SE EDC PILIBHIT
Near Roadways Pilibhit
The new 250 KVA Distribution TF installation at different places under EDD Pilibhit Puranpur and incoming outgoing VCB installation at different 33 11 KV S S under EDD-Pilibhit.
2024_MVVNL_917163_1
T-56/EDCP/2023-24
Open Tender
Miscellaneous Works
Item Rate
90 days
Pilibhit/Puranpur
As per tender form
3 documents required · 3 mandatory
₹1,180
SE EDC
₹9,500
1 Jul 2024
14 Mar 2024
9 Apr 2024
14 Mar 2024
9 Apr 2024
14 Mar 2024
Amount
Safe carriage of following materials from store centre under Electricity Store Division Bareilly to site to Jatto ka chouraha, Lekhraj chouraha, Ballabh nagar and Neoriya town under EDD-Pilibhit including loading & unloading up to 0-30 Km. in system strengthening work in different district plan 2023-24
11/0.4 KV, 250 KVA T/F.
STP-11mtr/PCC-8.5 mtr.
Other Balance material, TF channel, top channel, Disk Insulator complete, pin insulator, TPMO, LT XLPE Cable, Stay Complete, Earthing rod etc.
Safe carriage of following materials from store centre under Electricity Store Division Bareilly to site to Purani state bank, Balmeeki Basti and Purani pani ki tanki under EDD-Puranpur including loading & unloading up to 0-50 Km. in Additional Business Plan 2023-24
11/0.4 KV, 250 KVA T/F.
STP-11mtr/PCC-8.5 mtr.
Other Balance material, TF channel, top channel, Disk Insulator complete, pin insulator, TPMO, LT XLPE Cable, Stay Complete, Earthing rod etc.
Construction of 250 KVA T/Fs plinth for 250 KVA T/F of size 5 fit x5 fit x5 fit with the help of first class bricks, cement & coarse sand as per norms. Filling the structure completely by brick blast & plastering work of walls Including CC work on top in ratio 1:2:4 by cement, stone grit & sand and grouting of 2 nos. M.S. channel of size 50x50x5 mm on the top of T/Fs plinth whole work should be done as per RESSPO norms complete in all respect. (All Material will be provided by Contractor own his cost).
Mounting of 250 KVA T/F on newly constructed plinth, laying of cable jumpering and making all HT/LT connections complete work in all respect.
Fabrication and grouting of wire mesh fencing of 28 fit running length in rectangular shape height 2 meter with M.S. angle of size 50x50x06 mm. including gate at one side as per norms complete work and painting of same with 2 coats of red oxide and 2 coats of synthetic enamale paint. (All Material will be provided by Contractor own his cost).
Earthing of T/Fs by boaring type up to water level by providing GI pipe and making connection from boaring site to body and neutral of T/F. (All Material will be provided by Contractor own his cost).
Laying of AB cable 3x95
Erection of the following supports including cutting, making holes, fixing of all types of accessories digging of pits complete in all respect, as per RESSPO drawing. All types of clamps, stone pad, nut, bolt washers would be provided by the contractor.
Double pole structure on PCC. Pole 8.5mtr long complete with bracing.
Erection of stay set with stay wire, stay clamp & stay insulator including with grouting of stay set by concrete of ratio 1:4:8 as per RESSPO norms before back fitting of the pits including binding, climbing, clamping, tightening and nozzeling of stay wire in all respect as per RESSPO norms. All clamps, nuts, bolts, stay insulator, cement. Brick, ballast, sand etc would be provided by the contractor.
Concreting of STP at the time of erection of pole in 1:4:8 concrete ratio from bottom of pole to ground level and plinthing of supports upto 300mm above ground level by using cement, sand & coarse aggregate in ratio 1:4:8 as per RESSPO drawing with watering/curing properly upto proper setting of plinthing. All matrial would be provided by the contractor.
Earthing of STP of the line is to be done by inserting the MS earth rod (1800x20mm) into soil by hammering and properly fastning with GI wire to each support by nut & bolt. Earthing rod must be 0.15Mtr.above from the plinth of the support. All type nut & bolt would be given by the contractor.
Fabrication and Installation of 11 KV fuse set on midway 11 KV double pole structure with mention material As- MS channel 100x50x2028 mm, Iron strip-50x5x305 mm, fuse wire and holding clamps etc. complete work in all respect all required materials provided by contractor on his own cost.
Providing and fixing of henely type LT tailess units for suitable of 250 KVA T/Fs. Complete work in all respect all required materials provided by contractor on his own cost.
Safe carriage & errection of replacement of defective 11 KV incoming and outgoing VCB at 33/11 KV S/S Ramleela Gramin, Jhahnabad and Naktadana under EDD-Pilibhit including loading unloading at both end distance up to 0-15 Km. in system strengthening work in different district plan 2023-24
Safe carriage & errection of 11 KV VCB I/C
Safe carriage & errection of 11 KV VCB 0/C
ASTHA TRADERS
DURGESH CHANDEL
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Tendernotice_1.pdf
Tender Document • 0.72 MB
Corrigendom8.pdf
Tender Document • 0.25 MB
Corrigendom.pdf
Tender Document • 0.23 MB
form.pdf
Tender Document • 1.30 MB
BOQ_1585220.xls
BOQ • 0.63 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .