submitted in Hard copy.
1. Demand Draft for Tender Fee and EMD (Original) cover only to submit through RPAD/Speed
post only.
2. The bidder shall have a separate Provident Fund Code of RPFC in the name of company. The
bidder, who does not possess such separate P.F. code, shall not be considered for acceptance
of tender. The contractor has to submit attested copy of such certificate showing P.F. code
along with the tender.
3. Attested copy of PAN No.
4. Attested copy of work experience certificate for the similar works executed.
5. List of work in progress.
6. Attested copy of firm registration [Applicable only to the firms registered under Company
7. Attested copy of partnership deed. [Applicable only to the partnership firms.]
8. Attested copy of power of attorney, if any, for signing the bid document.
9. Attested copy of balance sheet of profit & Loss account duly audited by Chartered
Accountant of at least 3 financial years, if work estimate is more than Rs. 50 Lacks.
10. Attested copy of latest solvency certificate not older than 12 months issued by any
nationalized bank OR Banks as per Annexure – I.
11. Details of equipment, tools and plants immediately available with the tenderer for use of this
12. Details of technical personnel.
13. Undertaking duly Notarized as per attached Declaration Form
14. Any other documents required to verify technical, financial capability of the bidders & other
Credentials
15. Attached The Copy Of GST Registration.
All such documents should be strictly uploaded in N-procure only expect Tender Fee and
EMD details cover. Otherwise the offer will not be considered and no any further
communication in the matter will be entertained.
2) In case any deviation is found in Data / Details / Documents uploaded on N-procure online
offer (e-tendering) documents then such tender will not be considered and no any further
communication in the matter will be entertained. Tenders must be un-conditional.
Conditional Tenders will be rejected.
3) Further bidders are requested to submit Technical Bid documents and price – bid i.e.
Schedule-B on line only and not to submit the Technical bid and price bid in physical form
expect Tender Fee and EMD details cover. This is mandatory. If Technical bid document and
price bid is submitted in physical form expect Tender Fee and EMD details cover, same will
not be opened and only on-line Uploaded/submitted Technical bid document and price will
be considered for evaluation. The bidder is requested not to upload/submit the by online
(n)procure while bid submission on in (n)procure tender document, condition of the
contract, specification & other relevant documents, except documents as stated here
above. Instead of the same, the bidder shall upload on (n) procure scan copy of the duly
Notarized Undertaking as stated below declaration form on the stamp paper of Rs. 300/-.
However, bidder may download tender document & preserve with them in Hard Copy
for their future reference. Later on, L1 bidder shall be asked to collect the tender
documents from the tender inviting authorities for the purpose of contract agreement
execution and place their signature with seal of the company.
4) It is mandatory for all the bidders to submit their tender documents viz. on-line (e-tendering)
and uploading on (n) procure in scheduled time. Tender documents submitted in physical
form will not be accepted and considered expect Tender Fee and EMD details cover. Also, all
bidders shall submit required Physical documents as stated in Tender Notice
5) GSECL reserves the rights to reject any OR all tenders without assigning any reasons
6) Tender Notice Number & name of the work shall be clearly written on the covers of
containing the Tender Fee and EMD.
7) Technical / Price Bids will be opened on the day and time indicated in the tender notice by an
Officer nominated by the Purchaser in the presence of such of the bidders who wish to be
present. Any technical questions, information and clarifications that may be required
pertaining to this tender should be referred to the CHIEF ENGINEER (GEN.) Gandhinagar
TPS. Also during pre-bid meeting (if arranged) the same may please be discussed
The exemption in payment of Tender Fee & EMD shall be given to
1. Micro & small-scale enterprises which participate directly in tendering
process for the product which they are manufacturing / service which
they are providing and have Udyam registration for items / service under
EW- 270 PUR-F-006 RFQ-75883
procurement.
2. Start-ups which participate directly in tendering process for the product
which they are manufacturing/service which they are providing and re-
cognized by DPIIT under the Start-up India Program and has obtained
Udyam registration.
3. Organization which has registration certificate for the manufacturing
product of the tender, from Gujarat Khadi Gramodyog Board or Khadi and
Village Industries Commission(K.V.I.C)or Commissioner of Cottage
Industries.
4. Board/Corporations/PSUs of the Central/State Government for their
own manufactured items.
5. State Government recognized organizations like(i) organizations for blinds,
dumb and deaf, disabled, mentally disabled persons;(ii)women's self-help
group recognized by Gujarat Livelihood Promotion Company; which
participate directly in tendering process for the product which they are
manufacturing / service which /they are providing.
1. Micro & Small Enterprises (MSEs) who participates directly in the
tendering process as Manufacturers or Service Providers, and holds a
valid Udyam Registration, are eligible for exemption from payment of
Earnest Money Deposit (EMD).
2. Agencies registered under Udyam in the capacity of Traders, Re-sellers, or
similar categories (i.e. other than Manufacturers/Service Providers) are
not eligible for EMD exemption.
3. Migration period for Reclassification of MSMEs: - ln case of an upward
change in terms of investment in plant and machinery or equipment or
turnover or both, and consequent re-classification, an enterprise shall
continue to avail of all non-tax benefits of the category (micro or small or
medium) it was in before the re-classification, for a period of three years
from the date of such upward change.
For & On behalf of GSECL
CHIEF ENGINEER
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 270 PUR-F-006 RFQ-75883
DECLARATION FORM CUM UNDER
TAKING TO BE SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE BIDDER
EW- 270 PUR-F-006 RFQ-75883
(To be uploaded on (n) procure online process duly notarized on Rs. 300/-
Non – Judicial Stamp Paper)
DECLARATION FORM
sheet and other Misc. Civil Work of ESP at Gandhinagar TPS.”
Tender No/ RFQ No:
1. I/We hereby declare that I/We have carefully studied the entire tender
placed on the WEB site and conditions of contract, specifications and other
documents of this work mentioned in the tender and abide by the same.
Also, I/We hereby agree to execute the same accordingly.
2. I/We hereby abide to execute the contract agreement by downloading the
copies of the conditions of contract, specifications and other documents of
this work of otherwise I/we will get copy of the same from the office of the
3. I/We hereby accept and confirm that any dispute on this regard shall not
4. I/We hereby declare that I/We have visited the work site and fully
acquainted myself/ourselves with the local situations regarding materials,
labour and other factors pertaining to the work before submitting the
5. I/We hereby confirm that our offer is Un-conditional and without any
technical & commercial deviations.
6. Should this tender be accepted, I /We hereby agree to abide by to fulfill all
the terms-conditions and provision of the Tender and Contract for Works
as applicable and default thereof, to forfeit and to pay to the Gujarat State
Electricity Corporation Limited the sums of money due.
7. The full value of the “Earnest Money Deposit” paid herewith should be
absolutely forfeited to the Corporation, should I/ we do not execute /
commence the work after issuance of date of commencement by GSECL.
EW- 270 PUR-F-006 RFQ-75883
8. If, I fail to submit all required documents with application or tender copy (
in each tender ) then my tender will be cancelled, which is binding to me.
9. If, full or part work will be given to me, it will be accepted to me with same
terms, rate & conditions.
10. I, ______ proprietor / owner / partner / Authorized Agent of M/s. ______ do
hereby also declare and undertake as under:
a) That in capacity of independent contractor for M/s. ______ (Sub-
Contractor of M/s. ______ ) worked as contractor at GSECL,
___________Thermal Power Station for the nature of work of ______ against
work Order No. ______ Dt. ______., I have complied with the provisions of
all laws as applicable. I have paid the wages for the month/s of my
contractual period which is / are not less than the minimum rates as
applicable, to all my employee/s and no other dues are payable to my
employee/s.
b) That I have covered all the eligible employee/s under the Employees’
Provident Funds and Miscellaneous Provisions Act, 1952 and deposited
the contributions under my PF Code No. ______, place: ______ for the
month/s of my contractual period and as such no amount towards
contribution whatever is payable.
c) I further declare and undertake that in case any liability pertaining
to any of my worker, labour, employee/s is/are to be discharged by the
principle employer i.e. Gujarat State Electricity corporation Limited,
___________Thermal Power Station due to my lapse, I undertake to
reimburse the same or the principle employer is authorized to deduct the
same from my dues as payable.
d) I further declare and undertake the legal consequences which may
arise in future under the said work order awarded, and I bond myself to
resolve the same at the risk and cost of M/s. ______.
authorized signatory of M/s
______________________________________________ here by certify that M/s
_________________________________________________ and their proprietor /
any partner / any directors of the firm is not stop deal and / or banned
for business dealing and / or black listed by GUVNL and / or their any
subsidiary company viz. GSECL / GETCO / DGVCL / MGVCL / UGVCL /
PGVCL as well as Government and / or Semi Government company /
department.
Seal & Signature of the Bidder
Phone / Mobile/ Fax No. & Company’s Seal
EW- 270 PUR-F-006 RFQ-75883
e- Tender for the work of “Providing and fixing New G.I Sheet in ESP 3 in place
of corroded sheet and other Misc. Civil Work of ESP at Gandhinagar TPS.”
RTGS DETAIL OF BIDDER
Following RTGS details shall be submitted by agency along with the tender for direct
deposit of payment to the beneficiary account. Bidder has to submit the details as under:
1 Name of Bidder :-
2 Address for correspondence :-
3 E-Mail ID :-
4 Phone / Mobile No. :-
5 Name of Beneficiary :-
6 Bank Account Number of :-
beneficiary
7 Name of Bank of beneficiary :-
8 Name of Bank, branch & :-
9 Type of account :-
10 Bank Code :-
11 RTGS Code :-
12 IFSC Code :-
EW- 270 PUR-F-006 RFQ-75883
Project Synopsis and Data
1) Location :- Gandhinagar Thermal power station
2) Purchaser :- GUJARAT STATE ELECTRICITY
CORPORATION LTD
3) Engineer :- Chief Engineer(Gen)
4) Site of Project :- Gandhinagar,Gujarat State
5) Nearest town :- Gandhinagar
6) Nearest Railway Station :- Gandhinagar Capital(Ahmedabad is
situated at a distance of about 30.00Km)
7) Nearest Port :-
8) Nearest Air Port :- Ahmedabad-20Km(Approx)
9) Access Road :-
10) Site Elevation from MSL :- RL 81.5 M(floor level)
11) Meteorological Data
Ambient Air temperature
1] Highest monthly mean of :- 350 C
daily Max. Temperature
2] Maximum dry bulb :- 450 C
Temperature ( In 0C)
3] Minimum dry bulb :- 8.60 C
Temperature ( In 0C)
Rainfall
1] Average annual rainfall :- 1000 to 1200mm
2] For 01 hour ( In mm) :- 75 to 100mm
3] For 24 hour ( In mm) :- 250mm
Wind velocity
1] Maximum wind velocity :-
(In m/sec)
2] Wind direction – N,NE & :-
3] For 24 hour ( In mm) :-
Relative Humidity
1] Annual mean humidity ( In :- 50 to 60%
2] Maximum humidity (In %) :- 98%
3] Minimum humidity (In %) :- 2%
4] Type of Atmosphere :- Dry
12) DESIGN DATA
Seismic Data :-
Zone :- Zone-III as per IS 1893-1975
Intensity :-
Ambient temperature :-
Other Data :-
EW- 270 PUR-F-006 RFQ-75883
SCOPE OF WORK AND SITE CONDITIONS
and other Misc. Civil Work of ESP at Gandhinagar TPS”.
The main scope of the work is “Providing and fixing New G.I Sheet in ESP 3 in place of
corroded sheet and other Misc. Civil Work of ESP at Gandhinagar TPS”. Under the scope
of this tender the agency has to carry out the subject work, various civil works
as per all items of Schedule B and as per detail technical specifications items.
The quantities taken under individual items are very tentative. However the
agency has to carry out the works as per the Company’s requirements.
The agency has to carry out the works as per item & specifications of the tender
by providing all materials of best quality and of standard manufactures as the
samples approved by EIC and providing best workmanship through expert
The agency has to carry out the works as per the priority & schedule given by
EIC time to time even in on or off working hours of the office. The agency will
take complete care and will not damage any other structure in premises of
The agency has to carry out all the works by taking all due cares of safety,
security norms, with all risks including scaffolding, strutting, shoring, etc up to
any height irrespective of quantum of the work.
Contractor has to make arrangement for workable site condition with the co
operation of departments of company and agencies, all necessary arrangement
to get work permit is to be made by contractor. Day to day cleaning is required
after completion of job. The removed materials and any other unwanted
materials are to be transported and taken away as instructed by E.I.C.
All safety measures shall be taken by the contractor with his own cost.
The scope of work to be carried out by the Contractor shall also include
Clearance of the sump, Disposal of debris etc,
The major works involvement generally mentioned as here under---
Demolition of brick work, stone masonary, Plaster, roof sheet including
ridges, hips, valleys, gutters etc., door, windows, ventilators etc.
Brick work using common fly ash building bricks in foundation and plinth
and above plinth level up to floor level.
Providing 15mm thick cement plaster
Providing corrugated G.I. Sheet of class-3 roofing fixed with galvanized iron J
or L Hook, Bolts and nuts 8mm diameter with bitumen and G.I. Limpet washer
or G.I. Limpet washer. Filled with white lead complete excluding the cost of
purlins, Rafters and Trusses (1) 0.80 mm thick sheet.
Providing ridges or hips 600 mm overall in plain G.I. Sheet class-3 fixed with
G.I.J. Or L Hooks and nuts 8mm dia. G.I. Limpet and bitumen washer complete
(1) 0.80 mm thick sheet
Providing and fixing 150mm wide 450mm over all semicircular /rectangular
shape in plain G.I sheet class-3 gutter with iron brackets 40mm x 3mm size
Bolts, Nuts, Washers etc. Including making necessary connection with rain
water pipes (i) 0.80mm thick sheet
EW- 270 PUR-F-006 RFQ-75883
White washing………
Providing & applying two coats of exterior premium emulsion paint of approved
brand and make as mentioned…….
Providing up to floor two level precast cement concrete jali or gril 1:2:4
Providing and applying two coats of synthetic enamel paint……
Steel work riveted in built up sections…….
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 270 PUR-F-006 RFQ-75883
Registration in VMS System
Additional Note: Vendor gets to register in VMS System through
vms.guvnl.com. For registration following documents are required and mail to
[email protected] and [email protected]. After registration vendor
have to upload the invoice in the VMS system for smooth functioning of
Documents required for Registration:
(1) PAN Copy
(2) GST Certificate Copy
(3) Email ID
(4) Full Name of Vendor
EW- 270 PUR-F-006 RFQ-75883
SPECIAL NOTE FOR PRE-QUALIFICATION
and other Misc. Civil Work of ESP at Gandhinagar TPS”.”
The tender documents are of two separate bids i.e. technical and price bids.
Bidder is requested to submit the technical bid with the following credentials
for post-qualification.
1. Bidder should produce evidence of having experience of successfully
completed of similar works as defined hereunder, carried out in Central &
State Government / Semi-Government / GSECL / GETCO / DGVCL /
MGVCL / UGVCL/PGVCL during the last seven years ending last day of
the month previous to the one in which tender is invited. Bidder should
submit self-attested copies of documentary evidence, preferably photo
copies of work completion certificate, certificate regarding works on hand
progressing satisfactorily along with certificate of amount of work done,
work order with Schedule-B, etc. from the respective department. The
amount of work completed works should be either of the following:-
a. Three similar completed works each costing not less than the amount
equal to Rs. 19,82,037.36.
b. Two similar completed works each costing not less than the amount
equal to Rs.
c. One similar completed works each costing not less than the amount
equal to Rs.
2. Similar work means Any civil work related to buildings
repair/construction/maintenance, works etc.
3. Experience certificate of work executed with private firm shall not be
accepted. Experience as a joint venture or sub-contractor is not allowed and
price bid of such bidders will be rejected.
4. EMD: To pay EMD in form of DD OR in form of B.G. given by bank
as described in the Annexure – I.
5. Tender Fee: The tender fee shall be accompanied in the form of
6. Separate employee’s Provident Fund code number towards
registration of firm with Regional P.F. Commissioner.
7. Last three year Audited annual accounts, Positive net worth
certificate, and average annual turnover certificate certified by
chartered accountants as per qualification requirement.
Financial qualification criteria:
EW- 270 PUR-F-006 RFQ-75883
1. The Average Annual Turnover of the bidder shall not be less than
Rs. Rs. 14.86 lakh during the preceding three (3) financial years as
one date of Techno-Commercial bid opening.
2. Net worth of bidder shall not be less than 100% of the bidder’s paid
up share capital as on the last day of the preceding financial year. In
case the Bidder meets the requirement of Net worth based on the
strength of its Subsidiary (ies) and/or Holding company and/or
Subsidiaries of its Holding Companies wherever applicable, the Net
worth of the Bidder and its Subsidiary (ies) and/or Holding company
and/or Subsidiary (ies) of the Holding Company, in combined manner
should not be less than 100% of their total paid up share capital.
However individually, their Net worth should not be less than 75% of
their respective paid share capitals.
Net worth in combined manner shall be calculated as follows:
Net worth (combined )= (x1+x2+X3)/(y1+y2+y3) X 100, where x1,x2, x3
are individual net worth which shall not be less than 75 % of the
respective paid up share capitals and y1, y2, y3 are individual paid up
share capitals.
3. In case the bidder is not able to furnish its audited financial
statements on stand-alone entity basis, the unaudited unconsolidated
financial statements of the bidder can be considered acceptable
provided the bidder further furnishes the following documents for
substantiation of its qualification.
Copies of the unaudited unconsolidated financial statements of the
bidder along with copies of the Audited consolidated financial
statements of its Holding Company.
A Certificate from the CEO/CFO of the Holding Company, stating
that the unaudited unconsolidated financial statements form part of
the Consolidated Annual Report of the company.
4. In cases where audited results for the last preceding financial year as
on the date of techno-commercial bid opening are not available, the
financial results certified by a practicing Chartered Accountant shall be
considered acceptable. In case, Bidder is not able to submit the
Certificate from practicing Chartered Accountant certifying its financial
parameters, the audited results of three consecutive financial years
proceeding the last financial year shall be considered for evaluating the
financial parameters. Further, a Certificate would be required from the
CEO/CFO, stating that the financial results of the Company are under
audit as on the date of Techno-commercial bid opening and the
Certificate from the practicing Chartered Accountant certifying the
financial parameters is not available.
The bidder must submit Average Annual Turnover and Net worth
Certificate in support of Financial QR, duly certified and verified for
authenticity from Independent Statutory Auditor of their company /
Practicing Charted Accountant/ C.A. Firms / TPIA (Third-Party
Inspection Agency ) empanelled / approved by GSECL along with copy of
EW- 270 PUR-F-006 RFQ-75883
Annual Audited Accounts of last three years.
8. Attested copy of relevant document duly signed and sealed on each and
every page shall be submitted.
9. Attach copy of GST Registration.
10. Details of orders for similar nature/jobs carried out along with
documentary Evidence, Performance Certificate and their organization set up
for such work executed in past there of indicating the Names of the
organizations, order no and date.
11. Bidder shall have to submit the PAN card No for Income Tax with documentary
12. Details of the partnership deed.
13. Details of Tools, tackles, equipments and personals available with firm relevant
to the job/subject matter.
14 Copy of the updated valid labor contract license from the appropriate authorities
and updated workman group insurance policy covering labor engaged.
15. The tenderer shall have to produce the document of last three years annual
account, i.e. profit & loss account and balance sheet, if the estimated cost of tender
is more than 50 lakhs along with technical bid.
16. Details of skilled/semi-skilled persons presently employed by the contractor
having sufficient knowledge of similar jobs.
For & On behalf of GSECL
CHIEF ENGINEER
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
GENERAL INSTRUCTIONS TO THE BIDDERS
1. SUBMISSIOIN OF TENDER
The tender should be uploaded/ submitted online on n-procure process.
Technical bid cover:- This cover shall contain all relevant attested qualifying
documents as prescribed in tender notice along with tender fee & EMD. Bidder shall
have submit Tender Fee and EMD cover only, All other require document to be upload
on online (n)procure process only
Note: - If attested copies of qualifying documents stated as prescribed in tender
notice are not found in on-line Technical bid, but same should be submitted by
mail during scrutiny will be treated as final to consider the bid for pre-
qualification. Any missing documents, if required will be asked from the bidder as
mentioned in this tender elsewhere. If party has not submitted tender in online is
liable to be ignored.
Technical Bid
“Please note that the Notarized / self-attested copies of original required
documents should be invariably uploaded in n-procure portal before due date and
time in pdf form (Scanned copy). This is mandatory. No physical documents are
required to be submitted except tender fee and EMD.
Price bid:-
The price bid shall have to be submitted online only. The percentage rates and price
shall be written both in words, and figures and the units in words. In case of any
ambiguity or mistakes, the unit rates and prices written in words shall be considered as
Offered rate shall include cost of all Materials, wastage of material , Labours for all
leads and lifts, Supervision, setting out works, Machinery and equipment with its
mobilization / demobilization, transportation charges, Clearing of the site both prior to
commencement and after completion of work. Consumables such as, but not limited to
petrol, oil, diesel, lubricants, drill bits, pipes, ropes etc. Construction facilities such as
scaffolding, tarpaulins, wind break, etc., Overheads / profits of Contractor for due
performance of the work under this contract.
Applicability of goods and service tax:-
1) The tenders shall be evaluated on firm price and cost with GST and cess as applicable
unless otherwise mentioned in the tender documents.
2) IF the supplier/contractor have opted for the composition scheme of GST, the same
must be clearly specified with valid declaration and certificate from department. In the
event of withdrawal/ cessation of the supplier from composition scheme during the
tenure of the contract, the rate(i. e. price) mentioned in the price bid shall be final and
any additional GST will have to be borne by the tenderer himself, In no case additional
amount towards GST or otherwise will be paid/reimbursed to supplier/contractor.
3) The bidder shall have to inform their GST no. of the registered place(s) where from the
bidder intends to supply the goods/services, meaning there by the bidder has to supply
the goods/services from the relevant declared/ registered place(s) of supply only.
4) The bidder shall not include GST in their quoted rates; but the bidder has to separately
indicate the GST rate, amount in the price bid schedule.
EW- 270 PUR-F-006 RFQ-75883
5) In-case Govt notification comes for change in GST , the same will be applicable.
6) Bidder should indicate GST no.( copy of GST registration to be enclosed) and PAN NO.
(copy of PAN to be enclosed) Tenders submitted without GSTIN No by the firms, the
offer will be rejected without entering into further correspondence.
Further information required, if any, can be had from the office of the Chief Engineer,
GSECL, GTPS. But it must be clearly noted that the tenders must be received
complete in every respect by the due date and time.
i. The bidder must clearly quote rates in figure as well as in words. In case of any
discrepancy, whatever written in words shall prevail.
ii. No deviation in terms & conditions, Schedule-B and technical specifications will be
entertained. Any ignorance for this shall not relieve the contractor from his
contractual liability arising as per tender documents and conditions contained in it.
iii. The bidders are required to quote only firm prices. No variation will be accepted on
price/ raw materials/ finished products or on any other cause.
iv. The bidders should note that the completion of above mentioned works in all respect
in accordance with the time limit given is very important and should be strictly
adhered to. The work is to be completed in time limit from the date of issue of written
order to commence the work by the Chief Engineer (Gen.), GSECL, Gandhinagar TPS.
v. The bids should be valid for a minimum period of 180 Days from the date of opening
of technical bid. During this period tenderer shall not be allowed to withdraw their
tender and if withdrawn, the Earnest Money Deposit submitted with the tender will be
forfeited.
vi. The works covered under these specification shall be carried-out and governed by
“Tender and contract for Works” booklet appended herewith except where conditions
specified in this specifications.
vii. The successful bidder shall have to enter in to an agreement for contract as per
G.S.E.C.L rules on a stamp paper of Rs.300/- and necessary stamp duty charge shall
be borne by the contractor/consultant.
viii. The complete specification comprises of the following.
Bill of Quantities (Schedule-B), instructions to the bidders, Tender specifications and
scope of work, Tender and contract for Works booklet, General Conditions,
Instructions to bidder & Technical specifications. All these sections are
complimentary to each other. The particulars and requirements contained herein shall
cover the execution of the works covered under these specifications.
ix. The tenderer must visit the site of works and see for him self the site conditions
regarding availability of approach road during all seasons and other matters affecting
the above works before submitting the tender.
x. The submission of tender by a contractor implies that he has read these instructions
the conditions of contract etc. and has himself aware of the scope and specifications of
the work to be done and of conditions and local conditions and other factors bearings
on the execution of the works. GSECL will not therefore after acceptance of
contractor's rate pay any extra charge for any other reason; in case the contractor is
found later on to have misjudged the site condition.
xi. GSECL’s authorized officers who accepts tender, shall have the right of rejecting all or
any of the tenders and will not be bound to accept the lowest offer nor to assign any
reason whatsoever for the rejection of any tender or all tenders.
xii. Bidders shall provide evidence of their continued eligibility to the satisfaction of the
xiii. Bidders shall not be listed under a declaration of ineligibility for corrupt or fraudulent
Practices issued by the Govt., the list of black listed Contractors announced by
GSECL (erstwhile GEB) Govt. of Gujarat or its Public Sector undertakings or the
contractors who are under stop dealing in GUVNL and /or their any subsidiary
company viz. GETCO/MGVCL/UGVCL/PGVCL/DGVCL.
xiv.The bid, and in case of a successful bid, the Form of Contract Agreement, shall be
signed with the name of Firm / company which will be legally binding on all
partners / parties.
xv.If the application is made by an individual, it shall be signed by the individual
above his full typed written name and current address.
xvi.If the application is made by a proprietary firm. It shall be signed by the proprietor
above his full typed written name and the full name of his firm with its current
EW- 270 PUR-F-006 RFQ-75883
xvii.If the application is made by a partnership firm, it shall be signed by all the
partners of the firm above their full type written names and current addresses or
alternatively by partner holding power of attorney for the firm in which case a
certified copy of the power of attorney shall accompany the application. A certified
copy of the partnership deed, full names and current addresses of all the partners
of the firm shall also accompany the application.
xviii. If the application is made by a limited company or a Corporation, it shall be
signed by the authorized person holding power of attorney for signing application in
which case a certified copy of the power of attorney shall accompany the
application. Such Limited company or Corporation may be required to furnish
satisfactory evidence of its existence before the pre-qualification evaluation. They
should also furnish Articles of Memorandum of Association. If the application is made
by group of companies, it shall be signed by the authorized person. The authority
letter shall be accompanied with the application.
1. SECURITY DEPOSIT
It should be mandatory to submit security deposit as per cl no.7 of Section C (i.e.
General condition of contract).
2. MAINTENANCE:
i] The contractor shall be responsible to make good and remedy at his own expense any
defect which may develop or may be noticed before the period mentioned hereunder
from the certified date of completion. The same shall be attended within 15 days of
receipt of the notice. In the case of failure on the part of the contractor, the Engineer-
in-charge may rectify or remove or re-execute the work at the risk & cost of the
contractor. The Engineer-in-charge shall be entitled to appropriate the whole or any
part of the amount of security deposit towards the expenses, if any, incurred by him in
rectification, removal or re-execution. The defects liability period shall be as under,
a) For all works costing up to Rs. 50,000 (amount put to tender), the period shall
be 03 months from the certified date of completion.
b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount
put to tender), the period shall be 06 months from the certified date of
completion OR one monsoon, whichever is later.
c) For major projects costing more than Rs. 01 crore, the period shall be 12 months
from the certified date of completion which should include one monsoon.
d) For building works, the period specified in (a), (b) shall be same except that time
period shall be 12 months instead of 06 months OR (c) shall be same as above except
that time period shall be 03 years OR elapse of 3 monsoon periods from certified date of
completion whichever is later.
e) For original building works the defect liability period will be 03 years OR elapse
of 03 monsoon periods following date of possession of building taken over by user
agency OR 04 years or elapse of 04 monsoon period following the certified date of
completion whichever is later.
For the purpose of deciding monsoon period, the 30th September may be treated as
the last date.
f) For painting work (irrespective of amount put to tender): 1 year.
ii] For Water Proofing works guarantee period shall be kept as 5 (five) years from
actual date of completion. Besides above 5 years Performance bank Guarantee
(PBG) equivalent to 10% amount of estimate cost OR Work Order cost whichever
is more shall be submitted by the contractor prior to release of final bill payment.
Subsequently, if during the year (from date of completion of the work) no leakage
is observed in treated area, out of above 10% PBG, 2% amount shall be released each
EW- 270 PUR-F-006 RFQ-75883
year to the contractor on his written request.
In case of any leakages during the year is observed contractor must attend the
same during dry atmosphere but not later than 6 Months from date of intimation &
subsequently 2% PBG can be released.
If contractor fails to attend the complaint, 2% PBG of respective year shall liable
to forfeit with written intimation to the contractor.
iii] Over and above 10% PBG, there shall be provision of 5% S.D. which shall be
released after 6 months from actual date of completion of work.
iv] For anti-termite treatment guarantee period shall be kept as 3 years, with PBG &
shall be released on completion of Guarantee period.
3. TIME LIMIT FOR WORK:
The scheduled time limit for the completion of work shall be 11 (Eleven)
Months calendar months from the date of issue of letter to commence the
work. However extension in time limit will be granted by GSECL for the
genuine reasons only as per terms of the contracts.
4. TERMS OF PAYMENTS:
Contractor shall be paid RA bill after observing GSECL’s general procedure and
submission of bill by the agency. Also, 75% payment shall be made immediately
within a week period on receipt of recorded bill by Account Section without
checking of detail bill and compliance of queries & statutory requirement.
However, remaining balance 25% amount shall be released only after through
checking of detail bill and compliance of various quarries, statutory compliance
etc. The above payment term is applicable to all the bills of general civil works &
ARC/BRC works, provided the bills are recorded regularly and submitted to
Account Section within Ninety [90] days. If the contractor fails to submit the
bills regularly in such a way so that the same cannot be recorded and submitted
to account section within Sixty [60] days, ad-hoc payment as stated above, may
not be released and payment will be released as per GSECL’s general procedure.
The period of Sixty [60] days shall be considered from the date of receipt of last
R.A. Bill by Account Section.
5. METHOD OF PAYMENT:
a. The payment for the work done will be made by running bills every
month after taking joint measurement within 30 days.
b. Final bill will be paid within reasonable time after settlement of material
account by you and after recording of joint measurement.
6. “All bidders shall submit the details/documents in support of Technical
Qualification Requirements duly certified and verified for authenticity from
Specified Third-Party Inspection Agency (TPIA) or Statutory Auditor of
their Company or Practicing CA/CA Firm along with a certificate regarding
verification of a
7. uthenticity of documents as per the format placed at Appendix 1. All the
documents submitted by the bidder in support of meeting Technical QR
only shall be digitally signed by the Specified Third-Party Inspection Agency
(TPIA) or Statutory Auditor of their Company or Practicing CA/CA Firm.
In case documents are certified & verified for authenticity through TPIA, the
verification and certification of authenticity of documents is acceptable from
any of the following TPI As:
1. M/s Competent Inspectorate and Consultants Pvt. Ltd, Hyderabad,
2. M/s Gulf Lloyds Industrial Service India Pvt. Ltd.-Ahmedabad.
EW- 270 PUR-F-006 RFQ-75883
3. M/s International Certifications Services.
4. M/s Intertek India Pvt. Ltd.
5. M/s SGS India Pvt. Ltd.
6. M/s Moody International (India) Pvt. Ltd.
7. M/s TUV SUD South Asia (P) Ltd.
8. M/s TUV Rheinland (India) Pvt Ltd.
9. M/s Bureau Veritas (india) Pvt. Ltd.
10. Hertz Inspection & services Pvt. Ltd.
11. IRCLASS Systems and Solutions Pvt. Ltd.
Verification for authenticity shall not be applicable in following cases.
1. Bidders having proven track record or regular suppliers/contractors (i.e.
OEM/OES/PSUS)
2. Past order copies of GSECL as these documents can be verified
internally.
The Bidder shall be responsible to get their documents/ credentials verified &
certified by the Specified Third- Party Inspection Agency (TPIA) or Statutory
Auditor of their Company or Practicing CA/CA Firm in support of Technical
QR. All the costs pertaining to third party verification and certification
(including those by statutory auditors) shall be borne by the Bidder. GSECL
shall have no liability (financial or otherwise) towards the same and shall not
be liable for any claim/ dispute between the bidder and the Specified Third-
Party Inspection Agency (TPIA) or Statutory Auditor of their Company or
Practicing CA/CA Firm.”
The following website may be referred for contact details of above TPIAs:
http://nabcb.qci.org.in//accreditation/reg_bod_inspection_bodies.php
Annexure-1
Undertaking from Third Party Inspection Agency/Statutory Auditor or Practicing
CA/CA Firm
(On letter head digitally signed by a person duly authorized to Sign on behalf of the
Ref: Date:
Power Station ……………….
Subject: Authentication of veracity of documents submitted by M/s …… in support of
Meeting the Qualifying Requirements
Ref: Tender no. …………………..
Name of the Package/ Tender: ………………………………………
M/s. ……………… (here in after called Bidder) having Registered office at
…………………… intend to participate in above referred tender of GSECL.
The tender condition stipulates that the bidder shall submit supporting Documents
pertaining to Qualifying Requirement duly verified and certified by Third-Party
EW- 270 PUR-F-006 RFQ-75883
Inspection Agency (TPIA) or Statutory Auditor of their Company or Practicing CA/CA
Firm as per the list mentioned in the bidding documents.
In this regard, it is hereby confirmed that we have examined the following documents,
which are also attached with this letter. The same has been verified from the Original
Documents and / or Client for authenticity.
We hereby confirm that the following documents are found to be genuine and
authentic.
1. Doc ref. no. ……….. Dated …….. (Name of Documents)
2. Doc ref. no. ……….. Dated …….. (Name of Documents)
All the aforesaid documents have been digitally signed by us as a certificate of
authenticity.
We further confirm that we neither have any vested interest in aforesaid tender nor
have any conflict of interest in respect of above tender.
This certificate is issued at the request of M/s ………………. (Bidder) for the purpose of
participating in the subject tender/s
Thanking you,
1. ASSIGNMENT:
The rights and liabilities of the contractor shall not be assigned or transferred by them
without the consent in writing of the GSECL to any other person, firm or
organization.
2. The successful Bidder, on receipt of letter of intent will submit within a week's
time his planning / programme of works, for scrutiny of the GSECL in a Bar Chart
format, clearly indicating GSECL's inputs also. Contractor will plan his works such
that simultaneous work should progress in such a way that entire job is completed in
scheduled time limit on all the fronts released by GSECL.
3. The successful bidder will have to depute his authorized representative to attend
progress review meetings to be held at GSECL, Gandhinagar TPS without any extra
4. The Contractor will be responsible for complying with all rules and regulations
and labour laws applicable to him and the GSECL will not be responsible for any
lapses committed by them. If there is any claim from any Government authority
pertaining to the contract, the same amount will be deducted from the Contractor's
5. The time limit for completion of work is stipulated as in the tender will be adhered
6. The Contractor's rates should be firm and no variation clause is to be quoted by
the Contractor and GSECL will not accept the same, during contractual period
including extended time limit if any.
7. BIDDER TO STUDY, ANALYSE & CONSIDER:
a) The information given in this specification is in good faith and meant to
serve as a guide to the Bidder. It is, therefore, imperative that Bidder shall obtain and
examine for himself all the data, information and particulars required for the
satisfactory execution of the work under this tender. The submission of a bid by
Bidder implies that he has fully read the specifications, bid drawings, instruction to
the bidder along with Contract Document and Conditions of Contract, applicable
labour laws, safety norms etc., and has made himself aware of the scope and the
specifications for the work to be performed and local conditions and other features
which have a bearing on the cost and execution of the work. This specification is
intended as a general description of quality envisaged for materials and workmanship
EW- 270 PUR-F-006 RFQ-75883
and of the finished work. It is not intended to cover minute details. The work shall be
executed in accordance with the best modern practice and to the complete satisfaction
of the Purchaser. Special techniques approved by the Purchaser shall be used if and
where found necessary. This specification shall have precedence if anything contrary
to this is stated elsewhere in the contract documents. The Purchaser’s decision shall
be final and binding on the contractor on any issue arising out of such discrepancies.
b) Inspection of site by bidder:
Before submission of his bid, Bidder shall inspect the site, examine and obtain all
information required and satisfy himself regarding matters such as:
weather characteristics,
Location of site and access, right of way, means of communication & mode of
Transport to site,
The type and number of equipment and facilities required
The quantity of various items of the work.
The availability and rates of material.
Labours condition.
Local working conditions, obstructions and hindrances that may arise etc.
Power house, which is under running conditions.
Required GSECL’s security checks.
All materials brought to site only after making entries in security register at
Control gate
c) These factors are likely to affect the satisfactory completion of work and or cost
thereof. The submission of a bid by the Bidder will be construed as evidence that
such an examination was made and any later claims/ disputes in regard to rates
quoted shall not be entertained or considered by the GSECL.
d) The site visit shall be done by the bidder on his own responsibility and all
liabilities including cash, arising out of the site visit shall be at the bidder’s
e) Contractor’s scope of work shall also include making all necessary arrangements
for access to work sites, stores and site offices etc. from the nearest approach
road to facilitate transportation of man power, machinery and equipment duly
considering the existing site conditions. No extra claims / costs will be
entertained by GSECL.
f) The bidder shall carefully study the work to be carried out & consider all the
factors & shall take into account &consider all the factors such as lead, lift
haulage of materials, sequence of construction, etc. & shall allow for all such
information / data in the rates quoted.
g) The GSECL will not pay any extra charges or rate for any reason in case the
contractor claims, after acceptance of contract to have misjudged the site
condition. Ignorance of the intents and contents of the specification document
and site conditions shall not be accepted by the Owner as basis for any claims
for compensation.
h) BIDDER shall inspect the site, examine and obtain all information required and
satisfy himself regarding matters such as sub-surface conditions, water records,
access to site, communication, transport, right of way, the type and number of
equipment and facilities required for the satisfactory completion of work, the
quantity of various items of the work, the availability and rates of material, local
working conditions, uncertainties of weather, obstructions and hindrances that
may arise etc. which may affect the work or cost thereof, before submission of
his bid. Ignorance of site conditions shall not be accepted by the ENGINEER IN
CHARGE as basis for any claim for compensation.
i) The rates quoted by BIDDER shall be based on his own knowledge and judgment
of the conditions and hazards involved and shall not be based on any
representations of the Engineer in Charge. No claim on this account shall be
admitted by the GSECL.
j) The bidders shall submit on online in n-procure with their offer without any
deviations in general terms and conditions of the contract or in technical
specifications.
k) Tenders received after the time and date specified in the tender notice will not be
accepted. Once the offer is submitted by bidder before due date of submission,
EW- 270 PUR-F-006 RFQ-75883
the bidder shall not be allowed to submit revised/ additional/ modified offer even
before due date and time of submission of tender. However, if the date of issue
and/or submission of tender are extended by the Corporation due to any reason,
the bidder may submit if their wishes the revised/additional/modified offer
before extended due date and time of submission.
l) The Corporation reserves the right to accept any tender irrespective of whether it
is lowest or not or to reject all the tenders without assigning any reasons thereof.
Tenders deferring from the technical specifications or the method of bidding in a
radical manner may also be rejected.
m) The bidder shall be presumed to have carefully examined the drawings,
conditions & specifications of work & to have fully acquainted themselves with
all details of the site conditions, locations, materials, geological & weather
characteristics, labour conditions & in general all the necessary information and
data etc. pertaining to and need for the work.
n) This specification is intended as a general description of quality envisaged for
materials and workmanship and of the finished work. It is not intended to cover
minute details. The work shall be executed in accordance with the best modern
practice and to the complete satisfaction of the Purchaser. Special techniques
approved by the Purchaser shall be used if and where found necessary. This
specification shall have precedence if anything contrary to this is stated
elsewhere in the contract documents. The Purchaser’s decision shall be final and
binding on the contractor on any issue arising out of such discrepancies.
o) Each bidder shall also submit a 'Declaration' to the effect that the tenderer is an
engineering construction firm or an association of firm or firm which has
successfully carried out large works of this nature and has adequate
organization and experienced personnel to handle this type and magnitude of
work. Information should also be given regarding the constitution of the firm; it’s
authorized, subscribed & paid up capital, the date & place of registration, the
place of business, the names of the directors and other relevant information.
p) It is the intent of the ENGINEER IN CHARGE to incorporate these specification
documents in the final ‘Contract’. BIDDERS are required to review these
documents and clearly state in their proposals their acceptance of the same.
q) Each page of the bid document including the bid drawings shall be signed,
stamped and dated in ink by the BIDDER as a token of having examined the
same. Any correction in price and the rates entered in the Schedule of Price
shall also be signed and dated by the BIDDER in ink, before submitting the bid.
Non-compliance with this condition will make the bid liable for rejection.
r) All safety measures as required to be adopted as per the Statutory Regulations
and the Safety Rules of the Plant shall be strictly followed by the Contractor
during the execution of the Contract. The Contractor shall set up a suitable
safety organization of his own in this regard.
s) In connection with the execution of the Contract, the Contractor shall comply
with all applicable statutory Rules & Regulations including employment of
labours at site.
t) The Contractor shall carry out any and all such works, as may be required, for
civil work to be completed in all respect as per the Contract Specification.
u) If the GSECL Engineer-in-Charge is not satisfied with the progress of work at
site, he shall direct the Contractor to depute more numbers of supervisory
personnel/workers to meet the completion schedules as per the Contract. Upon
receiving such direction, Contractor shall deploy additional personnel within
days without any extra cost.
v) The GSECL may during the progress of work, order the removal of part or whole
of the work executed, found not in accordance with the specifications/
instructions. No extra claims shall be entertained for re-executing or altering of
such work.
8. SAFETY MEASURES:
The contractor shall ensure the safety of workers, material and structure
including existing structures during execution of the contract. Safety measures
shall be followed during operations of equipments/machinery being used. No
separate payment shall be made for the safety measures and the quoted rates
shall include the cost for all safety measures.
EW- 270 PUR-F-006 RFQ-75883
9. COMPLETENESS:
Any technical services as set forth here in above and which might not have been
specifically mentioned in this Contract relating to the work or in the
specifications and which are not expressly excluded therefore but which are
necessary for the performance in accordance with the specifications as an
integral part of the painting and misc. Civil works shall be rendered by the
Contractor without any extra cost.
10. TOTAL RESPONSIBILITY
The Contractor shall be solely responsible for the entire technical works /
services irrespective of works / services have been made /rendered by him.
11. PAYMENT TO THE LABOURES:
(a) Contractor has to pay the CPF as well as salary to his skilled/unskilled
manpower by cheque A/c payee only, as per minimum wages & prevailing
applicable rules on or before 7th day of next month.
(b) Contractor has to produce challan of PF with list of employees.
(c) Contractor shall have to make payment to his labours in presence of Personal
Officer (Estt.) GSECL, Gandhinagar TPS.
12. CONTRACT AGGREMENT ON ACCEPTANCE:
The successful contractor will have to sign an agreement as per the Gujarat
State Electricity Corporation Ltd.'s rules on stamped paper and the necessary
stamp duty charges shall be borne by the contractor.
On acceptance of the tender the name (s) of the accredited representative (s) of
the tenderer who would be responsible for taking instructions from the
Engineers of the GSECL shall be communicated to Chief Engineer (Gen.)
Gandhinagar Power Station, Gujarat State Electricity Corporation Limited.
13. Unsatisfactory progress of the work:
If the work is found not progressing as per the requirement or found not
satisfactory then GSECL will take such action to get the work done through the
other agency at agency’s risk and cost with 15% supervision charges and same
will be recovered from agency.
14. The EMD will be returned promptly to the unsuccessful bidder except that of L1,
L2 & L3 till the successful contractor pays the Security Deposit as mentioned
in tender document or after the expiry of the validity of the offer, whichever is
The EMD will be returned to the successful tenderer after he furnishes the
Security Deposit for the tender work. If he fails to furnish the SD, his EMD shall
be forfeited and the tenderer will not be allowed to participate in the tenders
invited by this office for a period of ONE Year in respective Power Station.
The EMD in form of Bank Guarantee shall be valid for Ten Months from the
date of submission of the tender.
15. Effect and validity of Bid: The submission of bid with these documents and
specification shall constitute an agreement that bidder shall have no cause of action
or claim against the GSECL for rejection of his bid. The GSECL shall always be at
liberty to reject or accept, split any bid or bids at its sole discretion and any action
will not be called into question and the bidder shall have no claim in that regards
against the GSECL.
16. Stop Deal / Banned for business dealing / Blacklisting :-
Has submitted fake, false or forged documents/certificates
Has revised/ withdrawn price bid after opening of Techno-commercial bid, until
and unless it is sought for,
Has tempered with the stipulated tendering procedure.
Has refused to accept Letter of Acceptance / Purchase order / Work Order after
the same is issued by the company within the validity period and as per agreed
terms and conditions,
Has committed breach of contract or has failed to perform a contract or has
abandoned the contract,
Has failed to provide suitable expertise for the work as per pre-scheduled
EW- 270 PUR-F-006 RFQ-75883
Has failed to submit all the necessary tests reports / documents within time
scheduled / as per company’s time limit, as mentioned in the LOA, if the Letter
of Acceptance (LOA) is placed subject to submission of type reports /
documents to the firm.
Has indulged in construction and erection of defective works.
Has supplied inferior quality / defective materials and refused to replace with
stipulated time frame, as specified by the company,
Has substituted materials in lieu of materials supplied by the company or has
not returned or has short returned or has unauthorisely disposed of materials
/ documents / drawings / tools or plants or equipment supplied by the
Has involved in malpractices such as bribery, corruption, fraud, canvassing
and pilferage,
Has unauthorisely obtained official company information or copies of
documents, in relation to the Tender / Contract.
Has failed to follow the stipulated mode of communication, if specified by the
tendering authority / Purchaser.
Has parted with, leaked or provided confidential / proprietary information of
the company given to the firm only for its use (in discharge of its obligations
against an order) to any third party without prior consent of the Company,
Any other ground for which in the opinion of the Company makes it
undesirable to deal with the Firm
In case the state Government directs the Company to place a firm in stop
dealing / banned for business dealing / blacklisting.
Conflict of Interest among Bidders / Agents
A bidder shall not have conflict of interest with other bidders for particular quoted
item. Such conflict of interest can lead to anti-competitive practices to the detriment
of Procuring Entity's interests. The bidder found to have a conflict of interest shall be
disqualified. A bidder may be considered to have a conflict of interest with one or
more parties in this bidding process for particular quoted item, if:
a) They have proprietor/partner(s)/Director(s)in common; or
b) They receive or have received any direct or indirect
subsidy/financial stake from any of them; or
c) They have the same legal representative/agent for purposes of this bid; or
d) they have relationship with each other, directly or through common third
parties, that puts them in a position to have access to information about or
influence on the bid of another bidder, or
e) bidder participates in more than one bid in this bidding process. Participation
by a bidder in more than one Bid will result in the disqualification of all bids
in which the parties are involved. However, this does not limit the inclusion
of the components/ sub-assembly/ assemblies from one bidding
manufacturer in more than one bid.
f) In cases of agents quoting in offshore procurements, on behalf of their
principal manufacturers, one agent cannot represent two manufacturers or
quote on their behalf in a particular tender enquiry. One manufacturer can
also authorise only one agent/ dealer. There can be only one bid from the
following:
1. The principal manufacturer directly or through one Indian agent on his
behalf; and
2. Indian/foreign agent on behalf of onIy one principal.
g) A Bidder or any of its affiliates participated as a consultant in the preparation
EW- 270 PUR-F-006 RFQ-75883
of the design or technical specifications of the contract that is the subject of
h) in case of a holding company having more than one independently
manufacturing units, or more than one unit having common business
ownership/ management, only one unit should quote. Similar restrictions
would apply to closely related sister companies. Bidders must proactively
declare such sister/common business/ management units in same/ similar
line of business.
i) Bidder shall not act in contravention/violation to the provisions of
competition act, as amended from time to time.
Every bidder should, at the time of submission of bid, give a declaration, that
bidder shall not have conflict of interest with other bidders for particular quoted
item, as above.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
SECTION-C:
GENERAL CONDITIONS OF CONTRACT
EW- 270 PUR-F-006 RFQ-75883
GENERAL CONDITIONS OF CONTRACT
1. DEFINITIONS :
(a) The Contract means the documents forming the tender and acceptance
thereof, together with the documents referred to therein or individual work
order in the case of term contract, including these conditions, schedules
and/or additional conditions attached to the form of tender or individual
works, order, rate schedule, the specifications and the drawings and all these
documents, as applicable, taken together shall be deemed to form the
(b) The “Tender Document” means the form of tender, the applicable schedules
and/or additional conditions and the specifications and/or drawing as issued
to the contractors for the purpose of preparing tender.
(c) The expression “Works” or “Work” when used in the condition of contract
shall, unless there be something in the subject or context repugnant to such
construction means, the works or the work contracted to be executed under or
in virtue of the contract whether original or altered.
(d) The “Contractor” means the individual or firm or Corporation, whether
incorporated or not, undertaking the words and shall include his or its legal
personal representatives, successors and permitted assignees.
(e) “Corporation” means The Gujarat State Electricity Corporation Ltd. and the
“Accepting Officer” means the Officer who is authorized to sign and signs the
contract on behalf of the “Corporation”.
(f) The letter “EE” means Executive Engineer who in the case of measurement
and lump sum contract, direct the contract and the letters “SE” means
Superintending Engineer and “GM” means General Manager who administers
and in the case of the term contracts, directs the contract.
(g) The “Engineer-in-charge” means all officers of the Corporation appointed by
the General Manager to supervise the works or part of the works.
(h) “Approved” and “Directed” means the approval or direction of the Chief
Engineer (Gen), Gandhinagar TPS to Superintending Engineer or the person
deputed by him for the particular purpose.
(i) “BS.” means “British Standards” as issued by the British Standards
Institution. “A.S.” means the “American Standards” as issued by the American
Standards Institution, and “I.S.” means the “Indian Standards” as issued by
the Indian Standards Institution. Wherever the above-mentioned
abbreviations are referred to, in the specifications and/or work orders, they
mean the addition with all amendments current at the date of issue of tender
document of work orders.
(j) In the case of measurement and terms of contract “Specifications” mean those
contained in Gujarat State Electricity Corporation Ltd. scheduled together
with any amendments etc. embodied in the tender documents. “Drawing”
refers to those incorporating the tender documents and/or any work orders
referred therein.
(k) The “Contract Sum” means the sum accepted or the sum calculated in
accordance with the prices accepted in the tender and/or the contract rate as
payable to the contractor for the full and entire executing and completion of
(l) “The date for completion” is the date or dates of completion of the work or any
part of the works set out or ascertained in accordance with the individual
work orders and the tender documents or any subsequent agreed
amendments thereto.
2. CONTRACTOR TO INFORM HIMSELF FULLY:
A. Notwithstanding anything contained to the contrary in the specifications or
tenders in subsequent exchange of correspondence, the conditions of contract
shall be binding on the Contractor and any change or variation expressed or
implied, however made in the said conditions, shall not be valid or operative
EW- 270 PUR-F-006 RFQ-75883
unless expressly sanctioned by the Corporation. The Contractor shall be
deemed to have fully informed himself and to have special knowledge of the
provisions of the conditions of the Contract herein contained.
B. The contractor shall be deemed to have carefully examined the work and site
conditions, the general conditions, the special conditions, specifications,
schedules and drawing and shall be deemed to have visited the site of the
works and to have fully informed himself regarding the local conditions.
C. If there shall have any doubt as to the meaning of any portion of these
general conditions or special conditions of the scope of work of the
specifications or any other matter concerning the contract, he shall in good
time before submitting his tender, send for the particulars thereof and submit
them to the Engineer-in-charge in writing in order that such doubt may be
3. CONTRACT DRAWING AND SPECIFICATIONS:
The contractor will be entitled to receive one set of agreement along with one
certified copy of accepted tender.
The drawings which form part of these specifications show the work to be done
in as much detail as is possible at the present stage. They will be
supplemented by such additional detailed drawings as may be necessary as
the work progresses. The contractor shall perform the work on these features
and in accordance with these additional or revised drawings as the case may
be and at the applicable rates as per the contract.
The contractor shall check all drawings carefully and shall bring to the notice
to the Engineer-in-charge immediately of any errors or omissions discovered.
The contractor shall not take advantages of errors or omissions of any kind in
the drawings supplied.
4. INPUTS BY GSECL:
The electric power supply and connection for construction / work purpose shall
be given at one mutually agreed point at work site free of cost by the GSECL.
Further extension for construction site as well as bore well site for using
construction water will have to be carried out by the contractor as per
requirement at their cost. The necessary electric charges will be paid by the
contractor as per rates prevailing from time to time in the respective DISCOM.
1. If there are any surplus quarters available after meeting the requirement of
GSECL's staff, then GSECL will consider allotment of quarters on rent as per
GSECL's rule.
2. The contractor will have to make their own arrangement of water for
construction work as well as for their labourers at his own cost. If
possible, water for construction purpose only at one point as decided by
EIC and recovery for water charges shall be affected at the 2 % of the
item of which water is used or by quantity measured by meter reading of
water meter installed by contractor, rate of water supply will be charged
at prevailing purchase rates of GSECL, for water supplied by GSECL is
used as certified by EIC. In case of agency is installing bore well and
pumps at his cost, after completion of work agency will hand over the
bore well in good condition with pumps to the GSECL.
5. DATA TO BE FURNISHED BY CONTRACTOR:
The contractor shall submit to the Executive Engineer for approval within one
week of the date of contract, a layout plan of construction plant and
equipment for the execution of work which the contractor proposes to
adopt at site.
Prior to commencement of work, the contractor shall submit to the Executive
Engineer for approval, plans in triplicate showing the location of Major
plant shop and storage buildings, storage yards, offices, contractor's power
house including its services and housing facilities which he proposes to put
up at site and also indicate the programme of the work.
The successful bidder on receipt of letter of intent will submit within a week's
time his planning/programme of works for scrutiny of GSECL in a PERT/Bar
chart format, clearly indicating GSECL inputs also.
EW- 270 PUR-F-006 RFQ-75883
Contractor will plan his works such that on all the fronts released by GSECL,
simultaneous work should progress in such a way that entire job is
completed in scheduled time limit.
No change in the approved layout shall be carried out without specific written
approval of the Executive Engineer.
6. ERRORS, OMISSIONS AND DISCREPANCIES:
In all cases of errors, omissions, doubts or discrepancies in the dimensions,
or discrepancies in the drawings and items of work in specification, reference
shall be made to the Executive Engineer whose elucidation and elaboration
shall be considered as authoritative. The contractor shall be held responsible
for any error that may occur in the work thorough lack of such reference and
precautions.
7. SECURITY DEPOSIT:
SECURITY DEPOSIT: In tender process for L1 bidder (lowest bidder)
security deposit will be charged as per table below:
Category of the Unit Security Deposit
Works up to Rs. 5 Works More than
Lakh Rs. 5 Lakh
Enterprise or Exempted 3% of order value
Organization which are
exempted from paying
Tender Fee & EMD
For all other 5% of order value 5% of order value
Enterprises
Note: Security Deposit will be collected from the successful tenderer at the
rates mentioned above. This may be recovered by deduction through running
bills of the contractors and / or by treating the Earnest Money Deposit (Bid
Security) paid at the time of submission of the tender.
After issue of Work order and Date of commencement, if successful bidder failed to
start the work then, RPAD notice will be issued to the successful bidder mentioning
that on failing to start the work within next 07 days from the date of issue of RPAD
Notice the EMD will be forfeited and he will not be allowed to participate in the tenders
invited from Gandhinagar TPS office for the period of One year.
The security deposit of the contract value shall be released on finalization of final bill /
successful completion of the work.
All damages, costs, charges, expenses and other sums which may be or may become
due or payable by the contractor to the Corporation under the terms of the contract,
may be deducted from the cash in the proceeds of sale of the securities/bank guarantee
so deposited (which the officer or person to whom the same may be endorsed as
aforesaid is hereby authorized to sell/to encase for that purpose) or from the interest of
any such securities or from any sums due or which may become due to the contractor
by the Corporation or from the whole or the balance unpaid as aforesaid of the encase
securities so deposited being repaid or transferred and returned as the case may be, to
the contractor on finalization of final bill OR after 06 (six) months of successful
completion of the work, whichever later OR on furnishing of the Performance Bond
amounting to 5% of contract value against the defect liability period as mentioned in
this document elsewhere.
If entire security deposit is paid in approved form of Bank Guarantee should be remain
valid during the contractual period and such bank Guarantee should not be reduced on
the basis of the work actually done.
8. USE OF LAND:
EW- 270 PUR-F-006 RFQ-75883
The land required for office, godowns and for labour camp if not available with GSECL,
then the contractor has to arrange the same at his cost. GSECL will give the land only if
the spare land is available with the following conditions.
The contractor shall be permitted to use for the bonafide purpose of execution of this
contract free of cost. The contractor shall be permitted to use for the bonafide purpose
of execution of this contract free of cost.
1. Site required for the construction of the work.
2. Required approach road. The contractor shall make their own arrangements for
the necessary approach, road, for transport of their materials and be responsible for the
compensation on account of damage to crop etc. and shall till completion of work.
3. He will be charged the rent at the annual rate of rupees one hundred per every
acre or part thereof, for the construction of temporary hutments and his store yard.
However area required for such purpose may be clearly indicated in this offer.
All areas of operation, including those for his staff and labour colonies handed
over to the contractor shall be cleared and handed over back in good condition to the
Engineer except areas under works as per this contract or those for which specific
approval has been obtained from the Engineer. The contractor shall make good to the
satisfaction of the Engineer any damage or alternation made to areas which he has to
hand over back or to other property land handed over to him for purpose of this work.
Temporary structures may be erected by the contractor for storage sheds,
offices, residence etc. for noncommercial use on the land, handed over to him at his
own expense and with the permission of the Engineer. These structures shall comply
with the regulation that may be in force and/or specified by the Engineer with regard,
thereto. In any circumstances for constructing temporary structures for contractor's
use, GSECL's free supply materials shall not be used. If it is found that GSECL's free
supply materials are used for other than approved project drawings work, same will be
recovered at
penalized rate.
The contractor shall preserve all existing vegetation such as trees on or adjacent
to the sites which do not interfere with the construction as determined by the
The contractors shall take all possible precautions in felling trees
authorized for removal to avoid any unnecessary damage to vegetation
and trees not to be felled and to structures under construction, or to
workmen, and shall be responsible for any damage if it occurs in such
operations
All produce from cutting of trees; grass etc. shall be the property of
GSECL and shall be stocked at the place specified by the Engineer. No
claim shall be made for such cutting and stacking of trees or grass etc. by
the contractor
The contractors shall not unnecessarily or for use as fuel, cut any trees
brush wood, grass or other vegetation nor shall set fire there to without the
written permission of the Engineer. When such permission is given, the
contractor shall take necessary measures to prevent damage or to prevent
fire spreading to surrounding property, and shall be responsible for any
such damage, if cause.
The land shall as herein before mentioned be handed back to Engineer in
Charge immediately after the completion of the work under this contract.
Also no land shall be held by the contractor longer than the Engineer shall
deem necessary and the contractor shall, on due notice by the Engineer,
vacate and return the land which the Engineer may certify as no longer
required by the contractor for purpose of the work.
9. START OF WORK:
The contractor shall not enter upon or commence any portion of work except
with the written authority or instructions of the Executive Engineer or his
subordinate in charge of the work, failing such the contractor shall have no
claim to ask for measurement or payment for work and shall be responsible
for any claims or damages that may arise due to such unauthorized
commencement or entry.
10. COMPENSATION FOR THE DELAY:
EW- 270 PUR-F-006 RFQ-75883
The time allowed for carrying out the work as entered in the tender shall be
strictly observed by the contractor and shall be reckoned from the date on
which the order to commence work is given to the contractor. The work shall
throughout the stipulated period of contract be proceeded with all due
diligence (time being deemed to be the essence of contract) and for delay, the
contractor shall pay compensation, an amount equal to ½ (half) percent per
one week for the contract amount or part thereof, including taxes & duties (
i.e. End cost of contract amount including taxes & duties) and maximum up
to 10 % of the order value, including taxes & duties ( i.e. End cost of contract
amount including taxes & duties) or such smaller amount as per the decision
of the Competent Authority of the GSECL The penalty will be invariably
deducted from the bills of the contractor and no refund will be given unless
the competent authority approves the reduction. The reasons for delay,
attributable to GSECL as well as to party will be brought out clearly while
putting the proposal for waiver/reduction in penalty.
11. ACTION WHEN WHOLE OF SECURITY DEPOSIT IS FORFEITED:
In any case in which under any clause or clauses of this contract the
contractor shall have tendered himself to pay compensation amounting to
the whole of his security deposit (whether paid one sum) or in the case of
abandonment for the work owing to serious illness or death of the contractor
or any other cause, the Executive Engineer on behalf of the Corporation,
shall have powers to adopt (a) below and any of the following courses under
(b) and (c) as he may deem best suited to the interest of the Corporation.
(a) To rescind the contract (for which rescission notice of 10 days) in writing to
the contractor under the hand of the Executive Engineer shall be conclusive
evidence and in that case the security deposit of the contractor shall stand
forfeited and absolutely at the disposal of the Corporation. To employ labour
paid by the Corporation, to supply materials, to carry out the works or any
part of the work debiting the contractor with the cost of the labour and the
price of the materials (as to the correctness of which cost and price, the
certificate of the Executive Engineer shall be final and conclusive against the
contractor) and crediting him with value of the work done in all respects in
the same manner and at the same rates as if it had been carried out by the
Contractor under the terms of this contract and in that case the certificate of
the Executive Engineer as to the value of the work shall be final and
conclusive against the contractor.
(b) To order that the work of the contractor be measured up and to take such
part thereof, as shall be unexecuted, out of his hands and to give it to
another contractor to complete, in which case, any expenses, which may be
incurred in excess of the sum, which would have been paid to the original
contractor, if the whole work would have been executed by him (as to the
amount of which excess expenses, the certificate in writing of the Engineer-
in-charge shall be final, conclusive and shall be borne and shall be paid by
the original contractors and shall be deducted from any money due to him by
the Corporation under the contract or otherwise from his security deposit of
his proceeds sale thereof or a sufficient part thereof.
(c) In the event of the above courses being adopted by the Executive Engineer,
the contractor shall have no claim to compensation for any loss sustained by
him by reason of his having purchased or procured any materials or entered
into any engagements or made any advances on account of or with a view to
the execution of the work or the performance of the contract. And in case the
contract shall be rescinded under the provision aforesaid, the contractor shall
not be entitled to recovery or be paid any sum for any works thereof actually
performed by him under this contract unless and until the Executive
Engineer shall have certified in writing the performance of such work and the
amount payable to him in respect thereof and he only be entitled to be paid
the amount so certified.
12. NOTICE UNDER UNSATISFACTORY PROGRESS:
If the progress of a particular portion of the work is unsatisfactory, and also
if as per the opinion/observation of the Executive Engineer (whose decision
shall be final) in charge that the general progress of work is not satisfactory,
EW- 270 PUR-F-006 RFQ-75883
then Executive Engineer in charge shall be entitled to take action under
clause 11 (c) after giving the contractor ten days’ notice in writing and the
contractor will have no claim for compensation for any loss sustained by him
owing to such action.
13. ACTION IN THE CASE OF DEFAULT BY THE CONTRACTOR :
In any case in which any of the powers conferred upon the Executive
Engineer by Clauses 11 and 12 hereof shall have exercisable and the same
shall not have been exercised, the non-exercised thereof shall not constitute
a waiver of any of the conditions hereof and such powers shall not
withstanding be exercisable in any further case of default by the contractor
of which, by any clauses hereof, he is declared liable to pay compensation
amounting to the whole of his security deposit and liability of the contractor
for past and future compensation shall remain unaffected in the event of the
Executive Engineer taking action under sub-clause (a) or (c) of Clause 11, he
may if he so desires, take possession of all or any tools, plants, materials,
and stores in so upon the work or the site thereof belonging to the
contractor, or procured by him and intended to be used for the execution of
the work of any part thereof paying for allowing for the same in account at
the contract rates, or in the case of a contract rates not being applicable of
current market rates to be certified by the Executive Engineer whose
certificate thereof shall be final. In the alternative, the Executive Engineer
may by notice in writing to contractor or his clerk of works, foreman or other
authorized agent, require him to remove such tools, plant, materials or
stores from the premises within a time to be specified in such requisition, the
decision to the contractor failing to comply with any such requisition, the
decision of the Executive Engineer as to the expense of any such removal
and the amount of the proceed and expense of any such sale, be final and
conclusive against the contractor
14. EXTENSION OF TIME LIMIT
If the contractor shall desire an extension of the time limit for completion of
the work on the ground of his having been unavoidably hindered in its
execution or on any other ground, he shall apply in writing to the Executive
Engineer and the Executive Engineer may, if in his opinion there are
reasonable grounds for granting extension, recommend such extension as he
may think necessary or proper. The decision of the competent authority in
this regard shall be final, and binding to the contractor. Any delay attributed
to Corporation, shall be thus compensated only by way of extending the
15. COMPLETION CERTIFICATE
On completion of the work, the Contractor shall be furnished with
Completion Certificate by the Executive Engineer. No such certificate shall be
given nor shall be the work considered to be completed until works are taken
over and/or duly tested and put to operation as the case may be, nor until
the work shall have been measured by the Engineer-in-Charge or where the
measurement have been taken by his subordinates until they have received
the approval of the Executive Engineer the said measurement being binding
and conclusive against the contractor.
16. EFFECT OF THE CERTIFICATE :
No payment shall be made for any work estimated to cost less than Rs.1,000
till after the whole of said work shall have been completed and a certificate of
completion given. But in the case of works estimated to cost more than
Rs.1,000, contractor shall on submitting a monthly bill thereof, be entitled to
receive payments. Proportionate to the part of the work then approved and
passed by the Engineer-in-Charge, whose certificate of such approval and a
passing of the sum so payable shall be final and conclusive against the
contract. All such intermediate payment shall be regarded as payment by
way of advance against the final payment only and not as payments for work
actually done or completed and shall not preclude the Engineer-in-charge
from requiring bad, unsound, imperfect or unskillful work to be removed and
taken away and reconstructed or re-erected nor shall any such payment be
EW- 270 PUR-F-006 RFQ-75883
considered as admission of the due performance of the contract or any part
thereof in any respect of the occurring of the claim nor shall conclude,
determine or effect in any way the powers of the Engineer-in-Charge as to the
final settlement and adjustment of the accounts otherwise or in any other
way, vary or affect the contract. The final bill shall be submitted by the
contractor within one month of the date fixed for completion of work;
otherwise the certificate of the Engineer-in-charge of the measurement and of
total amount payable for the work shall be final and binding on all parties.
total amount payable for the work shall be final and binding on all parties.
17. PAYMENT TO CONTRACTORS :
The rates for several items of works estimated to cost more than Rs.1,
agreed to within shall be valid only when the item concerned is accepted,
having been completed full, in accordance with the sanctioned specification.
In case, where the items of the work, are not accepted, as so completed, the
Engineer-in-charge, may make payment on account of such items at such
reduced rates, as he may consider reasonable in the preparation of final or
running accounts bills and it will be binding to the contractor.
18. BILLS :
The Bill Shall be submitted by the contactor each month on or before the
date fixed by the Engineer-in-charge, for all works, executed in the previous
month and the Engineer-in-charge shall take or cause to be taken the
requisite measurement for the purpose or having the same verified and the
claim so far as it is admissible, shall be adjusted, if possible, within Fifteen
days from the presentation of the bills. If the contractor does not submit the
bill, within the time fixed, as aforesaid, the Engineer-in-charge may depute a
subordinate to measure up the said work in the presence of the contractor or
his duly authorized agent, whose counter signature in the measurement
shall be sufficient warrant and the Engineer-in-charge may prepare a bill
from such list which shall be binding on the contractor in all respects. In
case if contractor/ representative does not remain present on specified date
for taking measurement than EIC may take the measurement one sided and
the same shall be binding to the contractor irrespective whether he has
signed or not.
19. SUPPLY OF MATERIALS TO CONTRACTOR [APPLICABLE ONLY
WHERE MATERIAL IS TO BE SUPPLIED BY CORPORATION AS
MENTIONED IN SCHEDULE A ]
If the specification of the estimated work provides for use of any special
description of material to be supplied from the Corporation’s stores or if it is
required that the contractor shall use certain stores to be provided by the
Engineer-in-charge, (such material and stores and the prices to be charged
thereof as hereinafter mentioned being so far as practicable for the
convenience of contractor but not so as in any way to control, the meaning or
effect of this contract specified in the schedule or memorandum hereto
annexed). The contractors shall be supplied with such materials and stores
as may be required from time to time be used by him for the purpose of the
contract only and the value of the full quantity of materials and stores so
supplied shall be set off or deducted from any sum due or thereafter to
become due to the contractor, under the contract or otherwise or from the
security deposit or the proceeds of sale thereof if the deposit is held in
government securities the same or a sufficient portion thereof, shall be sold
for the purpose. All materials supplied to the contractor shall remain the
absolute property of the Corporation and shall on account be removed from
the site of work and shall at all times be open to inspection by the Engineer-
in-charge. Any such materials unused and in perfectly good condition at time
of completion or determination of the contract shall be returned to the
Corporation’s store if the Engineer-in-charge so requires by notice in writing
given under his hand but the contractor shall not be entitled to return any
such materials except with such consent and he shall have no claim for
compensation on account of any such materials supplied to him as aforesaid
but remaining unused by him or for any wastage in or damaged thereto. The
contractor shall be responsible for the loss, destruction or deterioration of
EW- 270 PUR-F-006 RFQ-75883
the materials, stores or articles supplied to him by the Corporation even if
such loss, destruction or deterioration has occurred under any
circumstances whatsoever beyond his control as if the materials, stores or
articles so supplied were his property.
20. WORKS TO BE EXECUTED IN ACCORDANCE WITH SPECIFICATIONS,
DRAWING, ORDERS ETC.
The contractor shall execute the whole and every part of work in the most
substantial and workman like manner and both as regarding materials and
in every other respect in strict accordance with the specification. The
contractor shall also confirm exactly, fully and faithfully to the designs,
drawings and instructions in writing relating to the work signed by the
Engineer-in-charge and lodged in his office and to which the contractor shall
be entitled to have access for the purpose of inspection at such office, or on
the site of the work during office hours and the contractor shall, if he so
requires, be entitled at his own expense to make or cause to be made copies
of the specification and of all such designs, drawings and instructions as
aforesaid.
21. ALTERATIONS IN SPECIFICATIONS AND DESIGNS NOT TO
INVALIDATE CONTRACTS
The Executive Engineer shall have powers to make any alterations, or
additions to the original specification, designs and instructions that may
appear to him to be necessary or advisable during the progress of the work
and the contractor shall be bound to carry out the work in accordance with
any instruction in this connection which may be given to him in writing,
signed by the Engineer-in-charge and such alterations shall not invalidate
the contract. Any additional work which the contractor may be directed to do
in the manner above specified as part of the work shall be carried out by the
contractor on same conditions in all respect on which he agreed to do the
main works and at the same rates as are specified in the tender for the main
Where, however, the work is to be executed according to the designs,
drawings and the specifications recommended by the contractor and
accepted by the competent authority, the alteration above referred to shall be
within the scope of such designs, drawings and specifications appended to
the tender.
22. RATES FOR WORKS NOT ENTERED IN ESTIMATE OR SCHEDULE OF
RATE OF THE CORPORATION
If the additional and altered work includes any class of work for which no
rate is specified in this contract, then such class of work shall be carried out
at the rates entered in the Schedule of Rates of the Corporation or at the rate
mutually agreed upon between the Executive Engineer and the Contractor,
whichever are lower. If the additional or altered work for which no rate is
entered in the Schedule of Rates of the Division is ordered to be carried out
before the rates agreed upon then the contractor within seven days of date of
receipt by him of the order to carry out the work should inform the Executive
Engineer for the rate which it is his intention to charge for such class of work
and if the Executive Engineer does not agree to this rate, he shall be noticed
in writing, be at liberty to cancel his order to carry out such class of work
and arrange to carry it out in such manner as he may consider advisable
provided always that if the rates shall have been determined as lastly herein
before mentioned then in such case he shall only be entitled to be paid in
respect of the work carried out or expenditure incurred by him prior to the
date of the determination of the rate as aforesaid according to such rate or
rates as shall be fixed by the Executive Engineer in the event of disputes, the
decision of the General Manager of the Corporation will be final.
23. EXTENSION OF TIME LIMIT IN CONSEQUENCE OF ADDITION OR
ALTERATION
The time limit for the work shall be extended in the proportion that the
increase in its cost occasioned by alterations or additions bears to the cost of
EW- 270 PUR-F-006 RFQ-75883
the original contract work and the certificate of the Engineer-in-charge as to
such proportions shall be conclusive.
24. NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF
WORK TO BE CARRIED OUT
If at any time, after the execution of the contract documents, the Engineer-
in-charge shall, for any reason whatsoever, requires the whole or any part of
the work, as specified in the tender, to be stopped for any period or shall not
require the whole or part of the work to be carried out at all or to be carried
out by the contractor, he shall give notice in writing of the fact to the
contractor who shall thereupon suspend or stop the work totally or partially
as the case may be in any such case, except as provided here under. The
contractor shall have no claim to any payment or compensation whatsoever
on account of any loss in profit or advantage which he might have derived
from the execution, of the work in full but which he did not so derive in
consequence of the full amount of work not having been carried out or on
account of any loss that he may be put to on account of materials purchased
or agree to be purchased or for unemployment of labour recruited by him. He
shall not also have any claim for compensation by reason of any alterations
having been made in the original specification, drawings, designs and
instructions which may involve any curtailment of the work as originally
contemplated. Where, however, materials have already been purchased or
agreed to be purchased by the contractor before receipt by him of said notice,
the Executive Engineer provided they are not in excess or requirement and
are of approved quality and/or shall be compensated for the loss, if any, that
he may put to in respect of materials agreed to be purchased by him. The
amount of such compensation to be determined by the Executive Engineer,
whose decision shall be final. If the contractor suffers any loss on account of
his having to pay, his labour charges during the period, during which the
stoppage of work has been ordered under this clause the contractor shall on
application be entitled to such compensation on account of labour charges
as the Executive Engineer whose decision shall be final, may consider
reasonable provided that the contractor shall not be entitled to any
compensation on account of labour charges if, in the opinion of the Executive
Engineer, the labour could have been employed by the contractor elsewhere
for the whole or part of the period during which the stoppage of the work has
been ordered as aforesaid.
25. NO CLAIM FOR COMPENSATION ON ACCOUNT OF LOSS DUE TO
DELAY IN SUPPLY OF MATERIALS BY CORPORATION
The contractor shall not be entitled to claim any compensation from
Corporation for the loss suffered by him on account of delay by Corporation
in the supply of materials entered in Schedule A where such delay is caused
Difficulties relating to supply of railway wagons.
Force Majeure
Act of God
Any other reasonable cause beyond the control of Corporation, including
shortage of materials to be supplied by the Corporation and difficulties in
time by reaching at the site of any materials equipment.
In the case of such delay in the supply of materials, Corporation shall grant
such extension of time for the completion of the works as shall appear to the
Executive Engineer to be reasonable in accordance with the circumstances of
the case. The decision of the Executive Engineer as to the extension of time
shall be accepted as final by the contractor.
26. TIME LIMIT FOR COMPENSATION CLAIMS
Under no circumstances, whatsoever, shall the contractor be entitled to any
compensation from Corporation on any account unless the contractor has
claimed in writing to the Executive Engineer within one month of the cause
27. ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK
EW- 270 PUR-F-006 RFQ-75883
If at any time, before the security deposit is refunded to the contractor, it
shall appear to the Executive Engineer or his subordinate in charge of the
work that any work has been executed with unsound, imperfect or unskillful
workmanship or with materials of inferior quality or that any materials or
articles provided by him for the execution of the work are unsound or of
inferior quality to that contract for or are otherwise not in accordance with
the contract, it shall be lawful for Engineer-in-charge to intimate this fact in
writing to the contractor and then notwithstanding the fact that the work,
materials, or articles complained of, may have been inadvertently passed,
certified and paid for, the contractor shall be bound forthwith to rectify or
remove and reconstruct the work so specified in whole or any part, as the
case may require or if so required shall remove the materials or articles so
specified and provided other suitable materials or articles at his own charge
and cost, and in the event of his failing to do so within a period to be
specified by the Engineer-in-charge in the written intimation aforesaid the
contractor shall be liable to pay compensation at the rate of one percent on
the amount of the estimate for every day not exceeding ten days during
which the failure so continues and in the event of any such failure as
aforesaid, the Engineer-in-charge may rectify or remove or re-execute the
work or remove and replace the materials or articles complained of, as the
case may be, at the risk and expense in all respects of contractor should the
Engineer-in-charge consider that any such inferior work or materials as
described above may be accepted, or made use of, it shall be within his
discretion to accept the same as such reduced rates as he may fix thereof.
Provided that in the case of any work of which visible check is not possible if
the Engineer-in-charge or his subordinate in charge of the work feels that
such work has been executed with unsound, imperfect or unskillful
workmanship or with materials of inferior quality, he shall take sample tests
at random, cost of which shall have to be borne by the contractor and if after
taking such test part of such work is found to be defective in any respect or
to have been executed with materials of inferior quality then the contractor
shall pay for the whole work such amount as may be fixed by the office of the
Engineer-in-charge on the basis of the lowest quality of work found by him in
such sample tests.
28. WORK TO BE OPENED TO INSPECTION, CONTRACTOR OR
RESPONSIBLE AGENT TO BE PRESENT.
All works under execution or in pursuance of the contract shall at all times
be open to the inspection and supervision of the Executive Engineer and his
subordinate and contractor shall at all times, during the usual working
hours and at all other times at which reasonable
notice of the intention of the Executive Engineer or his subordinate to visit
the works shall have been given to the contractor, during which period either
he should be present to receive order and instruction, or have a responsible
agent duly authorized agent shall be considered to have the same force and
effect as if they had been given to the contractor himself.
29. NOTICE TO BE GIVEN BEFORE WORK IS COVERED UP
The contractor shall give not less than five days’ notice in writing to the
Executive Engineer or his subordinate in charge of the work, before covering
up or otherwise placing beyond the reach of measurement of any work, in
order that the same may be measured and correct dimensions thereof, taken
before the same is so covered up or placed beyond the reach of measurement
and shall not be covered up or placed beyond the reach of measurement and
work without the consent in writing of Executive Engineer or his Subordinate
in charge of work. If any work shall be covered up or placed beyond the reach
without such notice having been given or consent obtained, the same shall
be uncovered at the contractor’s expense and in default thereof no payment
or allowance shall be made for such work or for the materials with which the
same was executed.
30. CONTRACTOR’S LIABILITIES
EW- 270 PUR-F-006 RFQ-75883
The contractor shall supply, at his own cost, all materials (except such
special materials, if any as may be supplied from the Corporation stored in
accordance with the contract). Plant, tools, appliances, implements, ladders,
cordage, tackle, scaffolding and any temporary works which may be required
for the proper execution of the work, in the original, altered or substituted
form and whether included in the specification and other document forming
part of the contract or referred to in these conditions or not and which may
be necessary for the purpose of satisfying and complying with the
requirements of the Engineer-in-charge as to any matter on which under
these conditions, he is entitled to be satisfied or which he is entitled to
require together with carriage thereof to and from the work. The contractor
shall also supply without any charge the requisite number of persons of
setting out works and counting, weighting and assisting in the measurement
of examination at the time and from time to time of the work or materials,
failing this the same may be provided by the Engineer-in-charge at the
expenses of the contractor and the expenses may be deducted from any
money due to the contractor under the contract or from his security deposit
or the proceeds of sale thereof or of a sufficient portion thereof, the
contractor shall provide all necessary fencing and light required to protect
the public from accident and shall also be bound to bear expenses of defense
of every suit, action or other legal proceedings of law that may be brought by
any person for injury sustained. Owing to neglecting of the above
precautions and to pay any damage and cost which may be awarded in such
suit, action or proceedings to any such person or which may with the
consent of the contractor be paid in comprising any claim by any such
31. CONTRACTOR LIABLE FOR ALL DAMAGE
Compensation for all damage done intentionally or unintentionally by
contractor’s laborer, whether in or beyond the limit of Corporation’s property,
shall be estimated by the Executive Engineer or such other office as he may
appoint and the estimates of the Executive Engineer, subject to the decision of
the Superintending Engineer, on appeal, shall be final and the contractor shall
be bound to pay the amount of the assessed compensation demand, failing
which, the same will be recovered from the contractor as damages or deducted
by the Engineer-in-charge from any sums that may be due to or become due
from Corporation to the contractor under this contract or otherwise.
The contactor shall bear the expenses of defending any action or other legal
proceeding that may be brought by any person for injury sustained by him
owing to negligence of precautions for prevent the spread of fire and he shall
also pay any damage and cost that may be awarded by the court, if in
consequence
32. RESCISSION OF CONTRACT AND FORFEITURE OF DEPOSIT
The contractor shall not assign or sublet, without the written approval of the
Engineer-in-charge and if the contractor assign, or sublet his contract, or
attempt to do so or become insolvent or commence any proceedings to be
adjudicated as insolvent or make any composition with creditors, attempt to
do so, the Engineer-in-charge may, by notice in writing rescind the contract.
Also, if any bribe, gratuity, gift, loan, perquisite, reward or advantage
pecuniary or otherwise shall either directly or indirectly be given, promised or
offered by the contractor or any of his servants, or agents, or any person to
the employee of the Corporation in any way relating to his office or indirectly
interested in the contract, the Executive Engineer may, by ten days’ notice in
writing, rescind the contract. In the event of a contract being rescinded the
security deposit of the contractor shall there upon stand forfeited and be
absolutely at the disposal of the Corporation and the same consequences shall
ensure as if the contract has been rescinded under Clause 11 thereof and in
addition the contractor shall not be entitled to recover or be paid for any work
thereof actually performed under the contract.
33. COMPENSATION
EW- 270 PUR-F-006 RFQ-75883
All sums payable by a contractor by way of compensation under any of these
conditions shall be considered as a reasonable compensation to be applied to
the use of Corporation without reference to the actual loss or damage
sustained and whether any damage has not been sustained.
34. CHANGE IN THE CONSTITUTION OF FIRM TO BE NOTIFIED
In case of tender by partners of a Firm, any change in constitution of firm
shall be forthwith notified by the contractor to the Executive Engineer for his
information.
35. WORKS UNDER DIRECTION OF SUPERINTENDING ENGINEER
All works to be executed under the contract shall be executed under the
direction and subject to the approval of Superintending Engineer /Engineer-
in-charge for the time being who shall be entitled to direct at what point or
points and in what manner they are to be commenced and from time to time
to be carried on.
36. DECISION OF SUPERINTENDING ENGINEER TO BE FINAL
Except where otherwise specified in contract and subject to the power
delegated to him by Corporation under the Corporation’s rules, then in force,
the decision of the Superintending Engineer/EIC for the time being shall be
final, conclusive and binding on all the specifications, designs, drawings and
instructions herein before mentioned and as to the quality of workmanship or
material used on or as to any other question, claim, right matter or thing
whatsoever in any way arising out of or relating to the contract, designs,
drawings, specifications, estimates, instructions, orders or these conditions or
otherwise concerning, the works or the execution or failure to execute the
same, whether arising during the progress of the work or after the completion
or abandonment thereof.
37. Dispute Resolution Mechanism: For works contracts and composite
Contracts, the arbitration mechanism shall be governed by the Gujarat
Public Works Contracts Disputes Arbitration Tribunal Act, 1992 as per
below details.
sub clause 37(1) Amicable Settlement : Any dispute, difference,
controversy or claim between the Parties arising out of or relating to this
contract with reference to the construction, interpretation, breach,
termination or validity thereof (hereinafter referred as "the Dispute") shall,
upon the written request of either Party be referred to the authorized
representatives of the Disputing Parties for resolution. The authorized
representatives shall promptly meet and attempt to negotiate in good faith a
resolution of the Dispute within thirty days of the service of the request.
sub clause 37(2) Arbitration : If the Parties fail to amicably resolve the
disputes or differences or contrary claims as indicated herewith in sub
clause (1) of Clause 37 arising under or in connection with the present works
contracts, whether pertaining to works contracts alone or works and
procurement both, the same shall be referred to arbitration under the
Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992."
38. STORES TO BE OBTAINED FROM CORPORATION [APPLICABLE ONLY
WHERE MATERIAL IS TO BE SUPPLIED BY CORPORATION AS
MENTIONED IN SCHEDULE A]
The contractor shall obtain from the Corporation stores, such articles as are
mentioned in schedule “A” which may be required for the work or any part of
the work or in making up any articles required therefore or in connection
therewith, unless he has obtained permission in writing from the Executive
Engineer or obtained such stores and articles from elsewhere. The value of
such stores and articles as may be supplied to the contractor by the
Engineer-in-charge will be debited to the contractor in his account at the
rate shown in the schedule “A” attached to the contract and if they are not
entered in said Schedule, they shall be debited to him at cost price which for
the purpose of this contract shall include cost of carriage and all other
expenses whatsoever which may have to be incurred in obtaining delivery of
the same at the stores aforesaid and further overhead charges 15%.
EW- 270 PUR-F-006 RFQ-75883
The Contractor shall be responsible for the loss, destruction or deterioration
of the materials, stores or articles supplied to him by the Corporation, even if
such loss, destruction or deterioration has occurred under any
circumstances whatsoever beyond his control as if the materials, stores or
articles so supplied were his property. The contractor shall be responsible for
returning the residual materials after completion of the contract and it fails
to return, the balance materials supplied to him by the Corporation, the cost
of the residual materials will be recovered from the contractor at the market
rate or stock issue rate whichever be higher at the time of materials account
39. LUMP SUMS IN ESTIMATE
When the estimate on which tender is made, includes lump sums in respect
of parts of the works the contractor shall be entitled to payment in respect of
the items of works involved or the part of the work in question at the same
rates as are payable under this contract or such items or if the part of work
in question is not in the opinion of the Engineer-in-charge capable of
measurement the Engineer-in-charge may at his discretion pay the lump
sum amount entered in the estimate and the certificate in writing of the
Engineer shall be final and conclusive against the contractor with regard to
any sum or sums payable to him under the provision of this clause.
40. LUMP SUM TENDERS
Whenever lump sum tenders have been invited for buildings or other
structures of the same type, design, the contractor shall submit his bill
stated in Clause No. 18 and the Engineer-in-charge not below the rank of
work, Executive Engineer shall certify by general measurement or by other
method considered suitable to him, the value of work done and the
contractor shall be paid monthly a sum equal to 90% of the total value the
work so certified, since the last payment, after deducting a part or whole of
the secured advance if not already paid for the materials utilized on the
works. An additional secured advance for any fresh materials utilized on the
works. An additional secured advance for any fresh materials brought on site
will also be paid if certified by the officer not below the rank of Executive
Engineer. After the work is completed final bill would be paid on the
certification of officer not below the rank of Executive Engineer, that the
work, is done according to drawing and specifications attached to the tender.
If any additions and alterations have been carried out, detailed measurement
in respect thereof shall be recorded and extra payment or deductions are
regulated as per item rates quoted by the contractor while submitting the
tender and if there are any items in the additions and alterations for which
the contractor has not quoted a rate, the payment shall be as per Clause
41. ACTION WHERE NO SPECIFICATION
In the case of any class of work for which there is no such specification as is
mentioned, such work shall be carried out in accordance with the PWD and
in the event of there being no PWD specification, the work shall be carried
out in all respects in accordance with the instructions and requirements of
the Engineer-in-charge of the Corporation etc.
42. NO CLAIM FOR VARIATION IN QUANTITIES OR WORK
Quantities shown in the tender are approximate and no claim shall be
entertained for quantities of work actually executed, being either more or less
up to any extent than those entered in the tender or less than those entered
in the tender or estimate.
43. NO CLAIM FOR COMPENSATION FOR DELAY IN STARTING WORK
No compensation shall be allowed for any delay caused into starting of work
on account of acquisition of land and in the case of clearance for works or
any delay in according sanction to estimates.
44. NO CLAIM FOR COMPENSATION FOR DELAY IN EXECUTION OF
No compensation shall be allowed for any delays in execution of the work on
account of water standing in borrow pits or compartment. The rates are
EW- 270 PUR-F-006 RFQ-75883
inclusive for hard or cracked soil, excavation in mud, sub-soil water or water
standing in borrow pits and no claim for any extra rate shall be entertained
unless otherwise expressly specified and mentioned in the tender.
45. EMPLOYMENT OF TECHNICAL PERSONS:
The contractor shall keep one full time qualified Civil Engineer at the site,
who shall be fully authorized to receive and comply with such instructions,
as given by the Executive Engineer. The contractor shall intimate the name
of such Engineer with his qualifications and experience. The Executive
Engineer shall have the right to demand the removal of any technical
personnel, skilled or unskilled workmen, who in his opinion are considered
to cause bad workmanship in the execution of works or to cause indiscipline.
46. INDUSTRIAL LABOUR LAWS
T erm s and C ondition s re g ardin g L abour L a w s
During the entire period of the contract, the Contractor and his Sub- Contractor shall
at all times comply with all applicable labour laws, rules, regulations, notifications,
and bye-laws issued by the Central Government, State Government, or Local
Authorities. This includes all existing laws as well as any amendments or new
notifications that may come into force during the contract period.
The Contractor and his Sub-Contractors shall, at all times abide by the following Act /
statutes related to Human Resources:
1. Factories Act, 1948;
2. Contract Labour (Regulation & Abolition) Act, 1970;
3. EPF & MP Act, 1952;
4. Building & Other Construction Workers (Regulation of Employment &
Conditions of Service) Act, 1996;
5. ESI Act,
6. Minimum Wages Act, 1948;
7. Payment of Wages Act, 1936;
8. Payment of Bonus Acq 1965;
9. Payment of Gratuity Act, 1972;
10. Workmen's Compensation Act, 1923;
11. lD Act, 1947;
12. Maternity Benefit Act, 1961 ;
13. Inter-State Migrant Workmen (Regulation of Employment & Conditions of
Service) Act, 1979;
14. The Building And Other Construction Workers' Welfare Cess Act,
17. The Carriage by Road Act,2007.
The above list is only indicative and not exhaustive. The Contractor shall remain fully
responsible for ensuring compliance with all other applicable labour and welfare
legislations, rules, and regulations in force during the contract.
The following are some of the major responsibilities of the contractor, in addition to
other obligations prescribed under various labour laws, rules, and regulations issued
by statutory authorities such as the State Government or Government of India from
time to time, which the contractor shall strictly comply with during the execution of
the contract.
1) The Factories Act,
The conhactor should not deploy worker below the age of 18 years and above
years for the awarded work.
Earn Leave shall be paid to their bonafide contract workers as per the provisions of
the Factories Act,
Payment of Earned Leave should be made monthly together with wages for better
compliances of law. The contactor shall maintain Earn leave Register in Form No.
EW- 270 PUR-F-006 RFQ-75883
as per the provisions of the said Act and submit the same on demand.
All the written registers, Performa etc. shall be maintained up to date and kept ready
for inspection at any time or submitted on-time to the concerned authorities as per
applicability of the Acts by contractor.
2) The Contract Labour (Regulation and Abolition) Act,
The Contractor / Agency shall have to obtain the Labour License under Contract
Labour (Regulation & Abolition) Act from the appropriate authorities before
commencement of work. The contract tor shall maintain a valid labour license under
the Contract Labour (Regulation and Abolition) Act for employing necessary man
power to be required by contractor.
The contractor should not be allowed to engage fifty (50) or more contract labourers
without initiating to obtain the labour license under the Contract Labour Act. (the
said number i.e., fifty (50) or more includes Supervisor and other staff).
3) Minimum Wages Act,
Contractor shall have to make the payment of wages to the Contract Labours
engaged by them, on or before 7th of every month through nearest Nationalized
Bank compulsory, preferably situated in the premises of TPS area in case of all works
contract. The Contractor shall supply copy of Bank Statement duly stamped by the
Concerned Bank as well as debited entry of amount displayed in the contractors' own
bank account as token of proof towards payment of Wages through CLIM/prevailing
system at relevant time.
Apart from Payment of wages through Bank, Contractors shall have to make all other
payments like Advances, Bonus, Leave Encashment etc. to their labours through
bank only and cash payment / entry will not be allowed.
Wages rates for contract laborers are applicable as per the terms and conditions of
the license. The contractor shall have to pay wages to workers as notified by the
Government of Gujarat from time to time.
Any default to pay the minimum wages to the engaged workers and deprived of their
right to minimum wages payment on or before 7th of each month shall be dealt as
per the provision of labour laws. Recurrence of the same may lead to cancellation of
awarded contract.
4) The Provident Fund and Miscellaneous Provisions Act,
The contractor must possess separate P.F. code on the name of the Firm /Agency
/Company itself for the subject work.
It should be ensured that all the contract labours engaged by contractor are covered
under the provident fund scheme and employee's pension scheme and their
contribution must be remitted regularly to the concemed RPFC. The photocopies of
challan along with ECR in this regards should be submitted regularly to the User
Department to enable their onward billing clearance.
The contractor shall submit along with his bill (month wise) statement regarding
deductions against employees' provident fund and family pension scheme in respect
of each concerned employee' Provident fund and family pension scheme at the rate
of 12 %o of wages (or at the rates made applicable by the Government time to
time). The contractor's contribution and his workers contribution towards provident
fund and family pension scheme shall deposited by the contractor with concerned PF
Authorities.
5) Workmen's Compensation & Employer's Liability Insurance.
The contractors shall have to obtain Employee Compensation Policy under the
Employees Compensation A ct before starting the work. Employee Compensation
Insurance shall be obtained for all the workers engaged for the execution of awarded
EW- 270 PUR-F-006 RFQ-75883
contract. If any of the work is sub-letted the contractor shall ensure that the sub
contractor take and provide workmen's compensation and Employer's liability
insurance for the labours engaged. Contract tor is liable to pay compensation in case
of accidental injury arising or.t of and in the course of employment as per the said
Act and shall bear medical expenses due to on duty accident.
6) The Payment of Gratuity Act,
For better compliance, contractor shall pay amount of gratuity on a monthly basis
along with the payment of wages, calculated on a pro-rata basis per month, which is
equivalent to 15 days' wages for each completed year of service for every worker. (*
applicable to ARC / BRC works contract only).
7) The Payment of Bonus Act,
Every worker shall be entitled to be paid by the contractor in an accounting year,
bonus, in accordance with the provisions of this Act, For better compliance, the
contractor should pay bonus amount on a monthly basis along with wages calculated
on a pro-rata basis per month. Contractor has to submit the paid bonus details of its
worker in Form No. C as per the provisions of the said Act as and when required by
the Govt. Authority as well as by GSECL.
8) The maternity Benefit Act,
Contractor shall ensure that entitled female worker should provide Maternity Leave
and other benefits as per the provision of the said Act.
9) The Building and other Construction Workers' Act,
For any construction work, fall under the definition of Section 2(1Xd), happening
outside / inside the Factory premises the said act will be applicable and the
contractor or its sub-contractor shall be liable to comply with the provisions framed
there under.
10) The contractor shall give preference to existing or local contract workers for
engagement in the awarded contract and shall issue appointment orders to each and
every workers individually at the time of their engagement during the period of
contract and terminate the same at the end of the each contract.
Follow the mentioned procedure at each milestone for the execution of works
11) On Commencement of Contractual Work
1. Before starting the work, the contractor may contact Labour Welfare Officer /
Industrial Relations Officer for all formalities related to labour law compliance before
commencement of the contract and onward Labour Law compliance thereof, so that
later no dispute will arise in respect of compliance of labour laws.
2. It is the responsibility of the contractor to ensure that contractor's employees
maintain strict discipline as regards security, methods of safe working etc, and not to
cause any hindrance to smooth running of power station or in execution of duties by
GSECL staff Any lapse in this regard will be viewed seriously and if lapse found,
contact is liable to be terminated. If any of contractor's staff is found unsuitable or
not behaving properly, the contractor shall have to remove such worker from the
work-site on demand by EIC. To maintain harmonious industrial relations amongst
contact labours is solely the responsibility of contrac tor. Any breach of the same will
be viewed seriously.
3. A digital system developed at the request of the agencies working at the premises
of GSECL, is to facilitate them for easy, efficient, effective management of data, gate
passes, attendances, medical records, Police Verification documents etc related to
their employees / workers deployed for various works and services against work
order of GSECL.
EW- 270 PUR-F-006 RFQ-75883
4. On receipt of LOA and before commencement of work, authorized representatives
of the agency shall login in the CLIMS online portal / prevailing system at relevant
time and apply for registration of their employees / workers uploading all information
with required documents in digital form. Upon completion of due verifications,
clearance by EIC and HR departments, contracting agency will obtain gate passes.
GSECL will only consider documents like wage sheet duly accepted and signed by
individual workers, as per the engagement/deployment duration/hours of individual
worker duly certified by the agency, being the employer, for the purpose of payment
of bills and HR clearances.
Agency shall be solely responsible for maintaining accurate and upto- date data of
their workers in the portal/ prevailing system at relevant time. All statutory
compliances under prevailing laws shall remain the responsibility of the contracting
agency. The agency shall indemnit/ GSECL against any liabilities arising from
noncompliance of legal provisions or inaccuracies in the data maintained by them in
the digital portal of CllMS/prevailing system at relevant time.
5. The Contractor who intends to engage labours more than the specified limit under
law, then necessary - Form No. V under the Contract Labour (R& A) Act, 1970 or
Form No. VI under the Interstate Migrant worker (employment regulation) Act
as applicable is to be obtained for the purpose of obtaining labour License from the
Licensing Authority.
6. It shall be the duty of the Contractor or his Supervisor to ensure Bio-Metric
punching and reporting at the location of work.
7. The contractor shall employ adequate number of experienced staff at site for daily
supervision and for maintaining of various registers and records required under the
Labour laws and contracts. No payment for such supervision shall be admissible.
8. The gate passes obtained for any specific work order will be valid for that specific
work order only and contractor should not divert the man power for any other work
order. If any work or part thereof is desired/required to sublet, the contactor shall
obtain the necessary permission of EIC in black and white well in advance which is
mandatory for considering the statutory documents of agency other than the agency
who awarded work order.
12) During Contractual Work under the progress:
1. All C-ontrac tors shall have to make the payment of wages to the Contract
Labours engaged by them, on or before 7th of every month through Nearest
Nationalized Bank compulsory, preferably situated in the premises of power station
The Contractor shall supply copy of Bank Statement duly stamped by the Concerned
Bank as a token of proof towards payment of Wages through CLIMS i prevailing
system at relevant time.
2. All C-ontra c tors has to comply & maintain statutory documents /registers under
the provision of labour laws & EPF Act.
3. In case the contractor having more than one contract in the same TPS, the
contractor shall have to obtain work order wise separate Gate Passes and submit the
same with the documents of statutory compliance that too work order wise every
month to the User Department to enable their onward billing clearance.
(13) CONTRACTOR TO INDEMNIFY THE GSECL REGARDING LABOUR LAWS
The contractor shall indemnify and keep indemnified the GSECL, and every member,
officer and employees of the GSECL, also Engineer-in-charge and his staff against all
actions, proceedings, claims, demands, costs and expenses whatsoever arising out of
or in connection with the matter referred in above clauses and elsewhere and against
all actions, claims demands, cost and expenses which may be made against the
EW- 270 PUR-F-006 RFQ-75883
GSECL by any workman/ employees of contractor or any sub- contractor and or from
any liability any wise to any workman/employees of the contractor or sub-contractor
under any laws, rules or regulation having in force of law including but not limited to
claims against the owner under employee compensation Act, 1923. The Employee's
Provident Fund Act.l952, and/or the contract labour (Abolition and Regulation) Act,
The GSECL shall not be liable for or in respect of or in consequence of any accident
or injury to any workmen or other person in the employment of the contractor or his
sub-contractor, and the contractor shall indemnify and keep indemnified the GSECL
against all such damage and compensation and against all claims, demands
proceedings costs, charges and expenses whatsoever in respect of or in relation
The contractor shall at his own expense / risk and cost to comply with all the labour
laws as above-mentioned and keep the G.S.E.C.L. indemnified in respect thereof.
GSECL : shall be entitled /empowered to deduct directly from the bills, the amount to
be paid to engaged bonafide contract workers or the contract workers engaged by
Sub-contractor any sum or sums payable by main contractor / sub-contractor and
which sum/sums the Corporation is required to pay in capacity of Principal Employer
on account of the default of contractor in respect of all liabilities incurred out of
noncompliance regarding any provisions of Labour Laws and same amount shall be
recovered from the pending dues of the contractor with 15% administrative charges.
Any other rules and regulation, conditions, circulars etc., that are in force at present
and that may be famed by the G S E C L from time to time in connection with
contracts will be binding and acceptable to contractor.
The above are some of the major liabilities of the contractor in addition to other
liabilities prescribed under the various labour laws in force from time to time from
Statutory Authorities like State Government / Government of India, which the
contractor shall have to comply with.
The contractor shall provide the name of authorized representative, as provided to
other statutory Government authorities and will be notified to Engineer In-Charge
time to time.
14) Submission of Statutory documents to ensure the compliances:
The contractor shall upload statutory documents, work order-wise, under Labour
Laws and EPF in CLIMS / prevailing system at relevant time.
Required documents shall be uploaded by the contractor in existing portal /prevailing
system at relevant time invariably each month to Engineer In-Charge for onward
process and smooth clearance by HR Department.
List of documents required for gatepasses of contract workers through
clims / prevailing system
Sr No Description of documents attached
01 Copy of Work Order
02 Copy of P. F. Code No.
03 Insurance Policy as per subject of work order under the Workmen
Compensation Act,1923
04 Contract agreements/ subletting work contract documents with approval
05 Copy of Id proof of Aadhar card or Election voting card or driving license
or Passport only
EW- 270 PUR-F-006 RFQ-75883
06 Copy of Police Verification in respect of each contract workers
15. The contractor whose work order value is above Rs. 5 lacs shall have to submit
"Declaration cum Indemnity Bond" on Rs. 300/- Non-Judicial stamp paper in
prescribed Performa (Annexure- "B") with Agreement and Indemnity Bond before the
commencement of the contract.
Annexure- “B"
DECLARATION CUM INDEMNITY BOND
( On Rs.300/- Non Judicial Stamp Paper duly notarised)
THIS DECLARATION CUM INDEMNITY BOND made at…………………….(mention location) by
M/S……………………………. having its Reg. Office at
(hereinafter referred to as "Contractor" which expression shall unless it be repugnant to the
context or meaning thereof, be deemed to mean and include their respective assigns,
successors, executors, subcontractors and / or administrators) of the ONE PART in favour of
M/S Gujarat State Electricity Corporation Limited having its power Station at
.......................Therma1 Power Station (hereinaffer referred to as the "Company" ), which
expression shall unless it be repugnant to the context or meaning thereof be deemed to mean
and include its assigns, successors) of the OTHER PART.
WHEREAS the COMPANY has entered into a contract with the Contractor for the work of
under order No: …………………………………..dated…………………….”hereinafter called the
"Contract");
AND WHEREAS it is one of the essential conditions of the Contract that the Contractor shall
comply with all the provisions of the Labour & Industrial Laws, as may be applicable from time to
time for the discharge and completion of the works and completion of the Works and Services
covered under said Contract Labour (R & A) Act 1970, Child Labour (Prohibition and Regulation)
Act 1986, The Employees Provident Funds & Miscellaneous Provisions Act,1952, Employees State
Insurance Act 1948, Minimum Wages Act,1948, Payment of Bonus Act,l965,Payment of Wages
Acl,1936, Employees Compensation Act.1923, Factories Act,1948 and other Labour Laws, Rules,
Notifications and Codes which are at present applicable to the contractor and which may be
applicable during the tenure of the contract (hereinater referred as the 'Laws').
AND WHEREAS the Contractor has agreed to execute this Declaration cum Indemnity Bond to
this effect and has agreed to indemnify and Company, it's D ire c tors, Officers and employees
and representatives indemnified and hold harmless against all third party claims, charges
,penalties, fines, expenses ,losses, damages costs, suits or any other levy against the Company
and/or the management due to the failure of the Contractor to observe or follow all applicable
NOWTHIS DEED WITNESSETH AS UNDER
1. The Contractor hereby declares that all acts, deeds, actions, activities, conduct and lapse,
delays, misdeeds, faults, breaches, inactions etc done by his assigns, successors, executors,
subcontractor and / or administrators shall be construed to be have been done by the contractor
and he alone shall be liable for such acts, inactions etc.
EW- 270 PUR-F-006 RFQ-75883
2. In consideration of the Company awarding the Contract to the Contractor subject to the
condition of execution of this Declaration cum Indemnity bon{ the Contractor declares and
represents to the Company that the Contractor has obtained all Statutory registrations,
Certificates, licenses and approvals required under the Laws enabling the Contra ctor to execute
the Contract in a legal and lawful manner.
3. That in the event of any liability arising out of non-compliance of any 'Laws' of the land by the
Contractor in connection with the Performance of the contract the Contractor shall bear all the
resultant liability (ies) whatsoever, if any and that the company , its Directors, Officers and
employees, representatives, shall not be liable for any such liability(ies). The Contactor
undertakes to indemnify and keep the Company and its Directors, Officers and employees,
representatives indemnifies, defend and hold harmless, against all losses, costs, damages,
claims, penalties, interest, expenses, demands, fines, legal liability, causes of action, injury to
persons, suits etc., which may be suffered, incurred, undergone and / sustained by the Company
including the Costs and expenses that may be incurred in defending any such liability(ies)
claim(S), Proceeding ( S) etc. that maybe made or taken or taken or arise on the same by any
Person, body, authority, government, judicial / quasi - judicial authority due to the failure or non-
compliance of any such laws and rules there under (including any amendments in acts, laws,
statutes & rules there under) of whatsoever kind and nature arising out of or in any way
connected with, whether or not such acts or omissions are actual or alleged, active or passive
with regard to the discharge of the said Contract.
4. The Contractor further declares that in case of any suit / claim/ right / damages /
compensation / fine / levy / charges / expenses / losses / penalties / costs raised by the third
party, including contract labours engaged by the contractor, he shall join such proceedings in
such Suit/Court/Tribunal/Authority and effectively defend the same.
5. The Contractor hereby agree and undertakes to make good any loss, damage, claims, suits,
demands, decrees, expenses that the Company may suffer to the fullest satisfaction of the
Company and if the Contractor fails to make good the same then the Company shall have the
right to recover the same from and or any other loss sustained, without any restriction or
limitation, together with any
other incidental expenses, costs, and all incidental logistic expenses etc that may be suffered by
the Company from the Contractor and the Contractor hereby further confirms and declares that
this Declaration cum Indemnity Bond is irrevocable and shall be final and binding on him, his
heirs, executors, administrators, legal representatives, successors, subcontractors and assigns,
wherever the context applies. any claims, demands, shall be adjusted against any amount due
and payable to the Contractor and the Company shall have the right to withhold any amounts
due and payable to the
Contractor, till the settlement of such claims, disputes to the Contractor towards discharge of
such claims, obligations etc.
This Declaration cum indemnity bond shall be in accordance with the laws of India and any
dispute between the parties with regard to this Declaration cum Indemnity Bond shall be
resolved through the dispute resolution process mentioned in the General Conditions of the
Contract (GCC).
IN WITNESS WHEREOF, the said Contractor has hereunto set their hand the day and year first
hereinabove written.
SIGNED SEALED AND DELIVERED By the within named *CONTRACTOR"
(Authorised Signatory)
Rubber Stamp of Firm/Company
Full Name:
Designation:
EW- 270 PUR-F-006 RFQ-75883
In presence of Witness
Name & Address of Witness Signature
1. Full Name :
Residential Address:
Contact No. :
2. Full Name :
Residential Address:
Contact No. :
47. MATTERS RELATED TO EXECUTION OF WORK:
a) Work shall commence from the date given in letter to commence the work by
EIC at site. The Contractor shall make all necessary arrangements at site to
mobilize labour, operators, divers and materials and maintain necessary
number of machinery and equipment, barge, pontoons etc., to guarantee the
agreed rate of progress of work as per schedule.
b) A detailed work schedule showing how he proposes to carry out the work,
specifically mentioning time periods as well as date of commencement and
completion of each activity and such approved schedules must be strictly
adhered to by the CONTRACTOR. After the owner has agreed with the
schedule, the Contractor shall prepare detailed program of each work
front/activity breaking it down giving daily quantifiable/measure of progress.
The schedules are to be reviewed periodically with the OWNER / ENGINEER
to ensure that the completion date will be met or to institute corrective steps
(at no extra cost to the ENGINEER) to adhere to the completion dates. The
OWNER reserves the right to revise the schedule at his discretion in order to
keep up to the completion date and to suit the project requirement and such
alterations shall not entitle the CONTRACTOR to any extra payment.
c) A work schedule with PERT / Bar Chart for carrying out the work in
prescribed time limit mentioning date of commencement, activity to be
carried with its time period, starting & finishing event for each activity,
completion of total project in critical path etc, shall be jointly fixed and
approved by the GSECL. Such approved schedules must be strictly adhered
by the Contractor.
d) After the GSECL has agreed with the schedule, the Contractor shall prepare
detailed program of each work front / activity breaking it down to daily
quantifiable measure of progress. The schedules are to be reviewed
periodically with the Owner / E.I.C to ensure that the completion date will be
met or to institute corrective steps (at no extra cost to the GSECL) to adhere
to the completion dates. The Owner reserves the right to revise the schedule
at his discretion in order to keep up to the completion date and to suit the
project requirement and such alterations shall not entitle the Contractor to
any extra payment.
e) The GSECL reserves the right to delete any item of schedule-B for which
contractor shall not have any right to claim on this account.
f) One permanent reference bench mark and a reference base line shall be given
for lay out of work, which shall be maintained without disturbance by the
CONTRACTOR during the tenure of the contract. CONTRACTOR shall
establish local bench marks as directed by the ENGINEER IN CHARGE.
g) The contract or any part thereof shall not be subject to change without the
written permission of the Chief Engineer (Gen.) GSECL, GANDHINAGAR
TPS or his authorized representatives.
h) During the execution of the work if it is found that the work is not
progressing as per the scheduled program approved by the GSECL & planned
by the contractor, due to the reasons attributable to the contractor, suitable
action shall be taken as per Clauses in this tender elsewhere & other relevant
clauses appearing in the section of “Terms & condition of tender & works
contract, Legal conditions of works contract” of tender document. And the
GSECL may also take such action as it may deem fit to ensure that the work
is completed in time at Risk and Cost of the contractor.
EW- 270 PUR-F-006 RFQ-75883
i) Contractor shall attend meetings at EIC's office at site or any other place as
fixed by the EIC, as and when required for review, discussion, coordination
etc. Attending these meetings shall be obligatory on the part of the
Contractor, at no cost to the GSECL.
j) The Contractor shall take all requisite & necessary care to observe that no
damage is caused to the existing, pumps, existing works, service road, or any
other structure etc. For any damage to the existing structures of the GSECL,
the Contractor shall be held responsible and he will have to rectify the
damage immediately up to the satisfaction of Engineer in Charge, at his own
k) The work shall be completed within the period stipulated in the contract. &
site clearance arranged according to the progress of work at site. Therefore,
the contractor has to organize & coordinate the work to suit these
circumstantial conditions. In the event of any delay due to the above or due
to any other reason not attributable to the contractor, reasonable extension
in completing the work may be given at the discretion and as decided by the
GSECL but no compensation or idle charges will be payable to the contractor
on this account or any site conditions under any circumstances.
l) No idle charges shall be entertained by GSECL for any site condition or any
circumstances. The corporation will not pay any type of advances including
mobilization advance
48. RECOVERIES:
a) In case of any damage to equipment / machinery or structure / building of
GSECL or any public property due to negligence of contractor or any other
reasons attributed to contractor, the decision of E.I.C. regarding the amount
of recovery shall be final.
b) If the contractor fails to execute the work as per direction of E.I.C. within the
time frame given, the GSECL shall get the work done through any other
contractor at the risk and cost of the contractor and the cost of execution of
such work along with 15% overhead charges shall be deducted from
contractor’s monthly bill over and above recovery as per rules.
c) Recoveries due from the contractor, up to the end of the month previous to
the one in which the bill is prepared shall be made from bills approved for
payment every month or at other periods when the bills are prepared, for
the various items in the following order of priorities and extents.
d) Deduction on account of security deposit in full together with shortage, if
any, to be made good.
e) Penalty in full, if levied.
f) Expenditure, if any, incurred by the Corporation on Contractor’s behalf in
labour or materials in full.
g) Charges for services such as water and power supply etc. in full.
h) Charge on account of supply of materials like cement and steel in case of
shortages found in balance or excess consumption than specified.
i) Hire charges for Corporation or Government machinery if any.
j) Recoveries of advance and secured payment or payments for preliminary
work in full or the installment due if and as the same as may have been
k) Rent recovery on account of allotting quarters on rent as per Corporation’s
l) Income tax and sales tax in full as per Government rules.
m) Outstanding recoveries in respect of other contracts awarded by the
Corporation if any.
n) Other recoveries. (If any)
49. WORK TO BE EXECUTED TO THE SATISFACTION OF THE ENGINEER
-IN-CHARGE:
The contractor shall proceed with the work with diligence and expedition
and the whole of the work herein specified as well as the mode of
execution shall be under the supervision and direction and shall be
carried on to the entire satisfaction of the Engineer-in-charge, who shall
have full power to order the contractor to alter, enlarge or diminish the
form, dimensions, positions, or quantities of any of the work or to make use
of material and workman-ship of different descriptions and qualities from
this herein specified.
EW- 270 PUR-F-006 RFQ-75883
The whole of the works, together with any temporary works, associated
therewith, shall be carried on in the most substantial proper and mannered
workman like manner, with the best materials and workmanship and to
the entire satisfaction of the Engineer-in-charge and in such order of time
as he may direct. The contractor shall attend to and execute without delay
all orders and instruction which may from time to time be issued by the
Engineer-in-charge.
50. MATERIALS WORKMANSHIP etc.:
The work shall be executed in thoroughly substantial manner with material
and workmanship of best quality and strictly in accordance with the
specifications and with the drawings, or with such other drawings or written
instruction as may from time to time be furnished to the contractor, in
accordance with terms of this contract and shall be completed in every
respect with all materials and workmanship implied and necessary according
to the fair interpretation and meaning of the same and should there be any
discrepancy between the drawings and specifications or any difference or
disputes as to the dimensions to be worked to or the quality of the materials
to be used, or the mode of doing periodical quantity of the work to be
executed or with respect to any subject arising out of this contract, the
decision of the Engineer-in-charge shall be final and binding on all parties.
Rejected material shall be so disposed off as to obviate any possibility of their
use on works. The place, method and period of disposal shall be as directed
by the Engineer-in-charge.
51. SAMPLES OF DESCRIPTIVE DATE:
Samples of descriptive date, requiring approval, shall be submitted by
contractor to the Engineer-in-charge in good time before the use of such
material for inspection and permission of testing if required. The samples
shall be properly marked to show the name of the material, manufacture,
place of origin, and place where to be used etc. Failure of any sample to
pass specified tests will be sufficient cause for the refusal to consider any
further sample from the same source.
52. FENCING AND LIGHTING AND VENTILATION
Except as herein after provided, the contractor shall unless otherwise
specified, be responsible for the proper fencing, guarding, lighting and
taking of the necessary safety measures for all works comprised in the
contract and or the proper provision of temporary roadway, footways,
guards fences, caution notices etc. as far as the same may be rendered
necessary by reasons for the work for the accommodation and protection of
workman foot passenger or other traffic and of the owners and occupiers of
adjacent property and of the public and shall remain responsible for
any accidents that may occur on account of his failure to take proper
and timely precautions.
All the arrangements made for fencing, lighting and ventilation shall be
maintained by the contractor throughout the tendency of the contract
till physical taking over of the work by the department.
53. LIABILITY FOR DAMAGE TO WORKS OR PLANTS
The contractor shall during, the progress of the work, properly cover up
and protect the work, and plant, and materials placed at his disposal or
acquired for him by the Corporation, from injury by exposure to the
weather, or any cause what so ever and shall take every reasonable proper
timely and useful precaution against accident or injury to the same from
any cause and shall be and remain answerable and liable for all accidents, or
injuries thereto which until the same be or be deemed to be, taken over by
the Corporation, may arise or be occasioned by the acts or omissions of the
contractor or his workmen of sub-contractors, and all losses and damages
to the works or such plant or material arising from such accidents or
injuries as aforesaid shall be made good in the most complete and substantial
manner by and at the sole cost of the contractor and to the reasonable
satisfaction of the Engineer-in-charge. If the contractor fails to make good
such losses & damages within the time given by the Engineer-in-charge, the
Corporation shall be at liberty to recover the amount fixed by the Engineer-in-
EW- 270 PUR-F-006 RFQ-75883
charge for such losses or damages or any part thereof by deducting it from any
sum due by the Corporation to the contractor under this contract or otherwise.
Further the contractor shall, at all time, protect and preserve all materials,
plant and equipment that he may himself have procured for the execution of
the work. All reasonable requests of the Engineer-in-charge to enclose or
especially protect any of the above shall be expeditiously compiled with.
If the Engineer-in-charge considers that the work or materials or plant is not
sufficiently protected by the contractor, he shall be entitled to arrange for
such protection at his unfettered discretion and recover the cost thereof from
the contractor.
Until the work shall be or be deemed to be taken, over as aforesaid, the
contractor shall also be liable for and shall be deemed to have indemnified the
Corporation in respect of all damage or injury to any person or any property of
the Corporation or of others, occasioned by the negligence of the contractor or
his workmen, or his sub-contractor, or by defective design, work or
materials.
54.EXPLOSIVE PROCUREMENT AND STORAGE (IF APPLICABLE)
i) Explosives, petrol, oils, fuels and other inflammable materials shall be stored
strictly in accordance with the rule of the Explosive Department.
ii) The contractor shall at his own expense construct and maintain, proper
magazines which are required for the storage of explosive and arrange for
proper storage facilities for oils, fuels etc. for use in connection with the work.
iii) The contractor shall at his own expense obtain such license or licenses as
may be necessary for strong and using explosives, oils, fuels etc. The
department shall not take any responsibility whatsoever in connection with the
storage or use of explosives on the site, or any accident or occurrence
whatsoever in connection therewith. All operation of the contractor in which or
for which Explosives are employed shall be at risk of contractor and upon his
own responsibility.
55. MATERIALS TOOLS AND PLANT BROUGHT ON THE SITE OF WORK
All materials, tools and tackle of the contractor brought to and delivered
upon the site for the purpose of the work shall from the time of their being
so brought shall be deemed to be the property of the Corporation in its
possession to be used for the purpose of the work and for that purpose only
and shall not on any account be removed or taken away by the contractor
or any other person without the written permission of the Engineer-in-charge
but the contractor shall nevertheless be solely liable and responsible for
and loss destruction thereof or damage thereto. The Corporation shall have
a lien on such materials, tools and tackle for any sum of sums which may at
any time prior to the completion of the works be due or owing to the
Corporation by the contractor, under in respect of and dispose of any such
materials, tools and tackle in such manner as the Corporation may think fit
and to apply the proceeding in or towards the satisfaction of such sum or
sums so due or owing as aforesaid but subject to such lien and power of
sale and disposal such surplus materials, tools and tackle shall belong to the
contractor and may be removed and disposed off by him as he may think fit.
56. ACCESS TO SITE AND WORK ON SITE
The Engineer-in-charge or his authorized representative may if he consider
fit from time to time enter upon any lands which may be in the
possession of the contractor under this contract, for the purpose of
executing any work not included in this contract and may execute such
work not included in this contract by agents, or by other contractors at his
option and the contractor shall in accordance with the requirements of
the Engineer-in-charge, afford all reasonable facilities for execution of the
works including occupation of lands by structure or otherwise for any
other contractor employed by the Corporation and his workmen or for the
workmen of the Corporation who may be employed in the execution on or
near the site of the work not included in the contractor’s any contract in
connection with or ancillary to the works and in default, the contractor shall
be liable to the Corporation for any delay or expense incurred by reason of
such default. Provided always that if the exercise of those power shall cause
EW- 270 PUR-F-006 RFQ-75883
any damage to the contractor he may within fifteen days of such damage
arising make a statement of the same to the Engineer-in-charge who shall
from time to time assess the value in his Judgment of such damage and the
Corporation shall from time to time shall pay to the contractor the amounts
(if any accepted as justified) by the Engineer-in-charge. The contractor shall
not however, on account of any such modified, new or extra work executed
by or for the same of the Corporation be entitled to claim relief from the
obligation to execute other works.
57. INSPECTION OF WORKS
The Engineer-in-charge or his duly authorized agent shall have at all time
full power to inspect the works, wherever in progress, either on the site, on
the contractor's premises or at the premises wherever situated, of any firm or
Corporation where work in connection with this contract may be in hand.
Further, the contractor shall not allow, without written authorization permit
entry on site of work, any person except authorized agents of the Corporation
of the Engineer-in-charge or the contractor's staff and labour directly
engaged on and in connection with the work.
The contractor shall, during working hours, maintain supervisors having
sufficient training and experience to supervise the various items and
operations of the work and the said supervisors shall remain present during
the inspections of the Engineer-in-charge. All orders and directions given to
such supervisors or other staff of the contractor shall be deemed to have
been given to contractor. Further the Engineer-in-charge may be due notice,
desire a higher ranking members of the supervisory staff of the contractor to
be present on any specified inspection and the contractor shall comply with
such direction.
58. CLEANING UP
The contractor shall at all times keep the construction area and his power
house and storage areas free from accumulation of waste, or rejected
materials.
Prior to the completion of the work the contractor shall remove all rubbish
from and about the premises, and all tools, scaffolding, equipment and
materials which are not part of permanent structure. The premise will be left in
a manner fully satisfactory to the Engineer-in-charge, thereafter only the
completion certificate will be issued.
59. CONTRACTOR TO KEEP INVENTORY OF MATERIALS etc.
The contractor shall prepare and maintain an inventory of all materials
temporary rolling stock, plant purchased or hired for use of employment or
for any of the purposed for this contract and such inventory or a copy thereof
shall at all times be available for inspection by the Engineer-in-charge. A
complete and up to date copy of the inventory shall be submitted to the
Engineer-in-charge in the beginning and once a year; thereafter changes in
the interim period, if any shall be communicated on every three months.
60. CONTRACTOR TO RESTORE PLANT
Upon completion of the work, the contractor shall deliver to the Corporation,
all appliances, materials, and plants which may have been loaned or hired
to him by the Corporation and make good all damages which may have
occurred to them, except such as shall be caused by fair wear and tear in
execution of the works.
61. PROGRESS SCHEDULE
i) The contractor shall furnish, within one week unless extended by the
Engineer of the order to start the work, a progress schedule in quadruplicate
indicating the date of start the weekly progress expected to be achieved and
the anticipated completion date of each major items of work to be done by
him, also indicating dates of procurement and setting up of materials, plant
and machinery. The schedule should be such as is practicable of achievement
towards completion of the whole work in the time limit and of the particular
items on due dates specified in the contract and shall have the approval of
the Engineer. Further, the dates for the progress as in this schedule shall be
kept up-to-date. In case it is subsequently found necessary to alter this
schedule, the contractor shall submit in good time a revised schedule
EW- 270 PUR-F-006 RFQ-75883
incorporating necessary modifications proposed and get the same approved
by the Engineer. No revised schedule shall be operative within such
acceptance in writing.
Detailed schedules for each week showing the progress proposed to achieve
shall be submitted to the Engineer and got approved. The Engineer is further
empowered to ask for more detailed schedule or schedules any week by week,
for any items or items, and the contractor shall supply the same as and when
asked for.
ii) The Engineer shall have, at all times the right without in any way vitiating
this contract, or forming grounds for any claim to alter the order of the works
or any part thereof and the contractor shall after receiving such direction
proceed in the order directed. The contractors shall also revise the progress
schedule accordingly and submit four copies of the revised schedule to the
Engineer within seven days of the Engineer's direction to alter the order of
iii)The contractor shall furnish sufficient plant equipment and labour and shall
work such hours and shifts as may be necessary to maintain the progress on
the work as per the approved progress schedule. The working and shift hours
shall comply with all GSECL's regulations in force and shall be such as may
be approved by the Engineer. They shall not be varied without the prior
approval of the Engineer.
iv)The contractor shall from time to time as may be required by the Engineer,
furnish the Engineer, with a statement in writing of the arrangement he
proposes to adopt for the execution of this contract and the Engineer may if
he considers, necessary at any time advise alteration in the same, which the
contractor shall adopt on notice thereof.
v) The progress schedules shall be in the form of progress charts, forms,
statement and/or reports as may be approved by the Engineer. Further, the
contractor shall submit four copies showing the progress of work in forms
and charts etc. at periodicals intervals as may be specified by the Engineer.
62. DATE OF COMPLETION
The contractor shall supply, erect, equip and construct the whole of the
works and hand over them to the Corporation on or before the date
specified in the tender document including "Special Conditions" and save as
herein provided, in no circumstances whatever shall extend or alter the
date for the completion of works. Provided always that if in the opinion of
the Engineer-in-charge the completion of the works shall be delayed by
any change of original design or by the order of the Engineer-in-charge, of
any altered, modified substituted or additional works or materials omitted or
by strikes, lock outs or stoppages of labour, or revolution, riots, civil or
political disturbance or by causes directly due to war or by the contractor
not being given possession of the site or any part there-of or by the
Corporation taking possession of and using the site or any part thereof or
the works or any part thereof, whether any nonperformance of work under
the powers herein contained or otherwise or by any nonperformance of
work or non-supply of materials to be performed or supplied by the
Corporation or by the contractor not receiving any orders, drawings,
instructions or directions in time or by the suspensions of the works or by
fire, flood exceptionally bad weather tempest, storm, or by from
unforeseen circumstances (and whether the same shall be due to any act
or omission of the Corporation or its agents or those in their respective
service or not) the Engineer-in-charge may, if in his unfettered discretion,
he thinks fit either forthwith or at any later time and from time to time
not withstanding that the prescribed or extended time for completion has
expired or that the work have been completed, by writing under his hand,
extend the time for the completion of the works to such date as he shall
appoint. Provided always that unless the contractor makes a written
application to the Engineer-in-charge within one month of the cause of
delay and unless the time is extended by the Engineer-in-charge, the
prescribed time shall not be extended notwithstanding delays from the
aforesaid foregoing or any other causes of whatsoever kind.
EW- 270 PUR-F-006 RFQ-75883
63. SUBLETTING OF CONTRACT
There will be generally no objection on the component parts for the work,
being given over to responsible sub-contractors but Corporation shall
under no circumstances recognize these sub-contractors and the
responsibility of executing the work in the accordance with the
conditions of contract will entirely rest on the main contracts. The main
contractors will therefore always have the very responsible member,
preferably a technical hand present on the works with power to sign all
work orders issued on the site of work and to take requisite actions in the
interest of very efficient execution of work. However, the subletting of the
contract can be made only with the prior approval of the competent authority
of the Corporation.
64. OTHERCONTRACTS FOR THE WORK SUSPENSION STOPPAGEOR
CURTAILMENTS OF WORK
If during the tendency of the contract the Engineer-in-charge shall for any
reasons (which shall be unquestioned) whatsoever require the whole or
any part of the work as specified in the contract to be suspended for any
period or shall not require the whole or any part of the work as specified
in the contract to be carried out at all by the contractor, he shall give
notice in writing of the fact to the contractor who shall thereupon suspend
or stop the work totally or partially as the case may be. In any, case,
except as provided hereunder, the contractor shall have no claim to any
payment or compensation whatsoever on account of any profit or advantage
which he might have derived from the execution of the work in full but
which he did not so derive in consequence of the full amount of the work
not having being carried out, or on account of any loss that he may be put
to on account of materials purchased or agreed to be purchased or for
unemployment of labour recruited by him. He shall not also have any claim
for compensation by reason of any alterations having been made in the
original specifications, drawings, designs and instruction which may involve
any curtailment of the work as originally contemplated. Where, however,
materials have already been purchased or agreed to be purchased by the
contractor, before receipt by him of the aforesaid notice, the contractor
shall be paid for such materials at the rate determined by the Engineer-
in-charge, provided they would have been useful for the work curtailed or
stopped are not in excess of requirements, are of approved quality and
cannot be used on other contract works or otherwise by the contractor
and/or shall be compensated for the loss if any, that he may be put to, in
respect of materials agreed to be purchased by him, the amount of such
compensation to be determined by the Engineer-in-charge, whose decision
shall be final.
The Engineer-in-charge may grant extension of time for the execution of any
item or items of work affected by such suspension of work. The decision for
the Engineer-in-charge, regarding the granting of extension and the period
thereof shall be final. The Engineer-in-charge may order the contractor to
suspend any work on account of bad weather; rain or storm and such other
adverse climate conditions and the contractor shall comply with the same.
The contractor shall not be entitled to an compensation for such suspension
of work, concrete lining at the junctions of the different works under
different contract shall be done with particular care regarding forms,
construction joints, interconnecting reinforcement etc. If any and the
joint planning of such work shall be with prior approval of the Engineer-in-
65. OTHER CONTRACTORS
Apart from this work, the other works connected with the power house will
be simultaneous going on either departmentally or through agencies inside
or outside the power house. Each contractor or agency shall co-operate
with others to the fullest extent and shall allow to each other every
facility and co-ordination for execution of their works simultaneously and
satisfactorily, during their action of machinery or execution of any other co-
ordination works of the power house, the contractor will have to work only
EW- 270 PUR-F-006 RFQ-75883
at places as directed by the Engineer-in-charge. He will have some time to
suspend his work partially or totally in the interest of the work at large.
In such cases and at such time, he will be informed from time to time and
directed by the Engineer-in-charge where to work. He may also be required
to remove the scaffolding or to erect the scaffolding and shuttering in such a
manner as to be of little obstruction and inconvenience for erection of
machinery. In such cases he shall not be given any compensation on
account of reduction or stoppage or labour force or removal and
reinstatement of scaffolding shuttering etc. It will be seen that contractor is
not put to unnecessary inconvenience.
In the matter of dumps, haul, roads, drainage, diversion and the like, each
contractor shall take into consideration the needs and requirements of the
other constructors, if any working in the vicinity. Further no contractor
shall take or cause to be taken any stops or action that may cause
disruption, discontent or disturbance to the work, labour of arrangements
etc. or other contractors in the neighboring project localities.
Any action, by any contractor, which the Engineer-in-charge in his
unquestioned discretion may consider as infringement of the above code,
would be considered as a breach of the contract conditions and the
Engineer-in-charge may take such action as he may deem fit against the
contractor and the action taken shall be considered as final and binding.
66. SPEED OF WORK
The contractor shall at all times maintain the speed of work to confirm to
the latest operative progress schedule but the Engineer-in-charge may at
any time with sufficient notice in writing direct the contractor to slow down
any part or the whole of the work for any reason (which shall not be
question whatsoever, and the contractor shall comply with such orders of
the Engineer-in-charge. The compliance of such orders shall not entitle the
contractor to any claim or compensation.
67. CONTRACT DOCUMENT AND MATTERS TO BE TREATED AS
All documents, correspondence, decisions and other matter concerning the
contract shall be considered as of confident and restricted nature by the
contractor and he shall not divulge or allow access there to any unauthorized
persons of any kind.
68. ACCESS TO THE CONTRACTOR'S BOOK
Whenever it is considered necessary by the Engineer-in-charge to ascertain
the actual cost for execution of any particular item of work of supply of plant
or material shall direct the contractor to produce the relevant documents
such as pay rolls records of personnel, invoices of materials and any
other data relevant to the item or necessary to determine its cost etc. and
the contractor to the aforesaid items in the mode and manner that may be
specified.
69. INTEREST ON MONEY DUE TO THE CONTRACTOR
The contractors shall not be entitled to get interest on any amount either of
their bills or arrears whatsoever because of delay in payment by the
Corporation. Similarly they shall not be entitled for any interest on amount
of bank guarantees given by them. Non-payment of interest by the
Corporation therefore, shall not cause breach of contract.
70. MEASUREMENTS TO BE PROVISIONAL AND SUBJECT TO
CORRECTION
Every measurements for running payment on account of work, done or
supplies made, shall be subject to adjustment or final measurements. In
case of disagreement between such intermediate and final measurements,
the latter shall prevail. All works shall be measured, met by standard
measure and according to rules and custom and usual in the use in Gujarat
EW- 270 PUR-F-006 RFQ-75883
State Electricity Corporation Ltd., and no proposal to adopt alternative
method will be accepted, the Executive Engineer’s decision as to what is “the
usual method in use in the Gujarat State Electricity Corporation Ltd.” shall
71. BREACH ON PART OF CORPORATION NOT TO ANNUAL CONTRACT
No breach or non-observance on the part of the Corporation of any of the
agreements contained herein, shall annul this contract or discharge the
contractor from the observance and performance thereof, or of any part
thereof, but on application by the contractor and in the unfettered
discretion of the Engineer-in-charge an extension of time may be given to
the contractor in respect of such breach or non-observance by the
Corporation.
72. PROFORMA RETURNS
The contractor shall maintain Performa, charts and details regarding
machinery equipment materials, labour personnel and other matters as may
be specified by the Engineer-in-charge. He shall further, submit returns
of Performa and details as may be specified by the Engineer-in-charge
from time to time.
73. LOCAL LAWS
All local laws in force at the time of entering into the contract and those
enacted thereafter shall be binding on the contractor and he shall abide by
All import duties, sales tax and other local taxes shall be borne by the
contractor and they shall be deemed to have been covered by this quoted
tender rate
74. WORKS IN SHIFT DUTY
Works shall be planned in shift duties, if possible in three shifts, depending
on emergency of the work with prior approval of Eng. - in- charge. 0n Sunday
or any other holidays work shall be continued in order to maintain progress
with prior permission of Eng.-in -charge. Such works shall not form any
grounds for complaint, compensation or extension of time limit.
If on the other hand, the Engineer-in-charge directs that the work shall be
proceeded with on days and during hours which are not permissible
under this contract, the contractor shall proceed with the work as directed
without in any way vitiating this contract or forming any grounds for
compensation of claim.
The contractor shall in his dealing with labour, atall times, during the period
of this contract, have due regard to local festivals and religious and other
A working day shall consist of two shifts each of eight hours, a working day
shall constitute any day on which in the opinion of the Engineer-in-charge,
work can be carried out in one or more shifts.
75. LIENS
Final payment to the contractor shall not be made until the contractor shall
deliver to the purchaser or receipts in full in lieu thereof, and in either case,
an affidavit that so far he has knowledge or information the releases and
receipts include all the labour and material for which in lien could be filed. If
any lien remains unsatisfied after all payments are made, the contractor
shall refund to the purchaser all moneys that the latter may be compelled to
pay in discharging such a lien, including all costs and a reasonable
attorney's.
76. MISCELLANEOUS:
1. In case of conflict / discrepancies among clauses of different specifications
given in this document, the stringent specification shall be followed and
under such circumstances, the decision of the EIC shall be final and binding
EW- 270 PUR-F-006 RFQ-75883
to the Contractor
2. The Notice inviting tender, general instruction to bidders and all other
documents of this tender shall form part of the contract
3. No receipt for any payment alleged to have been made by a Contractor in
regard to any matter relating to tender of the contract shall be valid and
binding on the Corporation unless it is signed by the Engineer-in-Charge.
4. As per provisions of Income Tax Act, Corporation shall deduct Income Tax at
the applicable rate.
5. Agency has to note that the extension of Time limit/excess saving in the
works if required to approve, than it shall be processed as per the provision
of DoP and will take time for process the same.
6. The contract is inclusive of the cost of materials required to complete the
work in totality.
7. It will be absolutely incumbent on the contractors to have on the site of work
only such of the materials as have been duly passed by the Engineer-in-
charge. Materials that have been rejected must on no account be allowed to
remain on the site, and in spite of written order to do so, any such rejected
materials is on the site beyond a period of 48 hours’ notice, the Engineer-in-
charge shall have the right to remove it, at the risk and cost of the
contractors and even to destroy it.
8. It must be distinctly understood that conditions of contract and of claims in
respect of extra work, will not be allowed unless the works to which they
relate is clearly without the spirit and meaning of the specifications or
unless such works are ordered in writing by the Engineer-in-charge and
claimed for in specified manner.
9. Contractor will be asked to present the sample of materials, and the
approved samples will be preserved at the site of work, and no change in the
approved sample will be allowed, without the written permission of the
Engineer-in-charge.
10. The department reserves the right to make any change in the design and the
plans of the works. The contractor shall be bound to carry them out at the
rates tendered. No claim or compensation will be allowed on this account.
11. The contractor shall keep instruction book on site, for taking site
instructions from time to time. This book shall be made available on site
whenever asked for.
12. Above construction equipment brought to site shall be allowed to be taken
out only after the work for which it has been brought is over. The equipment
shall be taken out only with the specific permission in writing from the E.I.C.
Only the equipment required for the work and in fit condition shall be
brought to the site. The Contractor shall ensure that proper documentation
is followed at entry gate of GSECL's premises for such items which shall be
carried back by Contractor after completion of work.
13. The Contractor shall provide all temporary ladders, scaffolding materials,
platforms, supports and other necessary facilities required for trimming &
cutting of trees. The Contractor shall provide sufficient, strong and safe
staging so as to ensure safety of the laborers.
14. The Contractor shall provide sufficient fencing, notice Corporations and
lights to protect and warn others as may be considered necessary by the
GSECL and safety authority.
15. The GSECL may during the progress of work, order the removal of part or
whole of the work executed, found not in accordance with the approved
drawings, specifications/ instructions. No extra claims shall be entertained
for re-executing or altering of such work.
16. On completion of the work, the site shall be left in good order and the excess
materials, scraps, debris, if any shall be removed and dumped by the
Contractor at place/places as designated by the GSECL. The Contractor
shall also dismantle and remove the staging and other temporary facilities
like stores, offices, labor camp etc. on completion of work.
17. Contractor is required to maintain proper records at site of work in addition
to normal routine requirement of own office. The records to be maintained
shall include but not limited to the following:
(a) Daily Progress Record.
(b) Work Site Order Book.
EW- 270 PUR-F-006 RFQ-75883
(c) Instruction by GSECL's Officers.
(d) Test Registers of other materials/fittings, fixtures, equipment as
stipulated in the tender.
(e) Register for Working Details.
(f) Log Book of Defects.
(g) Hindrance Register giving details of commencement and removal of
each hindrance.
(h) Supply and consumption registers of all materials shall be maintained.
(i) Day to day Record of used/received materials shall be entered in the
register and signed by the Site Engineer of the GSECL as well as
contractors' representative at site.
(j) Measurement Book.
77. SALES TAX ON WORK CONTRACT
The Gujarat Government by its amendment to the Gujarat sales tax
act has also made works contract subject to Sales Tax. However works
contract tax shall be liability of the contractor and shall be born by the
contractor. More ever you shall also have to submit form No 702 as
prescribed by Gujarat Sales Tax act while submitting invoice.
More ever the purchaser will not pay any composite tax/turnover
tax/works contract tax which contractor has to pay as per act. Hence
the incidence of sales tax or such type of taxes shall not be payable by
the purchaser in any case even if such taxes are levied on the
party/contractor at a future date.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES
LIST OF SAFETY TOOLS
EW- 270 PUR-F-006 RFQ-75883
TENDER & CONTRACT FOR WORKS
I/We hereby tender for the Gujarat State Electricity Corporation Ltd. (herein Referred
as “Corporation”) of the work specified in the underwritten memorandum within the
time specified in Schedule B (memorandum showing items of work to be carried out)
and in accordance, in all respect, with the specifications, design, drawings and
instructions in writing and as per annexed conditions of contract and agree that when
the materials for works are provided by the Corporation, such materials and rates to
be paid for them shall be as provided in Schedule A hereto.
MEMORANDUM
(a) General description of work : “ Providing and fixing New G.I Sheet in
ESP 3 in place of corroded sheet and other Misc. Civil Work of ESP at
Gandhinagar TPS”.
(b) Estimated cost : Rs. …………………/-
(c) Earnest money : Rs. 1, 48,653.00 /-
(d) Security deposit : As per cl. no.7 of Section C (i.e. General
condition of contract).
(e) Time allowed for the completion of work from date of written order to commence.:
11 (Eleven Months)
Should this tender be accepted, I/We hereby agree to abide by and fulfill all the terms
and provision of the conditions of contract annexed hereto as applicable and in default
thereof forfeit and pay to the Corporation, the sums of money mentioned in the said
conditions.
Receipt No. Date from the Gujarat State Electricity Corporation Ltd. in respect of the
sum of Rs____________________________________. (The amount to be specified in
figures and words) is herewith forwarded representing the earnest money (the full
value of which is to be absolutely forfeited to the Corporation, should I / we do not
execute / commence the work after issuance of date of commencement by
Signature of the Contractor:
Address of the Contractor:
Dated__________________ day of _______________year
Signature of Witness:
Address of the Witness:
Occupation:
Dated__________________ day of _______________year
The above tender is hereby accepted by me on behalf of the Gujarat State Electricity
Corporation Ltd.
For & On behalf of GSECL
Chief Engineer (Gen)
GSECL GANDHINAGAR TPS
his duly authorized Assistant
EW- 270 PUR-F-006 RFQ-75883
General Safety Rules & List of Safety Tools.
“GENERAL SAFETY RULES / NORMS” TO BE OBSERVED BY THE CONTRACTORS
All the contractors working in Gujarat State Electricity Corporation Limited Factory
like Coal/Lignite/Gas/Hydro/Pumping Station shall have to strictly observe the
following Safety Rules. Concern principle contractors are responsible for informing &
observance of these rules by their supervisors/contract workers as well as the
owner/supervisors/ workers of sub-Contractors engaged, if any, by them for the work
contract awarded to them. Prior to commencement of the work, Contractor shall have to
submit a written assurance on their letterhead to the concerned Sectional Head /
Engineer-in-charge that they have thoroughly gone through these Rules, have educated
their employees / workers of their sub contractor and will strictly observe the said
Rules while execution of work under work contract awarded to them. They will have to
indemnify the company for any loss or damage / accident / injury to the company’s
property / employee or employee of their own in default of non - observing these rules.
(01) Cont rac tor s ho ul d issue pho to ga te pass fo r th eir wo rkers f rom
GSEC L Fact ory Mana ger a s p er Guj a rat Factor ies r ul es, 1963 &
detai ls shal l be fil l ed up in GSEC L gat e pass f orm at as pe r Aadh ar
car d / Electi on car d i d pr oof & t o foll ow th e gat e pass is su e pr ocedure
thro ugh concern department EE & SE, Security Officer, LWO/IRO/DGM, Factory
Medical Officer, Safety Officer/Dy. Safety Officer & Factory Manager.
(02) In case of emergency, temporary photo gate pass shall be issued by Security
Officer only for three days with prior permission of Factory Manager only. More
than three days, Permanent photo gate pass procedure shall be completed by
contract agency for their contract workers.
(03) Certificate of Fitness of employment in hazardous process & operations in form
no.33 of Gujarat Factories rules, 1963 shall be issued by GSECL Factory Medical
Officer for all contractor workers before commencement of work & examination
responsibility shall be taken by contractor as well as concerned Head of
Department .Pre-employment & Periodical medical examination of contractor
workers shall be carried out in form no.32 from GSECL Factory Medical Officer
after every six (06) months of contractor with their contractor workers. Contractor
shall be fulfilled all health requirements before commencement of work. After
completion of medical examination in form no.32/33, GSECL Factory Medical
Officer shall be signed in contract worker gate pass procedure format.
(04) Contract worker gate pass will issue after completion of safety induction 3D
animation movie & Training record is to be maintained in IMS/OHSAS training
format by TK Office/LWO.
(05) As per Gate pass format of GSECL, Safety Officer/Dy. Safety Officer shall be
checked the issue PPE to contract workers as per nature of job, Form no.10 of
lifting tools and tackles, Driving license, Electrical contractor license, Electrical
trade qualifications, Safety induction training, SOP, supervisor qualifications etc.
After fulfillment of all Safety compliances, Safety Officer/Dy. Safety Officer shall be
signed in Contract worker Gate pass procedure format.
(06) Work Contract shall be completed by principle contractor/agency/person who is
awarded the work order. Subletting of contract shall be allowed only if prior
approval of Power station chief before execution of work. Contractor/agency shall
be submitted the entire subletting contract documents with gate pass application
through concern department EE & SE, LWO/DGM, Safety Officer/Dy.Safety
Officer & Factory Manager.
(07) Under The Conditions Framed Under Rule-45 Of The Indian Electricity Rules,
1956, Valid Electrical contractor License shall be submitted to concern electrical
department EE/SE/Electrical Safety Officer/ Safety Officer/Factory Manager at the
time of apply gate pass by agency/party with latest renewal from Chief Electrical
Inspector, Gandhinagar- Gujarat. Electrical License photocopy shall be checked by
Concerned HOD of Electrical Department/Electrical Safety Officer/Dy.Safety
Officer/ Safety Officer/Factory Manager.
(08) As per nat ure o f job/work, qualified supervisor (Diploma (Electrical/
Mechanical/Civil/C&I) + 3 years experiences or ITI + 10 years) shall be engaged by
EW- 270 PUR-F-006 RFQ-75883
contract agency & qualification certificate with experience certificate shall be
submitted to concern EE/SE/LWO/IRO/DGM/ Dy. Safety Officer /Safety
Officer/Factory Manager at the time of apply gate pass.
(09) As per rule 3 of CEA regulation ,2010: Designating person(s) to operate and
carry out the work on electrical lines and Apparatus, Contract person/worker
possesses a certificate of competency or electrical work permit, issued by the
Appropriate Government. That means, Electrical trade Qualification of contract
worker/person like ITI-wireman/ Electrician, Diploma (Elect), BE/B. TECH (Elect),
ME/ M. TECH (Elect) shall be submitted to concern EE/SE/LWO/IRO/DGM, Dy.
Safety Officer/ Safety Officer/Factory Manager at the time of apply for photo gate
pass procedure.
(10) As per nature of job/work & during capital overhauling work /Annual overhauling
work /24X7 round the clock work/major shut down work, Qualified Safety
Officer/Manager/Supervisor (BE/Diploma (Elect/Mech./Civil) + PDIS-Post Diploma
in Industrial Safety) shall be engaged by contractor during dangerous
operations/dangerous works as well as day to day dangerous activities, safety
supervision, tool box talk, Safety awareness programme, SOP preparation with
hazards & its control measures with each step , checking of lifting tools & tackles,
hydra mobile crane, Safety precautions, coordination with Safety Department etc.
(11) License of driver shall be submitted with gate pass issue application as per nature
of vehicles & to follow the Motor vehicle Act,1988, the Central Motor Vehicles
(Amendment) Rules,2016 as well as Gujarat Motor Vehicles rules,1989 & driver
license shall be checked every day by security shift in charge before entry in the
Factory premises.
(12) SOP with JSA (Job Safety Analysis) shall be prepared by contractor through
competent person as per GFR, 1963 or Qualified Safety Officer as per GFR,
with 05 years experiences. SOP will review & approve by concern
JE/DE/EE/SE/Elect. Safety Officer/Dy. Safety Officer /Safety Officer/Factory
Manager before execution of work.
(13) It is compulsory to use standard make Personal Protective Equipments (P.P.Es.) as
per the job requirement. Do not work without use of required P.P.Es. Contractor is
responsible to provide standard make (ISI/DGMS/CE/EN/ANSI approved) & to
checked standard/make in PPE issue format by concern JE/DE/EE/SE/Safety
Officer/Factory Manager. Personal Protective Equipments / Safety Gadgets suitable
to give sufficient protection against hazards involved in their work / job to their
staff, as per the job requirement and insist / enforce their workers to put on the
same while at works.
The ongoing work is liable to be stopped at any time if your contract workers/staffs
found working without P.P.Es. Following is the list of various P.P.Es (as per
ISI/DGMS/CE/ EN/ ANSI approved only) to be used for various works / worksites.
In any work, Contractor shall be issued the minimum 05 nos. of PPEs like Safety
Shoes, Safety Helmet, Safety goggles, Mask & Reusable Ear plug to their
workers/supervisor compulsory & it will check by concern section HOD & Dy.
Safety Officer /Safety Officer at the time of gate pass procedure.
Industrial Safety Helmet For protection of head against falling objects or
during fall of person from height. Yellow Colour
helmet is used for contract worker with agency
Safety Goggles/welding For protection of eyes against flying particles / dust,
goggles/chemical splash chemical splash, welding spark, arc, flashover etc.
Full Face shield For protection of face against flying particles / dust,
chemical splash, spark, arc, flashover etc.
Reusable Earplug / Ear For ear / hearing system protection while working
muffs. in high noise level area.
Chemical suit/Gas tight suit For body protection against chemicals, oils, sharp
/Fire proximity suit/FR edged objects, heat, hot objects etc.
Boiler Suit
Safety Hand Gloves For protection of hands against chemicals, oils,
sharp edged objects, heat, hot metals/objects,
EW- 270 PUR-F-006 RFQ-75883
electricity etc.
Safety shoes/ Gum Boots For protection of leg/feet against falling objects,
with sharp edged objects, heat, hot metals/objects,
Oil/Chemical/water/heat/ electricity etc..
Electrical resistance etc.
Safety Belt(full body For fall prevention while working at heights or in
hardness with double depth, working in vessel or in confined space.
lanyard & shock absorber) /
Rope / Life line / Fall
arrestor etc.
Dust Mask/Respirator with Protection of respiratory system against dust.
valve(FFP2)
Chemical Cartridge Protection against toxic chemical fumes /
Respirator with full face gases/vapors/dust etc.
mask type A2B2E2K2
Trolley mounted Air line Working in oxygen deficient zone or confine space
respirators with full face area
Portable Single gas detector Working in hazardous storage/process area
like Chlorine, Ammonia,
Hydrogen, etc
Portable Multi gas Detector Working in oxygen deficient zone & use in entry of
( LEL,O2,CO,H2S,SO2, etc) confine space & Major fire
Automatic voltage detector To check the present voltage or induction voltage of
electrical equipments/ bus/switch gears from
(one) feet distance before starting the any electrical
Auto darkening welding The new auto darkening welding helmet combines
helmet (EN 379 & EN 175 legendary Speed glass quality and auto darkening
Level-B) with PAPR as per technology with an innovative wide-view grinding
EN 12941:1998, class TH2 visor to give welders an all-in-one solution for more
and AS/NZS 1716 flexibility, precision, and efficiency.
Respiratory System is a combined face and
breathing protection device, for increased comfort
and safety in welding. The unit is equipped with a
particle filter which removes particles from the air.
The unit provides a constant airflow independent of
filter combinations and clogging. The unit can also
be equipped with a gas filter (for example A1B1E1).
The unit supplies air to the head top via the
connecting breathing tube. The airflow creates a
slight positive pressure which together with the
sealing to the face prevents particles and other
contaminants from entering the head top.
(14) All PPEs (as per ISI/DGMS/CE/EN/ANSI approved only) Should issued by
party/agency/contractor to their contractor workers as per nature of job and
allotment of PPE list shall be submitted to Safety Officer, Dhuvaran on his letter
head as per below mentioned format by Contractor before commencement of work
through concerned JE,DE,EE/SE .
Sub: Issue of PEE to Contractor workers
Sub of work Order:
Work order no.
Name of Agency:
Date of Commencement:
Time limit for work order:
Sr. Name Desig Name of Name of PPE IS Make Qty Un Date Receivin
no. of natio Section :Code of it of g
worke n under no. of PPE issu signatur
rs work PPE e e
EW- 270 PUR-F-006 RFQ-75883
Safety Helmet No
Safety goggles No
Reusable Ear Pai
Dust Mask No
Safety Shoes Pai
(15) Shift Security Inspector/Security Officer shall be checked Safety Shoes & Safety
Helmet of all contractor workers at entry gate of Factory Premises & shall entered
contractor workers with Safety Shoes & Safety Helmet with photo ID Gate Pass.
(16) Shift Security Inspector/Security Officer shall be checked validity of Gate pass of
all contractor workers on daily basis.
(17) During the work execution, one trained & competent supervisor of agency should
always remain present at work site. Concern JE/DE of GSECL shall be supervised
the contract work as per SOP .
(18) Approved NABL laboratory calibration certificates of
electrical/mechanical/Civil/C&I/Environment survey/Chemical etc measuring
/testing equipments/instruments which are used during contract work shall be
submitted before starting the work & shall be checked by concern JE/DE/EE
before starting work & it’s record shall be maintained in concern section.
(19) The contractor shall take all the required safety measures prior to commencement
of work on dangerous substances, machineries or area at which cautionary notice
is displayed and obtain “Line Clear” or “Work Permit” through the concern
Department / Section JE/DE and shall be informed to concern section JE/DE for
closed/ returned after completion of work.
(20) Safety talk/Safety work instructions shall be given to contractor workers by
concern JE/DE regarding hazards of specific work, risk & it’s control measure
(mentioned in HIRA) before starting the job work and records shall be maintained
for each & every job works.
(21) Display Safety instructions shall be strictly followed by all workers who are working
in factory premises.
(22) Material Safety Data Sheet (MSDS) of each chemical shall be available with Chief
Chemist/Control room & work related Chemical information shall be taken by
contractor & contractor workers from Concern EE/Chief Chemist before starting of
chemical handling work.
(23) The contractor shall be checked & securely covered or securely fenced any opened
fixed vessel, sump, tank, pit or opening in ground or in floor which, by reason of its
depth, situation, construction or contents ,is or may be a source of danger before
starting the work each & every days or after interval/recess. Contractor supervisor
shall be informed to concerned HOD regarding any unsafe conditions.
(24) Prohibition of smoking, fires, lights, spontaneous ignition substance, matches;
fuses, mobile phone etc are to be strictly followed by all workers who are working in
factory premises.
(25) Prior to carrying out welding, gas cutting, furnace heating or any other hot work
job, remove all the inflammable material lying at or nearby worksite or cover it
properly by suitable protective covering. Also, special care shall be taken before
carrying out such job & see that all possible contributing factors to set fire shall be
removed / vanished prior to commencement of the work. Advance intimation shall
be given to concerned section / fire section to commence the work in fire prone
areas. They should also keep ready all the First Aid Fire Extinguishers /
equipments & fire extinguishing media / material like sand / water buckets or
other appropriate equipment at such place.
EW- 270 PUR-F-006 RFQ-75883
(26) While carrying out work in confined space or inside vessel, obtain necessary
“Confined Space / Vessel Entry Permit” from concerned department prior to
commencement of the work.
For lighting in such areas, only 24-volt (ISI certified & with proper guard) hand
lamp shall be used. For taking care of the persons working inside the confined
space / vessel, a supervisor / person capable to keep continuous watch on
person(s) working inside, assist them in case of emergency or arrange to get
immediate outside help, shall remain present at entry point. Use full body safety
belt without failed.
While working inside sewage, trench or in-depth, a person to warn outsiders /
entrants / passers etc shall remain available near entry point or the entry point
shall be cordoned by a barricaded tape with a cautionary notice. After completion
of the works, all the lids / covers / grills / grits opened, shall be re-fixed / re-
placed in the original position as it were prior to commencement of the work and
leave the work place in safe condition in all respect, so as to prevent accident to
fellow workers.
(27) The contractor shall see that he / his persons do not work on or block (by stacking
material, spare parts, tools-tackles, equipments etc), any passages / walkways /
gangways / aisles / staircases / ladders / lifts or any other approaches / roads
leading to plans or its auxiliaries, on which there is traffic movements or possible
traffic movements in case of emergency. Such passages are meant for safe escape
in the event of emergency. If it is utmost necessary to carry out work in such area
with blocking of passage, prior permission of Competent Authority or the Engineer-
In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon
it using barricading tape & display suitable caution notice or keep a person to
restrict / divert the traffic on this route through other safe passage.
(28) The contractor shall see that he / his persons do not work on or block (by stacking
material, spare parts, tools-tackles, equipments etc), any passages / walkways /
gangways / aisles / staircases / ladders / lifts or any other approaches / roads
leading to plans or its auxiliaries, on which there is traffic movements or possible
traffic movements in case of emergency. Such passages are meant for safe escape
in the event of emergency. If it is utmost necessary to carry out work in such area
with blocking of passage, prior permission of Competent Authority or the Engineer-
In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon
it using barricading tape & display suitable caution notice or keep a person to
restrict / divert the traffic on this route through other safe passage.
(29) Prior to use power / electrically operated hand tools / equipments / machines /
gadgets like welding machine, hand grinder, hand drill etc, ensure for its safe
operation & use it only if it is found safe to use. Do not use defective, unsafe or
improperly maintained equipments.
The electrical power supply required to run such equipments shall not be taken
directly at their own but shall be obtained through concerned Electrical
Maintenance Departments or their authorized persons or under their observations
/ guidance only. The Electrical Section shall provide temporary electrical
connection up to contractor’s Mains Board on which it is compulsory to install
mains switch, ELCB & fuses of adequate capacity. All such equipments shall
invariably be earthed adequately to prevent electrical shock, sparking, short circuit
etc. Power cord to be used shall be of adequate capacity, without any joint & shall
consist of earth wire also. Hence, it is necessary to use adequate capacity 3-wire
power cord for single & 5-wire power cord for three phase power connections. The
plugs, receptacles, pins, holders etc shall be of adequate capacity & safe to use.
All electrical & mechanical equipments / tools-tackles viz. welding machine, cutting
machine, Grinder, Drill, Chain Pulley Blocks, Hook chooks etc required to be used
during work execution shall be of standard make & bear ISI certification mark on it.
The consumables like welding electrodes, grinding wheels / discs etc which has
specific prescribed life span shall not be used in any case if its expiry date is over.
(30) Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be used by
Electrical contractor for safe use in areas where hazardous, flammable, or
combustible vapors, liquids, dusts, or residues may be present in Gas Based
power plant and list of tools and tackles shall be submitted with technical bid.
EW- 270 PUR-F-006 RFQ-75883
Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be checked by
JE/DE before commencement of Electrical work.
(31) Before using lifting machines / tackles (like C.P.Bs., Hook chooks, winch, forklift,
mobile crane, EOT crane etc) & its attachments (like D-shackles, slings, U-clamps,
Eye bolts or any fixtures), it shall be checked and used only if found safe to use.
Also, ensure that these are tested, examined & certified in form no.10 by
Competent Person as per the Factory act-1948 & Gujarat Factories Rules and its
validity do not expire. Further, it shall be fixed properly and firmly prior to lifting
the weight. Valid Test certificate of all Lifting machines used by Contractor to
be submitted to Dy.Safety Officer/ Safety Officer before commencement of
work through concerned EE/SE.
(32) Metal Scaffoldings to be used for working at height shall be of adequate size &
capacity. Obtain the work permit when working at height. While climbing on such
scaffolding or working on any structure at height, use of full body safety belt /full
body hardness with double lanyard & Fall arrestor & Helmet is compulsory. It is
also necessary to fasten chinstraps of the helmet.
(33) Contractor or their employee shall not interfere in day-to-day routine plant
activities / works except the work assigned to them, shall not loiter in the areas
other than their work jurisdiction, as well as shall not temper / operate / touch the
machineries/equipments/auxiliaries with which they are not concerned. Also, the
contractor shall strictly instruct their staff for not to sit or take rest at/near/below
running plants, auxiliaries, systems or any place which is risky, hazardous &
prone to accident.
(34) The cylinders containing poisonous / toxic or inflammable / explosive gas like
Oxygen, Acetylene, LPG, Hydrogen, Ammonia, Chlorine, CO2 etc shall be handled
safely taking due care. To handle / shift such cylinders a special trolley /cage
meant for it must be used but in no case it should be rolled.
(35) In Gas Based Power station/Hydrogen storage area /Hydro carbon fumes-vapour
generated area, Spark arrestor (as per approved manufacturer of CCOE, Nagpur)
shall be provided on each vehicle by party/agency and it will check by shift
security in charge before entry of vehicles in the factory premises.
(36) No women or young person shall be employed or permitted to work in Lead-
compound area like battery room etc. as per schedule VI of GFR
(37) No women or young person shall be allowed to clean, lubricate or adjust any part of
a prime mover or of any transmission machinery while the prime mover or
transmission machinery is in motion. Examination or operation of motion
machinery shall be made or carried out only by a specially trained adult male
worker wearing tight fitting clothing as per section 22 of factories act
(38) In all risky job, before start the work, contractor should obtain General Safety
Work Permit through concerned section from Shift –in-charge well in advance.
(39) In case of noticing smoke or fire during their work execution, they shall make
immediate efforts to extinguish / control it and simultaneously inform the Fire
Station Mobile No as well as Station Fire Officer or Emergency Control room no
which is displayed at prominent place of factory like Main Security Gate, All unit
control room, Canteen area, Safe Assembly points, Fire Station, All security gates,
Occupational Health Centre.
(40) In case of any injury / accident while working, it shall immediately be reported to
Safety Department through concerned Sectional Head / Engineer. The prescribed
Form No. 21 & ANNEXURE may be obtained from concerned section or Dy.Safety
Officer/Safety Officer.
In case of any electrical accident, it shall immediately be reported to Electrical
Safety Officer through concern Sectional Head / Engineer. The prescribed
Electrical accident form no. A as per electricity act-2003 & Form No. 21 &
ANNEXURE as per Gujarat Factories rules shall be filled up by concern
department JE/DE with written consent of contractor. The Form may be obtained
from concerned Electrical section or Electrical Safety Officer. Electrical accident
investigation shall be carried out by Electrical Safety Officer with Factory Manager.
After any reportable accident, Contract agency shall be submitted the fitness
certificate of injured person with endorsement of GSECL factory Medical Officer to
LWO/Dy.Safety Officer/Safety Officer/Electrical Safety Officer then after injured
person may allow for work.
EW- 270 PUR-F-006 RFQ-75883
(41) For any incident occurred but have no injury to any persons should also reported
as per GSECL format and informed to Dy.Safety Officer/Safety Officer as Near Miss
(42) Safety penalty shall be imposed against violation by contract workers: if any
contract worker worked in a factory contravenes any provision of factories act or
any rules or orders made there under. Imposing any duty or liability on workers,
contractors/agency shall be punishable with fine which mentioned as under.
Sr. Description of penalty Amount
(i) Work without PPEs Rs.300/- per person
(ii) Work without work Safety permit like working at Rs.1000/- per day
height, confine space entry, hot work etc.
(iii) License of driver as per type of vehicles not registered. Rs.750/- per person
(iv) Welding work without flashback arrestor/double Rs.1000/- per set
gauge regulator set
(v) Operate Portable power tool without ELCB Rs.1000/-per
(vi) Work without qualified Supervisor as per nature of job Rs.1000/-per day
like mechanical, electrical, civil, C&I, chemical etc.
(vii) Work without SOP & JSA Rs.2000/-per day
(viii) Work without test report of lifting machines / tackles Rs.2000/- per
(like C.P.Bs., Hook chooks, winch, forklift, mobile equipment
crane, EOT crane etc) & its attachments (like D-
shackles, slings, U-clamps, Eye bolts or any fixtures)
in Form No.10 of Gujarat Factories Rules,1963
(ix) Work without Double lynyer Safety belt during Rs.3000/-per
working at Height work, work without anchoring in person
hook/line line
(x) Work without 24 Volt supply in Confine space area Rs.3000/-per
(xi) (a) Grinding machine used without safety guard/ Rs. 500/- per
machine guard equipment/ per set
(b) Unsafe welding machine like open body. Knob
without insulation. Connection without plug
(c) Damaged welding cables/gas pipelines
(d) Welding work doing without welding blanket.
(e) Electrical supply without 3 pin plug/industrial
(f) Use of damaged electrical wire for
lighting/equipments.
(g) Use of lighting lamp without cage.
(h) Use of open halogen tube.
(i) Use of damaged PPEs/use of non standard PPEs
(j) Unsafe lifting and handling of gas cylinders
(k) Cylinder handling without safety cap
(l) Temporary connection without ELCB. etc
During plants visit/supervision of concern JE/DE/EE,SE. Safety officer/Dy. safety
officer. Electrical safety officer , factory manager, if they will observed any safety
violations as per CO circular/statutory requirements then they must imposed
safety penalty through office note directly against contract workers/contract
agency and Office Note process through proper channel to concern sectional head
and Account head for recovery purpose. Photograph/CCTV Footage is to be put a
with penalty note by imposing officer.
(43) Party will damage any fire equipments or property or machinery in factory during
execution of work, total damage cost will be recovered from party RA bill and
recovery Office note put up by concern HOD.
(44) All the relevant labour and industrial laws shall also be followed compulsorily.
EW- 270 PUR-F-006 RFQ-75883
(45) After completion of work, cotton waste, grease, oil, unused material, welding rod
pieces, scrap etc. are to be removed by contractor and scrap shall be deposited to
scrap yard of Main Store.
(46) For performance evaluation of contractor, safety factors of work accident, fire
incident & near miss accident will be considered. Steps can be taken to review the
job assignment up to cancellation for negligence.
(47) Over & above these, contractor shall have to follow all the safety requirements
/rules & regulations / norms and legal provisions laid down in various statutes.
Particularly the provisions of The Factories Act-1948 & the Gujarat State Factories
Rules-1963 (Amended up to date), The Electricity Act-2003 & rules, BOCW
Act/Rules shall be followed strictly. The contractor shall also obey the rules /
regulations / instructions of the local Competent Authority for safety & health
requirements.
(48) The above rules shall be scrupulously followed and where required, Contractor
/contractor workers may contact to the Dy.Safety Officer/Safety Officer/Electrical
Safety Officer in case of any ambiguity or needs further guidance in this regard.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE - I
EW- 270 PUR-F-006 RFQ-75883
ON STAMP PAPER OF Rs.300/-
FORM OF BANKER’S UNERTAKING
(For Security Deposit for work period as per Terms and Conditions of
We, Bank of ______________________________________________ hereby agree unequivocally
and unconditionally to pay immediately on demand in writing from the Gujarat State
Electricity Corporation Limited, or any Officer authorized by it in this behalf any
amount up to and not exceeding Rs.__________ (in words) Rupees
to the said Gujarat State Electricity Corporation Limited on behalf of
M/s.___________________________________________________ who have entered into a
contract for the supply / works specified below :
L.O.I. No. _____________________________________________________ dated ______________.
This agreement shall be valid and binding on this Bank up to and inclusive
of________________ and shall not be terminable by notice or by change in the
constitution of the Bank or the firm of Contractors / Suppliers or by any other reason
whatsoever and our liability hereunder shall not be impaired or discharged by any
extension of time or variations or alterations made, given conceded or agreed, with or
without our knowledge or consent, by or between parties to the said within written
Notwithstanding anything contrary contained in any law for the time being in force or
banking practice this Guarantee shall not be assignable, transferable by the beneficiary
(i.e. GSECL or Subsidiaries). Notice or invocation by any person such as assignee,
transferee or agent of beneficiary shall not be entertained by the Bank. Any invocation
of the Guarantee can be made only by the beneficiary directly
“NOT WITHSTANDING” anything contained herein before, our liability under this
guarantee is restricted to Rs._______________ (Rupees
_______________________________________________________ only). Our guarantee shall
remain in force until _______________ (date of validity of the Guarantee). [Unless
demands or claims under this Bank Guarantee are made to us in writing on or before
_____________ (date of validity of the Guarantee), all rights of Beneficiary under this
Bank Guarantee shall be forfeited and we shall be released and discharged from all
liabilities there under]:
Please Mention here Complete Postal Signature of
Address of the Bank with Branch Code, Bank’s Authorized Signatory
Telephone and Fax Nos. with Official Round Seal
EW- 270 PUR-F-006 RFQ-75883
NAME OF DESIGNATED BANKS: (Annexure – I.)
A Guarantees issued by following banks will be accepted as SD/EMD on
permanent basis.
1. All Nationalized Banks.
B Guarantees issued by following Banks will be accepted as SD/EMD for
period up to March 31, 2026. The validity cut-off date in the GR is with
respect to date of issue of Bank Guarantee irrespective of date of
termination of Bank Guarantee.
1. AXIS Bank
2. A U Small Finance Bank
3. Bandhan Bank
4. Barclays Bank
5. City Union Bank
6. CSB Bank
7. DBS Bank India Limited
8. DCB Bank
9. Equitas Small Finance Bank
10. ESAF Small Finance Bank
11. Federal Bank
12. HDFC Bank
13. HSBC Bank
14. ICICI Bank
15. IDBI Bank
16. IDFC First Bank
17. Jammu and Kashmir Bank
18. Jana Small Finance Bank
19. Karnataka Bank
20. Karur Vysya Bank
21. Kotak Mahindra Bank
22. South Indian Bank
23. Standard Chartered Bank
24. Tamilnadu Mercantile Bank
25. Utkarsh Small Finance Bank
26. Yes Bank
27. Ahmedabad Mercantile Co-Operative Bank
28. Nutan Nagrik Sahakari Bank Ltd.
29. Rajkot Nagrik Sahakari Bank Limited.
30. Sarswat Co-Operative Bank Ltd.
31. SBPP Co-operative Bank LTD
32. SVC Co-Operative Bank Ltd.
33. The Cosmos Co-op Bank Ltd.
34. The Gujarat State Co-Operative Bank
35. The Mehsana Urban Co-Operative Bank Ltd.
36. The Surat District Co-operative Bank
37. The Surat Peoples Co-operative Bank Ltd.
38. The Kalupur Commercial Co-operative Bank
39. The Panchmahal District Co-operative Bank
40. The Baroda District Co-operative Bank
41. Baroda Gujarat Gramin Bank
42. Saurashtra Gramin Bank
EW- 270 PUR-F-006 RFQ-75883
EMD BANK GUARANTEE FORMAT
FOR TENDER /ENQ. NO. ___________________________________
(BANK GUARANTEE ON NON-JUDICIAL STAMP PAPER OF Rs.300)
WHERE AS M/s. _______________________________________________________________
(Name and Address of the Firm) having their registered Office at
_________________________________________________(Address of the Firm’s registered
Office) (hereinafter called the Tenderer) wish to participate in the Tender
No.__________________________ for______________________________________ of (supply /
Erection / Supply & Erection / Work) of __________________________________ (Name of
the material / equipment / work) for _________________________ Gujarat State Electricity
Corporation Limited and WHEREAS a Bank Guarantee for (hereinafter called the
“Beneficiary”) Rs. _____________ (Amount of EMD) valid till ____________ (mention here
date of validity of this Guarantee which will be 4 (FOUR) months beyond initial validity
of Tender’s offer) which is required to be submitted by the Tenderer along with the
(Name of the Bank and address of the Branch giving the Bank Guarantee) having our
registered Office at _____________________ (Address of Bank’s registered Office) hereby
give this Bank Guarantee No. _________________dated ____________ and hereby agree
unequivocally and unconditionally to pay immediately on demand in writing from the
Gujarat State Electricity Corporation Limited or any Officer authorized by it in this
behalf any amount not exceeding Rs.____________ (amount of EMD) (Rupees
______________________________________________________) (in words) to the said Gujarat
State Electricity Corporation Limited on behalf of the Tenderer.
We, ____________________________________________ (Name of the Bank) also agree that
withdrawal of the tender or part thereof by the Tenderer within its validity or non-
submission of Security Deposit by the Tenderer within one month from the date of
tender or a part thereof has been accepted by the Gujarat State Electricity Corporation
Limited would constitute a default on the part of the Tenderer and that this Bank
Guarantee is liable to be invoked and encased within its validity by the Beneficiary in
case of any occurrence of a default on the part of the Tenderer and that the encased
amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank up to and inclusive
of____________________ (mention here the date of validity of Bank Guarantee) and shall
not be terminated by notice or by Guarantor change in the constitution of the Bank or
EW- 270 PUR-F-006 RFQ-75883
the Firm of Tenderer or by any reason whatsoever and our liability hereunder shall not
be impaired or discharged by any extension of time or variations or alterations made,
given, conceded with or without our knowledge or consent by or between the Tenderer
and the Gujarat State Electricity Corporation Limited.
Notwithstanding anything contrary contained in any law for the time being in force or
banking practice this Guarantee shall not be assignable, transferable by the beneficiary
(i.e. GSECL or Subsidiaries). Notice or invocation by any person such as assignee,
transferee or agent of beneficiary shall not be entertained by the Bank. Any invocation
of the Guarantee can be made only by the beneficiary directly.
NOTWITHSTANDING anything contained hereinbefore our liability under this
Guarantee is restricted to Rs. ________ (amount of EMD) (Rupees
________________________________________ (in words). Our Guarantee shall remain in
force till _____________ (date of validity of the Guarantee). Unless demands or claims
under this Bank Guarantee are made to us in writing on or before ___________ (date of
validity of the Guarantee), all rights of Beneficiary under this Bank Guarantee shall be
forfeited and we shall be released and discharged from all liabilities there under.
Please mention here complete Postal Signature of the
Address of the Bank with Branch Code, Bank’s authorized
Telephone and Fax Nos. Signatory with Official Seal.
EW- 270 PUR-F-006 RFQ-75883
GUJARAT STATE ELECTRICITY CORPORATION LIMITED- GTPS
INTEGRITY PACT
OUR ENDEAVOUR
To create an environment where Business Confidence is built through Best Business
Practices and is fostered in an atmosphere of trust and respect between providers of
goods and services and their users for the ultimate benefit of society and the nation.
GSECL’S COMMITMENT PARTY’S COMMITMENT
To maintain the highest ethical Not to bring pressure recommendations
standards in business and from outside GSECL to influence its
professions. decision..
Ensure maximum transparency to Not to use intimidation, threat,
the satisfaction of stakeholders. inducement or pressure of any kind on
GSECL OR ANY OF it’s employees
under any circumstances.
To ensure to fulfill the terms of To be prompt and reasonable in
agreement/contract and to consider fulfilling the contract, agreement, legal
objectively the view point. obligations.
To ensure regular and timely To provide goods and / or services
release of payments on due dates timely as per agreed quality and
for work done. specifications at minimum cost to
To ensure that no improper demand To abide by the general discipline to be
is made by employees or by anyone maintained in our dealings.
on our behalf.
To give maximum possible To be true and honest in furnishing
assistance to all the information.
Vendors/Suppliers/Service Provider
and other to enable them to
complete the contract in time
To provide all information to Not to divulge any information,
suppliers/contractors relating to business details available during the
contract / job which facilitate him course of business relationship to
to complete the contract / job others without the written consent to
successfully in time. GSECL.
To ensure minimum hurdles to Not to enter into carter / syndicate
vendors / suppliers / contractors in /understanding whether formal / non
completion of agreement / contract formal so as to influence the price.
/ work order.
Seal & Signature Seal & Signature
(GSECL’s Authorized Signatory) (Party’s Authorized Person)
Name : Name:
Designation:
Name : Name:
Designation:
EW- 270 PUR-F-006 RFQ-75883
On Firm’s Letter Head
CERTIFICATE - A
I / We ________________________________________________ authorized signatory of
M/s._________________________________________________here by Certify that
M/s. _____________________________________________ is not related with other firms who
have submitted tenders for the same items under this inquiry / Tender.
Signature of the Tenderer
Designation
Seal of the Firm
EW- 270 PUR-F-006 RFQ-75883
GENERAL GUIDELINES RELEVANT TO I.S.
EW- 270 PUR-F-006 RFQ-75883
GENERAL GUIDELINES RELEVANT TO IS
Please refer latest edition of relevant Indian Standard Specification of Code
i.e. B.I.S. General relevant I.S. of B.I.S. shall prevail for all items including
materials, measurements etc.
The Item wise detailed specifications are intended for full description of
items covered by Schedule “B”. The specifications are not however intended
to cover every detail and the works shall be executed according to the spirit
of the specifications below and the best prevailing P.W.D. practice. The
clarification to any clause in detailed specifications shall be sought from the
latest edition of relevant I.S. specification and codes. Where these
specifications are at variance with the specification laid down in the I.S.
Books stated above, the former will be applicable. As regarded matters not
covered by any of the above specification, the decision of the Engineer-in-
charge shall be treated as final and shall be binding upon the contractor.
The contractor is expected to get clarified any doubt about specification, etc.
before tendering by discussing with Engineer-in-charge.
For detail technical specification, the item wise description along with above
general specifications shall hold good.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
EW- 270 PUR-F-006 RFQ-75883
SPECIAL CONDITIONS FOR USE OF CEMENT IN WORK
1 The rates in Schedule – ‘B’ is inclusive of cement cost. Contractor has to purchase fresh
grade cement confirming to as per IS 8112 Or PPC IS 1489 (Part-I) or as per tender condition.
2 Contractor has to construct pucca Go down at site of work so that cement bags can be properly
preserved to avoid damage due to any kind of water/Humidity.
3 Contractor has to bring sufficient quantities of cement bags to maintain progress of work. The
work should not suffer for want of cement.
4 Cement should be used to achieve required strength in cement concrete or as per item
proportion.
5 To bring sufficient & timely cement at site is full responsibility of contractor. Nothing extra will
be paid on account of any reason to maintain progress of work and to complete the work in
schedule time.
6 Contractor has to submit material A/c. For consumption of cement used with every bills. In
case of not submitting the same, bill will not be passed. Party has to submit the copy of cement
purchased bill and Challan/invoice along with each RA Bill/Final Bill.
7 No negative variation will be allowed for consumption in cement less then prescribed as per R &
B SoR OR Corporation/mix design and nothing will be paid extra for over consumption.
8 Contractor is fully responsible for safety of cement at site; nothing will be paid extra on account
of safety.
9 If Corporation’s authorized representative wants to check cement stock at site, contractor has to
allow for the same at any time.
10 Contractor has to maintain day to day cement consumption / balance account at site.
11 As far as possible, contractor has to maintain supply of cement of only one brand & grade
throughout the work and on account of closer/shortage of approved brand, cement of other
brand in accordance of condition No. (1) Will be allowed by Engineer – in – Charge.
12 Minimum cement consumption considered for cement concrete having grade of M–15 / M – 20 /
M – 25 / is 320 Kgs. / 375 Kgs / 400 Kgs. respectively. Contractor has to use minimum cement
as above. Contractor should not use less than the prescribed quantities of cement even in the
case of mix design recommends lower quality. For other items cement consumption shall be as
per provisions of SoR without any negative variation. Nothing will be paid extra for over
consumption.
13 Contractor will be allowed to carry out work only after physical verification of cement brought at
14 Full cement bags brought by contractor shall be entered at IN GATE of GANDHINAGAR TPS.
EW- 270 PUR-F-006 RFQ-75883
Approved name of Manufacturers: Allowing using steel
cementing being supplied by contractors in civil works
Sr. Name of approved Cement Sr. Name of Approved Steel
No. Company & their Brand Name in No Manufacturers & their Brand Name
Market in Market
1 A.C.C. Cement A.C.C. 1 Tata Iron & Steel TATA
2 Ambuja Cement Ambuja 2 Jindal JINDAL
3 Binani Cement Binani 3 Lloyds Lloyds
4 Birla Cement Birla A-1 4 Essar Steel Ltd. Essar
5 Gujarat Sidhee Sidhee 5 Steel Authority of SAIL
Cement India.
6 J.K. Cement J.K. 6 Parmeshwar Steel God TMT
7 J.K. Laxmi Cement J.K. Laxmi 7 Gallant Ispat Ltd. Gallant TMX
8 Sanghi Cement Sanghi 8 Aditya Ultra Steel KAMDHENU
Pvt. Ltd. NXT& Kay
9 Saurastra Cement Hathi 9 Mono steel India MONO TMT
10 Shree Digvijay KAMAL 10 Aashiana Rolling Friends Steel
Cement Mills Ltd.
11 India Cement Corromandal 11 Electro Therm (I) ET TMT
King Ltd.
12 Ultratech Cement Ultra-tech 12 H.K Ispat Pvt Ltd Kothi
13 HI-BOND Cement HI-BOND 13 SRJ peety steel Pvt. Shree Om
Ltd. TMT/ SRJ
TMT/ Kapila
Pune steel
14 Shree Cement Ltd Shree/Bangur 14 Nilkanth Concast Nilkanth
/Rock Private
strong/Roofo Limited
n/Bangur 15 Shreeyam Power & National
Power Steel
Industries Limited
16 Utkarsh Bars Utkarsh
Private Limited
CONSTRUCTION CHEMICALS 17 Bhagyalaxmi Polad
Rolling Mill Pvt. Ltd
1 Red-Wop Rajkot 18 Shri Khatu Shyam Khatu TMT
Alloys Pvt.
2 Samrock Chemicals Ahmedabad 19 Steefo Steels LLP, STEEFO TMT
20 Haq Steel & GERMAN TMX
Metaliks Ltd. Kutch
Water Proofing 21 K.B. Ispat Private KB TMT
& Wrapping Coating Ltd.,
1 Bitumag Industries Vadodara 22 VMS TMT Private KAMDHENU
Ltd., NXT& Kay
Ahmedabad TMT
2 A.R. Industries Vadodara 23 Briskon Multi Sabarkantha
metals LLP
3 Tiki tar Danosa Halol 24 Kalika Steel Alloys KALIKA
(India) Pvt Ltd Pvt Ltd. Jalna TMT
4 STP Ltd Ankleshwar 25 Anjar TMT steel pvt Welspun
EW- 270 PUR-F-006 RFQ-75883
Flooring Tiles 26 Shri Bajrang Power Goel TMT &
& Ispat Ltd Pipes
27 Rajuri steels & TMT Rajuri steel
Bars Pvt Ltd
28 SMW steel Sangam
1 Asian Granito Himatnagar 29 Rathi steel & Metal Icon steel
2 Somany Kaloal 30 Metarolls Ispat Pvt Metarolls TMT
3 Simpolo Morbi
4 Varmora Morbi
5 Sunheart Morbi
6 Emcer Morbi
7 Cengres Ahmedabad
In addition to the above Approved Vendor List of GSECL, the approved vendor
list of GUVNL and its subsidiary company i.e. GSECL/GETCO/MGVCL
/PGVCL/DGVCL & UGVCL which are available on their website- in tender head
including above mention various manufacturers are also to be treated as
Approved Vendors.
EW- 270 PUR-F-006 RFQ-75883
GENERAL GUIDELINES RELEVANT TO IS
Please refer latest edition of relevant Indian Standard Specification of Code
i.e. B.I.S. General relevant I.S. of B.I.S. shall prevail for all items including
materials, measurements etc.
The Item wise detailed specifications are intended for full description of items
covered by Schedule “B”. The specifications are not however intended to cover every
detail and the works shall be executed according to the spirit of the specifications
below and the best prevailing P.W.D. practice. The clarification to any clause in
detailed specifications shall be sought from the latest edition of relevant I.S.
specification and codes. Where these specifications are at variance with the
specification laid down in the I.S. Books stated above, the former will be applicable.
As regarded matters not covered by any of the above specification, the decision of
the Engineer-in-charge shall be treated as final and shall be binding upon the
contractor. The contractor is expected to get clarified any doubt about specification,
etc. before tendering by discussing with Engineer-in-charge.
For detail technical specification, the item wise description along with above
general specifications shall hold good.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
GENERAL SPECIFICATIONS
01. In the specifications, “as directed”/”Approved” shall be taken to mean “as
directed”/”approved” by the Engineer-in-charge.
02. Wherever a reference to any Indian Standard appears in the specifications, it
shall be taken to mean as a reference to the latest edition of the same in force on
the date of agreement.
03. In “Mode of Measurement” in the specification wherever a dispute arises in the
absence of specific mention of a particular point or aspect, the provisions on
these particular points or aspects in the relevant Indian Standards shall be
referred to.
04. All measurements and computations, unless otherwise specified, shall be carried
out as per Latest IS:
05. The distance which constitutes lead shall be determined along the shortest
practical route and not necessarily the route actually taken. The decision of the
Engineer-in-charge in this regard shall be taken as final.
06. Where no lead is specified, it shall mean “all leads”.
07. Lift shall be measured from plinth level.
08. Up to “floor two levels” means actual height of floor up to 6.5 Mt. Above plinth
09. Definite particulars covered in the items of work, though not mentioned or
elucidated in it, specification shall be deemed to be included therein.
10. Reference to specifications of materials as made in the detailed specification of
the items of work is in the form of a designation containing the number of the
specification of the material and prefix ‘M’ e.g. ‘M-5’.
11. Approval to the samples of various materials given by the Engineer-in-charge
shall not absolve the contractor from the responsibility of replacing defective
material brought on site or materials used in the work found defective at a later
date. The contractor shall have no claim to any payment or compensation
whatsoever on account of any such materials being rejected by the Engineer-in-
12. The contract rate of the item of work shall be for the work completed in all
13. No collection of materials shall be made before it is got approved from the
Engineer-in-charge.
14. Collection of approved materials shall be done at site of work in a systematic
manner. Materials shall be stored in such a manner as to prevent damage,
deterioration or intrusion of foreign matter and to ensure the preservation of
their quality and fitness for the work.
15. Cement, reinforcements bars & all other materials to be used shall be got
approved from EIC before starting of work. The cement, reinforcement steel &
other materials to be brought at site shall be entered at GANDHINAGAR, TPS
main entry gate.
16. Materials, if and when rejected by the Engineer-in-charge, shall be immediately
removed from the site of work.
17. No materials shall be stored prior to, during and after execution of a structure in
such a way as to cause or lead to damage or overloading of the various
components of the structure.
18. All works shall be carried out in a workmanlike manner as per the best
techniques for the particular item.
19. All tools, templates, machinery and equipment for correct execution of the work
as well as for checking lines, levels, alignment of the works during execution
shall be kept in sufficient numbers and in good working condition on the site of
20. The mode, procedure and manner of execution shall be such that it does not
cause damage or over loading of the various components of the structure during
execution or after completion of the structure.
21. Special modes of construction not adopted in general Engineering practice, if
proposed to be adopted by the Contractor, shall be considered only if the
contractor provides satisfactory evidence that such special mode of construction
EW- 270 PUR-F-006 RFQ-75883
is safe, sound and helps in speedy construction and completion of work to the
required strength and quality. Acceptance of the same by the Engineer-in-charge
shall not, however, absolve the contractor of the responsibility of any adverse
effects and consequences of adopting the same in the course of execution of
completion of the work.
22. All installations pertaining to water supply and fixtures thereof as well as
drainage lines and sanitary fittings shall be deemed to be completed only after
giving satisfactory tests by the Contractor.
23. The contractor shall be responsible for observing the rules and regulations
imposed under ‘Minor Minerals Act’ and such other laws and rules prescribed by
Government from time to time.
24. All necessary safety measures and precaution [including those laid down in the
various relevant Indian Standards shall be taken to ensure the safety of men,
materials and machinery on the works as also of the work itself.
25. The testing charge of all materials shall be borne by the Contractor unless
recovery at one percent towards using charges is separately made.
26. Approval to any of the executed items for the work does not in any way relieves
the contractor of his responsibility for the correctness, soundness and strength
of the structure as the drawings and specification.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 270 PUR-F-006 RFQ-75883
TECHNICAL SPECIFICATIONS
sheet and other Misc. Civil Work of ESP at Gandhinagar TPS”.
01. In the specifications, “as directed”/”Approved” shall be taken to mean “as
directed”/”approved” by the Engineer-in-charge.
02. In “Mode of Measurement” in the specification wherever a dispute arises in the absence
of specific mention of a particular point or aspect, the provisions on these particular points, or
aspects - the relevant Indian Standards shall be referred to.
03. All measurements and computations, unless otherwise specified, shall be carried out
nearest to the following limits:
a. Length, width and depth (height) -----------0.01 Meter.
b. Areas-------------------------------------------- 0.01 sq Mt.
c. Cubic Contents-------------------------------- 0.01 Cu. Mt.
04. The distance which constitutes lead shall be determined along the shortest practical
route and not necessarily the route actually taken. The decision of the Engineer-in-charge
in this regard shall be taken as final.
05. Where no lead is specified, it shall mean “all leads”.
06. Lift shall be measured from plinth level.
07. Reference to specifications of materials as made in the detailed specification of the items
of work is in the form of a designation containing the number of the specification of the material
and prefix ‘M’ e.g. ‘M-5’.
08. Approval to the samples of various materials given by the Engineer-in-charge shall not
absolve the contractor from the responsibility of replacing defective material brought on site or
materials used in the work found defective at a later date. The contractor shall have no claim to
any payment or compensation whatsoever on account of any such materials being rejected by
the Engineer-in-charge.
09. The contract rate of the item of work shall be for the work completed in all respects.
10. No collection of materials shall be made before it is got approved from the Engineer-in-
11. Collection of approved materials shall be done at site of work in a systematic &
sequantial manner. Materials shall be stored in such a manner as to prevent damage,
deterioration or intrusion of foreign matter and to ensure the preservation of their quality and
fitness for the work.
12. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed
from the site of work.
13. All tools, templates, machinery and equipment for correct execution of the work as well
as for checking lines, levels, alignment of the works during execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
14. Special modes of construction not adopted in general Engineering practice, if proposed to
be adopted by the Contractor, shall be considered only if the contractor provides satisfactory
evidence that such special mode of construction is safe, sound and helps in speedy construction
and completion of work to the required strength and quality. Acceptance of the same by the
Engineer-in-charge shall not, however, absolve the contractor of the responsibility of any
adverse effects and consequences of adopting the same in the course of execution of completion
of the work.
15. All installations pertaining to water supply and fixtures thereof as well as drainage lines
and sanitary fittings shall be deemed to be completed only after giving satisfactory tests by the
Contractor.
16. The contractor shall be responsible for observing the rules and regulations imposed
under ‘Minor Minerals Act’ and such other laws and rules prescribed by Government from time
17. The testing charge of all materials shall be borne by the Contractor & reports of authorize
laboratory shall be submitted timely.
18. Approval to any of the executed items for the work does not in any way relieves the
contractor of his responsibility for the correctness, soundness and strength of the structure as
per the drawings and specification.
19. Due care at all the items shall be taken to see that no damage is caused to the existing
setup of GSECL. In case of any such damage is caused, it shall be restored by the agency at his
EW- 270 PUR-F-006 RFQ-75883
NOTE: BOOKLET FOR “GENERAL TECHNICAL SPECIFICATIONS FOR BUILDING WORKS”
OF R. & B. DEPARTMENT, GOG, GUJARAT AND BOOKLET OF “GENERAL SPECIFICATION
FOR CIVIL WORKS” OF GSECL WILL BE AVAILABLE IN CIVIL OFFICE AT GANDHINAGAR
TPS FOR REFERNCE OF RELEVANT DETAIL SPECIFICATIONS OF ITEMS. SHALL BE
CONSIDERED & ADOPTED IN WORK.
DETAILED TECHNICAL SPECIFICATIONS
ITEM NO.1: Dismantling of sheet roofing including ridges, hips, Valleys, Gutters
etc stacking of serviceable materials and disposal of unserviceable materials with
all lead and lift. (1) GI Sheet roofing
1.0. Workmanship: 1.1. The relevant specification of item No.1 shall be followed except
that the G.I. sheet roofing shall be dismantled instead of Brick work.
2.0. Mode of measurements & payment :
2.1. The area of G.I. sheet roofing shall be measured in sq. meter. Ridge, hips and valley
shall be girthed and included with roof area. Corrugated and semi-corrugated surfaces
shall be measured flat and not girthed.
2.2. Supporting member such as rafters, purlins, beams, joints, trusses etc., Shall be
measured separately.
2.3. The rate shall be including disposal of unserviceable materials with all leads and lifts
and stacking the serviceable materials as directed.
2.4. The rate shall be for a unit of one sq. Meter.
ITEM NO. 2: Dismentaling of sheet roofing including ridges, hips, Valleys, Gutters
etc stacking of serviceable materials and disposal of unserviceable materials with
all lead and lift. (A.C. Sheet Roofing).
1.0. Workmanship: 1.1. The relevant specification of item No.1 shall be followed except
that the A.C sheet roofing shall be dismantled instead of Brick work.
2.0. Mode of measurements & payment :
2.1. The area of G.I. sheet roofing shall be measured in sq. meter. Ridge, hips and valley
shall be girthed and included with roof area. Corrugated and semi-corrugated surfaces
shall be measured flat and not girthed.
2.2. Supporting member such as rafters, purlins, beams, joints, trusses etc., Shall be
measured separately.
2.3. The rate shall be including disposal of unserviceable materials with all leads and lifts
and stacking the serviceable materials as directed.
2.4. The rate shall be for a unit of one sq. Meter.
ITEM NO. 3: Brick work using common Fly ash building brick having crushing strength
not less than 50 kg./sq.cm. In Super Structure in cement Mortar 1:6 (1- cement : 6 -fine
sand ) ( C ) Fly Ash Bricks above plinth level up to floor level. C) Fly Ash Brick
1.0 Materials:
Water shall confirm to M-1, Cement shall confirm to M-3, Sand shall confirm to M-6, Bricks
– M 15. Admixture is confirm to the manufacture specification and apply accordingly.
2.0 Workmanship:
Fly ash bricks (cement bonded) shall be locally made. Bricks shall have smooth rectangular
faces with sharp and square corners. Bricks shall be hand or machine molded and shall be
made from the admixture of suitable good quality of fly ash, sand and cement as per the
composition mentioned below:
FLY ASH: 50-60%
CEMENT: 8-12%
EW- 270 PUR-F-006 RFQ-75883
The fly ash bricks will be as per latest relevant IS code. The bricks will be of dimension as
per standard clay brick, suitable for making 230mm thick full brick wall, 115mm thick half
brick wall and 75mm thick minor partition walls, as applicable, as per
drawing/specification/BOQ. A maximum tolerance of (+/-) 2mm shall be allowed as the
manufacturing tolerance. The bricks shall have frog of 100 mm in length 40 mm in width
and 10 to 20 mm deep of one of its flat sides.
The bricks when tested in accordance with the procedure laid down in IS 3495 (part 2):
1992 after immersion in cold water for 24 hrs. water absorption shall be within 13-15% by
weight. Similarly, the porosity of the fly ash bricks shall be within 12-20%. The bricks shall
have a minimum crushing strength of 50 Kg/Cm Sq. Bricks shall be tested in a Govt.
Approved laboratory at the cost of contractor. Bricks shall be allowed to use after
satisfactory result. Mortar that can be utilized within initial setting time of the cement shall
be mixed with water. Mortar shall be prepared on pucca platform or on steel plate’s
platform. Mortar shall be uniformly mixed dry and then required quantity of water shall be
added. If work demands mixing or mortar in mixture, same shall have to be arranged
without any extra cost.
All joints vertical and horizontal shall be properly racked out to a depth of 12mm when
mortar is green and soft. The exposed faces of walls are to be provided with flush joint.
Brickwork shall be cured with water for a period of 10 days, keeping constantly moist.
During rainy season green work shall have to be protected from rain, by covering it with
suitable covering.
Work shall be measured in volume any opening more than 0.5 sq. Meter areas shall be
deducted. No payment shall be made for keeping in masonry any pipe, and sleeves etc.,
supplied by department. Thickness of brickwork shall be paid as per standard practice half
brick, full brick, 1 ½ bricks etc. as shown on drawings.
2.1 Proportion:
2.1.1 The proportion of the cement mortar shall be 1: 6 (1 cement: 6 fine sand) by volume.
2.2 Wetting of bricks: The bricks required for masonry shall be thoroughly wetted with
clean water for about two hours before use or as directed. The cessation of bubbles, when
the bricks are wetted with water is an indication of through wetting of bricks.
2.3 Laying:
2.3.1 Bricks shall be laid in English bond unless directed otherwise. Half or cut bricks shall
not be used except where necessary to complete to bond closers in such case shall be cut to
required size and used near the ends of walls.
2.3.2 A layer of mortar shall be spread on full width for suitable length of the lower course;
each brick shall first be properly bedded and set home by gently tapping lapping with
handle of trowel or wooden mallet. It side face shall be flushed with mortar before the next
brick is laid and pressed against it. On completion of course, the vertical joints shall be
fully filled from the top with mortar.
2.3.3 The walls shall be taken up truly in plumb. All courses shall be laid truly horizontal
and all vertical joint shall be truly vertical. Vertical joints in alternate course shall generally
be directly one over the other. The thickness of brick course shall be kept uniform.
2.3.4 The brick shall be laid with frog upwards. A set of tools comprising of wooden straight
edges, mason’s sprit level, square half meter rub, and pins, string and plumb, shall be kept
on the site of work for frequent checking during the progress of work.
2.3.5 Both the faces of walls of thickness greater than 23 cms. Shall be kept in proper
place. All the connected brick work shall be kept not more than one meter over the rest of
the work. Where this is not possible the work shall be raked back according to bond (and
not left toothed) at an angle not steeper than 45 degrees.
2.3.6 All fixtures, pipes, outlets of water, hold fasts of doors and windows etc which are
required to be built in wall shall be embedded in cement mortar.
2.4 Joints:
2.4.1 Bricks shall be so laid that all joints are quite flush with mortar. Thickness of joints
shall not exceed 12 mm. The face joints shall be raked out as directed by taking tools daily
during the progress of work, when the mortar is still green so as to provide key for plaster
or pointing to done.
2.4.2 The face of brick shall be cleaned the very day on which the brick work is laid and all
mortar dropping removed.
2.5 Curing: Green work shall be protected from rain suitably. Masonry work shall be kept
moist on all the faces for a period of seven days. The top of masonry work shall be kept well
wetted at the close of the day.
2.6 Preparation of foundation bed: If the foundation is to be laid directly on the excavated
bed the bed shall be leveled, cleared of all loose materials, cleaned and wetted before
starting masonry. If masonry is to be laid on concrete footing the top of concrete shall be
EW- 270 PUR-F-006 RFQ-75883
cleaned and moistened. The contractor shall obtain the engineer’s approval for the
foundation bed, before foundation masonry is started. When puccas flooring is to be
provided flush with the top to plinth the inside plinth offset shall be kept lower than the
outside plinth top by the thickness of the flooring.
3.1 Mode of measurement and payment:-
3.1.1 Measurement shall be made per CMT of Brickwork at site.
3.1.2 Rate shall be for unit of one CMT of Brickwork at site.
ITEM NO. 4: Providing 15mm thick cement plaster in single coat on Rough (Similar)side
of single or half brick walls for interior plastering upto floor two level and finished even
and smooth in (i) Cement mortar 1:3 (1-cement:3-sand)
1.0. Materials:
1.1. Water M-1. The cement mortar proportion 1:3 shall conform to M-13.
2.0. Workmanship :
2.1. Scaffolding: Wooden ballics, bamboos, planks, trestles and other scaffolding shall be
sound. These shall be properly examined before erection and use. Stage scaffolding shall be
provided for ceiling plaster which shall be independent of the walls.
2.2. Preparation of back-ground:
2.2.1. The surface shall be cleaned of all dust, loose mortar droppings, traces of algae,
afforescence and other foreign matter by water or by brushing. Smooth surface shall be
roughened by wire brushing if it is not hard and by racking if it is hard. In case of concrete
surface, if a chemical retarder has been applied to the form work, the surface shall be
roughened by wire brushing and all the resulting dust and loose particles cleaned off and
care shall be taken that none of the retarders is left on the surface. Trimming of projections
on brick/concrete surface where necessary shall be carried out to get an even surface.
2.2.2. Racking of joints in case of masonry where necessary shall be allowed to dry out for
sufficient period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If
the surface becomes dry such area shall be moistened again.
2.2.4. For external plaster, the plastering operation shall be started from top floor and
carried downwards. For internal plaster, the plastering operations may be started whenever
the building frame and cladding work are ready and the temporary supporting ceiling
resting on the wall of the floor have been removed. Ceiling plaster shall be completed before
starting plaster to walls.
2.3. Applications of plaster :
2.3.1. The plaster about 15 x 15 cms shall be first applied horizontally and vertically at not
more than 2 meters intervals over the entire surface to serve as gauge. The surfaces of
these gauges shall be truly in plane of the finished plastered surface. The mortar shall then
be applied in uniform surface slightly more than the specified thickness, and then brought
to a true surface by working a wooden straight edge reaching across the gauges with small
upward and sideways movement at a time. Finally, the surface shall be finished off true
with a trowel or wooden float according as a smooth or a sandy granular texture is required.
Excessive toweling or over working the float shall be avoided. All corners, arises, angles
and junctions be truly vertical or horizontal as the case may be and shall be carefully
finished. Rounding or chamfering corners, arises junctions etc shall be carried out with
proper templates to the size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water. Any mortar
or plaster which is partially set shall be rejected and removed forthwith from the size.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the
line both horizontally and vertically. When recommending the plaster, the edges of the old
work shall be scraped clean and wetted with cement putty before plaster is applied to the
adjacent areas to enable the two to properly join together. Plastering work shall be closed
at the end of the day on the body of the wall and nearer than 15 cm to any corners or
arises. Horizontal joints in plaster work shall not also occur on parapet tops and copings
as these invariably load to leakage. No portion of the surface shall be left out initially to be
packed up later on.
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a
minimum period of 7 days. Moistening shall commence as soon as plaster is hardened
sufficiently. Soaking of walls shall be avoided and only as much water as can be readily
absorbed shall be used, excessive evaporation on the sunny or windward side of building in
EW- 270 PUR-F-006 RFQ-75883
hot air or dry weather shall be prevented by handing mattings or gunny bags on the outside
of the plaster and keeping them wet.
3.0. Mode of measurements & payment :
3.1. The rate shall include the cost of all materials, labour and scaffolding etc involved in
the operations described under workmanship.
3.2. All plastering shall be measured in square meters unless, otherwise specified, Length,
breath or height shall be measured correct to a centimeter.
3.3. Thickness of the plaster shall be exclusive of the thickness of the key i.e. Grooves or
open joints in brick work, stone work etc. Or space between laths. Thickness of plaster
shall be average thickness with minimum 10 mm at any point on this surface.
3.4. This item includes plastering up to floor two levels.
3.5. The measurement of wall plastering shall be taken between the walls or partition
(dimensions before plastering being taken) for length and from the top of floor or skirting to
ceiling for height. Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings. Flowing soffits shall be
measured separately.
3.7. For jambs, soffits, sills etc. For openings not exceeding 0.5 Smt. Each in area for ends
of joints, beams, posts, girders, steps, etc. Not exceeding 0.5 sq. Mtr Each in area and for
openings exceeding 0.5 sq. Mt. And not exceeding 3.00 sq. Mt. In each area deductions and
additions shall be made in the following manner:
(a) No deductions shall be made for ends of joints, beams, posts etc. And openings not
exceeding 0.5 Smt. each and no addition shall be made for reveals, jambs, soffits, sills etc.
Of these opening for finish to plaster around ends of joints, beams, posts etc.
(b) Deduction for openings exceeding 0.5 Smt but not exceeding 3.0 Smt each shall be
made as follows and no addition shall be made for reveals, jambs, soffits, sills etc. of these
(i) When both faces of all walls are plastered with same plaster, deduction shall be made for
one face only.
(ii) When two faces of wall are plastered with different types of plaster or if one faces is
plastered and the other pointed, deductions shall be made from the plaster or pointing on
the side of frame for door, window etc. On which width of reveals is less than that on the
other side but no deductions shall be made on the outer side. Where widths of reveals on
both faces of all are equal, deductions of 50% of area of opening on each face shall be made
from area of plaster and/or pointing as the case may be.
3.8. For openings having door frames equal to projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
3.9. In case of openings of area above 3.0 Smt each, deduction shall be made for opening
but jambs, soffits and sills shall be measured.
3.10. The rate shall be for unit of one sq. Meter.
ITEM NO. 5: Providing corrugated G.I. Sheet of class-3 roofing fixed with glavanished iron
J or L Hook, Bolts and nuts 8mm diameter with bitumen and G.I. Limpet washer or G.I.
Limpet washer. Filled with white lead complwtw excluding the cost of purlins, Rafters and
Trusses (1) 0.80 mm thick sheet.
1.0 Materials: Corrugated G. I. Sheets shall conform to M-23 and as per manufacturer’s
specification.
Providing and fixing TATA /JINDAL/ ESSAR make corrugated G.I Sheet of class-3 as
per item specification.
2.0 Workmanship :
2.1 Spacing of purlines : One purlin shall be provided at the ridge and one at the caves.
The spacing of other purlines for 0.8 mm. Thick G. I. Sheet shall not exceed 1.80 meter. The
purlin shall coincide with the center line of the end lap. The ridge purlins shall be placed in
such a way that the ridges can be fixed properly. The portion over handing the wall support
shall not be more than one fourth of the spacing of purlins.
2.2 The top surface of the purlins shall be painted before the sheets are fixed over them.
Embedded portions of purlins shall be finished with two coats of coal-tar.
2.3 Laying of sheets :
2.3.1 The sheets shall be laid in purlins to a true plane with the line of corrugations truly
parallel or normal to the sides of area to be covered. The sheets shall not generally be built
into gables and parapets. They shall be bent up along their side edges clost to the wall and
EW- 270 PUR-F-006 RFQ-75883
the junction shall be protected by suitable flushing or by projecting drip course.
2.3.2 The laps at end shall be provided 150 mm. Minimum for roof slopes 1 in 2 (1 vertical
: 2 horizontal) and steeper but 200 mm. Shall be provided for flatter slopes than those
above. The side lap shall be provided two ridges of corrugations at each side.
2.3.3 The sheets shall be but to the dimensions of the shape of the roof either along their
lengths or their width or in slant across the line of corrugations at hips and valleys. The
sheets shall be cut carefully with a straight edge and chisel to give straight finish. The
sheets shall be laid such that the laps are turned away from the usual direction of local
heavy rain.
2.3.4 Fixing of Sheets :
2.3.4.1 Sheets shall be fixed to the purlins or other roof members such as hips of
valley rafter etc. With ‘J’ or ‘L’ galvanized hook bolts and galvanised nuts 8 mm. Dia with
bitumen impact washers and G. I. Washers. Limpet washers with white lead shall be used.
Length of hook bolt shall be varied to suit the site requirement. Bolts shall be sufficiently
long so that after fixing the project above the top of their nuts by not less than 12 mm. The
grip of ‘J’ or ‘L’ hook bolts on the side of purlins shall not be less than 25 mm. There shall
be minimum of three hooks bolts placed at the ridge of corrugations in each sheets in every
purlin and their spacing shall not exceed 300 mm. Coach screw shall not be used for fixing
the sheets to purlins.
Where the slopes of roof are not less than 2½ horizontal). (1 vertical : 2½ horizontal). Sheets
shall be jointed together at the side laps by galvanished iron bolts and nuts 25 mm. X
mm. Size each bolt with a bitumen and G. I. Limper washer filled with white lead. Where
the overlaps at the sides extend to two corrugations these bolts shall be placed zigzag over
the two over lapping corrugations so that the ends of the overlapping sheets are drawn
tightly towards each other. The spacing of same bolts shall not exceed 600 mm. Along each
of the staggered rows.
2.3.5 Holes for all bolts shall be drilled and not punched in the ridges of the corrugations
from the under side while the sheets are on the ground. The holes in the sheets shall be at
least 50 mm. From the edge. Sheets drilled wrongly shall be rejected. The holes in the
washers shall be of the exact diameter of hook, bolts or the seam bolts. The nuts shall be
tightened from above to give a leak-proof roof.
2.3.6 The roof when complete shall be true to lines and slopes and shall be lead-proof.
3.0 Mode of measurements & payment :
3.1 The measurements of the C.G.I. sheet roof shall be taken for finished work in
superficial area in general plane (not girthed on the roof). The lapse between the C.G.I.
sheets both at their ends and along the side edges shall not be measured. The overlaps of
C.G.I. sheets over the valley piece and their under lap under the ridge, hip and flashing
piece shall be included in the measurements.
3.2 No deductions in measurements shall be made for openings for chimney stacks, sky
light etc. Of area upto 0.40 sq. Mt.nor extra be paid for extra labor in cutting and for extra
labor in cutting and for wastage etc. In forming such openings.
3.3 The rate of roof shall include the cost of all materials and labor involved in all
operations described above. The rate also includes the cost of provision, erection and
removal of the scaffolding, benching, ladders, templates and tools required for the proper
erection and completion of the work. The rate includes the cost of purloins, rafters and
The rate shall be for a unit of one sq. Meter.
ITEM NO. 6: Providing ridges or hips 600 mm overall in plain G.I. Sheet class-3 fixed with
G.I.J. Or L Hooks and nuts 8mm dia. G.I. Limpet and bitumen washer complete (1)
mm thick sheet
1.0 Materials : The G. I. Valley gutters and ridges shall conform M-23 A.
2.0 Workmanship :
EW- 270 PUR-F-006 RFQ-75883
2.1 The relevant specifications of item No. 9 shall be followed except that the work shall be
carried out for ridges of hips. The overlaps for ridges and hips or either side over the C.G.I.
sheets and end legs shall be minimum 225 mm. Width of the ridges and hips shall be as
described in the item.
2.2 Ridges shall be fixed to the purlins with same 8 mm. Dia. G. I. Hook bolts and nuts and
bitumen and G. I. Limpet washers, which fix the sheets for the purline. Hips shall be fixed
to the roof members with the same 8 mm. Dia. G. I. Hook bolts and nuts and bitumen and
G. I. Limpet washers which fixed the sheets. At least one of the fixing bolts shall pass
through the end laps of the ridges and hips on other sides. If this is not possible, extra hook
bolt shall be provided. End laps of ridges and hips shall be jointed together by galvanized
iron seam bolts and G. I. Washers. There shall be at least two such bolts in each end lap.
2.3 Ridges and hips shall fit in squarely on the sheets.
3.0 Mode of measurements & payment :
3.1 The measurements of ridges or hips shall be taken for finished work in length along
their center lines.
3.2 No laps shall be measured.
3.3 The payment for ridges and hips be made in a similar way as incase of C. G. I. Sheet
The rate shall be for a unit of one running meter
ITEM NO. 7: Providing and fixing 150mm wide 450mm over all semicircular /rectungular
shape in plain G.I sheet class-3 gutter with iron brackets 40mm x 3mm size Bolts, Nuts,
Washers etc. Including making necessary connection with rain water pipes (i) 0.80mm
thick sheet.
1.0 Materials : 1.1 These shall be of plain galvanised sheets Class-3 of 0.80 mm.
Thickness. The gutter shall be desired to carry the maximum discharge from the roof
without flowing over and shall be constructed wherever possible with shrunk channel or
2.0 Workmanship :
2.1 The longitudinal edges shall be turned back to the extent of 12 mm. And beaten to form
a rounded edge. The ends of the sheets at junction of pieces shall be hooked into each other
and beaten flush to avoid leakages.
2.2 The size of gutters shall be as specified in the item.
2.3 The gutter shall be laid with a minimum fall 1 in 120 Gutter shall be true to line and
stop and shall be supported on fixed M. S. Flat iron brackets bent to shape or any other
suitable bracket.
3.0 Mode of measurements & payment :
3.1 The measurements of gutters shall be taken for finished work in length along their
centerlines. No laps shall be measured.
3.2 The rate of gutter shall include the cost of all labor and materials specified above
including all specials such as angles, junctions, drop ends or funel shaped connecting
piece, stop ends etc. Flat iron brackets and bolts and nuts required for fixing the latter to
the roof members.
3.3 The rate shall be for a unit of one running meter.
ITEM NO. 8: White washing with lime on wall surface ( one coats ) to give an even shade
including thoroughly booming the surface to remove all dirt, dust; mortar drops and loose
scales of lime wash and other foreign matter.
1.0. Materials :
1.1. The elearcolle shall be made from glue and boiling water by Mixing 1 kg. Mixture shall
be suitably tinted where required for use under coloured distemper if directed. Glue shall
conform to I.S. 852-1969 (Specifications for animal glue). 1.2. Line used shall be freshly
burnt class ‘C’ Lime (fat lime) and white in colour conforming to I.S. 712-1973/ Water shall
EW- 270 PUR-F-006 RFQ-75883
conform to M-1 Best quality of gum shall be used in the preparation of white wash.
Ultramarine blue or Indigo : This shall conform to I.S. 55-1970 for points, and shall be used
for preparation of white wash. Pigments : Mineral colours, not affected by lime shall be
used in preparing colour wash.
2.0. Workmanship: 2.1. Preparation of white wash solution:
Surface already white or colour. The fat lime shall be slaked at site and shall be mixed and
stirred with about five litres of water for 1 kg. Of unslaked lime to make a thin cream. This
shall be allowed to stand for a period of 24 hours and then shall be screened through a
clean coarse cloth, 4 kg. Of gum dissolved in hot water shall be added to each cubic metre
of lime cream. Small quantity of ultramarine blut (Upto 3 gms. Per kg. Of lime) shall also
be added to the last two coats of white wash solution and the whole solution shall be stirred
thoroughly before use.
2.1. Preparation of surface:
2.2.1. The surface shall be thoroughly cleaned of all dust, dirt, mortar croppings and other
foreign matter before white wash is to be applied.
2.2.2. The surface spoiled by smoke soot shall be scraped with steel wire brushes or steel
scrapers or shall be rubbed with over-burnt surkhi or brick bats. The surface shall be then
broomed to remove all dust, dirt and shall be washed with clean water.
2.2.3. Oil or grease spots shall be removed by suitable chemical and smooth surface shall
be rubbed with wire brushes.
2.2.4. All unsound portion of the surface plaster shall be removed to full depth of paster in
rectangular patches and plastered again after raking the masonry joints properly. Such
portion shall be wetted and allowed to dry. They shall then be given one coat of white wash.
2.2.5. All unnecessary nails shall be removed, the holes cracks patches etc. Shall be made
good with materials similar in composition to the surface to be prepared.
2.3. Scaffolding: Wherever scaffolding is necessary it shall be erected in such a way that
as far as possible on part of scaffolding shall rest against the surface to be white or colour
washed. A properly secured strong and well tied suspended platform (Zoola) may be used
for white washing of ceilings proper stage scaffolding shall be erected where necessary.
2.4. Application of white wash :
2.4.1. On the surface so prepared the white wash shall be applied with “Moon” brush. The
first stoke of the brush shall be from top downwards, another from bottom upwards over
the first stroke and similarly one stoke from the right another from the left, over the first
stroke brush before it dries. This will from one coat. Each coat shall be allowed to dry
before next coat is applied. Number of coats as specified in item shall be applied. It shall
present smooth and uniform finish free from brush marks and it should not come off easily
when rubbed with finger.
2.4.2. Splashing and dropping if any on the doors and windows, ventilators etc. Shall be
removed and the surface cleaned.
2.4.3. Priming and Alkali resistant treatments, scraping of surface washing etc. Surface
spoiled by smoke soot removed of oil and great spots treatment for infection with
efflorensence moulds moss, funji algae and litchen and patch repairs to plaster.
Wherever done shall not be paid extra.
3.0. Mode of measurements & payment :
3.1. All the work shall be measured in the decimal system as under :
(a) Dimensions shall be measured to the nearest 0.01 M.
(b) Area in individual items shall be worked out to the nearest 0.01 Sq.mt.
All the work shall be measured in sq.mt. Deductions for jambs, soffits, sills etc. For
opening not exceeding 0.5 sq.mt. Each in area for ends of joints, posts, beams, girders,
steps etc. Not exceeding 0.5 sq.mt. Each in area and for opening exceeding 0.3 sq.mt. And
not exceeding 3.0 sq.mt. Each in area deductions and additions shall be made as under :
3.2. No deductions shall be made for ends of joints beams, posts etc. And openings not
exceeding 0.5 sq.mt. Each. No addition shall be made for reveals, jambs, soffits, sills etc. Of
these openings :
EW- 270 PUR-F-006 RFQ-75883
(a) When both the faces or walls are provided with finish, deduction shall be made for one
face only.
(b) When each face of walls are provided with different finish deduction shall be made for
that side of frame for door, windows etc. On which width of reveals is less than that of the
other side, where width of reveals on both faces of wall are equal, deduction of 50% of area
of opening on each face shall be made from total area of finish.
(c) When only one face of wall is treated and the other face is not treated, full deduction
shall be made if the width of reveal on the treated side is less than that on the untreated
side, but if the width of the reveal is equal or more than on the untreated side neither
deductions nor additions be made for reveals, jambs, soffits, sills etc.
3.4. In case of area of opening exceeding 3 sq.mt. Each, deduction shall be made for
openings but jambs, soffits, shall be measured.
3.5. No deduction shall be made for attachment such as casing, conducts, pipe, electric
wiring and the like.
3.6. Corrugated surfaces shall be measured flat as fixed and not girth. The quantities so
measured shall be increased by the following percentage and the resultant shall be included
with the general areas.
(a) Corrugated steel sheets 14%
(b) Corrugated A.C. sheets 20%
(c) Semi Corrugated A.C. sheets 10%
(d) Nainital pattern roof (Plain sheeting with rolls) 10%
(e) Nainital pattern roof (with corrugated sheets) 25%
3.7. Cornices and other wall features, when they are not picked out in a different
finish/colour shall be girthed and included in the general area.
3.8. The rate shall include the cost of all materials, labour, scaffolding, protective measures
etc. Involved in all the operations described above.
3.9. The rate shall be for a unit of one sq.mt.
ITEM NO. 9: Providing & applying two coats of exterior premium emulsion paint
(excluding priming coat) of approved brand and make as mentioned below on existing
plastered surface including finishing & thinning as per manufacturer’s specifications. A
gap of 6 hrs should be given between 2 subsequent coats. The work should be carried out
strictly as per manufacturer’s specifications and requirement including scaffolding,
jhoolas etc., complete as directed by E.I.C. 1. Asian Paint : Apex Ultima
2. Nerolac Paint : Excel Total 3. ICI Dulux (Akzo Nobel) : Weathersheild Max 4. Berger
Paint : Weather Coat Allguard.
1.0 Materials: Paint of approved make shall be got approved. 1. Asian Paint: Apex Ultima,
2. Nerolac Paint: Excel Total, 3. ICI Dulux (Akzo Nobel): Weathersheild Max, 4. Berger
Paint: Weather Coat Allguard.
2.0 Workmanship: applying two coats of exterior premium emulsion paint on existing
plastered surface including finishing & thinning as per manufacturer’s specifications. A
gap of 6 hrs. should be given between 2 subsequent coats. The work should be carried
out strictly as per manufacturer’s specifications and requirement including scaffolding,
jhoolas etc., complete as directed by E.I.C.
2.1 Preparation of surface, Scaffolding & Application: The relevant specification of item
no. 12 shall be followed except that the work shall be carried out with approved exterior
premium emulsion paint.
3.0 Mode of measurements & payment: The relevant specification of item no. 12 shall be
The rate shall be for a unit of one Sq.mt.
ITEM NO. 10: Providing and applying two coats of synthetic enamel paint (excluding
priming coat) on new /existing structural steel and other metal surface of approved brand
and make as mentioned below, up to any height with all tools, tackles and risk of
accident. The rate is inclusive of labour cost and scrapping out the corrosion cleaning the
surface by course paper air/brush/cloth, removing all rust, grease oil, dust, any foreign
materials like cement mortar splashes etc, with wire brush and emery paper including
EW- 270 PUR-F-006 RFQ-75883
scaffolding platform, jhoolas and machinery, equipment required for the work shall be
arranged by the contractor at his own cost and take all safety measures etc. complete as
directed by EIC. Basic rate including taxes per liter Rs 225.00)
1) Asian Paint – Apex Ultima. (2) Nerolac Paint- Excel Total (3) ICI Dulux(Akzo
Nobel)- Weather shield Max (4) Berger Paint –
Weather Coat Allguard. 5). GROWEL Paint: Pentolite Super Synthetic Enamel..
1.0. Materials: The enamel paint shall satisfy in general requirements as mentioned in
specification of oil paints. Enamel paint shall conform to I. S. 2933-1975.
2.0. Workmanship: 2.1. General:
2.1.1. The materials required for work of painting work shall be obtained directly from
approved manufactures or approved dealer and brought to the site in maker’s drums, kege
etc. With seal unbroken.
2.1.2. All materials not in actual use shall be kept properly protected, lids of containers
shall be kept closed and surface of paint in open or partially open containers covered with a
thin layer of turpentine to prevent formation of skin. The materials which have become stale
or flat due to improper and long storage shall not be used. The paint shall be stirred
thoroughly in its container before pouring into small containers. While applying also the
paint shall be continuously stirred in smaller container. No left over paint shall be put back
into stock tins. When not in use, the containers shall be kept properly closed.
2.1.3. If for any seasons, thinning is necessary, the brand of thinner recommended by the
manufacturer shall be used.
2.1.4. The surface to be painted shall be thoroughly cleaned and dusted. All rust, dirt and
grease shall be thoroughly removed before painting is started. No painting on exterior or
other exposed parts of the work shall be carried out in wet, damp or otherwise unfavourable
weather and all the surfaces shall be thoroughly dry before painting work is started.
2.2. Application :
2.2.1. Brushing operations are to be adjusted to the spreading capacity advised by the
manufacture of particular paint. The paint shall be applied evenly and smoothly by means
of crossing and laying off. The crossing and laying off consists of covering the area over with
paint, brushing the surface hard for the first time over and then brushing alternately in
opposite directions two or three times and then finally brushing lightly in direction at right
angles to the same. In this process, no brush marks shall be after the laying off is finished.
The full process of crossing and laying off will constitute one coat.
2.2.2. Each coat shall be allowed to dry completely and lightly rubbed with very fine grade
of sand paper and loose particles brushed off before the next coat is applied. Each coat
shall vary slightly in shade and shall be got approved from Engineer-in-charge before next
coat is started.
2.2.3. Each coat except the last cost shall be lightly rubbed down with sand-paper of fine
pumic stone and cleaned of dust before the next coat is applied. No hair marks from the
brush or clogging of paint puddles in the corners of panels angles jof mouldings etc. Shall
be left on the work.
2.2.4. Special care shall be taken while painting over bolts, nuts, rivets, overlaps etc.
Approved best quality brushes shall be used.
3.0. Mode of measurements & payment :
3.1. The new steel and other metal surface shall be measured under this item.
3.2. All the work shall be measured net in the decimal system as executed subject to the
following limits unless otherwise stated hereinafter :
(a) Dimensions shall be measured to the nearest 0.01 metre.
(b) Areas shall be worked out to the nearest 0.01 Sq. Metre.
3.3. No deductions shall be made for openings not exceeding 0.5 sq. Mt. Each and no
addition shall be made for painting to beadigns, mouldings, edges, jambs, soffits, etc. Of
such opening.
EW- 270 PUR-F-006 RFQ-75883
3.4. In case of fabricated structural steel and iron work, priming coat of paint shall be
included with fabrication. In case of trusses if measured sq. M. Compound girders,
stanchions, lattices, girder and similar work, actual area shall be measured in sq. M. And
no extra shall be paid for painting on bolts, heads, nuts, washers etc. No addition shall be
made to the weight calculated for the purpose of measurements of steel and iron works for
paint applied on shop or at site.
3.5. The different surfaces shall be grouped into one general item, areas of uneven surface
being converted into equivalent plain areas in accordances with the table given as per
Annexure II for payment.
The rate is excluding priming coat.
3.2. The rate shall be for a unit of one sq, metre.
ITEM NO. 11: Steel work riveted in built up sections framed work including cutting,
hoisting, fixing, in position and applying a priming coat of read lead paint (A) in beams
and joists channels angles tees, flat, with connecting plates or angle cleats as in main and
cross beams. Hip and jack rafters, purling connected to common rafters and the like
Materials : The structured steel work shall conform to M-22. Red lead paint primer shall
conform to I.S. : 102-1962.
2.0 Workmanship :
2.1 The steel sections as specified or required shall be cut, square and to correct lengths
as per drawings and design. The cut Ends exposed to view shall be finished smooth. No two
pieces shall be welded or otherwise jointed to make up the required length of member,
except as indicated in the drawing or as directed. All straightening and shaping to form
shall be done by application of pressure and not by hammering. Any bending or cutting
shall be carried out in such a manner as not to impair the strength of the metal. All
operations shall be done in cold state unless otherwise directed/permitted.
2.2 Steel riveted or bolted up sections, frame work.
2.2.1 The steel structure as shown in the drawings or as per direction of the Engineer-in-
charge shall be laid out on a level platform to full scale and to full size or in parts. A steel
tape shall be used for measurements to ensure maximum accuracy.
2.2.2 Wooden templates 12 mm. To 19 mm. Thick or metal sheet template shall be made to
correspond to each connecting gussets plate and rivet holes shall be accurately marked on
them and drilled. The templates shall be laid on the steel members, and holes of the steel
members shall also be marked shall also be marked for cutting. The base of steel columns
and the position of Anchor bolts shall be carefully set out.
2.2.3 All stiffeners shall be formed by pressure and where practicable, the metal shall not
be cut and welded in making these. In major works or where so specified. Shop drawings
giving complete details and information for the fabrication of the component parts of the
structure, including location type size, length and details of rivets, bolts, or weld shall be
prepared in advance of the actual fabrication and as approved. The drawings shall indicate
the shop and field rivets and bolts. The steel members shall be distinctly marked or
stenciled with paint with the identification mark as given in the shop drawings.
The bars shall be thickened at the ends, so as to provide for screwed threads and gradually
tapered off to meet their normal section.
Great accuracy shall be observe in fabrication of various members, so that these can be
assembled without being unduly packed, strained or forced into position ad when built up,
shall be true and free from twists, bikes, buckles, or open joints. Before making holes
individual members for fabrication, the steel work intended to be riveted or bolted together
shall be assembled or clamped properly and tightly so as to ensure close abutting or
lapping of the different members. All stiffeners shall bear tightly both at top and bottom
without being drawn or caulked. The abutting joints shall be cut or dressed true and
straight and fitted close together.
Web splice plates and fillers under stiffeners shall be cut to fit within 3 mm. Or flange
Angles, web plates of Girders shall have not cover plates, shall have their ends flush with
the top of angles forming the flanges unless otherwise required. The web plates when spiced
EW- 270 PUR-F-006 RFQ-75883
shall have clearance of more than 6 mm.
The erection, clearance for cleared ends of members connecting steel to steel shall
preferably be not greater than 1.5 mm. The erection clearance at the ends of beams without
web cleats shall not be more than 3 mm. At each end but where for a practical reason
greater clearance is necessary, suitably designed seating shall be provided.
Pins and rollers shall be accurately turned to gauge. These shall be straight and smooth
and free from flows. The roller bearing shall be provided with adequate arrangement for
holding the girders or truss resting on it. In columns caps and bases, the ends of shafts
together with the attached gussets Angles, channels etc. After riveting together shall be
accurately machanised so that the part connected but against each other over the entire
surfaces of contract connecting angles or channels shall be fabricated and placed in
position with greater accuracy so that they are not unduly reduced in thickness by
machining.
The ends of bearing stiffeners shall be machanised or ground to fit tightly both at the top
and bottom. All holes shall generally be drilled to the required size and at required position.
Sub punching shall be permitted, provided it is done 3 mm. Or less in diameter and
reemerged thereafter to the required size. The holes for rivets and bolts shall be larger by
0.4 to 6 mm. Than the nominal diameter of rivets or black bolts depending upon the
diameter of rivets.
Holes shall have their axis perpendicular to the surface bored through. The drilling or
reemerging shall be free from butts, and the holes should be clean and accurate. Holes for
counter shrunk bolts shall be made in such a manner that their heads fir flush with the
surface after fixing.
The fabrication work shall be completed in workshop as far as it is practicable to do so. Site
joints shall be done with rivets and fitted bolts or black bots, as shown in the drawings or
as directed. Generally the following principles shall govern the use of rivets turned and
fitted bolts, and black bolts.
(i) Rivets and turned and fitted bolts shall be used where the connection is such that slip
under load has to be avoided.
(ii) Black bolts may be used very sparingly where a force is carried through a connection
without impact, vibration or reversal of stresses.
2.2.4 Riveting : The parts assembled for riveting shall be in close contact with each other
and the bearing stiffeners shall Bear tightly both at top and bottom without being drawn or
caulked. Members to be riveted shall be properly pinned or bolted and rigidly held together
while riveting. Drifting of holes shall not be permitted except to draw the parts together and
the drifting tools so used shall have maximum diameter not exceeding the nominal diameter
of rivets or bolts. Drifting done during assembling shall not distort the metal or enlarge the
The shanks of rivets shall project beyond the plate-surface sufficiently so as to fill the hole
thoroughly and from the required head after riveting.
The riveting shall be done by hydraulic or pneumatic process. However, where such
facilities are not available, hand riveting may be permitted. The rivet shall be heated red
hot, care being taken to control the temperature of heating so as not to burn the steel.
Rivets of diameter less than 10 mm. May be fitted cold. Rivets shall be of heat finish with
heads full and of equal size. All loose, burnt or badly formed rivets with concentric or
deficient heads shall be cut out and replaced. The heads of rivets shall be central to shanks
and shall grip the assembled members firmly. In cutting out rivets, care shall be taken so
as not be injure the assembled, members, caulking or recopying shall not be permitted.
For testing rivets, hammer weighing approximately 0.25 Kg. Shall be used. Both heads of
the rivets shall be tapped, slack rivets will give a hollow sound and a jar.
All rivet heads shall be painted with red lead paint within a week of their fixing.
2.2.5 Bolting all bolt heads and nuts shall be hexagonal and of equal size unless specified
otherwise. The screwed heads shall conform to I. S. : 1363-1960 and the threaded surface
shall not be tapered.
2.2.6 The bolts shall be of such length so as to project two clear threads beyond the nuts
when fixed in position and these shall fit in the holes without any shakes. The nut shall be
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
GTPS_Tender _ EW-270_19_03_2026.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .