| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹62.4 LAdmitted-Finance | ₹62.4 L | L1 | Admitted-Finance |
| 2 | L2₹65.9 L+₹3.5 L (5.60%)Admitted-Finance | ₹65.9 L+₹3.5 L (5.60%) | L2 | Admitted-Finance |
| 3 | L3₹70.1 L+₹7.7 L (12.4%)Admitted-Finance | ₹70.1 L+₹7.7 L (12.4%) | L3 | Admitted-Finance |
| 4 | L4₹72.8 L+₹10.4 L (16.7%)Admitted-Finance | ₹72.8 L+₹10.4 L (16.7%) | L4 | Admitted-Finance |
| 5 | L5₹73.7 L+₹11.4 L (18.2%)Admitted-Finance | ₹73.7 L+₹11.4 L (18.2%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | LINGAM RAVI KIRAN L6 | V SURENDRA NAIDU L4 | CHINTHADA VENKATA RAO L5 | M N NAIDU CONSTRUCTIONS L2 | B SIVA KUMAR L1 | Sri Shivanagoud S Yalwar L3 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Fixing the double scaffolding system (cup lock type) with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform and maintaining it in a serviceable condition for the required duration and removing it after completion of work etc., complete as directed by the site in-charge | 234 | Sq.m | 400 ₹93,600 | 350 ₹81,900 | 420 ₹98,280 | 598 ₹1,39,932 | 306.17 ₹71,643.78 Lowest | 500 ₹1,17,000 |
| 2.00 | Careful dismantling of damaged weathering course over the roof and disposing the debris away from the site including conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 15.83 | Cu.m | 1,500 ₹23,745 | 1,440 ₹22,795.2 | 1,400 ₹22,162 | 1,999 ₹31,644.17 | 1,235.61 ₹19,559.71 Lowest | 1,300 ₹20,579 |
| 3.00 | Careful dismantling of damaged/cracked CR masonry wall and stacking useful materials for reuse and disposal of debris away from the site etc., complete as directed by the site in-charge | 6.1 | Cu.m | 1,900 ₹11,590 Lowest | 2,000 ₹12,200 | 2,200 ₹13,420 | 2,499 ₹15,243.9 | 1,916.97 ₹11,693.52 | 2,000 ₹12,200 |
| 4.00 | Erection of new granite stone pillars, capitals, stone beams and roof slabs for Vinayaka swami sub shrine and pointing stone joints in Lime mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 6.42 | Cu.m | 69,000 ₹4,42,980 | 67,500 ₹4,33,350 | 67,000 ₹4,30,140 | 39,999 ₹2,56,793.58 Lowest | 58,255.08 ₹3,73,997.61 | 70,000 ₹4,49,400 |
| 5.00 | Careful dismantling of bulged out stone masonry Prakara wall of temple and stacking useful materials for reuse and disposal of debris away from the site etc., complete as directed by the site in-charge | 26.7 | Cu.m | 2,400 ₹64,080 | 2,300 ₹61,410 | 2,700 ₹72,090 | 6,499 ₹1,73,523.3 | 2,009.91 ₹53,664.6 Lowest | 2,100 ₹56,070 |
| 6.00 | Reconstruction of Prakara wall with granite stone masonry (Veneering) (60% available and 40% new for missing portion) in lime mortar (1:2) and pointing the wall. Including cost, conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 26.7 | Cu.m | 30,800 ₹8,22,360 | 31,000 ₹8,27,700 | 30,000 ₹8,01,000 | 16,500 ₹4,40,550 Lowest | 27,567.39 ₹7,36,049.31 | 30,000 ₹8,01,000 |
| 7.00 | Core filling in between the restored veneer walls with brick jelly concrete using 20-40mm brick aggregate in Lime Mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 13.36 | Cu.m | 12,300 ₹1,64,328 | 12,500 ₹1,67,000 | 12,700 ₹1,69,672 | 8,000 ₹1,06,880 Lowest | 11,450.86 ₹1,52,983.49 | 13,000 ₹1,73,680 |
| 8.00 | Providing coping over the reconstructed prakara wall with brick jelly concrete using 20-40mm brick aggregate in Lime Mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and all other applicable taxes etc., complete as directed by the site in-charge | 2.26 | Cu.m | 12,300 ₹27,798 | 12,500 ₹28,250 | 12,700 ₹28,702 | 12,000 ₹27,120 | 11,411.68 ₹25,790.4 Lowest | 12,500 ₹28,250 |
| 9.00 | Providing plastering to the exposed roof brick portion of Veerabhadra swami sub shrine in Lime mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and all other applicable taxes etc., complete as directed by the site in-charge | 10.11 | Sq.m | 800 ₹8,088 | 600 ₹6,066 | 700 ₹7,077 | 1,200 ₹12,132 | 492.67 ₹4,980.89 Lowest | 580 ₹5,863.8 |
| 10.00 | Careful removal of deposited debris mixed with Veneering stones and stone boulders and careful sorting and stacking of useful stone blocks Including conveyance of all materials, labour charges, GST and all other applicable taxes etc., complete as directed by the site in-charge | 173.86 | Cu.m | 1,800 ₹3,12,948 | 1,700 ₹2,95,562 | 1,600 ₹2,78,176 | 1,800 ₹3,12,948 | 1,525.39 ₹2,65,204.31 Lowest | 1,700 ₹2,95,562 |
Tender Value
₹68.9 L
EMD Value
₹1.7 L
Closing Date
21 Jul 2026, 11:00 amClosed
SA, ASI, Amaravati Circle, Vijayawada
Aurobindo Plaza,6-134/1, Kanuru Main Road, Kanuru, Vijayawada -520007 (A.P.)
As per Tender document
2026_ASI_915304_1
12/NIT/2026-27/Amaravati/ Anantapuram sub Circle
Open Tender
Civil Works
Works
120 days
Kambaduru, Anantapuram district
As per Tender document
3 documents required · 3 mandatory
₹0
₹1.7 L
Yes
20 Aug 2026
1 Jul 2026
22 Jul 2026
1 Jul 2026
21 Jul 2026
1 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Fixing the double scaffolding system (cup lock type) with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform and maintaining it in a serviceable condition for the required duration and removing it after completion of work etc., complete as directed by the site in-charge | 234 | Sq.m | 1 | ₹234 |
| 2 | Careful dismantling of damaged weathering course over the roof and disposing the debris away from the site including conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 15.83 | Cu.m | 1 | ₹15.83 |
| 3 | Careful dismantling of damaged/cracked CR masonry wall and stacking useful materials for reuse and disposal of debris away from the site etc., complete as directed by the site in-charge | 6.1 | Cu.m | 1 | ₹6.1 |
| 4 | Erection of new granite stone pillars, capitals, stone beams and roof slabs for Vinayaka swami sub shrine and pointing stone joints in Lime mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 6.42 | Cu.m | 1 | ₹6.42 |
| 5 | Careful dismantling of bulged out stone masonry Prakara wall of temple and stacking useful materials for reuse and disposal of debris away from the site etc., complete as directed by the site in-charge | 26.7 | Cu.m | 1 | ₹26.7 |
| 6 | Reconstruction of Prakara wall with granite stone masonry (Veneering) (60% available and 40% new for missing portion) in lime mortar (1:2) and pointing the wall. Including cost, conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 26.7 | Cu.m | 1 | ₹26.7 |
| 7 | Core filling in between the restored veneer walls with brick jelly concrete using 20-40mm brick aggregate in Lime Mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and other applicable taxes etc., complete as directed by the site in-charge | 13.36 | Cu.m | 1 | ₹13.36 |
| 8 | Providing coping over the reconstructed prakara wall with brick jelly concrete using 20-40mm brick aggregate in Lime Mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and all other applicable taxes etc., complete as directed by the site in-charge | 2.26 | Cu.m | 1 | ₹2.26 |
| 9 | Providing plastering to the exposed roof brick portion of Veerabhadra swami sub shrine in Lime mortar (1:2) Including cost, conveyance of all materials, labour charges, GST and all other applicable taxes etc., complete as directed by the site in-charge | 10.11 | Sq.m | 1 | ₹10.11 |
| 10 | Careful removal of deposited debris mixed with Veneering stones and stone boulders and careful sorting and stacking of useful stone blocks Including conveyance of all materials, labour charges, GST and all other applicable taxes etc., complete as directed by the site in-charge | 173.86 | Cu.m | 1 | ₹173.86 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 15.66 MB
BOQ_961902.xls
BOQ • 0.34 MB
cover1.pdf
Additional Documents • 4.89 MB
12SignedNIT.pdf
Additional Documents • 15.64 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .