| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹22.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹22.9 L+₹8,004.70 (0.35%)Rejected-AOC C O LT MAAHANTA NARZARY W NO 5 TENGAPARA P O P S KOKRAJHAR DIST KOKRAJHAR BTC ASSAM PIN 783370 | KOKRAJHAR | KOKRAJHAR | ASSAM | 783370 | L2 | Rejected-AOC L2 | |
| 3 | Rejected-Technical | - | Rejected-Technical reject |
Tender Value
₹22.9 L
EMD Value
₹45,800
Closing Date
25 Oct 2023, 1:30 pmClosed
the Addl. Chief Engineer, PWD
O/o the Addl. Chief Engineer, PWD
Re-Const. of Boundary Wall with Iron Gate etc. of Bagribari Revenue Circle, Office, Bagribari under Kokrajhar District. TN_25_1
2023_BTC_32749_1
No. ACE-106/PWD/IFB/2021-22/260
Open Tender
Civil Works - Building
Item Rate
180 days
Kokrajhar
Please refer Tender documents.
4 documents required · 4 mandatory
₹1,000
₹45,800
Yes
O/o the Addl. Chief Engineer, PWD
20 Nov 2023
3 Oct 2023
25 Oct 2023
3 Oct 2023
25 Oct 2023
3 Oct 2023
3 Oct 2023 - 20 Oct 2023
20 Oct 2023
Amount
Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- charge.
Boundary Wall: Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 2.8.1 All kinds of soil.
Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete : 16.12.1 With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Providing and laying in position cement concrete of specified grade all works upto plinth . (a) In prop.1:3:6
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. TMT bar Fe 500D or more .
Centering and shuttering including strutting, propping etc. and removal of the same... 5.9.1 Foundations, footings, bases of columns, etc. for mass concrete.
Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders,cantilevers etc .
Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillar, Piers, Abutments, Posts and Struts
Providing and laying in position specified grade of R.C.C. Excluding cost of centering , Shuttering up to P.L. 5.1.3 Prpo.1:2:4
Reinforcement RCC works column, pillar, pire, etc. upto floor v (Five) level, excluding cost of centering, shuttering and reinforcement. 5.2.2 Prop.1:1.5:3
Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level. 6.13.2 Cement mortar 1:4
15 mm thick cement plaster in single coat on rough side of single or half brick wall 13.5.1 1:4 (1 Cement : 4 Coarse Sand)
Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface : 13.43.1 Water thinnable cement primer.
Finishing wall with water proofing cement paint of approved brand and manufacture of required shade : 13.44.1 New work (Two or more coat @ 3.84 kg/10 sqm)
Iron Gate Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 2.8.1 All kinds of soil.
Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Providing and laying in position cement concrete of specified grade all works upto plinth . A) In prop.1:3:6
Steel reinforcement for R.C.C. work including straightening, cutting, bending, to proper shape plaing in position and binding up to plinth level. 5.22.6 TMT bar Fe 500D or more .
Centering and shuttering including strutting, propping etc. and removal of the same 5.9.1 Foundations, footings, bases of columns, etc. for mass concrete
Centering and shuttering including strutting, propping etc. and removal of the same 5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts
Providing and laying in position specified grade of R.C.C. Excluding cost of centering , Shuttering up to P.L. 5.1.3 Prpo.1:2:4
Reinforcement R.C.C. works column, pillar,pire, etc upto floor v (five) level, excluding cost of centering, shuttering and reinforcement. 5.2.2 Prop.1:1.5:3
15 mm thick cement plaster in single coat on rough side of single or half brick wall 1:4 (1 cement: 4 coarse sand)
Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface : 13.43.1 Water thinnable cement primer
Finishing walls with water proofing cement paint of approved brand and manufacture of required shade : 13.44.1 New work (Two or more coats applied @ 3.84 kg/10 sqm)
With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works
Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : 13.62.1 Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture.
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works.
Protection wall Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 2.8.1 All kinds of soil.
Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete : 16.12.1 With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Providing and laying in position cement concrete of specified grade all works upto plinth. A) in prop.1:3:6
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: 6.1.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
DHARAMSING NARZARY
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .