Assistant Engineer
Office of the Assistant Engineer, Line Maintenance Section, Pala
Converting ST and SS Hardware fittings to DT and DS Hardware fittings at various locations from 110 kV Udumbannoor Substation to 110 kV Pala Substation and to 110 kV Erattupetta Substation under Line Maintenance Section, Pala.
2025_KSEB_821041_1
LMS PALA/E TENDER NO.1/2025-26 DATED 21.11.2025
Open Tender
Electrical Works
Percentage
60 days
Udumbanoor to Pala and Erattupetta
6 documents required · 6 mandatory
₹5,900
₹37,000
3 Dec 2025
3 Dec 2025
22 Dec 2025
3 Dec 2025
18 Dec 2025
3 Dec 2025
Dismantling one set tension stringwith conductor from D-shackle of the 66/110kV tension tower after tensioning the conductor by using special appliances after giving jumper connections, then lowering the conductor with tension string, dismantling existing tension clamp with fittings from the conductor , marking the position of the tension hardware fittings after changing the damaged portion of line conductor if any with new conductor and providing single tension hardware fittings/double tension hardware fittings(double tension hardware fittings for road crossings etc.) on the conductor using compressor, replacing damaged disc insulators ,re-assembling the insulator string to the tension hardware fittings with conductor, lifting the same, re-assembling to the existing D-shackle at the cross arm and giving necessary jumper connections etc. as per the direction of departmental staff. Special tools if available will be supplied at free of cost.
Dismantling of one set suspension clampwith line conductor from 66/110kV Single/Double suspension string after lifting the conductor using special appliances, placing the conductor with suspension clamp on tower cross arm , lowering the string using rope and pulley, dismantling the string and re-assembling the same with new Composite disc insulator/double disc set after changing all rusted/flashed/damaged disc insulators then lifting the same and placing it to the existing U bolt at cross arm using rope and pulley then lifting the line conductor with suspension clamp and connecting the same to the bottom of string insulator as per the direction of department staff.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.20 MB
Tendernotice_2.pdf
PDF • 0.69 MB
Tendernotice_3.pdf
PDF • 0.30 MB
Tendernotice_4.pdf
PDF • 0.74 MB
Tendernotice_5.pdf
PDF • 0.15 MB
BOQ_1376926.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .