Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.6 LAccepted-AOC | L1 | Accepted-AOC being L1 bidder | |
| 2 | L2₹12.0 L+₹1.4 L (13.5%)Rejected-AOC | L2 | Rejected-AOC being L2 bidder |
| Sl No | Description | Qty | Unit | Rajan P Mathews L1 | SRI SASTHA CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 1.00Rectification to Paramaon distributory | |||||
| 1.00 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 1,480 | sqm | 13.62 ₹20,157.6 Lowest | 15.49 ₹22,925.2 |
| 1.00 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 177.6 | cum | 192.96 ₹34,269.7 Lowest | 219.37 ₹38,960.11 |
| 1.00 | 15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar | 3.6 | cum | 1,903.95 ₹6,854.22 Lowest | 2,164.48 ₹7,792.13 |
| 1.00 | 60.7.9:RR with Departmental. Stone - Random rubble masonry using departmental rubble in foundation and plinth including through and bond stone and levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with Cement mortar 1:6 (1 cement : 6 coarse sand). | 2.52 | cum | 4,624.58 ₹11,653.94 | 4,404.9 ₹11,100.35 Lowest |
| 1.00 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 19 | cum | 1,164.26 ₹22,120.94 Lowest | 1,323.61 ₹25,148.59 |
| 1.01 | 15.56:Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | 440 | sqm | 42.32 ₹18,620.8 Lowest | 48.11 ₹21,168.4 |
| 1.01 | 7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) | 1.08 | cum | 6,249.27 ₹6,749.21 Lowest | 7,104.57 ₹7,672.94 |
| 1.01 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 33.3 | cum | 6,917.74 ₹2,30,360.74 Lowest | 7,864.54 ₹2,61,889.18 |
| 1.01 | 50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete | 2,753 | sqm | 257.49 ₹7,08,869.97 Lowest | 292.74 ₹8,05,913.22 |
Tender Value
₹14.1 L
EMD Value
₹35,370
Closing Date
21 Jan 2026, 2:00 pmClosed
Executive engineer
Executive engineer PIP Division Chengannur
Rectification works to Paramon distributary of Malakkara branch c a n a l b e t w e e n c h 0 m t o 1 4 8 0 m
2026_Irrig_827420_1
IRR/PII/TR/6913/2023_5_1_1/1
Open Tender
Civil Works - Canal
Item Rate
PIP Division Chengannur
Please refer Tender documents.
8 documents required · 8 mandatory
₹2,760
Yes
₹35,370
Yes
19 Feb 2026
13 Jan 2026
23 Jan 2026
13 Jan 2026
21 Jan 2026
13 Jan 2026
Rectification to Paramaon distributory
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
60.7.9:RR with Departmental. Stone - Random rubble masonry using departmental rubble in foundation and plinth including through and bond stone and levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with Cement mortar 1:6 (1 cement : 6 coarse sand).
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix)
15.56:Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead.
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
BOQ_1388550.xls
BOQ • 0.30 MB
viewsbd.pdf
Tender Documents • 3.00 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .