Tender Value
₹31.8 Cr
EMD Value
₹63.6 L
Closing Date
12 Oct 2026, 3:00 pm
Superintending Engineer and Project Director PIU-I
Office of the Superintending Engineer and Project Director Project Implementation Unit - I,P.W. (Roads) Directorate, 3No. Commissariat Road Hastings Kolkata-700022.
Saltora-Murulia Road from 0.00 km to 12.70 km, Strengthening work including 4 nos. CD Structures, 600 mtr. Boulder Sausage and 500 mtr. Drain under Bankura Highway Division in the District of Bankura under RIDF-XXXII.
2026_WBPWD_5023136_1
WBPWD/PW(R)/SEPD/PIU-I/NIT-26 OF 2026-2027
Open Tender
CIVIL WORKS
Percentage
300 days
Saltora
Please refer Tender documents.
5 documents required · 5 mandatory
₹63.6 L
Yes
Project Implementation Unit - I, P.W.(Roads) Direc
12 Oct 2026
9 Sept 2026
14 Oct 2026
10 Sept 2026
12 Oct 2026
17 Sept 2026
16 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0PART-A: ROAD WORKS. | |||||
| 1.01 | Cold Milling
Cold Milling of Bituminous Pavement surface upto the required depth by mechanical means using milling machine, without disturbing the under lying layers, to proper line and level, cleaning the surface properly after milling and removing the loose materials, stacking the
milled materials for re-use, necessary guarding,
barricading & lighting, including hire charges of machinery, cost of fuel and labour and other incidental charges all complete and as per direction of Engineer-in-Charge.
For depth upto 100 mm. | 40,220.1 | Sqm | 42.02 | ₹16,90,048.6 |
| 1.02 | Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately (Reference to MoRT&H's specification clause 202)
By Mechanical Means
Bituminous course | 1,456.14 | Cum | 312.86 | ₹4,55,567.96 |
| 1.03 | Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately (Reference to MoRT&H's specification clause 202)
By Manual Means
Granular course | 2,811.75 | Cum | 587.83 | ₹16,52,831 |
| 1.04 | Construction of Embankment with Material obtained from Borrow pits
Construction of embankment with approved material obtained from borrow pits (Using Govt. land) with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 & 300-1 .The size course material in the mix of earth ordinarily shall not be exceed 75mm.(Reference to MoRT&H's specification clause 305). | 4,623.72 | Cum | 168.16 | ₹7,77,524.76 |
| 1.05 | Construction of Embankment with Material obtained from Borrow pits
Construction of embankment with approved material obtained from borrow pits (land owned/arranged by the Agency with Royalty) with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 & 300-1 .The size course material in the mix of earth ordinarily shall not be exceed 75mm.(Reference to MoRT&H's specification clause 305). Cost of compensation for Earth material & its carriage from private land at 5km distance have been included in the rate.
[Note: Royalty as applicable will be deducted from Agency's bill if not produce Royalty clearance certificate from the competent authority.] | 3,082.48 | Cum | 220.72 | ₹6,80,364.99 |
| 1.06 | Construction of Embankment with Material Deposited from Roadway Cutting
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2 & 300-1.The size course material in the mix of earth ordinarily shall not be exceed 75mm.(Reference to MoRT&H's specification clause 305).
Note In case the earth cutting is done by dozer and pushed for filling in the embankment, the input of dozer in the cost of embankment i.e. ₹ 39.63/m3 (excluding overhead, Contractor profit & L.W. cess) shall be deducted from theEstimated Rate as the same is already provided in the cost of excavation. However, if the earth is dumped by tippers from roadway cutting, the input of dozer for spreading is required to be provided. | 2,822.49 | Cum | 105.59 | ₹2,98,026.72 |
| 1.07 | By Mix in Place Method
Construction of granular sub-base by providing graded materials such as crushed stone depending upon the required grading , spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator and compacting with vibratory roller to achieve at least 98% of the maximum dry density for the material determined as per IS:2720 (Part 8), complete as per clause 401 desired density, complete as per clause 401 | 2,472.87 | Cum | 2,377.49 | ₹58,79,223.7 |
| 1.08 | Granular Sub-Base with Graded Material
Plant Mix Method
Construction of granular sub-base by providing graded material such as natural sand/ crushed gravel/crushed stone/combination depending upon the required grading spreading in uniform layers with motor grader on prepared surface, mixing by appropriate mechanical mixure (with controlled addition of water), and compacting with vibratory roller to achieve at least 98% of the maximum dry density for the material determined as per IS:2720 (Part 8), complete as per clause 401
Granular Sub-Base (Grading - V) with Pakur quality Stone aggregate.
(Payment will be made on the basis of finished compacted volume) | 2,447.93 | Cum | 2,504.04 | ₹61,29,714.64 |
| 1.09 | Wet Mix Macadam
Providing, laying, spreading and compacting graded stone aggregate conforming to the grading of table 400- 13 revised vide table 2 of IRC : 109 (2015) to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density . The thickness of a single compacted layer shall not be less than 75 mm.(Reference to MoRT&H's specification 406.
Using Pakur variety stone material.
(Payment will be made on the basis of finished compacted volume) | 3,006.44 | Cum | 3,009.28 | ₹90,47,219.76 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 21.38 MB
BOQ_5106250.xls
BOQ • 0.47 MB
FORM_2911ii_for_25-50cr.pdf
Tender Documents • 0.18 MB
C26.pdf
PDF • 0.14 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .