| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.2 CrAccepted-AOC VILLAGE KAIRWAN KARANPUR PO RAJPUR DEHRADUN | DEHRADUN | DEHRADUN | UTTARAKHAND | ₹3.2 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹3.3 Cr+₹7.3 L (2.29%)Rejected-Finance | ₹3.3 Cr+₹7.3 L (2.29%) | L2 | Rejected-Finance Disqualified |
| 3 | L3₹3.5 Cr+₹27.6 L (8.65%)Rejected-Finance | ₹3.5 Cr+₹27.6 L (8.65%) | L3 | Rejected-Finance Disqualified |
Tender Value
₹3.5 Cr
EMD Value
₹6.9 L
Closing Date
9 Dec 2021, 5:00 pmClosed
Superintending Engineer
Office of Superintending Engineer Construction Circle UKPJN Dehradun
Supply and Laying and Jointing of pipe line and construction of OHT Pump House providing household connections construction of boundary wall installation of pumping plants and its appurtenant works in Nagla Khitab Block Laksar water supply scheme
2021_MDPEY_38954_1
Letter No. 5962/NIVIDA/713 dt. 24.11.2021
Open Tender
Civil Works
Item Rate
270 days
Haridwar
Please refer Tender documents.
3 documents required · 3 mandatory
₹9,440
Executive Engineer Construction Division UKPJN
₹6.9 L
Dehradun
8 Jul 2025
26 Nov 2021
13 Dec 2021
26 Nov 2021
9 Dec 2021
30 Nov 2021
29 Nov 2021
Amount
Tube well Assembly
Preparing & Lowering of Tube Well Assembly Starting From G.L to the Required Depth as per unit estimate. Including Cutting, Welding etc. as Required at Site With Complete T & P Required for Proper Completion of Work. Drilling of Bore by heavy duty direct rotary rig machine in Alluvial, Boulders, Pebbles, Rocky Stone, Sticky Clay etc. From Ground Level Upto Entire Depth for linear assembly complete as per items of unit estimate.
Pumping Plant
Electrification Of Tubewell
Rising Main
Providing Of all Material With Carting to site of Work, Lowering Into Trenches With True To alingement Laying Of MS ERW Pipe Grade Yst 210 Jointing By electric Welding process with proper grade of electrode suitable for jointing of water supply pipe lines ( Andor, L&T or Equivalent Electrode ) By cutting of pipe and making required bends by welding completion of work with testing of the pipe etc Complete.
100 mm DI 5.6mm thick pipes
Excavation of Earth for pipe line in soil mixed with Shingle, bajri, and boulder strata lift up to 1.5 m. lead up to 30 m. Including reffiling, watering, remaining if excavated earth into the trenches and removal of surplus earth upto a distance of 60 m from trenches including supply of labour T&P etc. all complete.
All Zone
Following and Fixing of valves and fitting ISI marked medium class:-Sluice valve.
D.I. Sluice/ Gate Valve
Pressure PN 1.0
Constructing masonry Chamber 90x90x100 cm, inside with 75 class designation brick work in cement mortar 1:4(1 cement: 4 coarse sand) for sluice valve,with C.I. surface box 100x100x75 mm with hinge cover fixedin RCC slab 1:2:4 cement sand and 20mm grit necessary excavation foundation concrete 1:5:10 and inside plastering with cement mortar 1:3:12 mm chambers as per type design including supply of all materials labour t&p etc complete.
All Zone
Pipe Line Work
Supply of HDPE pipe including laying jointing Field testing,commissioning complete at site of HDPE (pe100 grade compound)pipe as per IS 4984 and specifications for water application including all cost of material, labourrequired,transpotation,loading,unloading& stacking etc.
PE-100, Normal Pressure(PN)-6 in 6 kg/cm2
90 mm dia pipe
110 mm dia pipe
140 mm dia pipe
Supply, carting and fixing in position of following CI D/F sluice / Gate valve for flow regulation & scouring including cost of valve specials, labour & T&Pcomplete.
C.I. D/F Sluice Valves Confirming to IS: 14846-2000 ( Kirloskar or equivalent) of Pressure PN 1.0
D.I. Sluice/ Gate Valve
Pressure PN 1.0
Air valve 25 mm dia
Excavation of pipe line in soil mixed with course sand, shingle, kankar, including refilling of trenches after laying of pipe line including watering ramming etc.
House Hold connection including all material etc complete. Taking 100 % connection in initial Stage.
Dismantling of following type of road surfaces for laying of pipe line including sorting out of serviceable materials and disposal of unserviceable materials.
Cement concrete road
Reinstatement of following type of road surfaces after laying of pipe line including supply of all material ,labour,T&P etc complete.
Cement concrete road
Constructing masonry Chamber 90x90x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep (inside) with chained lid and RCC top slab 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size ), i/c necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5. For different types of valves.
Over Head Tank
Supply of all materials, T&P etc.and construct an RCC over head tank of following size with RCC staircase & 1 m wide balcony, G.I. pipes railing consisting of 3 rows of 20 mm dia. G.I. pipe and angle iron posts around balcony & at the dome periphery, M.S. ladder from balcony to top of tank and inside the tank, supply and fixing M.H. cover with locking device, 1.2m dia ventilator, lightening conductor, water level indicator, supply and fixing of pipes, CI D/F pines, supply and fixing M.S. clamps with RCC column 40mm PCC 1:2:4 over 80 mm PCC 1:4:8 in apron, 150 mm semicircular drain around the tank, escape channel of 20 m length, box type enclosure at the entrance of the staircase having locking arrangements, two coats of apex paint and testing of tank for water tightness and also excluding cost of supply and fixing of all necessary pipes and valves etc. all complete with inlet, outlet, overflow and washout pipes with bypass arrangement and necessary fittings and specials and testing of bearing capacity.
80 KL OHT Staging 18.0 Mtr (Zone-1)
80 KL OHT Staging 18.0 Mtr(Zone-2)
60 KL OHT Staging 18.0 Mtr(Zone-2)
Pump House
Construction of Pump House (3.6 m x 3.0 m) and its all Apprutment work including all material, Labour, T&P etc complete as per drawing provided and as per Direction of Engineer Incharge.
Boundary Wall
Construction of boundary wall around water works compound.
Fixing of 3.6m wide M.S. gate with wicket gate including fabrication and supply of steel and construction of boundary pillars etc. all complete.
ZONE 1- PEEPLI & BUDHA KHEDA
Transportation of Rig Machine, Air Compressor, O P Unit and camp equipages, connected T&P and necessary material required for drilling up to site of work, including loading, unloading etc. complete.
Errection and leveling of rig machine and barricading at site of work `
Dismantling of rig machine and clearance of site after satisfactory completion of work
Drilling of borehole by Dual rotary/ DR/ DC-RC/Percussion Rig machine.
Drilling of 600 mm dia borehole from GL to required depth.
Preparing & lowering of tube well assembly starting from G.L to the required depth including cutting, welding as required at site complete with all T&P required.
Supply and lowering of 200 mm dia MSERW plain pipe, 7.1 mm thick as per IS code 4270
Supply and lowering of 200 mm dia MSERW slotted pipe, 7.1 mm thick as per IS code 4270
200 mm dia bail plug
200 mm dia MS tube-well cap
Supply & fixing of 200 mm dia M.S.D.I. housing clamp & girder set
Supply & shrouding of pea gravel in between bore & tube well assembly to the entire depth of tube well.
Development of TW by 300 PSI/900 CFM Air compressor as below including Erection of compressor at site of work.
Running of compressor for development and testing of tube well.
Development of TW by suitable size of OP Unit as below including Erection of OP Unit and camp equipage at site of work.
Lowering of suitable size submersible pump motor set with column pipe and running of D.G. Set, running of OP Unit for development and yield test of tube well.
Geological survey of site
Chemical & bacteriological testing of water sample
Supply of submersible pump capable of delivering 600 Lpm discharge at 55 mt. head with suitable electric motor to be operated on 415 volt (+\- 10% ), 3 phase,50 C\s AC supply with 5 Mtr. submersible cable.
Supply of spare pumping plant as above .
Smart electrical panel cum starter suitable for automation of 15 HP capacity .
Supply of 63 amp. 3 phase with neutral main switch with enclouser and HRC fuses.
Supply of submersible cable 1x3x16 sq.mm .
Supply of aluminum armored cable 25 sq.mm 3.5 core .
SUPPLY OF MAIN PIPING AND VALVE OF 100mm DIA HAVING FOLLOWING ITEM .
C class M S column pipe (confirming IS: 4270 or latest IS code) in 3 mt. length with interlocking arrangement (flanged/socketed) .
CI D\F PN-1.6 Sluice Valve with hand wheel .
CI D\F PN-1.6 Reflux Valve .
MS D\F pipe of 1.5 Mt. length- 2 Nos, MS D/F pipe of 1.0 Mt. length-1 No., Ventury - 1 No, Tee-1 No, CI D\F bend-2 Nos, TW Cap-1 No., Packing & nut bolt etc. - 1 Lot.
S/o 100 mm dia M.S.D.I. clamp set .
S/o Jointing material for wiring connection including lugs, thimble, insulation tapes etc.
S/o Pressure Gauges with control cock & fitting, nipple, pipe, elbow etc complete- 10Kg/Sq Cm.
Installation & testing of pumping plants and accessories.
SITC of dozing pump with all necessary connecting accessaries complete.
Testing of pumping plants at manufacture`s works.
Earthing with G.I Earth plate of 600mmx600mmx 6mm size including accessories and providing masonry enclosure with providing and fixing 25mmx5mm GI strip on surface or in recess for connections with charcoal, salt as required.
Supply of 3 ton capacity and 4.5 mt. lift chain pulley block .
Supply of rubber resistance insulated sheet 2M x 1M x 25mm thick .
Supply of three phase rolling contact servo voltage stabilizer 40 KVA capacity with input voltage range 300 to 480 with constant output of 415+/-1% complete in all respect ONAN Type.
Earthing with G.I Earth plate of 600mmx600mmx 6mm size including accessories and providing masonry enclosure with providing and fixing 25mmx5mm GI strip on surface or in recess for connections with charcoal, salt as required.
Installation, Testing & commissioning of Three phase servo voltage stabilizer.
Wiring for light point, fan point etc. with 1.5 sq mm FR PVC insulated copper conductor single core cable in surface PVC conduit with piano type switch, phenolic laminated sheet, suitable size GI box, with earth wire of 1.5 sq mm FR PVC insulated copper conductor single core cable etc as required.
Wiring for circuit/sub main along with earth wire with the following size of FR PVC insulated copper conductor single core cable in surface PVC conduit as required.
2x2.5 sq. mm + 1x2.5 sq. mm earth wire
2x4 sq. mm + 1x4 sq. mm earth wire
Supply and fixing of metal box of 180 rnmx100mmx160 mm deep on surface with suitable size phenolic laminated sheet cover in front including providing and fixing 6 pin 5/6 amp and 15x16 amp socket outlet and 15/16 amp piano type switch, connections, painting etc as required.
Supply and fixing of following way S.P.N. sheet steel, MCB DB, 240 V on surface complete with copper bus bar, neutral bus bar, earth bar, inter connections including earthing etc as required. (But without MCB/RCCB/Isolator)
6 Way double door ,
Supply and fixing of 5 A to 32 A, 240 V, 10 KA, C serious MCB suitable for inductive load of following pole in the existing MCB DB complete with connection, testing etc as required.
Supply and fixing of double pole, 240 V, isolator in the existing MCB DB complete with connection, testing etc as required.
Supply and fixing of 20 W LED tube light complete in all respect (Bajaj/Philips OR Equivalent make)
Supply in fixing of LED external lighting luminaries with mounting bracket etc. complete.
O & M of pumping plant for six months.
ZONE 2- RAIPUR
Transportation of Rig Machine, Air Compressor, O P Unit and camp equipages, connected T&P and necessary material required for drilling up to site of work, including loading, unloading etc. complete.
Errection and leveling of rig machine and barricading at site of work `
Dismantling of rig machine and clearance of site after satisfactory completion of work
Drilling of borehole by Dual rotary/ DR/ DC-RC/Percussion Rig machine.
Drilling of 600 mm dia borehole from GL to required depth.
Preparing & lowering of tube well assembly starting from G.L to the required depth including cutting, welding as required at site complete with all T&P required.
Supply and lowering of 200 mm dia MSERW plain pipe, 7.1 mm thick as per IS code 4270
Supply and lowering of 200 mm dia MSERW slotted pipe, 7.1 mm thick as per IS code 4270
200 mm dia bail plug
200 mm dia MS tube-well cap
Supply & fixing of 200 mm dia M.S.D.I. housing clamp & girder set
Supply & shrouding of pea gravel in between bore & tube well assembly to the entire depth of tube well.
Development of TW by 300 PSI/900 CFM Air compressor as below including Erection of compressor at site of work.
Running of compressor for development and testing of tube well.
Development of TW by suitable size of OP Unit as below including Erection of OP Unit and camp equipage at site of work.
Lowering of suitable size submersible pump motor set with column pipe and running of D.G. Set, running of OP Unit for development and yield test of tube well.
Geological survey of site
Chemical & bacteriological testing of water sample
Supply of submersible pump capable of delivering 400 Lpm discharge at 52 mt. head with suitable electric motor to be operated on 415 volt (+\- 10% ), 3 phase,50 C\s AC supply with 5 Mtr. submersible cable.
Supply of spare pumping plant as above .
Smart electrical panel cum starter suitable for automation of 10 HP capacity .
Supply of 63 amp. 3 phase with neutral main switch with enclouser and HRC fuses.
Supply of submersible cable 1x3x6 sq.mm .
Supply of aluminum armored cable 16 sq.mm 4 core .
SUPPLY OF MAIN PIPING AND VALVE OF 80mm DIA HAVING FOLLOWING ITEM .
C class M S column pipe (confirming IS: 4270 or latest IS code) in 3 mt. length with interlocking arrangement (flanged/socketed) .
CI D\F PN-1.6 Sluice Valve with hand wheel .
CI D\F PN-1.6 Reflux Valve .
MS D\F pipe of 1.5 Mt. length- 2 Nos, MS D/F pipe of 1.0 Mt. length-1 No., Ventury - 1 No, Tee-1 No, CI D\F bend-2 Nos, TW Cap-1 No., Packing & nut bolt etc. - 1 Lot.
S/o 80 mm dia M.S.D.I. clamp set .
S/o Jointing material for wiring connection including lugs, thimble, insulation tapes etc.
S/o Pressure Gauges with control cock & fitting, nipple, pipe, elbow etc complete- 10Kg/Sq Cm.
Installation & testing of pumping plants and accessories.
SITC of dozing pump with all necessary connecting accessaries complete.
Testing of pumping plants at manufacture`s works.
Earthing with G.I Earth plate of 600mmx600mmx 6mm size including accessories and providing masonry enclosure with providing and fixing 25mmx5mm GI strip on surface or in recess for connections with charcoal, salt as required.
Supply of 2 ton capacity and 4.5 mt. lift chain pulley block .
Supply of rubber resistance insulated sheet 2M x 1M x 25mm thick .
Supply of three phase rolling contact servo voltage stabilizer 25 KVA capacity with input voltage range 300 to 480 with constant output of 415+/-1% complete in all respect ONAN Type.
Earthing with G.I Earth plate of 600mmx600mmx 6mm size including accessories and providing masonry enclosure with providing and fixing 25mmx5mm GI strip on surface or in recess for connections with charcoal, salt as required.
Installation, Testing & commissioning of Three phase servo voltage stabilizer.
Wiring for light point, fan point etc. with 1.5 sq mm FR PVC insulated copper conductor single core cable in surface PVC conduit with piano type switch, phenolic laminated sheet, suitable size GI box, with earth wire of 1.5 sq mm FR PVC insulated copper conductor single core cable etc as required.
Wiring for circuit/sub main along with earth wire with the following size of FR PVC insulated copper conductor single core cable in surface PVC conduit as required.
2x2.5 sq. mm + 1x2.5 sq. mm earth wire
2x4 sq. mm + 1x4 sq. mm earth wire
Supply and fixing of metal box of 180 rnmx100mmx160 mm deep on surface with suitable size phenolic laminated sheet cover in front including providing and fixing 6 pin 5/6 amp and 15x16 amp socket outlet and 15/16 amp piano type switch, connections, painting etc as required.
Supply and fixing of following way S.P.N. sheet steel, MCB DB, 240 V on surface complete with copper bus bar, neutral bus bar, earth bar, inter connections including earthing etc as required. (But without MCB/RCCB/Isolator)
6 Way double door ,
Supply and fixing of 5 A to 32 A, 240 V, 10 KA, C serious MCB suitable for inductive load of following pole in the existing MCB DB complete with connection, testing etc as required.
Supply and fixing of double pole, 240 V, isolator in the existing MCB DB complete with connection, testing etc as required.
Supply and fixing of 20 W LED tube light complete in all respect (Bajaj/Philips OR Equivalent make)
Supply in fixing of LED external lighting luminaries with mounting bracket etc. complete.
O & M of pumping plant for six months.
SADAN CONSTRUCTION AND SUPPLIERS
O.P. Gupta Constructions Pvt Ltd
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .