Loading…
Loading…
Tender Value
₹19.9 L
EMD Value
₹20,000
Closing Date
24 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Chief Officer, Halvad Nagarpalika
Construction Work of Retaining Wall, Smashan Chhapri and C.C. Flooring at Various Location Under MPLADS Year 2025-26
295936
Halvad/2026/April/01
Open
Civil - All
Morbi
1 document required · 1 mandatory
₹1,200
The Chief Officer, Halvad Nagarpalika
₹20,000
10 Apr 2026
10 Apr 2026
10 Apr 2026
24 Apr 2026
10 Apr 2026
NAME OF WORK :- CONSTRUCTION WORK OF RETAINING WALL,SMASHAN CHHAPRI,CC FLOORING AT
VARIOUS LOCATION IN HALVAD, DI. MORBI
TOTAL AMOUNT PUT TO TENDER
TOTAL AMOUNT PUT TO TENDER
PERCENTAGE RATE TENDER
Sr.No. Schedule Amount
1 Schedule - "B"- 1
2 Schedule - "B"- 2
3 Schedule - "B"- 3
Total Amount Rs.
Total Amount Rs.
I/We am/are willing to carry out the work @ ________% Above /
Below_____________Percentage (should be writen in figures and words) of the Estimated rates mentioned
above amount of my / our Tender works out as under.
Estimated Amount Estimated Amount
Put to Tender Rs. 19,86,539.00 Put to Tender Rs.
Add %Rs. Deduct %Rs.
Total Rs. Total Rs.
(In Words (In Words
Stamp with Signature of Contractor
Consl.Engineer Engineer
"DESIGN POINT" Halvad Nagarpalika
Chief Officer President
Halvad Nagarpalika Halvad Nagarpalika
HALVAD NAGARPALIKA - HALVAD
SCHEME :- MPLADS YEAR 2025-26
NAME OF WORK :- CONSTRUCTION WORK OF RETAINING WALL
LOCATION :- NEAR SHIVPARK SATVARA KANYA CHHATRALAY
SCHEDULE - "B-1"
PERCENTAGE RATE TENDER
Item No. & Description Quantity Rate Per Amount
Excavation for foundation in sand, gravel clay, soft soil ans murrum
etc. including shorting, strutting and dewatering as necessary ans
disposing of the excavated stuff as directed (A) Depth upto 3.0m. And
Lead Upto all lift and Lead.
Providing & laying spreading and compacting 150mm thick WBM
Grade - II of B.T.M.C. metal 40mm to 63mm size including using 20%
(13+7%) filler i.e. stone screeing 13.2 mm at the rate 0.16 Cumt. &
0.08 stone dust including spreading in uniform thickness hand packing
rolling with vibratory roller 8-10 tonnes in stages to proper garde and
camber applying and brooming required types of screening/binding
materials to fill up the interstices of coarse aggregate watering and
compacting to the required density.
Providing and filling in foundation with ordinary Cement concrete M-
100 mix and providing necessary vertical pin headers including 9.00 3345.58 Cumt.
formwork, vibrating, ramming and curing complete.
Providing & Laying controlled cement concrete M-200 for R.C.C Return
as per drawing including necessary shutering laying, vibrating, height 66.00 5198.58 Cumt.
from 0.00 to 5.00 m (a) Pier (b) Abutment (c) R.C.C Return.
Providing and laying in position FE 500D TMT bar reinforcement
including cutting, bending, hooking and tying complete as per detailed
drawings for the following.(A) Piers (B) Abutments (C) R.C.C. Returns
Providing and laying weep holes in abutment and return by using A.C.
pipes of 100mm diameter including laying in proper grade and jointing 400.00 86.69 Nos.
etc. complete as per detailed drawings.
Total Amounts Rs…
Total Amounts Rs…
Stamp with Signature of Contractor
Consl. Engineer Civil Engineer Chief Officer President
"DESIGN POINT" Halvad Nagarpalika Halvad Nagarpalika Halvad Nagarpalika
Amreli Halvad Halvad Halvad
HALVAD NAGARPALIKA, HALVAD
SCHEME :- MPLADS YEAR 2025-26
NAME OF WORK :- CONSTRUCTION WORK OF SMASHAN CHHAPRI, AT HALVAD
LOCATION :- KHAVAS (RAJPUT) SMASHAN GRUH
SCHEDULE - "B-2"
PERCENTAGE RATE TENDER
Item No. & Description Quantity Rate Per Amount
Excavation for foundation upto 1.5 m depth including sorting
out and stacking of useful materials and disposing off the 32.20 212.52 Cumt.
excavated stuff upto all ligt and lead all Stratt.
Providing and laying cement concrete 1:4:8 (1 Cement :
coarse sand :8 hand broken stone aggregates 40 mm nomial
size) and curing complete including cost of form work in (A)
Foundation and plinth.
Uncoursed Rubble Masonry with hard stone of approved
quality in foundations and plinth in Cement Mortar 1:5 (1- 21.98 2628.91 Cumt.
cement : 5-coarse sand including levelling up etc. complete.
Providing and laying cement concrete work 1:2:4 (1Cement :
2- Coarse sand : 4- graded stone aggregates 20mm nominal
size) and curing complete including cost of formwork and
excluding cost of reinforcement for reinforced concrete work 13.24 4073.54 Cumt.
in (A) Foundations, footings, Base or columns and Mass
Filling available excavated earth (excluding rock) in trenches.
plinth, sides of foundations etc. in layers not exceeding 20 cm.
in depth consolidating each disposited layer by ramming and
Providing and laying ordinary cement concrete 1:2:4
(1Cement 2- coarse sand : 4- graded stone aggregates 20mm
nominal size) and finishing smooth with,curing etc. complete
including the cost of formwork but excluding the cost of
reinforcement for R.C.C work in (A) BEAMS :(i) Having cross-
sectional area 0.05 to 0.08 Sq.M
Providing and laying ordinary cement concrete 1:2:4
(1Cement 2- coarse sand : 4- graded stone aggregates 20mm
nominal size) and finishing smooth with,curing etc. complete
including the cost of formwork but excluding the cost of 5.36 7665.60 Cumt.
reinforcement for R.C.C work in (A) BEAMS :(ii) Having cross-
sectional area more than 0.08Sq.M and upto 0.12 Sq.M
Providing and laying ordinary cement concrete 1:2:4
(1Cement 2- coarse sand : 4- graded stone aggregates 20mm
nominal size) exposed work with curing etc. complete
including the cost of formwork but excluding the cost of
reinforsement for R.C.C work in (iii) Slabs having more than
10 cm and upto 13 cm. thickness
Providing TMT Bar FE 500/500D reinforcement for R.C.C.
work including bending, binding and placing in position 1936.80 77.29 Kg.
complete upto floor two level.
Providing 15mm thick cement plaster in single coat on Rough
(Similar)side of single or half brick walls for interior plastering
upto floor two level and finished even and smooth in (i)
Cement mortar 1:3 (1-cement:3-sand)
White washing with lime on wall surface (two coats) to give an
even shade including thoroughly booming the surface to 242.34 12.70 Sqmt.
remove all dirt, dust; mortar drops and other foreign matter.
Providing and laying cement concrete flooring 1:2:4 (1-cement
: 2-coarse sand : 4-graded stone aggregate 20mm nominal
size) laid in one layer and finished with a floating coat of neat 32.49 290.63 Sqmt.
cement. (A) 40mm thick.
Providing and fixing named Marble takati as directed. 1 505.00 No.
Stamp with Signature of Contractor
Consl. Engineer Civil Engineer Chief Officer President
"DESIGN POINT" Halvad Nagarpalika Halvad Nagarpalika Halvad Nagarpalika
Amreli Halvad Halvad Halvad
HALVAD NAGARPLAIKA - HALVAD
SCHEME :- MPLADS YEAR 2025-26
NAME OF WORK :- CONSTRUCTION WORK OF CC FLOORING
LOCATION :-RABARI SMASHAN GRUH @ HALVAD
SCHEDULE - "B-3"
PERCENTAGE RATE TENDER
Description Quantity Rate Per Amount
Box cutting the road surface to proper slope and camber for
making a base for road work including ramming the excavated
stuff and despositing on the road side slope as directed up to lift
and lead all stratt.
Providing and Laying in position Controlled Concrete M-200
grade concrete for using cement content as per approved
design mix, improve workability without impiring strength and
durability as per direction of the engineer in charge. (min
cement level as per latest ID: 456 shall be maintained) for
150mm thick trimix C.C Road with trimix vaccume dewatering 104.28 5010.61 Cumt.
system work with power trowling sheet form with M.S Channel,
surface vibrator with providing road expansion joint having size
6mmx50mm by concrete cutter machine and filled with bitumen,
finishing with floor hardener necessary all equipments, all
labour charges complete.
Total Amount Rs.....
Total Amount Rs.....
Stamp with Signature of Contractor
Consl. Engineer Civil Engineer Chief Officer President
"DESIGN POINT" Halvad Nagarpalika Halvad Nagarpalika Halvad Nagarpalika
Amreli Halvad Halvad Halvad
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
01 Tender.pdf
02 Form B-1.pdf
03 Schedule -B.pdf
04 Location and Section 01.pdf
04 Location and Section 02.pdf
04 Location and Section 03.pdf
05 Term and Condition.pdf
06 Specifications of Building Work.pdf
07 Specifications of Road Work.pdf
08 Specifications of Electrical Work.pdf
09 Vendor Civil and LED work.pdf
10 Test Require For Construction Material.pdf
11 GR All.pdf
11.1 DMO_2876_01-May-2025_273.pdf
12 GR Affidavit GR_240217_161336.pdf
Download all tender documents and submit your bid