| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 LAccepted-AOC | ₹2.5 L | L1 | Accepted-AOC l1 |
| 2 | L2₹2.6 L+₹4,383.95 (1.72%)Rejected-AOC | ₹2.6 L+₹4,383.95 (1.72%) | L2 | Rejected-AOC L2 hence rejected |
| 3 | L3₹2.6 L+₹6,409 (2.52%)Rejected-Finance | ₹2.6 L+₹6,409 (2.52%) | L3 | Rejected-Finance High quoted bidder |
| 4 | L4₹2.6 L+₹8,448.54 (3.32%)Rejected-Finance | ₹2.6 L+₹8,448.54 (3.32%) | L4 | Rejected-Finance High quoted bidder |
| 5 | L5₹2.9 L+₹31,829.50 (12.5%)Rejected-Finance | ₹2.9 L+₹31,829.50 (12.5%) | L5 | Rejected-Finance High quoted bidder |
| Sl No | Description | Qty | Unit | UJEESH U S L5 | GOPU GS L3 | HARIKUMAR L7 | ARUNRAJ R T L2 | VISHNU VIJAI V L1 | harikumar vr L6 | GIBIN BABU L4 |
|---|---|---|---|---|---|---|---|---|---|---|
| 1.00Appendix 1 | ||||||||||
| 1.00 | 15.23.2:Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.For thickness of tiles above 25 mm and up to 40 mm | 112.1 | sqm | 101.04 ₹11,326.58 | 25 ₹2,802.5 Lowest | 107.75 ₹12,078.78 | 91.35 ₹10,240.34 | 89.8 ₹10,066.58 | 104 ₹11,658.4 | 92.78 ₹10,400.64 |
| 1.00 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 5.5 | cum | 1,341.09 ₹7,376 | 800 ₹4,400 Lowest | 1,430.07 ₹7,865.39 | 1,212.38 ₹6,668.09 | 1,191.89 ₹6,555.4 | 1,400 ₹7,700 | 1,231.45 ₹6,772.98 |
| 1.00 | 15.60:Disposal of building rubbish/ malba/ similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved | 5.5 | cum | 237.3 ₹1,305.15 | 200 ₹1,100 Lowest | 253.04 ₹1,391.72 | 214.53 ₹1,179.92 | 210.9 ₹1,159.95 | 320 ₹1,760 | 217.9 ₹1,198.45 |
| 1.00 | 50.4.1.1:Providing and laying in position cement concrete 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) up to floor five level excluding the cost of centering, shuttering, finishing for leveling coarse of floor and roof etc. | 5.5 | cum | 7,884.43 ₹43,364.37 | 5,000 ₹27,500 Lowest | 8,407.57 ₹46,241.64 | 7,127.75 ₹39,202.63 | 7,007.24 ₹38,539.82 | 8,600 ₹47,300 | 7,239.85 ₹39,819.18 |
| 1.00 | 21.1.1.2:Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminnium snap beading for glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash fasteners to be paid for separately):
For fixed portionPowder coated aluminium (minimum thickness of powder coating 50 micron) | 7 | kg | 504.47 ₹3,531.29 | 650 ₹4,550 | 537.94 ₹3,765.58 | 456.05 ₹3,192.35 | 448.34 ₹3,138.38 Lowest | 545 ₹3,815 | 463.23 ₹3,242.61 |
| 1.01 | 21.1.2.2:For shutters of doors, windows & ventilators including providing and fixing hinges / pivots and making provision for fixing of fittings wherever required including the cost of EPDM rubber/ neoprene gasket required (Fittings shall be paid for separately)Powder coated aluminium (minimum thickness of powder coating 50 micron) | 12 | kg | 611.04 ₹7,332.48 | 650 ₹7,800 | 651.58 ₹7,818.96 | 552.4 ₹6,628.8 | 543.06 ₹6,516.72 Lowest | 680 ₹8,160 | 561.08 ₹6,732.96 |
| 1.01 | OD279128/2024-2025:Labour engaging for cleaning the premises, shifting the materials before and after the completion of work. | 5 | each | 933.65 ₹4,668.25 | 850 ₹4,250 | 995.6 ₹4,978 | 844.05 ₹4,220.25 | 829.78 ₹4,148.9 Lowest | 1,004 ₹5,020 | 857.32 ₹4,286.6 |
| 1.01 | OD214496/2025-2026:Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS : 15622, of approved make, in all colours and shades, laid on 20 mm thick cement mortar 1:4(1 cement : 4 coarse sand), including Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-in-charge. Size of Tile 600 x 600 mm. | 116.3 | sqm | 1,780.71 ₹2,07,096.57 | 1,790 ₹2,08,177 | 1,898.8 ₹2,20,830.44 | 1,609.82 ₹1,87,222.07 | 1,582.5 ₹1,84,044.75 Lowest | 1,850 ₹2,15,155 | 1,635.13 ₹1,90,165.62 |
Tender Value
₹3.4 L
EMD Value
₹8,472
Closing Date
11 Feb 2026, 11:00 amClosed
The Assistant Executive Engineer.
O/O The Assistant Executive Engineer
DEPOSIT Urgent repair and maintenance of floor tiles in the Department of Public Health Dentistry attached to Govt Dental College Thiruvananthapuram workGeneral Civil Work 1
2026_PWD_831645_2
PWD/BLDG/TR/4189/2025_5_1_1/2
Open Tender
Civil Works - Buildings
Item Wise
PWD. MC Subdivision PMG TVPM
Please refer Tender documents.
7 documents required · 7 mandatory
₹750
₹8,472
Yes
18 Apr 2026
29 Jan 2026
13 Feb 2026
29 Jan 2026
11 Feb 2026
29 Jan 2026
Appendix 1
15.23.2:Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.For thickness of tiles above 25 mm and up to 40 mm
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix)
15.60:Disposal of building rubbish/ malba/ similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved
50.4.1.1:Providing and laying in position cement concrete 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) up to floor five level excluding the cost of centering, shuttering, finishing for leveling coarse of floor and roof etc.
21.1.1.2:Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded built up standard tubular sections/ appropriate Z sections and other sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash fasteners of required dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be smooth, rust free, straight, mitred and jointed mechanically wherever required including cleat angle, Aluminnium snap beading for glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash fasteners to be paid for separately): For fixed portionPowder coated aluminium (minimum thickness of powder coating 50 micron)
21.1.2.2:For shutters of doors, windows & ventilators including providing and fixing hinges / pivots and making provision for fixing of fittings wherever required including the cost of EPDM rubber/ neoprene gasket required (Fittings shall be paid for separately)Powder coated aluminium (minimum thickness of powder coating 50 micron)
OD279128/2024-2025:Labour engaging for cleaning the premises, shifting the materials before and after the completion of work.
OD214496/2025-2026:Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS : 15622, of approved make, in all colours and shades, laid on 20 mm thick cement mortar 1:4(1 cement : 4 coarse sand), including Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of 0.70kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin per kg), including filling / grouting and finishing complete as per direction of Engineer-in-charge. Size of Tile 600 x 600 mm.
stage.html
html • 0.05 MB
techsummary_1397588.pdf
finsummary_1397588.pdf
aoc.pdf
finance_1397588.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
epaymentnew.pdf
Other Document • 0.05 MB
BOQ_1397588.xls
BOQ • 0.30 MB
BID.pdf
Additional Documents • 1.63 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .