Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹48.6 CrAccepted-AOC KANNUR | KERALA | 670001 | L1 | Accepted-AOC L1 | |
| 2 | L2₹47.7 Cr−₹2.0 Cr (3.96%)Rejected-Finance 6 TELEPHONE NAGAR MOOLAPALAYAM ERODE 638 002 | ERODE | ERODE | TAMIL NADU | 638002 | L2 | Rejected-Finance L2 as price preference clause is applicable for the tender |
| Sl No | Description | Qty | Unit | S S Natarajan and Co L1 | THE URALUNGAL LABOUR CONTRACT CO-OPERATIVE SOCIETY L2 |
|---|---|---|---|---|---|
| 1.00SUBHEAD 1 CIVIL WORKS Pile Foundation | |||||
| 1.01 | Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-30(Cement quantity -400kg/m3) of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used.700 mm dia piles | 2,656 | metre | 8,770 ₹2,32,93,155.08 | 8,125 ₹2,15,80,032.5 Lowest |
| 1.02 | Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge.Note: 1. Initial and Routine Load Test shall not be carried out by Dynamic method of testing.Note: 2. Testing agency shall submit the design of loading platform for the approval of Engineer-in-charge.Initial test (Test Load 2.5 times the Safe capacity) test up to 110 tonne capacity(For 700mm dia pile) | 1 | each | 7,63,600 ₹7,63,600 | 1,11,782 ₹1,11,782 Lowest |
| 1.03 | Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge.Note: 1. Initial and Routine Load Test shall not be carried out by Dynamic method of testing.Note: 2. Testing agency shall submit the design of loading platform for the approval of Engineer-in-charge.Routine test(Test Load 1.5 times the Safe capacity) up to 110 tonne capacity(For 700mm dia) | 3 | each | 4,16,500 ₹12,49,500 | 62,280 ₹1,86,840 Lowest |
| 2.00Earth Work | |||||
| 2.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | 5,831.73 | cum | 240 ₹13,99,616.4 Lowest | 269 ₹15,68,736.71 |
| 2.02 | 2.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 800.36 | cum | 210 ₹1,68,076.44 Lowest | 373 ₹2,98,535.77 |
| 2.03 | 2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil | 807.05 | cum | 70 ₹56,493.43 Lowest | 133 ₹1,07,337.52 |
| 2.04 | 2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 2,669.41 | cum | 310 ₹8,27,517.1 Lowest | 324 ₹8,64,888.84 |
| 2.05 | 50.2.25.1 : Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge | 50 | cum | 1,340 ₹67,000 | 661 ₹33,050 Lowest |
Tender Value
₹44.2 Cr
EMD Value
₹5 L
Closing Date
22 Feb 2024, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
MD, INKEL Limited
First Floor, Ajiyal Complex, Kakkanad - 682030
Civil and MEP works
2024_INKEL_653549_1
NIT/INKEL/KIIFB/2023-24/153 Dated 02/02/2024
Open Tender
Civil Works - Buildings
Item Rate
540 days
Perambra Kozhikode
As per tender documennt
21 documents required · 21 mandatory
₹17,700
₹5 L
INKEL Limited
20 Sept 2024
2 Feb 2024
23 Feb 2024
2 Feb 2024
22 Feb 2024
8 Feb 2024
6 Feb 2024
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | SUBHEAD 1 CIVIL WORKS
Pile Foundation | - | - | - | - |
| - | Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-30(Cement quantity -400kg/m3) of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used.700 mm dia piles | 2,656 | metre | - | - |
| - | Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge.Note: 1. Initial and Routine Load Test shall not be carried out by Dynamic method of testing.Note: 2. Testing agency shall submit the design of loading platform for the approval of Engineer-in-charge.Initial test (Test Load 2.5 times the Safe capacity) test up to 110 tonne capacity(For 700mm dia pile) | 1 | each | - | - |
| - | Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge.Note: 1. Initial and Routine Load Test shall not be carried out by Dynamic method of testing.Note: 2. Testing agency shall submit the design of loading platform for the approval of Engineer-in-charge.Routine test(Test Load 1.5 times the Safe capacity) up to 110 tonne capacity(For 700mm dia) | 3 | each | - | - |
| 2 | Earth Work | - | - | - | - |
| - | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | 5,831.74 | cum | - | - |
| - | 2.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 800.36 | cum | - | - |
| - | 2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil | 807.05 | cum | - | - |
| - | 2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 2,669.41 | cum | - | - |
| - | 50.2.25.1 : Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge | 50 | cum | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
BOQ_1007381.xls
BOQ • 1.16 MB
138672912.pdf
Tender Documents • 0.34 MB
138672914.html
Tender Documents • 0.04 MB
GRIHA.pdf
Tender Documents • 0.24 MB
Technicalspec.pdf
Tender Documents • 3.88 MB
Tenderdoc.pdf
Tender Documents • 1.62 MB
Tenderdwg1.pdf
Tender Documents • 13.20 MB
Tenderdwg2.pdf
Tender Documents • 21.16 MB
Tenderdwg3.pdf
Tender Documents • 6.07 MB
soilreport.pdf
Tender Documents • 1.99 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .