Loading…
Loading…
Tender Value
₹2.0 Cr
EMD Value
₹1.3 L
Closing Date
17 Jul 2026, 5:30 pm
Chief General Manager (Thermal)
Package (A) Disposal of Ash at pre-designated locations of mines pit / any other locations, and Package (B) Cleaning of underneath and surrounding areas of Fly Ash and Bed Ash silos at 4 x 125 MW (Unit: 1 to 4) CFBC based Surat Lignite Power Plant
296460
SLPP/AHS/BRC/DC/2026-28
Open
Services
Surat
₹2,950
Nani Naroli Surat
₹1.3 L
30 Apr 2026
30 Apr 2026
21 Jul 2026
30 Apr 2026
17 Jul 2026
30 Apr 2026
documents for Technical Bid in Office of Surat Lignite Power Plant (SLPP)
E-Reverse Auction Will be informed by GIPCL to all qualified Bidders
1. Amendment / corrigendum of the Tender Document, forms, schedules, etc. may be
done any time by the GIPCL during the period of publication of Tender on the
website. The Bidders are required to visit the website regularly till the last date &
time of Bid submission.
2. GIPCL reserves the right to reject any or all the tenders without assigning any
reason thereof.
3. The Bidders are required to quote the rate strictly as per the terms and conditions
mentioned in the tender document, adhering to technical specifications as well.
4. The Bidders are required to submit their Bids online only through (n)Procure portal
(https://tender.nprocure.com)
5. The EMD, Tender fee & other supporting documents are to be submitted in physical
form only at the following address:-
Gujarat Industries Power Company Limited,
Surat Lignite Power Plant,
At Village: Nani Naroli,
Taluka: Mangrol, Dist.: Surat - 394 112, Gujarat.
INSTRUCTIONS TO BIDDERS
1. PLANT SYNOPSIS
Gujarat Industries Power Company Limited (GIPCL) (henceforth be named
Company/GIPCL), is a Premier Power Utility in the State of Gujarat with an installed
capacity of 1859.40 MW comprising of various conventional and renewable projects.
GIPCL commissioned its first power project: a 145 MW gas based combined cycle power
plant in 1992 at Vadodara. It expanded its capacity by 165 MW Neptha and Gas based
Combine Cycle Power Plant at Vadodara in
Surat Lignite Power Plant (SLPP) with four units of 125 MW capacities each is located at
Village: Nani Naroli, Taluka: Mangrol, District: Surat in Gujarat. GIPCL has also operating
its own captive Lignite and Lime Stone Mines close to the Power Plant. The Power Plant
is based on Circulating Fluidized Bed Combustion (CFBC) technology for the Boilers,
where Lignite is burnt along with Lime Stone in the Combustor of the Boiler.
It commissioned 5 MW Solar Power Plant on the Vastan Mine dump top adjacent to Surat
Lignite Power Plant in January 2012. Also, GIPCL has commissioned 1MWp Distributed
Solar Power Projects at two locations in Gujarat viz. at Village: Amrol, Dist.: Anand in
April, 2016 and at Village Vastan, Taluka Mangrol, and Dist.: 2016. Surat in May
GIPCL has successfully commissioned a 2 X 40 MW Solar Project in September 2017 as
well as a 75 MW Solar Power Project in June 2019 at Gujarat Solar Park, Village
Charanka, Dist.: Patan. GIPCL has also successfully commissioned 112.4 MW wind
farms at different location of Gujarat. The Company has commissioned the 100 MW Solar
Project at the Raghanesda Solar Park, Banaskantha, Gujarat on August 2021. The
Company has also commissioned 75 MW Solar project at Vastan Lignite Mine, Tal.
Mangrol, Dist. Surat, Gujarat in June 2025. The Company has also developed 2375 MW
Renewable Energy Park at Khavda in the Kutch district of Gujarat in Dec
Surat Lignite Power Plant (SLPP) is accessible by road from Kim and Kosamba, which
are on Mumbai-Ahmadabad highway. From Kosamba, SLPP is around 32 km, out of
which 27 km is part of the National & State Highway and balance 5 km is District Road.
From Kim, SLPP is around 18 km, out of which 13 km is the State Highway and balance
km is District Road. The nearest Broad Gauge Railway Line is at Kim, which is around
km from the SLPP. Surat is approximately 50 km from the SLPP. Location Map for SLPP
The Company intends to award Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-
designated locations of Mines pit / any other locations and (B) Cleaning of Areas underneath and
surrounding Fly Ash & Bed Ash Silos (Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW
Power Plant and is therefore inviting e-Tenders online on (n)Procure portal
(https://tender.nprocure.com)from experienced & resourceful Contractors.
2. SCOPE OF WORK
2.1 The brief Scope of Work covers:
Package A: The disposal of Ash (filled directly from the silos) at pre-designated locations of
mines pit / any other location. The pre-designated locations are situated at following four (4)
different distance ranges from Fly Ash Silos (FAS) – 3,4 of SLPP:
(i) 0 km to < 3 km (one way from FAS-3&4);
(ii) > 3 km to < 6 km (one way from FAS-3&4);
(iii) > 6 km to < 9 km (one way from FAS-3&4);
(iv) > 9 km to < 12 km (one way from FAS-3&4).
Package B:The regular cleaning of Silo areas which mainly includes underneath of Fly Ash and
Bed Ash Silos and also surrounding areas of Silos along with the connecting roads surrounding
and nearby Silo area. The collected / accumulated Ash thus shall be transported to locations as
directed by GIPCL’s Engineer In-charge.
The detailed scope of work is mentioned herein the Section - D (Special Conditions of Contract) of
this Tender document.
2.2 The Bid submitted by the Bidder not covering the total scope of work and services as
detailed out in the tender document shall be liable for rejection.
2.3 Quantum of job mentioned against all items in the Price bid are indicative only & may vary
as per site requirement & not to be construed as maximum or guaranteed quantity. The
quantities shown in the price bid are approximate quantities for the contract period and may
vary as per job requirements.
2.4 All the miscellaneous activities pertaining to specific work to be executed for satisfactory
performance is in the scope of Contractor in his quoted rates.
3. GENERAL INSTRUCTIONS
3.1 The Bidders who are interested in participating in the Tender must read and comply with
the instructions and the Terms & Conditions contained in the Tender Document.
3.2 The Bids shall be filled in by the Bidders clearly, neatly and accurately. Any alteration,
erasures or overwriting shall be liable to make the tender invalid unless the same is neatly
carried out and attested over the full signature of Bidder. The decision of the Company to
interpret the information and rates filled in by the Bidder shall be final and binding on the
3.3 The Bidders are requested to make themselves fully conversant with the General
Conditions of Contract, Special Conditions of Contract, Technical Specifications, Site
conditions, Safety & Health Aspects and Norms to be observed etc. before submitting their
bids so that no ambiguity arises in these respects subsequent to submission of the Bids.
3.4 Before quoting the rates, the Bidder should go through the specifications, scope of work
etc. and get himself fully conversant with them. The Bid should include cost of mobilization
and cost to adhere to all Safety Norms as described in the Tender. No relaxation or
request for revision of quoted / accepted rates shall be entertained subsequent to the
opening of Bid on account of mobilization or Safety costs.
3.5 Splitting of work is not advisable as the purpose of SoR method will not be fulfilled.
3.6 Bidder has to submit all the information as per required Bid document. Failure to furnish all
the information as per required Bid documents or submission of a Bid containing
deviations from the contractual terms and conditions, specifications and requirements,
shall be rejected.
3.7 The Bids shall be submitted within the time frames set out in the Notice Inviting Tender
(‘NIT’) and Bids submitted thereafter shall not be accepted and considered.
3.8 The Tender Document shall not be transferable.
3.9 The Bidders are expected to examine all instructions, forms, terms & specifications in the
Bid documents and to get fully acquainted themselves with all the conditions and matters
which may affect the subject matter of the work/tender or the cost thereof. If any Bidder
finds any discrepancies or omissions in the specifications and documents or any doubt in
true meaning or interpretation of any part, he shall seek necessary clarifications in writing if
3.10 Conditional offers shall not be considered and liable to be rejected.
3.11 The Company reserves the right to extend the deadlines for submission of the Bids by
giving amendments.
3.12 Bidders may visit site for detailed understanding regarding the “Scope of Work” as per the
Tender document, with due prior intimation in writing pertaining to the said Site visit.
3.13 During evaluation of Bids the Company may, at its discretion ask the Bidder(s) for
clarification of their Bid. The request for clarification and the response shall be in writing
and no change in prices or substance of the Bid shall be sought, offered or permitted.
3.14 The Company reserves the right to amend / modify the Bidding documents at any time
prior to the deadline for submission of Bids, either at its own discretion or in response to
the clarification requested by a prospective Bidder. In such case, the Company may in its
discretion extend the deadline for submission of Bids in order to facilitate the prospective
Bidders for incorporating the effect of the amendment in their Bids.
3.15 The Bidders shall bear all costs and expenses associated with the preparation and
submission of their respective Bids, to attend meetings or conferences, if any, including
any pre award discussion with the successful Bidder, technical and other presentations
etc. and the Company shall not be liable for any expense thereof.
3.16 If the successful Bidder is a joint venture, formed of two or more companies, the Bidder
along with the partners shall accept joint and several responsibilities and liabilities for all
obligations under the Contract.
3.17 Timely and satisfactory completion of the work and strict adherence to the allotted time
frames for jobs shall be the essence of the contract.
3.18 The Company reserves the right to qualify/disqualify any applicant without assigning any
3.19 The Bidder shall be disqualified if any untrue statement or misrepresentation is made in
the Bid forms, attachments and other supporting documents submitted by the Bidder.
It is perquisite and necessary for all interested Bidders to visit the site/plant after downloading the
Tender copy to understand the actual working conditions, compliance related to labour, safety etc.
before submitting their offer. Failing which, any consequential liabilities arising will be to Bidder’s
account. The Bidders shall examine the site of works and its surroundings at his own
responsibility. The Bidders shall collect information that may be necessary for preparing the Bid
and entering into a Contract. All costs and liabilities arising out of the site visit shall be at Bidder’s
The Bidder is deemed to have examined and understood the Tender document, obtained his own
information in all matters whatsoever that might affect the carrying out the works expressly
mentioned or works which may have to be carried out to fulfill his contractual obligations within the
scheduled rates and to have satisfied himself to the sufficiency for his offer.
The submission of Tender by a Contractor implies that he has read these instructions, conditions
of the contract etc. and has himself aware of the Scope, nature of works & specifications of the
works to be done. GIPCL will not, therefore after acceptance of Contractor’s rate, pay any extra
charges for any other reason in case the Contractor is found later on to have misjudged the site
Any error in description or quantity or omission in the contract document shall not vitiate the
contract or release the Contractor from executing the work comprised in the contract according to
scope of works, magnitude of the works, requirement of materials, equipment, tools & tackles,
labour, etc. Contractor has to complete the work in accordance with the contract documents
irrespective of any defects, omissions or errors that may be found in the contract documents.
BIDDER shall inspect the site, examine and obtain all information required and satisfy himself
regarding matters such as access to site, communication, transport, working condition including
constraint of work place, confined area, quantum of dusting, running equipment, importance of
work, round the clock working conditions, safety requirements, right of way, high flood level in
River, flow of water during monsoon/dry season in the River/Nullah, the type and number of
equipment and facilities required for the satisfactory completion of work, the quantity of various
items of the work, the availability of local labour, availability and rates of material, local working
conditions, uncertainties of weather, obstructions and hindrances that may arise, etc which may
affect the work or cost thereof, before submission of his Bid. Ignorance of site conditions shall not
be accepted by the GIPCL as basis for any claim for compensation. The submission of a Bid by
the BIDDER will be construed as evidence that such an examination was made. Any later claims /
disputes in regard to rates quoted shall not be entertained or considered by the GIPCL.
The rates quoted by BIDDER shall be based on his own knowledge and judgment of the
conditions and hazards/risk involved and shall not be based on any representations of the
5. ELIGIBILITY CRITERIA
The following criteria shall be adopted for qualifying the Bidders for further proceeding:
5.1 Bidder should possess minimum Three years of experience out of last five years ending
last day of the month previous to the one in which tender is invited in similar nature of
mechanized jobs involving the equipment / machinery / vehicle such as JCB / Loader,
Trucks, Dumpers and other similar types of HMVs / HCVs, Earth mover equipments and
Logistics / Transportation of Minerals/Sand/Earth material/Cement etc. Bidder shall
enclose the proof of the same. Bidder shall submit necessary evidence for the same like
attested copies of work orders along with work completion certificates from clients. The
work completion certificate shall comprise of Order value & Executed value. Bidders
should have executed the work directly. The work executed as a sub-contractor or
subletting agency shall not be taken in to consideration.
Note: For evaluation of the bid, the executed value mentioned in the work completion certificate
will be considered.
5.2 Bidder must Own / Possess the following category of equipments:
(i) Minimum one (1) loader of make and model: JCB (3DX) or equivalent equipment of
suitable capacity.
(ii) Minimum one (1) multi-axle open body tipper (truck/dumper) of suitable storage capacity
and having hydraulic unloading arrangement.
(iii) Minimum five (5) multi-axle closed body tippers (trucks/dumpers) of suitable storage
capacity (closed body tippers here meaning tippers completely enclosed with metallic
sheeting and having only one (1) suitable size opening for loading of Ash through
telescopic spouts installed at Fly Ash Silos of SLPP, and further having hydraulic
unloading arrangement.
The relevant copies showing the Ownership / Possession of the above mentioned equipments /
machinery / vehicle shall be submitted along with the Bid. In case of possession of the above
equipments, the Bidder shall submit the Possession Agreement on non-judicial stamp paper of
proper value, in accordance with the Stamp Act. The notarized Possession agreement shall
contain, without fail, (i) sign / stamp of the firms / persons / proprietors involved, (ii) appended
along with the self attested copy of any Government approved photo identities of the firms /
persons / proprietors, and copies of original R.C. Books of respective vehicles i.e. JCB / Truck /
Dumpers (iii) the Tender Title along with the Contract period (the possession agreement shall be
valid for, at least, the whole Contract Period including extension(s) in Contract period, if any).
5.3 Bidder should produce evidence of having experience of successfully completed
similar works as defined hereunder during last five years ending last day of the month
previous to the one in which tender is invited, satisfactory progress of ongoing works etc.
secured from clients along with certified copies of documentary evidence preferably photo
copies of work experience. The experience should be either of the following:
a. One similar completed work each costing not less than the amount equal to
b. Two similar completed works each costing not less than the amount equal to
c. Three similar completed works each costing not less than the amount equal to
Bidder should specifically mention fulfilling of above criteria in his offer along with details of work
orders & work completion certificates issued by clients.
5.4 Tender Fee: The Tender Fee shall be accompanied in form of RTGS only.
5.5 EMD: The EMD shall be accompanied in the form of DD/RTGS or Bank Guarantee given
by Bank as described in detail in Clause No. 7 of this Section of Tender Document.
5.6 Bidder should have separate Employees Provident Fund code number towards registration
of firm with RPF commissioner.
5.7 Attested copies of relevant documents duly signed & sealed on each & every page shall
be submitted. The above documents will be analyzed and if found satisfactory, the Price
Bid will be open. GIPCL may verify the documents, experience certificates issued by
concerned authority. After opening of Technical Bid, if any required attested documents
found missing in the Technical Bid submitted by the Bidder, the tender inviting authority
may inform to that Bidder only once by e-mail to submit the missing required documents
within stipulated time limit. If Bidder/Bidders fail to submit within stipulated time, their Bid
will be declared technically disqualified and no further correspondence will be entertained.
5.8 Bidder should have average annual turnover of 19.17 Lac for last three financial years
i.e. FY: 2022-23, FY: 2023-24 and FY: 2024-25. Bidder shall furnish annual audited
financial statement duly certified by/from a qualified Chartered Accountant, being a
member of the Institute of Chartered Accountants of India for the aforesaid three financial
years to demonstrate the financial healthiness of the company. The Balance sheet must
be in the name of the company. Any type of MOU for this purpose will not be entertained.
Note: In case, the annual turnover is less than the statutory guidelines which does not require
audit, the Bidder shall submit the turnover certificate from Chartered Accountant.
5.9 The Bidder has to submit Income Tax Permanent Account Number (PAN) & GST
registration number. Copy of the same shall be submitted.
5.10 The Net worth at the end of the financial year 2024-25 should be positive (+) as per
audited accounts audited by a qualified Chartered Accountant, being a member of the
Institute of Chartered Accountants of India .
5.11 In case Bidder is a Consortium / joint deed of undertaking of company, the above
requirements/credential of consortium leader / bidder shall be considered unless otherwise
specifically mentioned in the tender.
5.12 If Bidder or its Partner(s) or Director(s) is /are/was in any Litigation(s), Court Case(s) or
Arbitration(s), either completed or under progress during last five (5) years or Black Listed
/ Deregistered / Stopped or banned from dealing in the past by any Govt. of Gujarat
Undertakings / Depts. / Authorities and Govt. of Gujarat supported companies /
undertakings / organizations, Bid of that party will be liable to be rejected. Bidder agrees
and undertakes to accept decision of GIPCL in this regards as final and binding on the
Bidder without any demur and that no further correspondence shall be done in this regard
at any stage. Bidder shall have to submit the “Declaration for Contractual Disputes/
Litigations” as appended in Annexure – G (SECTION – F)
5.13 Bidder shall have to submit the “Declaration-cum-Undertaking for Compliance of Safety
Laws and Regulations” on his company letter head as amended in Annexure-F in Section-
F / Form attached.
If any Major Violation of any safety law(s) / Rule(s) is / are found during the
preceding Three (3) years, Bid of that party will be liable to be rejected. Bidder
agrees and undertakes to accept decision of GIPCL in this regard as final and
binding on the Bidder without any demur and that no further correspondence shall
be done in this regard at any stage.
If any of the details submitted in the prescribed Annexure / Form to the Bid is/are
found to be false, incorrect at any time in future, then the Contract awarded to that
Bidder / Contractor shall be liable to be terminated forthwith without any notice /
correspondence and Bidder agrees and undertakes to accept decision of GIPCL in
this regards as final and binding on the Bidder without any demur and that no
further correspondence shall be done in this regard at any stage. Further,
Performance / Security Deposit will also be liable to be forfeited. Any dues to
GIPCL from the Bidder / Contractor shall be recovered from the pending bills or
any other dues payable to the Bidder / Contractor, if any or otherwise through any
other recourse available under the Laws.
The Bidder shall submit all the evidences, documents, attested copies of Work Orders & Work
completion certificates etc. as a proof with EMD & Tender Fee and also provide the requisite
details ‘Online’ for meeting the pre-qualification requirements. GIPCL will verify the experience,
performance, capability & strength of Bidders, independently for executing the job. GIPCL may
visit the site & consult the owner of the industry/property where similar job is executed by the
Bidder. GIPCL reserves the right to accept / cancel / reject any / all Bids without assigning any
reason thereof. The Tenders of qualified Bidder/Bidders shall only be considered for further
5.14 Site Visit is mandatory prior to submission of bid to understand the scope of work, working
conditions, site conditions, equipments, tools & tackles, labor deployment, associated risk,
surrounding etc.
6. LANGUAGE OF BID
The Bid prepared by the Bidder, and all correspondence and documents relating to the Bid
exchanged by the Bidder and the Company, shall be written in the English language. Any printed
literature furnished by the Bidder, written in another language shall be accompanied by an English
translation for the purpose of interpretation of the Bid.
7. EARNEST MONEY DEPOSIT (EMD) and TENDER FEE
7.1 An EMD of Rs. 1,27,000/- and Non-refundable Tender fee Rs. 2950/- (18% GST
inclusive) shall accompany with Bid. The EMD shall be in the form of a crossed bank
Demand Draft in favour of Gujarat Industries Power Co. Ltd. as per following details:
Bank Payable at:
1. Bank of Baroda Mosali, Dist: Surat
2. State Bank of India Nani Naroli, Branch Code:
3. Any Nationalized bank Surat
The Tender Fee shall be paid through RTGS only.
Alternatively, the EMD may be submitted through RTGS / NEFT payment mode and the relevant
account details of GIPCL for the same being as follows:
Name of account holder Gujarat Industries Power Co. Ltd.
Name of Bank State Bank of India
Address of Bank Utility Building, Nani Naroli, Taluka Mangrol, Dist. Surat. Pin
IFSC code SBIN0013423
7.2 The EMD, in alternative, may be submitted in the form of irrevocable Bank Guarantee in
favour of Gujarat Industries Power Company Limited from any Nationalized Bank including
Public Sector bank - IDBI Ltd or AXIS Bank, HDFC Bank, Yes Bank, ICICI Bank or Kotak
Mahindra bank, Ratnakar Bank, IndusInd Bank, Karur Vysya Bank, DCB Bank, ING
Vyasya Bank or The Kalupur Commercial Co-operative Bank Ltd, Rajkot Nagrik Sahakari
Bank Ltd, The Ahmedabad Mercantile Co-operative bank Ltd, The Mehsana Urban Co-
operative Bank Ltd, Nutan Nagrik Sahakari Bank Ltd as per Proforma of BG enclosed with
this E-tender under Section-F.
7.3 In case EMD is paid in the form of BG, the same shall be valid for a period of 180 days
after the due date for submission of the Bid.
7.4 The EMD of the successful Bidder will be returned after payment of Security Deposit within
21 days from the date of award of contract by successful Bidder.
7.5 The Earnest Money Deposit will be refunded to the unsuccessful BIDDER as soon as the
Tender is finalized and after award of LOI/WO.
7.6 Any bid not accompanied with EMD and Tender fee will be rejected. In case of EMD not
submitted by way of RTGS, Physical form of the same with details of tender fees & RTGS
submission to be submitted directly to GIPCL as per Clause 7.9.
7.7 No interest shall be payable on EMD.
7.8 The EMD will be forfeited if the BIDDER (i) withdraws his Tender after acceptance or (ii)
withdraws his Tender before the validity date of the tender.
7.9 SCHEDULE OF EMD & TENDER FEES:
EMD & details of Tender fee Address for Submission:
paid by RTGS and other CGM (THERMAL),
GUJARAT INDUSTRIES POWER CO. LTD.,
documents duly signed to be
(Surat Lignite Power Plant)
submitted in physical form on
Village – Nani Naroli, Taluka – Mangrol
or before last date of online District – Surat 394 112, Gujarat
bid submission at the Phone : 02629-261063 (10 lines)
adjacent Address Fax : (02629) 261073 /
8. SUBMISSION OF BIDS
A. MODE OF SUBMISSION
The Bids shall be submitted online on (n)Procure portal (https://tender.nprocure.com) within
the dates specified in the NIT along with the details of Tender Fees, EMD in two parts as under:
(a) Pre qualification and Techno-commercial Bid without price:
The Tender document duly signed in all pages without price bid along with techno-commercial
deviations, if any, shall accompany the Bid. The following Information shall be provided in the
techno commercial bid:
a. Schedule of deviation (SECTION – F: Annexure E) Technical as well as commercial, if
The following supporting documents shall also be submitted along with EMD & Tender Fee in
1. The Tender Document duly signed in all pages without price bid along with Techno-
commercial deviations, if any.
2. Proof of experience meeting the minimum ‘Eligibility Criteria’ (Clause No. 5 above).
3. Performance certificate issued by clients.
4. Previous Work Order copies.
5. Details of present Work Order (if any).
6. Average Annual Turnover for the last three financial years i.e. FY: 2022-23, FY: 2023-24
and FY: 2024-25, audited annual accounts / financial statements i.e. Profit and Loss
account and Balance Sheet duly certified by a practicing CA will be required.
7. P.F Number and Allotment Letter.
9. GST registration number/certificate copy.
10. Copies of RC Books / Certificate showing Ownership / Possession for JCB, Open truck
(tipper) and closed body dumpers (tippers) as mentioned in ‘Eligibility Criteria’ (Clause No.
To participate in e-Reverse Auction, Bidders have to create e-Auction user Id on
https://e-auction.nprocure.com and it is mandatory to submit the same along with
physical Techno-commercial Bid; so that the Bidder shall be allowed to participate in
the e-Reverse Auction.
1. Value of Work displayed on (n)Procure is with GST@18%. Price Bid shall be submitted
online only in through (n)Procure portal (https://tender.nprocure.com).
Note: Estimate includes cost of all manpower, equipments, vehicles, consumables,
fuel, tools & tackles, transportation, Safety statutory compliance, mobilization etc.
2. GST shall be paid at actual as per prevailing rates as declared by Central Government on
submission of documentary evidence.
3. Bidder shall have to quote the rates in the form of percentage (%) i.e.
AT the estimated Contract value OR
_____% BELOW the estimated Contract value OR
_____ % ABOVE the estimated Contract value
4. The quantities shown in the Section – E: Schedule of Quantities and Price are
approximate for the Contract Period and may vary as per job requirement.
5. The Bidder shall fill the Bid documents with utmost care in consonance with the instructions
contained in the Bid documents.
B. METHOD OF TENDERING / SIGNATURE ON BIDS
(i) The Bid must contain the postal address like name, residence and place of business of the
person or persons submitting the Bid and must be signed and sealed by the Bidder with his
usual signature. The name of all persons signing the documents shall also be typed or
printed below the signature on each page.
(ii) Bid by a joint venture/partnership firm must be furnished with full names of all partners and
be signed with the partnership name, followed by the signature and designation of one of the
authorized partners or other authorized representative(s). A certified copy of the power of
attorney authorizing such partner or representative shall also be submitted.
(iii) Bids by a Corporation/Company must be signed with the legal name of the
Corporation/Company i.e. by the President/Managing Director/Secretary or other person or
persons authorized to Bid on behalf of such Corporation/Company. A certified copy of the
board resolution/power of attorney authorizing such partner or representative shall also be
(iv) The Bidder's name stated on the proposal shall be the exact legal name of the firm.
(v) Erasures or other changes in the Bid Documents shall be initialed by the person signing the
(vi) Bids not conforming to the above requirements of signing shall be disqualified.
9. MODIFICATION AND WITHDRAWAL OF BIDS
a. The Bidder may modify or withdraw the bid prior to the deadline prescribed for submission of
b. No Bid shall be modified subsequent to the deadline for submission of Bids.
c. No Bid shall be withdrawn in the interval between the deadline for submission of Bids and
the expiration of the period of bid validity.
10. POLICY FOR BIDS UNDER CONSIDERATION
a. Bid shall be deemed to be under consideration immediately after opening of the Bid and till
official intimation of award / rejection made by the Company to the Bidders.
b. While the Bids are under consideration, Bidders and / or their representative or other
interested parties are advised to refrain from contacting by any means, the Company. The
Engineer, if necessary, will obtain clarifications on the Bids by requesting for such
information from any or all the Bidders, in writing as may be necessary. The Bidder will not
be permitted to change the price or substance of the Bid after the Bid has been opened.
11. EFFECT AND VALIDITY OF THE BID
a. The Bid should be kept valid for acceptance for a period of one hundred and eighty (180)
calendar days from the last date of submission of Bids.
b. The submission of any Bid along with the required documents and specifications shall
constitute an agreement that the Bidder shall have no cause of action or claim, against the
Company for rejection of his Bid. The Company shall always be at liberty to reject or accept
any Bid or Bids at his sole discretion and any action will not be called into question and the
Bidder shall have no claim in that regard against the GIPCL.
12. OPENING OF BIDS
12.1 GIPCL will open the Pre-qualification / Technical Bid / Price Bid, as the case may be, in
presence of Bidder's representatives whenever such a procedure has been specified.
Otherwise the tender will be opened by the authorized officers of GIPCL.
12.2 Preliminary Examination:
12.2.1 The Company will examine the Bids for any computational errors, for sureties
furnished by Bidder, for authentication of documents submitted and completeness of
12.2.2 Arithmetical errors will be rectified on the following basis:
(a) If there is a discrepancy between the unit price and the total price that is obtained by
multiplying the unit price and quantity, the unit price shall prevail and the total price will be
corrected & will be binding to the Bidders.
(b) If there is a discrepancy between the Total Bid Amount and the sum of total prices, the
sum of total prices shall prevail and the Total Bid Amount will be corrected & will be binding
to the Bidders.
13. EVALUATION & COMPARISON OF BIDS
13.1 GIPCL shall evaluate the Bids received and accepted by it to ascertain the lowest
evaluated Bid in conformity with the specifications of the Tender Document.
13.2 The Technical Bids will be examined for minor matters regarding qualification of bids.
Subsequent to correspondence with the respective bidders, the decision of Tender
Committee will be final.
13.3 All responses to requests for clarifications shall be in writing and shall be presented to the
Company through e-mail or in a sealed envelope on or before the given date requested by
the Company. If the Technical clarifications sought by the Company do not reach the
Company on or before due date, the Bid will be rejected.
13.4 The comparison of all the Bids shall be carried out with reference to the scope of work as
per the technical specification. Any deviation / omission shall be evaluated at highest
quoted price of the deviation / omission quoted by any of the Bidder. In case a separate
price (for omission) is not given by any other Bidder, a reasonable price of the same shall
be taken & the same shall be binding to the Bidders.
13.5 The commercial deviation, if any, shall be loaded to bring all the Bids at par. The loading
shall be carried out at an interest rate of 2% above PLR of SBI.
13.6 A Bid to be substantially responsive shall be one which on evaluation confirms to all the
terms, conditions and specifications of the Bid documents without any material deviation or
13.7 For the above referred purpose, a ‘material deviation’ shall be one which:
(a) Affects in any substantial way the Scope, Quality or performance of the
(b) Limits in any substantial way and in a manner inconsistent with the Bid documents,
GIPCL’s right or the Bidder’s obligations, under the contract, or
(c) Rectification of it would affect unfairly the competitive position of other Bidders presenting
substantially responsive Bids.
14. RIGHT OF REJECTION OF TENDERS
14.1 GIPCL reserves the right to accept or reject any Bid or to cancel the Bidding process and
reject all Bids at any time prior to award of Contract, without thereby incurring any liability
to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders
regarding the same.
14.2 Any Tender without EMD and Tender Fee will be treated as non responsive and shall be
rejected at the outset & no further correspondence shall be entertained regarding this.
14.3 GIPCL reserves the right to debar any Bidder from participation in future Bids if such
Bidder has quoted an abnormally low rate in the Bid document/Price Bid.
15. AWARD OF CONTRACT
15.1 GIPCL will award the Contract to that Bidder whose quotation has been determined to be
substantially responsive and evaluated as the lowest quotation in conformity with the
requirements of the specifications and documents contained herein, provided further that
the bidder is determined and evaluated to be qualified to perform the contract
satisfactorily.
15.2 The successful bidder shall be intimated of his selection through the Letter of Intent or
Letter of Award/ Work Order which shall be sent to him through e-mail, courier, fax or
registered mail.
15.3 GIPCL reserves the right to cancel/short close the contract during the contract period by
giving prior notice of one month without assigning any reason.
15.4 GIPCL reserves the right to split the contract quantity between vendors
16. CONTRACT PERIOD
16.1 The Contract will be for a period of two (2) years and shall commence from the date as
mentioned in the Letter of Intent (LoI) / Work Order which shall be awarded to the
successful Bidder (‘Contract Period’).
16.2 GIPCL reserves the right to extend the Contract Period up to 3 months on the same
rates and terms and conditions without any price escalation and entering into any new
16.3 The said Contract Period can be extended if mutually agreed upon by both the parties up
to one year and in such a case a revised Work Order shall be issued at the same rates
and terms & condition or at negotiated rates acceptable by both parties i.e. the Company &
the Contractor.
17. ASSIGNMENT AND SUB-LETTING:
The contractor shall not directly or indirectly assign or sub-let total / any part of contract to
any other party or agency.
18. CONTRACTOR’S OBLIGATIONS
DEPLOYMENT OF EQUIPMENT / MACHINERY / VEHICLE
(i) The Contractor shall own / possess the vehicles as specified vide Clause No. 5.2 of
‘Eligibility criteria’ as per this tender document.
(ii) The Contractor shall deploy skilled JCB operator and tipper drivers having a valid driving
License of respective earth mover category and/or HMV / HCV category.
(iii) At the time of deploying manpower, the Contractor shall strictly comply all the applicable
labour laws / acts norms including but not restricted to the age of the workers, women
workers and shall also ensure that a police verification and security check for all the
workmen / labour engaged at the GIPCL site is done and necessary documents regarding
the same shall be submitted to the GIPCL’s authorized representative/officer-in-charge. Any
default in complying with the same or any misrepresentation regarding compliance of the
same shall compel GIPCL to initiate appropriate civil or criminal proceedings regarding the
(iv) Contractor has to keep required tools to tochan the vehicles (like wire rope, shovel etc. to
immediately remove the stuck vehicles at any place of disposal area.
(v) The Contractor shall also comply with the safety requirements and provide his
workmen/labour with safety equipment like safety shoes, safety helmets, safety shoes
masks, gum boots, a uniform and other necessary PPEs for properly undertaking the
operations involved under this contract. Following are also to be issued:
(vi) Contractor shall nominate / authorize experienced person in writing as Site In-charge /
Supervisor to co-ordinate with GIPCL’s Engineer and who shall bear overall responsibility for
performance of the Contract. Such person shall remain always available at site. Contractor
has to submit the authority letter and documentary proof for the same.
(vii) Site In-charge / Supervisor shall co-ordinate with GIPCL’s Engineer In-charge for daily
execution of job. They have to maintain daily records duly signed for the works carried out
and duly certified by Engineer-In-Charge. The Contractor in co-ordination with the Engineer-
In-Charge shall ensure the availability of adequate manpower / machinery / equipment /
vehicle to carry out the job satisfactorily on a daily basis. As per the instruction of Engineer
In-Charge they have to allot the work and execute the same in specified time limit.
(viii) During execution of the works, one or more jobs may be required to be done simultaneously
and the Contractor shall mobilize additional resources accordingly.
(ix) During emergency or similar situations the Contractor shall be required to mobilize
resources as per need within the period of four (4) hours as directed by GIPCL. If the
Contractor fails to mobilize sufficient resources to complete the job in time, GIPCL will
execute the job through other agency at the risk and cost of the Contractor with 10%
supervision charges plus applicable GST as per extant GST Laws & other taxes & duties as
per applicable extant laws & the same will be recovered from the Contractor’s bill.
19. CLARIFICATION OF BIDDING DOCUMENTS
If any Bidder requires any further information or clarification in the Bidding Documents, may notify
the Company before one week of last date of submission of online Bid, in writing or by E-mail at
the GIPCL's mailing address [email protected] as indicated in the 'Invitation to Bids'. The
GIPCL's response (including an explanation of the query) will be sent in writing or by E-mail to all
prospective Bidders who have received the Bidding Documents.
20. TIME SCHEDULE
The basic considerations and the essence of the 'Contract' shall be the strict adherence to the
time schedule for performing the specified 'Works'.
21. UNDERSTANDING AND CLARIFICATION ON DOCUMENTS AND
The Bidder is required to carefully examine the specifications and documents, all the conditions
and matters work wise & cost wise. If any Bidder finds any discrepancies or omissions in the
specifications and documents or is in doubt for any meaning of any part, he shall request in
writing for an interpretation/ clarification to the GIPCL.
All such interpretations and clarifications shall form a part of the Bid documents.
All the payments against the work order shall be in Indian currency and payable through cheque /
23. POINTS TO BE CONSIDERED DURING QUOTING ONLINE PRICE BID
a. The Schedule of Rates (SoR) shall be read in conjunction with Instructions to Bidders,
General Conditions of Contract, Special Conditions of Contract and Technical specifications.
b. The quantities given in the Schedule of Rates (SoR) are estimated and will be made as per
actual work carried out as per the rates of Work Order.
c. The method of measurement of completed work for payment shall be in accordance with the
method of measurement specified in the Tender document
d. No separate amount shall be payable for use of auxiliary equipment incidental to or in day to
day operation in the course of fulfillment of contractual obligation of the supplier.
Note: Interested Bidders are requested to submit the online tender at least two days in
advance from the due date set for Online submission of Bid in order to avoid non-
participation in e-Tender due to probable technical problem in (n)Procure portal.
The quantities specified are estimated and for tendering purpose only. Payment will be
made, based on actual work done as certified by Engineer In-charge of GIPCL.
Quantities of individual items may be revised during the course of Contract period based on site
requirement. Contractor shall not be entitled for any compensation on ground of such alteration in
scope of work. GIPCL reserves the right to operate or increase / decrease quantities in each item
or omit any item included in Schedule of Quantity at his discretion. Contractor shall have no claim,
whatsoever, on grounds of loss of anticipated profit etc. on account of the same.
After commencement of the work, GIPCL, for any reason may not require to be carried out the
whole/part of the work as specified in the tender, the Engineer In-charge shall inform the fact for
thereof to the Contractor and the Contractor shall have no claim for any payment or compensation
whatsoever on account of any profit or advantage which he might have derived from the execution
of the work in full but which he did not derive in consequence of the full amount of the work not
having been carried out nor shall he have any claim for compensation by reason of any change
having been made in the original specifications and instructions which shall involve any
curtailment of the work as originally contemplated.
INSTRUCTIONS TO BIDDERS FOR ONLINE TENDERING &
E-REVERSE AUCTION
SR. DESCRIPTION
Tender documents are available only in electronic format and same can be
01. downloaded from the website https://tender.nprocure.com and It can also be
viewed from Company’s website www.gipcl.com
Price bid should be submitted online through the website
02. https://tender.nprocure.com only. No physical submission of price bid will be
entertained as it should be furnished on-line only
Bidders who wish to participate in online tenders will have to procure / should
have legally valid Digital Certificate (Class III) as per Information Technology
Act-2000, using which they can sign their electronic bids. Bidders can procure
the same from any of the license certifying Authority of India or can contact
(n)code solutions- a division of GNFC Limited, who are licensed Certifying
Authority by Government of India
All bids should be digitally signed. The bidders are required to contact at the
below mentioned address for detailed training on on-line tendering and also for
(n) Code Solutions - A division of GNFC Ltd.
04. 403, GNFC Infotower, S.G Road,
Bodakdev, Ahmedabad – 380054 (Gujarat, India).
E-mail: [email protected], website: https://tender.nprocure.com
Interested bidders are requested to submit the online tender at least two days in advance
from the due date set for on line submission of bid in order to avoid non participation.
E-REVERSE AUCTION:
1 GIPCL reserves the right to conduct E-Reverse auction through (n) Procure platform.
2 E-Reverse auction shall be conducted amongst (a) the lowest 50% eligible bidders (rounded
to the next higher whole number) from the total bids received OR (b) Minimum three (03)
lowest bidders, whichever is higher, shall be invited for participation in e-Reverse Auction
through n-procure platform.
3 Opening Price, Detrimental value and duration for the e-Reverse Auction shall be informed
to the qualified bidders before start of e-Reverse Auction.
4 After e-Reverse Auction process, L1 bidder shall be decided on Lowest Total Contract Price
i.e. gross total quoted amount with GST.
5 After e-Reverse Auction process, the original % rate quoted by the final L1 bidder shall be
reduced proportionately on SoR of individual items/packages by total % reduction after e-
reverse auction, keeping GST % rate same as originally quoted by final L1 bidder.
6 To participate in e-Reverse Auction, Bidders have to create e-Auction USER ID on
https://e-auction.nprocure.com and it is mandatory to submit the same along with
physical Techno-commercial Bid; so that the Bidder shall be allowed to participate in
the e-Reverse Auction.
7 In case of any further information regarding online bidding or if a Bidder needs any
assistance in accessing/ submission of online bid/ clarification or if training is required for
participating in online e-reverse bidding, then the Bidder can contact the following office for
assistance or training:
(n) Procure Cell, (n) code solutions-A division of GNFC Ltd.,
403, GNFC Info tower, S.G. Road,
Bodakdev Ahmedabad – 380054 (Gujarat)
Fax: 079-26857321 / 40007533, Email: [email protected]
Bidder may visit https://tender.nprocure.com for information regarding e-tendering
registration process.
GENERAL CONDITIONS OF CONTRACT
1. CONTRACT SECURITY DEPOSIT/ PERFORMANCE BANK GUARANTEE
As a Contract Security, the successful Bidder, to whom the work is awarded, shall be required to
furnish a Performance Bank Guarantee (PBG) / Contract Security Deposit in favour of Gujarat
Industries Power Company Limited equivalent to Five percent (5%) of the “Annual Contract
Price excluding GST and 5% retention money from each RA bill as a cash security deposit”
(up to 10% of annualized contract price) from any Nationalized Bank, Axis Bank, ICICI Bank,
HDFC Bank, Kotak Mahindra Bank, IndusInd Bank, RBL Bank, DCB Bank, Federal Bank,
Bandhan Bank, Standard Chartered Bank in the format attached in SECTION-F, and it shall
guarantee the faithful performance of the 'Contract' in accordance with the terms and conditions
specified in these documents and specifications. Contract security deposit shall be submitted
strictly within twenty one days from the date of LoI or work order, whichever is earlier. The
guarantee shall be valid up to retention period of four months from the contract
completion date. The Guarantee amount shall be payable to the Company in Bidder's home
currency without any condition whatsoever.
The Performance Bank Guarantee (Security deposit) shall be returned to the Vendor / Contractor
without any interest at the end of the Retention Period after the completion of Contract and on
fulfilling contractual obligations throughout the retention period. However, any delay in submission
of initial SD will result in equivalent late release of entire SD after guarantee period.
2. PENALTY AND RECOVERY:
(i) In the event the Contractor causes undue delay in execution of work or the performance is
unsatisfactory causing interruption /stoppage of smooth operation of disposal of ash and
cleaning as per scope, harm to the plant and property of GIPCL, then in such a case, GIPCL
(Engineer In-charge) shall be entitled to levy a penalty on the Contractor at the rate of
times of the item rate up to a maximum of 10% of the Total Contract Price. The said penalty
amount may be recovered either from the monthly invoices or the Security deposit.
(ii) In addition to and without prejudice to the above, GIPCL shall also have the right to get the
affected work completed by a third party or agency at the risk and cost of the Contractor/
and the Contractor shall be liable for any differential amount in the Contract price.
(iii) In case of any damage of equipment / machinery / vehicle due to negligence of Contractor
or any other reasons attributed to Contractor, the decision of Engineer In-charge regarding
the amount of recovery shall be final and binding subject to a maximum of 10% of the
Contract value. Recovery will be affected from the monthly bills and / or retention money /
security deposit.
(iv) If the Contractor fails to execute the work as per directions of Engineer In-charge within the
time frame given in work order and / or day to day instructions given by Engineer In-charge,
GIPCL shall get the work done by third party at the risk & cost of the Contractor with 10%
additional overhead charges plus applicable GST as per extant GST Laws & other taxes
& duties as per applicable extant laws
(v) Penalty shall be imposed to Contractor for various instances as follows:
Due to whatsoever reasons, Cleaning underneath and surrounding areas of Silos if not
executed up to the mark, in consideration to the quantum of cleaning to be done and
degree of cleaning which is needed to be achieved: Rs 5,000 per day shall be levied as
Not meeting the daily Ash disposal targets (in MT), intimated to Contractor by GIPCL’s
Engineer In-charge daily in the evening for the next day, probably due to non-deployment /
inadequate deployment of sufficient closed body dumpers (tippers): Rs 3,000 per day per
inadequate dumper (solely based on Engineer In-charge’s assumption for total tippers
which might have completed the given Ash disposal target) shall be levied as penalty.
In case of emergency i.e. critical silo level, if contractor not deploying resources at all as per
his obligation for disposal of ash at predesignated location due to whatsoever reason, flat
penalty of Rs 5,000 per truck/dumper per day shall be levied. For example if contractor not
deploying five trucks, total penalty per day will be 5000 * 5 = 25000 Rs/day.
Non-conducting the inspection / re-inspection of closed body dumpers, in the presence of
representatives of GIPCL and non-obtaining of clearance certificate after thorough
inspection of these dumpers every 3 months: Rs 250 per each day per dumper till the
date of performing re-certification shall be levied as penalty.
Spillage even minor of bed ash or fly ash through truck / closed body dumper during loading
and transportation: Rs 500 per day / truck.
In any case the tippers deployed for Ash disposal to mines / spillage Ash cleaning shall
maintain the normal speed limits (max. around 30-40 km per hour) while travelling through
service roads / haul roads of GIPCL. If any tipper will be found over speeding, as reported to
GIPCL, by any third party, Rs 1,000 per instance shall be levied as penalty.
Absence of Site In-charge / Supervisors (except being his weekly off) without prior
information for leave and/or any intimation to GIPCL’s Engineer In-charge: Rs 500 per day
per person shall be levied as penalty.
Un-safe work execution: Rs 750 per day per Instance.
Damage to GIPCL equipment / machinery / vehicle: up to satisfaction of or free replacement
/ repair or 1.25 times the cost GIPCL shall incurs in repair / replacement.
In-spite of repeated instruction, if any worker found without safety appliances like Safety
shoe, Safety helmet (inside the plant premises) or any other Safety gear which he is
required to wear considering his job location, Necessary action shall be taken against that
particular workmen like not allowing him in to plant premises etc. Also, a token amount of Rs
100/- per day would be deducted as per the discretion of Engineer In-charge / Safety
(vi) The maximum total Penalty which shall be deductible considering all above instances shall
be limited to 10% of the Total Contract Price.
3. DEDUCTIONS FROM CONTRACT PRICE
All costs, charges or expenses that GIPCL may have paid, for which, under the Contract the
Contractor is liable, shall be recovered by the GIPCL. The Contractor shall pay all such claims
within 15 days of claim failing which the same shall be deducted from the bills of Contractor.
4. TERMINATION OF CONTRACT BY GIPCL
Contractor shall be responsible to complete the jobs within agreed time schedule and in case
Contractor fail to complete the job, GIPCL shall recover from his bill, Security Deposit and / or
whatsoever for expenses incurred to complete the job with additional 10% overhead charges plus
applicable GST as per extant GST Laws & other taxes & duties as per applicable extant laws.
In case if contractor’s services are not found satisfactory with respect to mobilization, time bound
completion of work, workmanship & safety (OHSAS policy of GIPCL) then GIPCL has right to
terminate the contract at any time by giving him 15 days advance notice without assigning any
reason and will make the alternate arrangement at the risk & cost of contractor.
GIPCL may terminate the contract after due recoveries of pending jobs / damages after giving
days advance notice to the Contractor if any of the following events occur:
i. Contractor is adjudged as insolvent.
ii. Contractor has abandoned the contract.
iii. Contractor fails to proceed with the work with due diligence as per requirements of the
iv. Contractor has neglected or failed persistently to observe or perform any of the acts,
matters or things, which as per the contract are to be observed and performed by the
v. Contractor repetitively violating the safety norms for more than three incidents.
vi. Any major contradiction of applicable labour laws.
vii. Any major deviations from contractual terms and conditions including quality of job.
viii. GIPCL reserves the right to terminate the contract without giving any reason whatsoever
and forfeit the PBG.
5. FAILURE & TERMINATION
If the Contractor after receipt of written notice from the GIPCL / Engineer In-charge requiring
compliance, with such further drawings and/or the GIPCL / Engineer In-charge’s instructions fails
within seven days to comply with the same, the GIPCL / Engineer In-charge may employ and pay
other agencies to execute any such work whatsoever as may be necessary to give effect thereto
and all costs incurred in connection therewith shall be recoverable from the Contractor by the
GIPCL on a certificate by the GIPCL / Engineer In-charge as a debt or may be deducted by him
from any money due or to become due to the Contractor.
If the Contractor fails to execute the work or fails to mobilize the resources and equipments as per
directions of GIPCL / Engineer In-charge within the time frame given and/or violating the GIPCL’s
safety rules & regulations, GIPCL / Engineer In-charge shall get the work done by third party at
the risk & cost of the Contractor with additional 10% overhead charges plus applicable GST as
per extant GST Laws & other taxes & duties as per applicable extant laws and all costs incurred
in connection therewith shall be recoverable from the Contractor by the GIPCL / Engineer In-
charge as a debt or may be deducted by him from any money due or to become due to the
6. SETTLEMENT OF DISPUTES
a. Any disputes or difference of opinion between parties arising out of the contract to the extent
possible shall be settled amicably between the parties. If amicable settlement cannot be
reached all the disputed issues shall be resolved through arbitration before a Sole Arbitrator
appointed by Managing Director, GIPCL according to the provisions of The Arbitration &
Conciliation (Amendment) Act, 2019, as amended from time to time. The place of arbitration
shall be at Vadodara/ Surat or any other place within state of Gujarat.
b. Work under the contract shall be continued by the contractor during arbitration proceedings
unless GIPCL shall order suspension thereof or any part thereof in writing or unless the matter
in such work cannot possibly be continued unless the decision of the Arbitration proceedings
7. INTERPRETATION OF CLAUSE
In case of disputes as regards interpretation of any of the clauses or specification, the decision of
CGM (THERMAL) - GIPCL will be final and binding on the Contractor.
8. EMPLOYEE’S COMPENSATION INSURANCE
Contractor shall take all risk Insurance Policy to cover all his workmen/employees, staff applicable
under the Employee Compensation Act 1923 or any amendment thereof as also insurance cover
for third party liability. The Contractor shall keep the GIPCL indemnified from all liabilities arising
out of his action in pursuance of this contract. The E.C. Policy should be obtained from Surat
Jurisdiction and shall be assigned to GIPCL. E.C. Policy should cover the specified contract
Contractor shall also obtain additional Off-duty coverage insurance policy for all his workers.
9. STATUTORY REQUIREMENTS
A. COMPLIANCE OF LABOUR LAWS
The Contractor shall at his own cost comply with the provision of labour laws, rules, orders
and notifications whether central or state or local as applicable to him or to this contract
from time to time. These Acts/Rules include without limitation of the followings.
1. Contractor shall be solely responsible and shall fully comply with all the provisions of
all the labor laws applicable such as the Minimum Wages Act, 1948, Contract Labor
(Regulation & Abolition) Act 1970, Factories Act, 1948, Payment of Bonus Act
Employees Provident Fund and Miscellaneous Provision Act 1952, Industrial Dispute
Act 1947, Workmen Compensation Act 1923, Payment of Gratuity 1972, Interstate
Migrant Workmen Act 1979, Equal Remuneration Act with Rules, Order and
Notifications issued/made there under from time to time.
2. All other Acts, Rules/Bye-Laws, Orders, Notifications etc. present of future applicable
to the Contractor from time to time for performing the contract job.
2.1 The Contractor shall provide and be responsible for payment of Wages, Salaries, Bonus,
Social charges, Insurance, Food, Accommodation, Transport, Medical and Canteen
facilities and other statutory privileges and facilities to his personnel as per law / rules /
regulations and orders of the Central Government, State Government, Local Authorities
or other authorities as are in force from time to time. All employees of the Contractor
shall be employee of the Contractor.
2.2 The Contractor shall have a valid license obtained from Licensing Authority under the
Contract Labor (Regulation & Abolition) Act, 1970 at the time of execution of the contract
covering all his employees working at SLPP site and furnish the same failing which
GIPCL may terminate the contract at its sole discretion.
2.3 The Contractor shall at the time of execution of the contract have a EPF Code Number
obtained from the Authorities concerned under the Employees Provident &
Miscellaneous Provisions Act, 1972 and remit contributions in respect of the employees
employed by him at SLPP Site to the P.F office concerned every month failing which
GIPCL will recover from the outstanding payment to the Contractor from GIPCL.PF code
of Gujarat region should be taken.
2.4 The Contractor shall maintain all records/registers required to be maintained by him under
various labor laws mentioned above and produce the same before the Statutory
Authorities whenever required.
2.5 The Contractor shall also submit periodical reports / returns to the various statutory
authorities such as the Contract Labour (Regulation & Abolition) Act-1970, Employees
Provident Fund Act etc. Under intimation to HR&A dept.
2.6 The Contractor shall not pay less than the Minimum Wages notified by the Government
from time to time to his employees of corresponding categories.
2.7 The Contractor shall be responsible for payment of overtime wages to his workmen, if any,
in case they are required to work beyond the prescribed hours under law as per
applicable rates.
2.8 The Contractor shall take Workmen Compensation Insurance Policy for all his employees
working at SLPP. The Contractor shall indemnify the company against any liability due to
any work injury or accident to any of its employees.
2.9 The Contractor shall in the event any of his workmen / employee sustains any injury or
disablement due to an accident arising out of and in the course of his employment,
provide necessary medical treatment and pay compensation as applicable, required
under the Workmen’s Compensation Act,
2.10 If any of the persons engaged by the Contractor misbehave with any of the officials or
the Company or commit any misconduct with regard to the property of the Company or
suffer from any serious communicable disease, the Contractor shall replace them
2.11 The Contractor shall not engage / employ persons below the age of 18 years.
Employment of women shall be strictly according to applicable laws.
2.12 GIPCL will have right to deduct and disburse the claims of the individual / parties being a
principal employer on any account whatsoever in relation to their employment with the
Contractor. The Security deposit will be released to the Contractor at the end of the
contractual tenure subject to an undertaking by the Contractor that in the event any of
his workmen or the heirs of workmen puts up a claim for recovery of money due to him
from the Contractor before the appropriate authority under the I.D.Act 1947 or under any
other labor laws or for compensation under the Workmen’s Compensation Act, 1923 and
the appropriate authority has given a direction for making payment the Contractor will
meet the same or indemnify GIPCL if in the event GIPCL pays it as Principal Employer.
2.13 The Contractor shall make payment of wages to his employees on fixed date within the
period specified under the applicable Law, in presence of representative of the company.
He will submit a true copy of wage sheet, attendance register and P.F. remitted challan
on monthly basis to HR&A dept. for verification and record.
2.14 The Contractor shall provide Safety items / kits to his employees such as safety shoes,
goggles, ear plugs, hand gloves, safety belts etc., if any, required under the law.
2.15 The Contractor shall conduct pre-induction and periodic medical checkup of his workmen
as per applicable laws.
2.16 The Contractor shall be solely responsible for any accident caused to his workers and
should adhere to all rules / regulations as per labor laws of Government and other
statutory laws as applicable.
2.17 The Contractor should register himself under the Contract Labour Act, Employee
Compensation Act and PF Act (Code no. to be mentioned) and submit the copy of
registration certificate and should possess the same from the date of commencement of
work, failing which the contract is liable to be cancelled. The E.C. Policy copy should be
submitted to the GIPCL before commencement of the work and Labor License should be
obtained within one week from the date of issue of form-V. Contractor should apply for
Form-V immediately after receipt of LoI. A copy of Labour License shall be submitted to
GIPCL, HR&A Department.
2.18 Contractor shall have to insure his workmen /supervisors etc. under Group Insurance
2.19 The Contractor shall be responsible for compliance of all statutory rules, regulation, act
enforced from time framed by the government such as Factory Act, Employee
Compensation Act, payment of ‘Wages Act’, Minimum Wages Act’, Provident Fund Act,
All Labor Laws Act in respect of employees engaged by him for the work and shall
have to maintain necessary records. In case any amount becomes due to be payable by
him to his employees or to the Government under the above rules, regulation, Acts,
GIPCL reserves the right to recover the same from the running bill of the contract.
2.20 Documentary evidence of deposit of PF paid shall have to be produced by the
Contractor along with the next bill.
2.21 Records as per the provisions of various statutory Acts will have to be maintained by the
Contractor and submitted as and when required.
2.22 All employees of Contractor should maintain due discipline and respect local sentiments.
GIPCL reserves the right to direct the Contractor to remove any such person who does
not comply with it.
2.23 The list is indicative in nature and not an exhaustive one. Any
amendment/alteration/Notifications or addition to the existing Law or a new statute shall
automatically and immediately become applicable.
2.24 Annual Health Check up- As per Statutory requirement, Contractor has to inform
workmen deployed at site for annual health check up as per schedule prepared by
HR&A department.
B. LEGAL ASPECTS
1. Contractor shall maintain all register required under the Labour Laws and make the
payment as per the Minimum Wages Act to the workers employed by him.
2. Contractor shall obtain requisite license to carry out this contract under the provisions of
Contract Labour Act, 1970 and maintain necessary records and registers under the said
3. Contractor shall submit a copy of each of the registration certificates with respect to
Employees Provident Fund and Employee Compensation Act within one-week time, from
the date of award of this contract.
4. Contractor’s employees, agent or sub-agent shall not smoke or light anything within the
premises of the GIPCL and carry match box / lighter or any other explosive and /or
inflammable material inside the plant.
5. Contractor shall abide by all the statutory rules and regulations like P.F., Labour Laws etc.
6. Contractor shall issue an appointment order to each casual workman stating therein the
nature of job to be performed by him and fix time for which the concerned workmen are
likely to be deployed. Contractor shall also issue a temporary identity card specifying the
period for which the workmen has been deployed.
7. Contractor is fully liable for the persons engaged by him for above work; however, GIPCL
reserves the right to deduct any amount legally justified towards any liability not fulfilled.
8. Contractor shall indemnify GIPCL from any liabilities arising out of the employment of the
9. If the Contractor fails to complete the allocated job within specified time frame, GIPCL
shall get the work done by third party at the risk and cost of Contractor.
10. PAYMENT OF WAGES
Contractor shall be responsible for compliance of all statutory rules, regulation, act enforced
from time framed by the government such as Factory Act, Employee Compensation Act,
payment of ‘Wages Act’, Minimum Wages Act’, Provident Fund Act, Payment of Bonus Act,
Labour Law Act, maternity benefit act, as amended from time to time in respect of
employees engaged by him/her for the work and shall have to maintain necessary records.
In case any amount becomes due to be payable by him/her to his employees or to the
Government under the above rules, regulation, Acts, GIPCL reserves the right to recover
the same from the running bill of the contract.
11. ACCIDENT TO WORKMEN
Contractor shall be fully responsible for injury or death of any of your or third-party workmen
due to any act omission / indiscretion on contractor part while undertaking the work and
contractor shall fully abide by the statutory requirements of the employee's compensation
act. GIPCL shall not be liable for any compensation due to accident, death or injury to any of
contractor’s workmen or any third party due to negligence, act or omission on contractor
General area lighting will be provided by GIPCL. However, work area specific lighting should
be arranged by contractor.
13. NIGHT / SUNDAY / HOLIDAY SHIFT
The contractor shall depute qualified and adequate resources in night shift / Sunday /
holidays for any emergency job, which may come up at night / Sunday / holiday.
14. SAFETY ASPECT
Contractor shall observe all the safety and security rules and regulation of the GIPCL which
are at present in force and which may come into force during the pendency of the contract.
Any violation of any rules and regulations will entail immediate termination of the contract.
When contractor moves his/her lifting tools and tackles to the plant area, required test
certificates as per the Factories Act 1948, as amended from time to time and the state
factories rules has to be submitted to safety Dept. Safety Dept. will check the certificates
and if found okay, then only materials will be allowed to enter inside the plant. Material
inward gate pass will be made only after certification from Safety Dept. Security Dept. will
inform to Safety Dept., as & when such tools and tackles brought at the gate for making
entry in the maintenance site.
The contractor has to submit the list of required safety gears along with safety equipments
available with him/her to safety Dept. Safety Dept. will check for quantity and quality of the
safety gears and then allowed permission of work. Poor quality material will not be allowed
to take inside the Plant. If quantity of required safety equipments is not satisfactory,
contractor will not be allowed to carry out the work using such safety gears inside the Plant
15. GENERAL SAFETY CLAUSES
1. The Contractor shall observe and comply, with regard to his workmen working at the SLPP
site, the safety norms as per the safety operating standards.
2. The Contractor shall ensure that his workmen are informed and trained regarding the safety
standards to be adopted while operating within the SLPP Plant & Mines premises and the
Contractor shall brief them regarding the same and use of the Personal Protective
Equipment (‘PPE’).
3. The Contractor shall issue safety shoes and safety helmet of IS standard to all his workmen
immediately on execution of the work and the contractor shall ensure that his workmen
wears the protective equipments at all times during the work operation. Following brand of
the safety shoes and helmet shall be issued to contract workmen. Contractor shall issue
safety shoes every year.
Sr No. Model Company Specifications
01. Tough Hat, HP-TH Sure Safety
02. V-Gard MSA IS : 2925 – 1984, ANSI / ISEA
03. PN 521 –Shelmet Karam
Sr No. Model Company Specifications
SSTEELE (Strom) – Double
01. Acme Fabrikplast Co.
TRIMAX(Adjacent) – Double
02. Acme Fabrikplast Co.
03. Worktoes Warren Worktoes - Warren Plus
4. Other safety gears like ear plug, dust mask, hand gloves, safety goggles, gum boots, full
body safety uniform and belts, safety net etc. shall be issued and used as per the job
requirements. Safety helmet shall be of YELLOW COLOUR ONLY. Contractor will procure
safety shoes & safety helmet from a reputed company with at least 12 months’ guarantee
and shall produce the guarantee certificate and IS standard certificate to the safety
department. Contractor should purchase safety shoes of reputed brands. Safety shoes will
be issued every year. IS certificate and guarantee certificate must be obtained from the
vendor and submitted to the Safety department. Safety shoes should be heat, water, oil and
chemical resistant, having an anti-slippery sole of 15298- 2002 make.
5. It is the duty of contractor to ensure that his workmen are wearing required PPEs as per
work requirement. Contractor should ensure that their workers are wearing Safety helmet,
safety shoes, dust mask, goggles, ear plug etc. at all times when they are at work
throughout the contract period. The contractor has to maintain the PPE issue registers with
signature of workmen.
6. Contractor will reissue these PPEs in case of damage or misplacement of the same.
Replacement shall be made immediately.
7. The contractor shall be responsible for providing first aid or emergency medical help and
treatment to his workmen in the event of any accident or injury.
8. If it is observed that contractor is not issuing required PPEs timely and that of required
quality, GIPCL will issue the required PPEs to contract workers and back charge the same
with 25% overhead charges plus applicable GST as per extant GST Laws & other taxes
& duties as per applicable extant laws incurred by GIPCL.
9. All lifting tools and tackles shall be duly certified by competent person in conformity with the
statutory requirements and certificate in form no. 10 as per rule 60 of Gujarat Factories
Rules, 1963 and section 29 of the Factories Act, 1948, as amended from time to time shall
be submitted every year before using such tools and tackles. In case of purchase of new
lifting tools and tackles, form no. 10 as per the said rules shall be submitted before they are
taken into use. All lifting tools and tackles shall be of reputed make having International
manufacturing standard and shall be maintained in proper and workable condition.
10. The Contractor shall nominate one Safety Officer with required qualification for supervising
the daily job / shutdown jobs for observing and maintaining the safety aspects at site. He is
solely responsible for any safety measures during maintenance work. He has to ensure that
all the workmen working at site are equipped with essential PPE’s and proper safety
arrangement is made at the SLPP site.
11. After mobilization of any tools & tackles to site, which includes chain pulley blocks, D-
shackles, wire ropes, winch machines, Mobile crane, Hydra etc. shall be offered for
inspection with all above statutory test certificate before using at site for any work. They
should use all tools and tackles only after certification by GIPCL representative / safety
12. When working at height, working on ceiling or roof covered with fragile materials, full body
harness safety belt, ladders and crawling boards, fall arrester, etc. shall be used to prevent
accident. Further, during working on height, contractor should arrange proper scaffolding of
still pipes, safety net, full body safety belt, fall arrestor system etc. Advice and instructions of
engineer in charge / safety in charge shall be strictly complied with in this regard. All
necessary safety precautions shall be taken by the contractor to prevent accident and
personnel injuries while working on height.
13. Flash back arrestors made of reputed manufacturer shall be provided on cutting torch, on
DA cylinders and on O2 cylinder. Cylinder caps also required for handling the cylinders at
the work at height area. Gas cylinders shall be transferred through gas cylinder trolley only
with cylinder cap and stored up right (vertical) position only. All gas cylinders shall be hydro
tested / certified as per gas cylinder rules 2004. Gas cylinders shall be stored, handled as
per gas cylinder rules
14. All vehicles shall be operated by licensed drivers only. All vehicles’ PUC to be tested as per
Government approved RTO guidelines. All Vehicles must be parked in Parking space
designated by GIPCL. If any vehicle is found inside the plant premises other than the
parking area such vehicles shall be handed over to Security dept. and their entry shall be
cancelled for movement inside the plant premises with immediate effect.
15. All electrical equipment shall be in good condition and free from any defect. Electrical tools
&equipments i.e. welding machine, grinding and drill machine etc. may be checked by the
electrical engineer of the contractors regularly, every six month at least and report to be
submitted to concerned HOD and safety depts.
16. During hot work, contractor will use fire curtains like asbestos sheets or fire blankets to
prevent falling and spreading of sparks and hot material on and around the work area.
Contractor will procure and use such items. ELCB / RCCB shall be provided with rating of 9-
30 milli amperes on welding machine and all portable power tools.
17. The contractor shall fill – up Incident notification form (S-I), Incident Investigation form (S-II)
and near miss report within time limit as specified in forms, if any accident, Incident, near
miss occurred while working at SLPP site.
18. Major AMC / ARC contractor (Where the man power strength is more than 50 and above)
should appoint / nominate one qualified safety officer and he shall be responsible for
addressing all the safety related aspects of execution of contract jobs and he will in close co
ordination with safety officer of SLPP and attend all safety related meeting such as safety
committee, on job safety training etc. Where the contractual man power is less than 50, the
site in-charge of the contractor will act as a safety officer and he will perform all the duties of
safety officer as mentioned above.
19. No loose connection / joints allowed in electrical cables during performance of any kind of
20. Safety shoes to be issued to female employees also.
21. All the vehicles shall be fit as per RTO guidelines and valid fitness certificate is required as
per RTO guidelines.
22. The Contractor’s nominated safety officer shall be imparted regular on-job safety training
like tool-box talk etc. and submit a record of such training in safety dept, respective dept and
23. The Contractor shall comply all the new requirements related with safety as informed by the
HOD / Safety department from time to time.
24. Penalty to be imposed for Violation of safety norms is proposed as follows:-
The Contractor & Contract workmen shall strictly adhere to Safety standards / Guidelines as
per practices. The list provided below is an indicative list to explain the principles behind
safety practice. If the contract workmen fail to comply with safety standards as per category
A, B & C below, penalty shall be levied on the contractor as per the table mentioned below:
Category Classification Examples / Cases Penalty
PPEs Working without helmet, shoes,
A Rs.100 /- per instant.
Related safety belt, gloves etc.
WI Related Failure to adhere to HSE
Rs.500 /- per
guidelines/plans, careless
attitude in material handling,
Machine being used with
damaged machine guard,
unsafe electrical work - workout After three
plug top/improper electrical incidence, Per
joints/cables lying on ground, incidence
electrical equipment working Rs.2500/-
without proper earthing,
machine being used without
machine guard, Welding Continuous
machine without ELCB / RCCB unsafe acts
of proper rating, Gas cylinder will disqualify
without test certificate, Cylinder the contractor
cap, NRV / Flash back arrester, from further
Cylinder trolley etc. participation in
Unsafe working practices at tender
height more than 3 meters of/contract
Working without permit or non- with GIPCL-
compliance with permit SLPP.
conditions like hot work, height
work etc. as applicable, lifting
tools and tackles being used
without third party inspection
certificates in form no. 9/10 as
per Factories Act – 1948 etc..
Suspend the entry gate
pass for one week.
Unsafe Breach of safe practices by a
C Practices particular person repeatedly for
After two suspensions his
gate pass will be
Penalty so levied against the contractors and company employees will be used during the
observation of National Safety Day.
The contractor, workmen following good safety practices in their work area
continuously will be rewarded / honored on National safety day.
16. REJECTION OF WORK:
If, as a result of inspection, examination or testing, the GIPCL’s Representative / Engineer
decides that any materials, work or workmanship is defective or otherwise not in accordance
with the Contract, the GIPCL / Engineer / GIPCL’s Representative may reject such plant,
materials, work or workmanship and shall notify the CONTRACTOR promptly, stating his
reasons. The CONTRACTOR shall then promptly make good the defect and ensure that the
rejected item complies with the Contract. If Contractor failed to rectify the rejected work or
workmanship, GIPCL / Engineer reserves the right to deduct or withhold amount against
rejected work or Workmanship. CONTRACTOR shall not entitle for any claim or release of
hold payment until rectify the defect up to satisfactory of GIPCL. If Contractor failed to rectify
any such defective work or workmanship, GIPCL reserve the right to rectify at risk and cost
of the CONTRACTOR and deducted by the GIPCL from any amount due, or to become due,
to the CONTRACTOR’s dues.
If the GIPCL / Engineer / GIPCL’s Representative requires such materials, work or
workmanship to be retested, the tests shall be repeated under the same terms and
conditions. If such rejection and retesting cause the GIPCL additional costs for the traveling
and lodging costs of GIPCL / Engineer’s personal for attending the retest, such costs shall
be recoverable from the CONTRACTOR by the GIPCL and may be deducted by the GIPCL
from any amount due, or to become due, to the CONTRACTOR.
17. GENERAL TERMS AND CONDITIONS:
a. All tools & tackles, labours, equipments, vehicles, tractors, etc., to execute the
contract are in the scope of the contractor. The contractor should ensure that tools
&equipments are in healthy condition.
b. The decision of the Engineer-in-charge shall be final and binding on the contractor for
defining the terms and condition included in this contract.
c. If the work is not found satisfactory, Engineer-in-charge reserves the right to take
suitable action.
d. Contractor shall depute full time independent experienced site-in-charge / independent
site supervisor / s at site. They shall co-ordinate with GIPCL engineer and shall bear
overall responsibility of contract including joint certification, billing etc. Such person
shall function from site office of contractor at SLPP.
e. Contractor shall also nominate one safety supervisor at site and shall submit
nomination of safety supervisor in writing before commencement of contract. Safety
supervisor shall arrange small safety talk on every day morning or whenever required
with all workers working under this contract. He shall coordinate with concern
department’s Engineer-in-charge on daily basis and report daily observations, tool-box
talk records etc. The work shall not be allowed without deploying safety supervisor
and a penalty equal to Rs.1,000/- per day absent of safety supervisor shall be levied
from Contractor.
f. Contractor shall strictly follow the existing work permit system of the GIPCL and any
future revisions.
g. The contractor has to take EC insurance policy for their workmen. The contractor has
to submit labour license (if applicable) and PF account number to the Engineer-in-
charge before start the work.
h. The contractor has to do the job timely. GIPCL shall not compromise in delay. In case
of delay of work without any valid reason, the GIPCL reserves the rights to carry out
the work by deploying other agencies at the risk & cost of contractor with additional
10% overhead charges plus applicable GST as per extant GST Laws & other taxes
& duties as per applicable extant laws.
i. Contractor shall mobilize the resources as per need within the period of twenty four
hours. If the contractor fails to mobilize sufficient resources to complete the job in time,
GIPCL will execute the job through other agency at the risk and cost of the contractor
with additional 10% overhead charges plus applicable GST as per extant GST Laws
& other taxes & duties as per applicable extant laws.
j. Contractor should mobilize all resources for efficient & smooth execution of contract
within seven to fifteen days from the date of issue of Letter of Intent/Work Order.
k. The prices / item rates quoted (based on quoted % above/equal or below SoR) shall
remain firm till completion of the contract and any agreed extensions thereafter and
shall not be subject to idle charges for labour, machinery, overhead expenses etc…
due to any reason whatsoever. No price escalation / idle charges shall be entertained
due to delay in work on unavailability of work front, non-issue of work permit, holding
of work permit for any reason, unavailability of contractor’s supervisor, unavailability of
contractor’s safety supervisor, violation of safety rules, unsafe act by any of
contractor’s worker, negligence & ignorance of safety & quality instructions of GIPCL
Engineer-in-charge or any other reason whatsoever.
l. Contractor must fulfill all the safety regulations and to take safety measures to avoid
hazards. Contractor shall arrange all standard adequate healthy safety PPEs like but
not limited to approved quality safety shoes & safety helmets, standard dust masks,
safety goggles, safety hand gloves, etc… as required and shall use exclusively under
this contract for all the time during working at specified locations failing which, the
Engineer-in-charge may hold the work and will take necessary action including penalty
as decided. If the contractor repeatedly violates safety rules / regulations (more than
three successive incidents), Engineer-in-charge may take necessary action against
the contractor, including appropriate financial penalty (Maximum of Rs.2,500/- per
incident per man-day and as per above clause no. 15) and / or termination of
m. One or more jobs may be required to be done simultaneously and contractor shall
mobilize additional resources accordingly.
n. Timely completion of all jobs and works shall be the essence of this Contract.
Contractor should closely monitor each activities and complete the jobs as per the
time given by and under the supervision of the Engineer-In-charge and shall ensure
that sufficient manpower is deployed for the same.
o. The contractor has to complete the works as per the planning schedule and their
respective supervisor has to interact with Engineer-In-Charge for PTW (Permit to
work), work instruction, Return of permit.
p. The contractor has to submit daily reports showing work carried out with details of
available manpower, equipments / vehicles (tractors) etc.
q. Any job other than the listed jobs in work order shall be executed by the contractor on
instruction from GIPCL and payment shall be made to the contractor on respective
item rate only.
r. The Government of India has enacted the Micro, Small and Medium Enterprises
Development Act, 2006 (the “Act”) and the Act has come into force from October
2006. The Bidder shall confirm whether your organization is registered under the
Micro, Small and Medium Enterprises Development Act, 2006, as amended from time
to time. If your organization is registered under the Act, please specify the category
i.e., Micro Enterprise, Small Enterprise or Medium Enterprise under which it is
registered and kindly attach a copy of your registration certificate.
s. The Bidder shall provide details of registration along with copy of the registration
certificate issued by the District Industries Centre/Department of Industries, etc of the
respective State Government. It is to be noted that large scale industries and trading
firms have been excluded from the purview of the Act.
t. GIPCL is an ISO 9001, ISO 14001, ISO 45001 & ISO 50001 (EnMS) certified
company and GIPCL gives extreme importance to maintain these global standards.
Contractor shall be required to fulfill the requirements of above standards while
working with GIPCL especially for controlling fugitive emission of ash (fly and Bed)
during collecting, loading, transportation and unloading activities. Contractor should
ensure that his workmen/labour work in accordance with them.
u. GIPCL shall impart safety training to the JCB operators and truck / dumper (tipper)
drivers in phased manner, considering their working in mines area, and relevant safety
aspects / use of safety PPEs pertaining to it. Contractor shall instruct the operators /
drivers for attending these training sessions, as and when informed by GIPCL’s
Engineer In-charge.
v. All laws, rules, regulations, notifications, etc. stated in this tender document, as
amended from time to time shall be applicable. Where applicable self-certified true
copies of the required documents to be furnished, unless stated otherwise explicitly.
18. CONTRACTOR’S SUPERVISION
The Contractor shall, during the whole time the work is in progress, employ a qualified
experienced Site In-charge /Supervisor of the works with adequate experience in handing of jobs
of this nature and with the prior approval of the GIPCL / Engineer In-charge. Such Site In-charge
/Supervisor shall be constantly in attendance at the site during working hours. During Contractor’s
Supervisor’s absence in working hours, if unavoidable, and also beyond working hours, when it
may be necessary to give directions, orders may be given by the GIPCL’s Engineer In-charge and
shall be received and obeyed by the Contractor’s superintendent who may have charge of the
particular part of the work in reference to which orders are given. If requested to do so, the
Engineer / GIPCL shall confirm such orders in writing. Any directions, instructions or notices given
by the Engineer / GIPCL to him, shall be deemed to have been given to the Contractor. The
representative of the Contractor shall have all necessary powers to receive materials from the
GIPCL, issue valid receipts for the same, engage labour or purchase materials and proceed with
the work as required for speedy execution.
None of the Contractor’s Superintendents, Supervisors or workmen should be withdrawn from the
work without due notice being given to the GIPCL’s Engineer In-charge; further no such
withdrawals shall be made if in the opinion of the GIPCL’s Engineer In-charge such withdrawals
will jeopardize the required pace of progress / successful completion of the work.
The Contractor shall employ in or about execution of the work only such persons as area careful,
skilled and experienced in their respective trades, and the GIPCL shall be at liberty to object to
and require the Contractor to remove any person employed by the Contractor in or about
execution of works who in the opinion of the Engineer misconducts himself or is incompetent or
negligent in the proper performance of his duties and all such persons shall not again be
employed upon the works without the prior permission of the GIPCL.
Neither the Contractor nor the Engineer shall hire or employ any employee of any other party
except by mutual consent.
19. CONTRACTOR TO REMOVE ALL OFFENSIVE MATTER IMMEDIATELY AND
All loose materials, wastage, packing materials, empty paint drums, cut pieces or other matter of
an offensive nature shall not be deposited on the surface, but shall at once be carted away by the
CONTRACTOR to some pit or place provided by him away from the site of work and approved by
local authorities.
As a part of the work included in this contract, the CONTRACTOR shall completely remove and
satisfactorily dispose of all temporary works & remove scaffolding materials to the extent directed.
He shall tear down and dispose of all temporary works, shall remove or grade, to the extent
directed, all plant and equipment, shall satisfactorily dispose off all rubbish resulting from the
operations under this contract and shall do all work necessary to restore the territory embraced
within the site of his operations to at least as good order and conditions as at the beginning of the
work under this contract.
20. FACILITIES TO BE PROVIDED BY GIPCL
A. The Company shall provide the following facilities to the Contractor at the site:
a. Electricity & water at nearest available one point. Further distribution to be done by
contractor at their cost.
b. Quarter / room & food for supervisors / engineers on chargeable basis in GIPCL’s
township at discretion of GIPCL if available. Food on chargeable basis at GIPCL’s
Industrial Canteen as available. If not available, contractor to make his own
arrangement for lodging and boarding locally or as appropriate at his cost.
c. Workshop facility as available at site only. However contractor may visit the workshop
to ensure the existing facility. For the facilities other than available, contractor has to
carry out the job outside at their own cost.
d. First aid facilities as available on chargeable basis. If not available contractor to make
his own arrangement for the same locally or as appropriate at his cost.
Apart from the above, no other facilities shall be provided by GIPCL.
B. GIPCL shall also conduct an orientation program appraising the workmen regarding
the safety norms and measures to be observed during work operations at the plant
21. WORK MEASUREMENT / CERTIFICATION
All trips filled in the trucks/dumpers (tippers) shall be weighed (both tare & gross weight) at
GIPCL’s AHS Weighbridges. The weighment slip (containing net weight) printed from AHS
Weighbridges duly signed by security / authorized person shall be treated as actual quantity of
ash disposed. If Weighbridges are out of order, the average weight transported by any respective
tipper in previous months shall be taken into account by the Engineer In-charge in this regard,
shall be considered for work certification / measurement.
22. PUBLIC HOLIDAYS
The Contractor shall be responsible for giving benefit to all his employees, employed in
whatsoever capacity, Nine (9) Public / Paid holidays and the same shall be notified in
advance and due communication thereof shall be made to the Management.
23. FORCE MAJEURE
The performance of the obligations herein contemplated may be suspended without incurring the
penalty in the event of the subsistence of Force Majeure conditions.
If a Force Majeure situation arises, the affected Party shall promptly notify the other Party in
writing of such conditions and the performance shall be suspended as per mutual agreement.
For the purposes of this clause, ‘Force Majeure’ means an event beyond the control of the Party
and not foreseeable by the Party and shall include events of floods, explosions, riots, wars,
hurricane, epidemics, any other Act of God, quarantine restrictions, terrorism, government actions
and provided always that such acts result in the impossibility of the further performance of the
The Contractor shall indemnify and keep harmless GIPCL from and against all actions,
proceedings, claims, demands, losses, costs, damages and expenses whatsoever which may be
brought against or suffered by GIPCL which it may sustain, pay or incur as a result of or in
connection with the performance/ purported performance / non-performance of the contract by the
In case, in any litigation pertaining to labour employed through Contractor if any direction or order
is issued by court at any point of time the Contractor shall comply with and implement such
direction or order whether passed at the time of award of contract or during the pendency of
contract. Further, the Contractor shall indemnify the GIPCL against all consequences arising and
affecting GIPCL owing to the compliance of the orders by the Contractor.
25. GOVERNING LAW AND JURISDICTION
This tender document and contract shall be governed by the laws of India and the Courts at Surat
shall have jurisdiction regarding the same.
26. Where any portion of the General Condition of Contract is repugnant to or at variance with
any provisions of the Special Condition of Contract, then unless a different intention
appears, the provision of the Special Conditions of Contract shall prevail to the extent of
such repugnancy of variance.
SPECIAL CONDITIONS OF CONTRACT
1. DETAILED SCOPE OF WORK:
PACKAGE A: Disposal of Ash at pre-designated locations of Mines pit / any
other locations
GIPCL Power plant generates Fly Ash & Bed Ash which is suitable for manufacturing bricks,
paving blocks, AAC blocks, etc. The external Ash customers / brick manufacturers are lifting the
Ash from power plant for their use. The scope of work here, as per this Contract, is needed to be
executed when these Ash stored in silos, is not lifted by these Ash customers corresponding to
the quantities in which the same is generated (Aprox Ash generation is in range of 1500 MT to
2000 MT per day for 4 x 125 MW plant). This remaining Ash shall be disposed at pre-designated
locations of Lignite mines pit on day to day basis, as and when required. The estimated quantity
of Ash required to be disposed at mines, as per this Contract, shall be as per the Section E –
Schedule of Quantities and Price. This quantity may increase or decrease, which shall depend
upon the Ash disposal requirement. If the Ash demand of external customers is more, the Ash
disposal to mines required may be less.
The ‘Scope of Work’ here is for disposal of dry ash from Fly Ash Silos & Bed Ash silos [four (4)
each] to the pre-designated locations of Lignite Mines pit or any other designated location of
mines, which shall be as directed by Engineer In-charge as per Ash requirement there. The
transportation of Fly Ash & Bottom Ash shall be done using closed body dumpers (tippers) which
shall travel along with the service road / haul road (after weighment). Minimum five (5) multi-axle
closed body dumpers (tippers) with hydraulic unloading arrangement of suitable storage capacity
shall be owned / possessed by the Contractor for the execution of said job. Considering
substantially high Ash disposal requirements especially during major festival times like Diwali, Holi
etc., in addition to the ownership/possession of closed boy dumpers (tippers) as per Clause No. 5:
Eligibility criteria of Section-A as per this tender document, Contractor shall have to deploy
additional five (5) multi-axle closed body dumpers (tippers), to handle the emergency Ash
disposal requirement.
The Ash shall be transported at following four (4) different pre-designated locations (distance
ranges) of mines pit / other location:
(i) at a one way distance of 0 km to < 3 km from Fly Ash Silos – 3 & 4;
(ii) at a one way distance of > 3 km to < 6 km from Fly Ash Silos – 3 & 4;
(iii) at a one way distance of > 6 km to < 9 km from Fly Ash Silos – 3 & 4;
(iv) at a one way distance of > 9 km to < 12 km from Fly Ash Silos – 3 &
Contractor shall comply the following pertaining to the Ash transportation & disposal of the same
at mines pit / any other locations:
1. Before using closed body dumpers (tippers) for dry Ash disposal, Contractor shall have to
conduct the inspection of these tippers, in the presence of representatives of GIPCL and
obtain clearance certificate after thorough inspection of these tippers. The validity of this
certification shall be 3 months, within which the re-inspection shall be carried out and renewal
certificate shall be obtained by Contractor. The delay in the said certification / re-certification
may attract due penalty as specified in Clause no. 2 of Section C as per this tender document.
2. The Contractor shall deploy for day to day job execution, the same dumpers (tippers) for
disposal of Ash to designated locations of mines pit, as per the ownership / possession shown
of aforesaid vehicles in accordance with the minimum ‘Eligibility Criteria’ (Clause No. 5 of
Section – A as per this tender document).
3. The weighment shall be done at GIPCL’s AHS Weigh-bridge. Gate pass will be generated for
each loaded trip after weighing. The duly signed/stamped gate pass copy, at receiving end by
either security personnel or concerned representatives, will be the supporting document for
arriving at the quantity of dry ash disposed by Contractor. At end of day, the total dry ash
disposed shall be reconciled along with GIPCL.
4. If at any point, the Weigh Bridge is found in-operative or out of order, average weight
transported of previous one month will be considered for billing purpose.
5. Contractor will ensure that during Ash loading & transportation along the road, there is no
spillage and dusting from the tippers. If any spillage of ash during loading at silo or
transportation along the road is reported to GIPCL, contractor shall have to clean the area
immediately by deploying their own resources without any cost implication to GIPCL.
6. While executing the contract, if any legal situation, local litigations, complains by nearby
villagers or farmers etc. arises, it will be the responsibility of Contractor to manage amicably
without any cost implication to GIPCL.
7. During execution of contract, Contractor has to follow safety norms, legal / statutory
compliances, etc. as applicable time to time.
8. The contractor shall transport and dispose Ash at any location of mines pit / other locations, as
per Ash requirement there and as directed by Engineer In-charge, falling in any of the above
specified distance ranges from Fly Ash silos – 3 & 4. Contractor shall quote rates considering
the transportation of Ash & unloading this filled Ash in tipper at the above pre-designated
locations (Ash filling to the tipper shall be done by silo operator provided by GIPCL).
9. The prime responsibility of Contractor shall be to empty the silos on daily basis, as per
the Ash disposal target (in MT) communicated by GIPCL’s Engineer In-charge, daily in
the evening for the next day. The number of tippers required as mentioned in the ‘Eligibility
Criteria’ is tentative. Contractor may need to deploy more numbers of tippers also (without any
cost implication to GIPCL), on any particular day or couple of days, if the Ash disposal target
for emptying of the Silos, communicated by Engineer In-charge may be substantially high. The
above specified Ash disposal targets, on any day, shall be strictly adhered to by the
10. Mobilization period: Initial mobilization period from the date of award of Contract is seven (7)
days. If the contractor fails to mobilize sufficient resources to complete the job in time, GIPCL
may execute the job through other agency at the risk and cost of the contractor.
11. All statutory requirements applicable for working in Power Plant and Mines area shall be
adhered to and followed.
12. The total estimated quantity of ash to be disposed at various distance ranges is described in
Section E – Schedule of quantities and prices. The quantity of ash may vary depending on the
performance of the plant, volume of rain fall, the off take of Ash by the external customers etc.
The remaining / balance quantity of Ash, not lifted by external customers, is to be disposed by
the Contractor. No any request regarding the idle charges of deployed vehicles, due to any
reason whatsoever shall be entertained by GIPCL.
13. No damages to GIPCL property or any public property shall be admissible.
14. Contactor has to provide smart mobile phone and two wheeler to its supervisor / site in-charge
for ease of communication while working in mines area.
15. Bidder can utilize the deployed trucks to supply ash to outside customers whenever there is
no dumping requirement in Mines by deploying in regular queue with other outside trucks.
Specific Requirement
Contractor shall submit copies of the following documents immediately on award of work and as
and when demanded by Engineer In-charge:
Suitable / valid driving licenses of dumper (tipper) drivers (of HMV / HCV category).
R.C. book of dumpers deployed at site.
Valid Insurance coverage of dumpers deployed at site.
Valid Fitness certificates of dumpers
Valid P.U.C of dumpers
Vocational Training certificate issued under VT rule
Medical of Driver/ Dumper Operator - as per Mine Rule
PACKAGE B: Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash
Silos and connecting roads
The evacuation of Fly Ash from ESP & Bed Ash from Boiler is being carried out through
pneumatic conveying system in all four (4) Units of Surat Lignite Power Plant. Finally, ash is
respectively collected in the Fly Ash & Bed Ash Silos. At Ash Handling System (AHS) of GIPCL-
SLPP, there are 4 nos. of Fly Ash & 4 nos. of Bed Ash silos. GIPCL is disposing ash in dry form
by means of trucks. The trucks are being loaded underneath the Silos for sale to external Ash
customers or for disposal to mines. During truck loading and transportation, there is spillage of
ash underneath and surrounding area of silos including connecting roads. Further overloaded
truck needs to be emptied at predefined location. All such spillage Ash has to be collected and
should be disposed immediately to keep the area clean. The scope of work here, as per this
Contract, includes accumulating the spillage fly ash & bed ash, from beneath silos and
surrounding areas including connecting roads [total four (4) fly ash silos and total four (4) bed ash
silos exists at GIPCL-SLPP],. Further, this accumulated/ collected ash shall be loaded in the Multi
axle open truck / dumper (tipper) and shall be transported without emitting dust in environment at
the following Ash disposal locations (distance ranges):
(i) at a one way distance of 0 km to < 3 km from Fly Ash Silos – 3 & 4;
(ii) at a one way distance of > 3 km to < 6 km from Fly Ash Silos – 3 & 4;
The spillage Ash disposal quantities at either of the above locations shall be tentatively as
mentioned in the detail scope of work & Section – E (Schedule of Quantities and Price). On any
particular day, the spillage Ash disposal location shall be confirmed by Contractor from GIPCL’s
Engineer In-charge daily in the evening for the next day.
Further to the above specified spillage Ash cleaning beneath and surrounding area of all fly ash &
bed ash silos, the following shall be executed on as and when required basis, as directed by
Engineer In—charge:
a) Cleaning of roads (i) connecting Fly Ash Silo – 3,4 to the main road for lignite transportation;
(ii) connecting AHS Weighbridges to security office at fly ash silo entry; (iii) connecting to
weighbridges & truck entry main road (connected to state highway), which are nearby Fly Ash
Silo (FAS-3, 4).
b) The parking area of trucks near weighbridges security office.
c) 158 N road connecting fly ash silo-1 & 2 to bed ash silo-1 &
d) Sides of weighbridges near Fly ash silo 3 &
e) Unloaded material on ground of Fly ash / Bed ash silos after internal cleaning of silos during
Contractor shall comply the following pertaining to the spillage Ash accumulation, collection,
loading, transportation & unloading which comprise the Cleaning job execution:
1. Cleaning of Area underneath & surrounding areas of Fly Ash & Bed Ash Silos incuding
connecting roads on daily basis by accumulation / collection of Ash by using a loader
(make & model: JCB (3DX) or equivalent) of suitable capacity and/or sufficient manpower.
Minimum one (1) JCB / Loader shall be owned/ possessed by the Contractor as specified in
Clause No. 5: Eligibility Criteria of Section-A as per this tender document. This accumulated
/ collected Ash shall be loaded into open truck/ dumper (tipper) and transported to either of
the above designated locations as directed by Engineer In-charge. Contractor has to ensure
that no dust spillage / emission occurred during transportation and for controlling the
emission of ash in ambient air; truck has to be transported after covering by tarpaulin.
Further, the Contractor shall always ensure that there is no accumulation of ash in their
scope of work area, which may hamper the normal truck loading process. This cleaning
activity shall be executed on daily basis and the same shall be certified by GIPCL’s Engineer
In-charge in the presence of Contractor’s supervisor on daily basis (probably in the evening).
The JCB / equivalent loader shall be retained at site till the cleaning of silo areas gets
completed for the day. The capacity of JCB / equivalent loader should be such that, it can
load Ash in to a multi-axle trucks easily.
2. Contractor shall deploy JCB/equivalent loader, everyday, without fail, from 8:30 AM to 5:30
PM as per requirement. During requirement of execution in extended hours, Contractor shall
keep the JCB deployed till the execution of the job, for the day, as directed by Engineer In-
charge. However in case of urgency, Contractor shall make the JCB available in one hour
notice other than above time, if required so.
3. Contractor shall own / possess minimum 1 No. multi-axle open truck/dumper (tipper) as
specified in Clause No. 5: Eligibility Criteria of Section-A as per this tender document. This
open tipper shall be deployed every day, for transporting the collected Ash at locations of
mines located at above specified distance ranges.
4. The weighment shall be done at GIPCL’s Weighbridges. Gate pass will be generated for
each loaded trip after weighing. The duly signed/stamped gate pass copy, at receiving end
by either security personnel or concerned representatives, will be the supporting document
for arriving at the quantity of spilled ash accumulated, collected, lifted and transported.
5. Contractor has to take tare weight & gross weight of truck at GIPCL’s Weighbridges to
derive nett weight. Payment will be made for actual weight of ash transported in each
vehicle. If Weighbridges are not in service or out of order, average net weight transported by
any respective tipper in previous months shall be taken into account by Engineer In-charge.
6. Contractor will ensure that during Ash loading & transportation along the road, there is no
spillage from the tippers. If any spillage of ash during loading at silo or transportation along
the road is reported to GIPCL, contractor shall have to clean the area immediately by
deploying their resources without any cost implication to GIPCL.
7. Contractor shall certified all the vehicles deployed by him at site, with Engineer In-charge for
their healthiness at an interval of every three (3) months.
8. Contractor shall mobilize the replacement for all the vehicles deployed by him at site,
immediately on any breakdown of the respective equipment / vehicle.
9. While executing the contract, if any legal situation, local litigations, etc. arises, it will be the
responsibility of Contractor to manage amicably without any financial burden to GIPCL.
10. During execution of contract, Contractor shall follow and comply all the safety, legal,
statutory, etc norms, as applicable time to time.
11. Contractor has to designate a person as a site incharge / Supervisor to look after and
coordinate the daily activities. The supervisor shall report to Engineer In-charge of GIPCL
and get the job certified on daily basis. The daily reports duly certified by GIPCL Engineer
In-charge shall be submitted along with the monthly bill and the payment shall be made on
the basis of the same.
12. Mobilization period: Initial mobilization period from the date of award of contract shall seven
(7) days. If the Contractor fails to mobilize sufficient resources to complete the job in time,
GIPCL may execute the job through other agency at the risk and cost of the contractor.
13. All statutory requirements applicable for working in power plant and mines area shall be
adhered to and followed.
14. Contractor shall report to AHS dept. for daily jobs executed.
15. No damages to GIPCL property or any public property shall be admissible.
16. All tools and plants and consumables shall be in the scope of contractor.
Specific Requirement
Contractor shall submit copies of the following documents immediately on award of work and as
and when demanded by Engineer In-charge:
Suitable / Valid Driving licenses for JCB operator and open truck (tipper) driver(s) (of
HMV / HCV category).
R.C. book of Vehicles deployed at site.
Valid Insurance coverage of Vehicles deployed at site.
Valid Fitness certificates of Trucks / Dumpers
Valid P.U.C of Trucks / Dumpers
Vocational Training certificate if issued under VT rule
Medical of Driver/ Dumper Operator - as per Mine Rule
Under-performance of work:
The daily operating hours shall be tentatively from 07.00 am to 05:00 pm. Contractor shall have
to empty the silos for the day, as and when required, as directed by Engineer In-charge by 5:00
pm in normal days (and by 9:00 pm in case of emergency) of the respective day. If the Contractor
shall not be able to empty the Fly Ash and / or Bed Ash silos as per requirement, by 9.00 pm of
the particular day and if Ash level in Silo becomes critical, it will be considered as Under
performance and GIPCL shall be free to deploy any other party to get the work done at the risk
and cost of Contractor. In case of such urgency, Contractor shall be prepared with the required /
additional resources for the Ash Disposal up to 1,500 to 2000 MT per day.
If Contractor under performs as above for three (3) times in a Fortnight period, GIPCL
reserves the authority to terminate the Contract immediately and forfeit the Security
deposit of the Contractor.
1.1 FAILURE DURING EMERGENCY
During any emergencies, Contractor shall have to carry out the work by deploying additional
required resources within four (4) hours of intimation, failing to which GIPCL reserves the right to
carry out this work by engaging any other party at the risk and cost of Contractor. The expenditure
occurred due to such situations, the Contractor will be held responsible & the same will be
recovered from the Contractor’s monthly bill / any other pending bills along with 10% Overhead
charges plus applicable GST as per extant GST Laws & other taxes & duties as per applicable extant laws.
For repetitive failure of such work for more than two incidents, GIPCL reserve the right to
terminate the entire contract by forfeiting all pending dues, Security Deposit, after giving 15 days
notice to the Contractor & this will be binding to the Contractor.
1.2 TO REMEDY DEFECTIVE WORK
If the work or any portion thereof shall be damaged in any way excepting by the acts of the
GIPCL, or if defects not readily detected by proper inspection shall develop before the final
completion and acceptance of the whole work, the Contractor shall forthwith make good, without
compensation, such damage or defects in a manner satisfactory to the Engineer In-charge /
GIPCL. In no case shall defective or imperfect work be retained even if Contractor followed all
technical specifications. GIPCL will not compromise for quality of materials, works &
The Contractor shall remain liable under the provisions of this clause notwithstanding the passing
by the GIPCL of any certificate, final or otherwise or the passing of any accounts.
2. DIESEL PRICE VARIATION
Diesel price variation will be applicable only if diesel price increase or decrease more than 5%
over the base price of diesel.
i) Base price will be the average of last 30 days diesel price at nearest PSU outlet (Nani
Naroli) from plant from the date of publication of tender.
ii) For calculation of diesel price variation, Monthly average diesel price for the claimed billing
period (generally 21st to 20th) will be considered.
iii) Diesel price variation will be applicable only on 50% component of respective items
mentioned in the Section-E of tender.
Effect of change in diesel price on SoR will be calculated as shown in below table. Diesel and
SoR rate considered here for calculation is indicative only.
Calculation for increase of Diesel price for item as mentioned in Package A
& & B of Section E
1 SoR rate Rs / Ton
2 Base Price of Diesel Rs/Lit
3 Monthly Average Price of Diesel Rs/Lit
4 Difference in Diesel Price (3-2) Rs/Lit
5 Change in Diesel Price (4/2*100) %
Change in Diesel Price which is not applicable as per tender
7 Change in Diesel Price which is applicable (5-6) %
8 Variable Component Specified in Tender %
9 Rise in SoR (1*7*8/10000) Rs / Ton
10 New SoR Rate after increase of diesel price (1+9) Rs / Ton
Calculation for decrease of Diesel price for item as mentioned in Package A
& B of Section E
1 SoR rate Rs / Ton
2 Base Price of Diesel Rs/Lit
3 Monthly Average Price of Diesel Rs/Lit
4 Difference in Diesel Price (3-2) Rs/Lit -9.00
5 Change in Diesel Price (4/2*100) % -9.09
Change in Diesel Price which is not applicable as per tender
7 Change in Diesel Price which is applicable (5-6) % -4.09
8 Variable Component Specified in Tender %
9 Rise in SoR (1*7*8/10000) Rs / Ton -0.80
10 New SoR Rate after decrease of diesel price (1+9) Rs / Ton
3. PRICE & RATES
The rates quoted by the Bidder in the online Price Bid shall be inclusive of cost of all equipments /
machineries / vehicles, labour, supervision, cost of safety supervisor, shifting, transportation,
loading, unloading, fuel, equipment, all tools & tackles, safety equipments & PPEs, Royalties,
Rents, Excise duty, Sales Tax, Stamp Duties, Central or State Government or Local body or
Municipal Taxes or Duties, Turn over Tax, Work Contract Tax, VAT, Octroi duty and / or any other
duty / tax (excluding GST), levied by the Central, State Government or other Public bodies etc.
and such other costs that are not specifically mentioned herein but will be incurred by the
Contractor for the satisfactory and timely completion of the work. The quoted rates shall be
deemed to include for everything mentioned in the specification, all leads & lifts, Contractor’s
overheads & profits for due performance of the work under this contract and such other costs that
are not specifically mentioned herein but will be incurred by the Contractor for the satisfactory and
timely completion of the work. The rates shall also include cost for mobilization / demobilization of
manpower, equipments, materials, etc.
The quoted rates by the Contractor shall be firm throughout the Contract period and any
agreed extension thereafter and shall not be subject to any escalation in prices, idle
charges for equipment / machinery / vehicles, labour, overhead expenses etc. However
Diesel price variation will be applicable as mentioned in the clause no 2 of Section D. No
idle charges, due to any reason whatsoever, shall be payable due to delay in work by
Contractor or due to non-availability of work front by GIPCL or any reason whatsoever.
The price / rate quoted by Contractor shall be considering mobilization of all required vehicles,
manpower, tools & tackles, materials, equipment for timely and satisfactory completion of total
The value and/or quantum of work may be increased or decreased depending upon day to
day requirement. However, item rates remains unchanged and the payment shall be made
as per the actual quantity executed as informed & certified by GIPCL representatives.
3.1 TERMS OF PAYMENT
A. Conditions of Payment:
The Contractor shall raise the running Invoices in duplicate every month in respect of the work
performed or completed during the month along with the documents as hereinafter provided. On
receipt of the invoice complete in all respects and with all the said documents, the payment in
respect of the same shall be made within 21 days of such receipt of a complete invoice as per the
following terms of payment:
(i) 100% of monthly RA bill along with 100% taxes shall be released against the work
executed duly certified by GIPCL Income Tax (IT) will be deducted at source from monthly
RA bills as per the rules in force.
(ii) Five percent (5%) of the “Annual Contract Price excluding GST and 5% retention money
from each RA bill as a cash security deposit” (up to 10% of annualized contract price)
shall be submitted as per Clause no. 1 of Section-C as per this tender document. Security
deposit & retention money will be returned to the Contractor without any interest after
retention period of four months from actual contract completion date as certified by
Engineer-in-charge as per Clause no.: 1 of Section-C.
(iii) GST shall be paid along with bills after fulfillment of following terms:
(a) Submission of copy of registration certificate issued by GST Authority (to be furnished
(b) Citing the GST Registration no. And the date of Issue of Registration certificate on
(c) Claim of GST amount with percentage (%) separately shown on the invoices.
(d) The Contractor shall be required to submit the proof of payment of GST in previous
month/quarter, as may be applicable as & when demanded by GIPCL.
(e) The Bidder shall inform the Owner in the event of its registration certificate is
cancelled or discontinued for whatsoever reason.
(f) The vendor shall also mention on their invoice the HSN/SAC code as applicable
under the GST laws under which GST is levied and a self certified authentic third
party evidence (www.cbic-gst.gov.in) shall be adduced, one time, to that effect by the
(iv) At the time of submission of the first monthly RA Bill, the Contractor shall submit a
certificate from Engineer In-charge regarding availability of required equipments /
machineries / vehicles with due healthiness, other required vehicles etc at site. The
Contractor shall also furnish the checklist as per enclosed Annexure A in SECTION - F of
this tender document along with the RA Bill of respective month.
(v) The Contractor shall submit his Final Bill within a period of four months of the expiration,
post any contract period extensions, if any, that may be granted by GIPCL to the
Contractor or earlier termination of the contract as applicable. GIPCL shall not entertain
any bill for any work item after expiration of period of four months.
(vi) The Contractor shall include all his claims in the Final Bill submitted by him and
accordingly the final bill submitted by the Contractor shall be deemed to be inclusive of all
and whatsoever the claims that the Contractor may have from GIPCL. The Contractor shall
not be entitled to claim any amounts which are not mentioned in the Final Bill and the
Contractor shall be deemed to have waived any claims not mentioned in the Final Bill and
shall not be entitled to recover the same from GIPCL subsequent to the submission of the
Final Bill on any account and GIPCL shall stand absolved of all its liabilities in respect of
any such claims not raised by the Contractor in his Final Bill.
B. Validity and Uniformity of Rates
The rates shall be firm and valid for the period of two years of the Contract Period, including any
agreed extensions thereof and shall remain unaltered during Contract Period, including any
agreed extensions thereof. However, Diesel price variation will be applicable as mentioned in
the clause no 2 & 3 of Section D respectively.
3.2 SUBMISSION OF TECHNICAL DOCUMENTS TO THE ENGINEER IN-CHARGE:
Contractor shall submit following documents to the Engineer In-charge for verification purpose of
Measurement sheets along with gate pass or joint record of work done in the form of joint
inspection report duly signed by authorized representative of Contractor and GIPCL’s
Engineer In-charge.
The Invoice will not be entertained without submission of above documents.
3.3 SUBMISSION OF STATUTORY COMPLIANCES WITH PERIODICAL / MONTHLY
RA BILL(S)/FINAL RA BILL:
Contractor shall submit one time or regularly, as applicable, the following documents along with
the periodical/monthly RA bill/Final RA bill.:
(i) Notarized Indemnity Bond as per standard Proforma, in case of Final bill.
(ii) No claim - No arbitration certificate as per Proforma at Annexure-D in Section-F after the final
bill amount is certified by GIPCL for payment and the same is made known to the contractor
by GIPCL & accepted by the contractor.
Bill submitted without any of the above documents shall not be processed for payment.
3.4 MOBILIZATION AND EXECUTION
a. Initial mobilization: After issue of LOI/ Work order, contractor has to mobilize all resources
within 7 days at site. Subsequently the contractor shall mobilize resources at site as per
need within period of four (4) hours as directed by GIPCL.
b. Contractor shall provide required separate & independent site supervisors who will be
responsible for supervision and execution of job in specified time with respect to quality,
specifications, site preparations, safety, co ordination with GIPCL, joint measurements, etc.
The supervisors shall coordinate with the Engineer In-charge of GIPCL for proper execution
c. The resources required for execution of above jobs will vary from time to time, hence
Contractor shall mobilize the resources accordingly.
d. Contractor shall provide accommodation for the persons deployed by him for the work at his
3.5 QUANTITY OF WORK
The estimated quantities of work required to be carried out by the Contractor are as given in the
Section - E (Schedule of Quantities and Price). These quantities are estimated and shall vary
according to the exigencies of work at site. However, the rates quoted by Bidder shall remain firm
irrespective of any variation in estimated quantities. Contractors shall engage required nos. of
workmen / machinery / equipment / vehicle along with required tools & tackles as per work load
and emergency situations throughout the contract period to perform his contractual duties.
In case, contract quantity / amount exhausted before completion of contract period, GIPCL
reserve the rights to increase the quantities or contract amount for successful completion of entire
contract period. Contractor shall responsible to complete the particular job up to entire satisfaction
of Engineer In-charge. The item rates remain firm & unchanged (except change due to Diesel
price variation) till completion of the contract and any agreed extensions thereafter and shall not
be subject to any escalation, idle charges for labour, machinery, equipment, vehicle, overhead
expenses etc. for any reason whatsoever. However, Diesel price variation will be applicable as
mentioned in the clause no 2 of Section D. The quantum of work of individual item may be up to
any extent depending upon requirement. Under this contract, Contractor has to execute all work
as per the Plant requirement.
3.6 GENERAL CONDITIONS OF CONTRACT
General Conditions of Contract (Section-C) and detail specification prepared by the company will
be applicable for this contract. The same is enclosed herewith. Bidders are advised to go through
Where any portion of the General Conditions of Contract is repugnant to or at variance with any
provisions of the Special Conditions of Contract, then unless a different intention appears, the
provision of the Special Conditions of Contract shall prevail to the extent of such repugnancy of
SCHEDULE OF QUANTITIES AND PRICE
Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of Mines pit / any
other locations and (B) Cleaning of underneath and surrounding areas of Fly Ash and Bed Ash Silos
(Contract Period: 2026-28)
Total Annual SoR
Sr. Detailed Scope SoR (Rs.)
Job Description UoM Annual Amount
No. of Work (excl. GST)
A. Disposal of Ash at pre-designated locations of Mines pit / any other locations
Ash disposal (Fly Ash or Bed Ash) by
Closed body dumpers (Tippers) to a
one way distance 0 km to < 3 km from
Fly Ash Silos (FAS) -
Ash disposal (Fly Ash or Bed Ash) by
Closed body dumpers (Tippers) to a
2 as detailed in MT 22,500 57.12
one way distance > 3 km to < 6 km
from FAS - 3,4 SECTION - D of
Ash disposal (Fly Ash or Bed Ash) by tender
Closed body dumpers (Tippers) to a document
one way distance > 6 km to < 9 km
Ash disposal (Fly Ash or Bed Ash) by
Closed body dumpers (Tippers) to a
one way distance > 9 km to < 12 km
B. Cleaning of underneath and surrounding areas of Fly Ash and Bed Ash Silos
Spillage Ash collection / accumulation
(by operating a JCB (3DX or equi.
loader) & its transportation through
Open truck (tipper) to a one way
distance 0 km to < 3 km from Fly Ash as detailed in
Silos - 3,4 SECTION - D of
Spillage Ash collection / accumulation tender
(by operating a JCB (3DX or equi. document
loader) & its transportation through
Open truck (tipper) to a one way
distance > 3 km to < 6 km from Fly Ash
sub-Total: Total Annual Estimated SoR amount
(excluding Contractors' Service Charge & GST) (Rs.)
Grand Total: Total Biennial Estimated SoR amount
Grand Total: Total Biennial Estimated SoR amount
(excluding Contractors' Service Charge & GST) (Rs.)
Grand Total: Total Biennial Estimated SoR amount
Grand Total: Total Biennial Estimated SoR amount
(excluding Contractors' Service Charge & including 18% GST) (Rs.)
Note: The rates shall include all equipments, machineries, vehicles, supervision, labour cost,
consumables, tools, tackles, all taxes & duties (excluding GST)
My Rates are as under:
AT Estimated value
OR _______ % (percentage) ABOVE the total estimated value
OR _______ % (percentage) BELOW the total estimated value
LIST OF ANNEXURES & FORMS
CHECKLIST FOR PASSING THE BILLS
For the month of :
1) Work Order / P.O. No. & :
2) Nature of work :
3) Duration of Work Order : From to
4) Maxi. No. of manpower per day : M F Total
deployed in the month.
5) Details of Labour License : Valid up to for
6) Details of E.C Policy : Valid up to for
7) Documents attached for verification : Wage & Attendance Sheets.
for the previous month. Yes/No
P.F Challan Yes/No
8) Documents attached for verification : Bonus Payment Register
(in case of Final Bill) Yes/No
: Leave wage register Yes/No
9) Security Deposit / Retention Money : Yes / No if yes, Rs.
Date: Signature of Contractor
with official stamp
PROFORMA FOR CONTRACT SECURITY-CUM-PERFORMANCE GUARANTEE BY SELLER /
(To be executed on non-judicial stamped paper of approximate value)
1. WHEREAS Gujarat Industries Power Company Limited having its office at PO: RANOLI,
Dist. Vadodara – 391 350, Gujarat State, India (hereinafter referred to as “The
Company/Owner” w h i c h expressions shall unless repugnant to the subject or context
includes its legal representatives, successors and assigns) has entered into a contract with
M/s. ………………………………../ has placed a purchase order on
M/s………………………….(hereinafter referred to as “Contractor(s)/ Seller(s)” which
expression shall unless repugnant to the subject or context includes their legal
representatives, successors and assigns ) for …………………………….on the terms and
conditions as set out inter alia, in the Company‟s contract No./ P.O.No.…………..date
…………and various documents forming part thereof hereinafter referred to as the “said
contract” which expression include all amendments, modifications and/ or variations thereto
and where as the Contractor(s)/ Seller(s) has agreed for due execution of the entire contract
and guarantees its performance including any parts executed through any other agencies/
subcontractors AND WHEREAS one of the conditions of the “said contract” is that
“contractor(s)/seller(s) shall furnish to the owner a Bank Guarantee from a bank for ….%
(……….percent) of the total value of the “said contract” against due and faithful performance
of the “said contract” including performance guarantee obligations of the
contractor(s)/seller(s) for execution/ supplies made under the “said contract.”
2. We …………………………….Bank having its branch office at ……….……..do hereby agree
and undertake to pay the amount due and payable under this guarantee without any demur
merely on a demand from the Company stating that in the opinion of the Company, which is
final & binding, the amount claimed is due by reason of default made by the Contractor(s)/
Seller(s) in performing any of the terms & conditions of the said Contract including defect
liability obligations, in fulfilling the performance guarantee obligation or loss or damage
caused to or would be caused to or suffered by the Company by reason of any breach by
the said Contractor (s)/ Seller(s) of any of the terms & conditions of the contract. Any such
demand made on the Bank by the owner shall be conclusive as regards the amount due
and payable by the Bank under this guarantee. However our liability under this guarantee
shall be restricted to Rs. ……(Rupees………………………only).
3. We undertake to pay to the Company any money so demanded not withstanding any
dispute or disputes raised by the contractor(s)/ Seller(s) in any suit or proceeding pending
before any office, court or tribunal relating thereto our liability under this present guarantee
being absolute and unequivocal. The payment so made by us under this bond shall be a
valid discharge of our liability for payment there under. Our liability to pay is not dependent
or conditional on the owner proceeding against the Contractor(s)/ Seller(s).
4. The guarantee herein contained shall not be determined or affected or suspended by the
liquidation or winding up, dissolution or change of constitution or insolvency of the said
Contractor(s)/ Seller(s) but shall in all respect and for all purposes be binding and operative
until payment of all money due or liabilities under the said contract(s)/ Order(s) are fulfilled.
5. The Bank further unconditionally agrees with Gujarat Industries Power Company Limited
(GIPCL) that Gujarat Industries Power Company Limited (GIPCL) shall be at liberty, without
the Bank’s consent and without affecting in any manner the Bank’s obligation under this
Guarantee, from time to time, to:
a. Vary and / or modify any of the terms and conditions of the Agreement.
b. Extend and / or postpone the time for performance of the obligations of the Contractor
under the Agreement.
c. Forbear or enforce any of the rights exercisable by Gujarat Industries Power Company
Limited (GIPCL) against the Contractor under the terms and conditions of the Agreement.
6. This guarantee shall be in addition to and not in substitution or in derogation of any other
security held by Gujarat Industries Power Company Limited (GIPCL) to secure the
performance of the obligations of the Contractor under the Agreement.
7. No action, event or condition, which by any Applicable Law should operate to discharge the
Bank from liability hereunder, shall have any effect and the Bank hereby waives any right it
may have to apply such law, so that in all respects its liability hereunder shall be irrevocable
and, except as stated herein, unconditional in all respects.
8. This guarantee will remain valid up ____________________ days or ______________
whichever is earlier. The Bank undertakes not to revoke this guarantee during its currency
without previous consent of the OWNER/PURCHASER and further agrees that if this
guarantee is extended for a period as mutually agreed between bidder & owner/purchaser,
the guarantee shall be valid for a period so extended provided that a written request for
such extension is received before the expiry of validity of guarantee.
9. We ……………Bank further agree with the Company that the company shall have the fullest
liberty without our consent and without affecting in any manner our obligations hereunder to
vary any of the terms and conditions of the said Contract(s)/ Order(s) or to extend the time
of performance by the said Contractor(s) Seller(s) from time to time or to postpone for any
time or from time to time any of the powers exercisable by the Company against the said
Contractor(s)/ Seller(s) and to forbear or enforce any of the terms and conditions relating to
the said Contract(s)/ Order(s) and we shall not be relieved from our liability by reason of any
such variation, or extension being granted to the said Contractor (s) / Seller(s) or for any
forbearance, act or omission on the part of the Company or any indulgence by the Company
to the said Contractor(s)/ Seller(s) or by any such matter or thing whatsoever which under
the law relating to sureties would, but for this provision, have affect of so relieving us.
10. Notwithstanding anything contained herein before, our liability shall not exceed
Rs…………….(Rupees…………only) and shall remain in force till..……..Unless a demand
or claim under this Guarantee is made on us within three months from the date of expiry we
shall be discharged from all the liabilities under this guarantee.
Corporate Seal of the Bank By its constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
With Seal & Signature code
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY DEPOSIT
(To be executed on non-judicial stamped paper of appropriate value)
1. WHEREAS M/s.Gujarat Industries Power Company Limited having its
Corporate Office at PO: R A N O L I , Dist.Vadodara – 391 350, Gujarat State,
India (hereinafter called “The Company Owner” which expression shall
unless repugnant to the subject or context includes its legal representatives,
successors and assigns) has issued tender paper vide its Tender
---------- (hereinafter called “the said tender”) to M/s.
……………………………(hereinafter called the said Tenderer(s)” which
expression shall unless repugnant to the subject or context includes their legal
representatives, successors and assigns and as per terms and conditions
of the said tender, the tenderer shall submit a Bank Guarantee for
Rs.………. (Rupees……………..only) towards earnest money in lieu of cash.
2. We ……………………………..Bank having its branch office at
……… do hereby undertake to pay the amount due and payable under this
guarantee without any demur, merely on a demand from the Company stating
that in the opinion of the company which is final and binding, the amount
claimed is due because of any withdrawal of the tender or any material
alteration to the tender after the opening of the tender by way of any loss or
damage caused to or would be caused or suffered by the Company by reason
of any breach by the said tenderer(s) of any of the terms and conditions
contained in the said tender or failure to accept the letter of Intent
Agreement or that the amount covered under this Guarantee is forfeited.
Any such demand made on the Bank by the owner shall be conclusive as
regards the amount due and payable by the Bank under this guarantee,
However, our liability under this guarantee shall be restricted to an amount not
exceeding Rs………………..(Rupees………………..only).
3. We undertake to pay to the Company any money so demanded
notwithstanding any dispute or disputes raised by the tenderer (s) in any
suit or proceeding pending before any office, court or tribunal relating thereto
our liability under this present guarantee being absolute and unequivocal. The
payment so made by us under this bond shall be a valid discharge of our
liability for payment there under. Our liability to pay is not dependent or
conditional on the owner proceeding against the tenderer.
4. The guarantee herein contained shall not be determined or affected or
suspended by the liquidation or winding up, dissolution or change of
constitution or insolvency of the said tenderer(s) but shall in all respect and for all
purposes be binding and operative until payment of all money due or
liabilities under the said contract(s)/ Order(s) are fulfilled.
5. The Bank further unconditionally agrees with Gujarat Industries Power Company
Limited (GIPCL) that Gujarat Industries Power Company Limited (GIPCL) shall be
at liberty, without the Bank’s consent and without affecting in any manner the
Bank’s obligation under this Guarantee, from time to time, to:
a. Vary and / or modify any of the terms and conditions of the Agreement.
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
b. Extend and / or postpone the time for performance of the obligations of the
Contractor under the Agreement.
c. Forbear or enforce any of the rights exercisable by Gujarat Industries Power
Company Limited (GIPCL) against the Contractor under the terms and conditions of
6. This guarantee shall be in addition to and not in substitution or in derogation of any
other security held by Gujarat Industries Power Company Limited (GIPCL) to secure
the performance of the obligations of the Contractor under the Agreement.
7. No action, event or condition, which by any Applicable Law should operate to
discharge the Bank from liability hereunder, shall have any effect and the Bank
hereby waives any right it may have to apply such law, so that in all respects its
liability hereunder shall be irrevocable and, except as stated herein, unconditional in
8. We ……………..Bank Ltd. further agree that the guarantee herein contained
shall remain in full force and effect during the period that would be taken
for the finalization of the said tender and that it shall continue to be enforceable till
the said tender is finally decided and order placed on the successful
tenderer(s) and or till all the dues of the company under or by virtue of the said
tender have been fully paid and its claims satisfied or discharged or till a duly
authorized officer of the company certifies that the terms and conditions of the said
tender have been fully and properly carried out by the said tenderer (s) and
accordingly discharges the guarantee.
9. That t h e O wn e r Company will have full liberty without reference to us and
without affecting this guarantee to postpone for any time or from time to time the
exercise of any of the power of the owner under the tender.
10. Notwithstanding anything contained herein before, our liability shall not
exceed Rs…………………. (Rupees…………………………only) and shall remain
in force till…………….. (Date to be filled up shall be 180 days from the date of
submission of Bid).
Bank Corporate Seal of
the Bank By its
constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
With Seal & Signature code
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
4.0 ANNEXURE – D
PROFORMA CERTIFICATE
(No claim, No arbitration)
Addl. General Manager (SLPP)
Gujarat Industries Power Company Limited,
Surat Lignite Power Plant,
Village: Nani Naroli, Ta. Mangrol,
Dist. Surat – 394112 (Gujarat).
We hereby confirm with free consent as under:-
1. The measurements certified in final bill are full and final. We accept all the certified
measurements and no claim related to the measurement is left.
2. The payment certified in that or above referred LoI / contract is full and final. We accept
this, and no claim related to payment is left.
3. The rates of the LoI / contract and its amendments are firm till completion of contract and
extension period. We shall not claim any escalation against these rates.
4. Along with the contract referred, the ARBITRATION CLAUSE also perishes i.e. we will
not resort to arbitration.
5. No extra items are left to be settled.
6. We do not have any claims against any item related to the LoI than those items certified
7. We are accepting the recoveries or hold amount from our bills, if any, made by GIPCL
against non compliance or as decided by GIPCL within terms & conditions of contract.
8. We have paid royalties, taxes for all the materials procured by us, for carrying out the
works for above LoI and we indemnify GIPCL from any liability arising thereof.
9. In case of any disputes arising in future related to payment of royalties, all liabilities of
settlement of dispute and its payment if any, will be borne by us.
10. We have paid wages to all the workmen who were deployed by us for carrying out above
referred work as per prevailing Minimum wages act. We have also fulfilled all
requirements of the P.F. Act. We have maintained all records necessary as per the
statutory requirements. We hereby indemnify GIPCL from any disputes arising in future
related to payment of labours, Provident Fund, etc.. and confirm that all liabilities of
settlements of disputes and their payment is our responsibility.
The above confirmation will come into effect as soon as payment from final bill after due
recoveries will be received by us.
For, M/s _____________________ Signature, Stamp and date
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
5.0 ANNEXURE – E
Schedule of Deviation from Technical Specification and Commercial Terms and
All the deviations from the terms & conditions of contract shall be filled by BIDDER
clause by clause in this schedule.
Sr. No SECTION TENDER DEVIATION
The bidder here by certifies that the above mentioned are the only deviations from OWNER’s
Tender enquiry. The bidder further confirms that in the events any other data and information
presented in the BIDDER’s proposal and accompanying documents are at variance with
specific requirements laid out in the OWNER’s Tender Document, then the latter shall govern
and will be binding on the BIDDER for quoted price.
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
6.0 ANNEXURE – F
Declaration cum Undertaking for Safety Laws and Regulations Compliance
(To be submitted on Company’s Letter Head)
I ______________________ on behalf of ………Name of Party/Company………..hereby
confirm, agree and undertake that all the Statutory and Safety Laws and Regulations of the
applicable Authority/ies shall be strictly followed for all types of works at the site during the
period of the Contract, if awarded to me.
Signed and Stamped by the
Authorized Signatory of the Bidder
Declaration for Contractual Litigations
(To be submitted on Company’s Letter Head)
Please Tick (√) whichever is correct option
I ______________________ on behalf of ………Name of Party/Company………..hereby
confirm that I /We have
a. Not invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings /
Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations for the last three ( 03) years. There are no ongoing/pending legal
matter(s) with any of the Govt. of Gujarat Undertakings / GoG supported
Companies, including GIPCL.
Please Tick ( )
b.Invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings
/Depts. / Authorities and Govt. of Gujarat supported companies / undertakings
/organizations for the last three (03) years.
Please Tick ( )
If “b” is applicable, please submit the details for the same.
The above is true, as on date, to the best of my knowledge. Any breach/ false statement in this
regard shall amount to disqualification of the Bid being submitted herein.
Signed and Stamped by the
Authorized Signatory of the Bidder
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
PARTICULARS OF THE BIDDER
Sr. No. Particulars Please provide information here.
1. Name of Bidder
2. a. Registered Office Address:
b. Address for Correspondence:
3. Contact Details:
Contact Person Name
Telephone No. :
Year of establishment
COMPANY SEAL SIGNATURE …………………
DESIGNATION ……………..
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
PROCEDURE FOR MAKING ONLINE PAYMENT OF EMD/SD/TENDER FEE
1. For making online payment, first go to the website: www.gipcl.com
2. Then, click on the caption/link as can see like:
“Click here for Making Online Payment of Advance for Ash, DM water etc.”
(The link is visible as horizontal highlighted below Tenders - News & Update Section. Can be
seen in below screenshot)
3. After clicking the link the new page will open. On this page, No need to enter User Name
and Password. Directly click on “Payment Form” given below the sign in option.
4. After clicking the “Payment Form”, the vendor has to enter the details asked which will be
self explanatory. It is desired that all the information may be filled correctly so that the
payment made can be tracked.
If the some required fields are not known/available, vendor may write “Not Available” and
then proceed. E.g. some information like Party code is not available to vendor or GST No. not
available with vendor.
Optional Note: Although mentioned as above can be proceeded with “Not available”, It will
be appreciated that regular vendors may obtain the party code from Materials Dept. or
Concerned Person, so that the vendor can be identified. The same party code may be used
for future transactions also.
After entering the details, click on SUBMIT Button.
5. The vendor/Party will be redirected to Payment Gateway. By selecting the desired
payment mode, payment can be made:
6. After making the payment, the receipt will be generated which has to be shared with
Concerned Person of GIPCL.
Important Note: Please note that for making online payment through the above gateway, the
charges* as below will be applicable, which has to be borne by Vendor/Party making the
Payment Mode Charges
Net Banking Rs.9 + GST
Credit Card 0.75% + GST
International 3.00% + GST
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
10.0 ANNEXURE-J
CERTIFICATE OF COMPLIANCE BY CONTRACTOR
(To be submitted with each monthly bill on letter head along with labour compliance records)
of.........................to.......................... at Gujarat Industries Power Company Limited –
Surat Lignite Power Plant, Nani Naroli. I undertake to be bound by all the provisions of
the Contract Labour (Regulation & Abolition) Act 1970 and the Contract Labour
(Regulation & Abolition) Rules 1972, The Employees’ Provident Funds and
Miscellaneous Provisions Act 1952, Minimum Wages Act 1948, Payment of Wages Act
1936 and Payment of Bonus Act 1965 and all other applicable labour laws in so far as
the provisions are applicable to me in respect of the employment of contract labour by
Authorized Signature with Stamp
Place: Nani Naroli
Tender Document for ‘Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-designated locations of
Mines pit / any other location and (B) Cleaning of Areas underneath and surrounding Fly Ash & Bed Ash Silo
(Contract Period: 2026-28) at GIPCL-SLPP: 4 x 125 MW Power Plant’ [Tender Ref. No.:
SLPP/AHS/BRC/DC/2026-28]
11.0 ANNEXURE – K
GUJARAT INDUSTRIES POWER COMPANY LIMITED
PO : RANOLI, DIST : BARODA –
Reference PO No. Date:
Integrity Pact No.: Contract Period:
To create an environment where Business Confidence is built through best business
practices and is fostered in an atmosphere of trust and respect between providers of
goods and services and their users for the benefit of stakeholder, society and the
GIPCL’S COMMITMENT PARTY’S COMMITMENT
Not to bring pressure / recommendation
To maintain the highest ethical standards in
from outside GIPCL to influence its
business and professions
Not to use intimidation, threat, inducement
To ensure maximum transparency to the
or pressure of any kind on GIPCL or any of
satisfaction of all stakeholders.
it's employees.
To fulfill the terms of agreement / contract and to To be prompt and reasonable in fulfilling
consider objectively the viewpoints of other the contract, agreement and legal
stakeholders. obligations.
To ensure regular and timely release of To provide goods and / or services timely
payments for works done/services provided as per agreed quality and specifications.
To ensure that no improper demand is made by To maintain the general discipline in our
employees or by anyone on our behalf. dealings and transactions.
To give maximum possible assistance to all the
Vendors / Suppliers / Service Provider and To be truthful and honest in furnishing
others to enable them to complete the works in information.
Not to divulge to others any information,
To provide all necessary information to suppliers
business details about GIPCL made
/contractors relating to contract / job to facilitate
available during the course of business
them to complete the contract / job successfully
relationship without the written consent of
To ensure that no hurdles are caused to vendors Not to enter into cartel / understanding
/ suppliers / contractors in execution of whether formal or informal so as to
agreement / contract / work. influence the price.
Seal & Signature Seal & Signature
(GIPCL’s Authorized signatory) (Party’s Authorized signatory)
Designation : Designation:
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Tender document Disposal and cleaning 2026-28.pdf
Tender document Disposal and cleaning 2026-28.pdf
CORRIGENDUM
Tender document Disposal and cleaning 2026-28.pdf
CORRIGENDUM
Tender document Disposal and cleaning 2026-28.pdf
CORRIGENDUM
Download all tender documents and submit your bid