Loading…
India Infra Updates on WhatsApp
Join the Tenderkart WhatsApp channel for India Tender Updates
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.7 CrRejected-Finance 10 12 1 REDNAM GARDENS OPPOSITE STATE BANK OF INDIA VISAKHAPATNAM ANDHRA PRADESH 530002 | VISAKHAPATNAM | VISAKHAPATNAM | ANDHRA PRADESH | 530002 | L1 | Rejected-Finance quoted high percentage | |
| 2 | Rejected-Technical D NO 6 60 9 6 SRAMIK NAGAR CHINAGANTYADA GAJUWAKA VISAKHAPATNAM 530026 | VISAKHAPATNAM | VISAKHAPATNAM | ANDHRA PRADESH | 530026 | - | Rejected-Technical not met the required value of work experience in similar nature of works as per NIT |
Tender Value
₹18.6 Cr
EMD Value
₹19.6 L
Closing Date
6 Mar 2024, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Chief Engineer, VPA, VSP
Chief Engineer office, III floor, AOB, VPA, VSP 0891-2873353, 0891-2873317 0891-2873332 0891-2873333
Construction of two additional breasting dolphins (BD-3 and BD-4) to accommodate medium range vessels at OSTT of Visakhapatnam Port
2024_VPT_184491_1
IENG/CP/EE(CT)/T/ 86 , dt. 05.02.2024
Open Tender
Marine Works
Percentage
545 days
VPA
As per NIT
3 documents required · 3 mandatory
₹1,770
Yes
₹19.6 L
Yes
Chief Engineer office, III floor, AOB, VPA, VSP
3 Jul 2024
5 Feb 2024
7 Mar 2024
5 Feb 2024
6 Mar 2024
26 Feb 2024
15 Feb 2024
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Conducting geotechnical investigation in soil/rock to a minimum depth of 20m from the existing seabed at the proposed locations as per the drawings including the cost of boring through soils of various strengths and drilling through all kinds of soil, weathered and hard rocks, collection of 90/100mm diameter and 450mm long undisturbed samples from bore holes, conducting SPT in in-situ condition and conducting laboratory experiments on the samples. The cost shall also include preparation and submission of draft report for comments and geotechnical investigation report including detailed results of laboratory studies, recommendation for foundation design etc. including the cost of jack-up barge, drlling rig, other drilling tools and accessories and personnel, minor tools etc. The cost may also include the cost of mobilisation and demobilisation of the equipment and personnel, as required and as directed by Engineer-in-charge complete. All labour and materials. | 1 | Each | 1,30,000 | ₹1,30,000 |
| 2 | Design, Supply, transport to site, deliver, construct test and anchor piles/system, install testing arrangements equipment and spares, jackup barges, reaction anchors, structural frame systems with working platforms and access ways as necessary with provision of specialist personal, to carry out initial vertical pile load test on test pile (bored cast in-situ pile) at the location selected by Authority Engineer including construction of test pile, anchor pile, anchorage system, kent ledge frame, testing equipment, labour, etc with interpretation of test results complete. The cost of all materials such as RCC (cement, sand, aggregate, water), reinforcement, structural steel, nuts and bolts, prestressing wires, testing equipment, etc all complete shall be paid under this item. Load test shall be conducted on test piles with a maximum load of 2.5 times the working load on piles (2.5 x 500MT=1250MT). Test pile and anchor piles or anchorage system shall be completely cut and removed above seabed after the completion of test.
Note: Test pile shall be carried out prior to any working pile construction and the location of test pile shall not obstruct the working pile. Test pile location shall be in close vicinity of proposed breasting dolphin or as directed by Engineer-in-charge complete. All labour and materials. Previously used reaction pile or test pile for other tests cannot be used for the this test. New pile for testing and reaction shall be constructed for this test. Alternate arrangement such as O-cell or hydraulic jack method or any other alternative will not be acceptable. | 1 | Each | 1,19,00,000 | ₹1,19,00,000 |
| 3 | Design, Supply, transport to site, deliver, construct test and anchor piles/system, install testing arrangements equipment and spares, barges, reaction anchors, structural frame systems with working platforms and access ways as necessary with provision of specialist personal, to carry out initial pull-out pile load test on test pile (bored cast in-situ pile) at the location selected by Authority Engineer including construction of test pile, anchor pile, anchorage system, kent ledge frame, testing equipment, labour, etc with interpretation of test results complete. The cost of all materials such as RCC (cement, sand, aggregate, water), reinforcement, structural steel, nuts and bolts, prestressing wires, testing equipment, etc all complete shall be paid under this item. Load test shall be conducted on test piles with a maximum load of 2.5 times the working load on piles (2.5 x 150MT=375MT). Test pile and anchor piles or anchorage system if any shall be completely cut and removed above seabed after the completion of test.
Note:Test pile shall be carried out prior to any working pile construction and the location of test pile shall not obstruct the working pile. Test pile location shall be in close vicinity of proposed breasting dolphin or as directed by Engineer-in-charge complete. All labour and materials. Previously used reaction pile or test pile for other tests cannot be used for this test. | 1 | Each | 79,00,000 | ₹79,00,000 |
| 4 | Design, Supply, transport to site, deliver, construct test and reaction piles install testing arrangements equipment and spares, jackup barges, structural frame systems with working platforms and access ways as necessary with provision of specialist personal, to carry out initial horizontal pile load test on test pile (bored cast in-situ pile) at the location selected by Authority Engineer including construction of test pile, reaction, testing equipment, labour, etc with interpretation of test results complete. The cost of all materials such as RCC (cement, sand, aggregate, water), reinforcement, structural steel, nuts and bolts, prestressing wires, testing equipment, etc all complete shall be paid under this item. Test shall shall be conducted for a test load of 25MT (Corresponding to maximum reinforcement for the proposed test pile diameter of 1600mm designed as cantilever) and the test results shall be extrapolated for the actual working load of 50 MT using load displacement relationship obtained from the test results. Test pile and reaction pile shall be completely cut and removed above seabed after the completion of test.
Note : Test pile shall be carried out prior to any working pile construction and the location of test pile shall not obstruct the working pile. Test pile location shall be in close vicinity of proposed breasting dolphin or as directed by Engineer-in-charge complete. All labour and materials. Previously used reaction pile or test pile for other tests cannot be used for the this test. New pile for testing and reaction shall be constructed for this test. | 1 | Each | 66,00,000 | ₹66,00,000 |
| 5 | Shifting and setting up of piling plant and equipment using jackup rig, winch / pile driving rig, rotary drilling rig, bailers, chisellers etc (as per the methodology of work) at each pile location for handling 1600mm dia vertical MS steel liner, boring and concreting the piles including fabrication and erection of pile driving plant, staging with various steel plates, girders, angles, channels etc., including cost of steel items, welding charges, strutting and fixing in position at each location, cost of mobilization and demobilization of all equipment, transportation charges of all materials to worksite, all labour charges and minor tools etc., as directed by Engineer-in-charge complete. All labour and materials. | 18 | Each | 30,000 | ₹5,40,000 |
| 6 | Supplying, fabricating, Transportation to the pile location and Driving of 1600mm steel cylindrical liners of 10mm thickness to the required depth along with the provision of additional stiffener plate including gas cutting, bending to required size, welding at yard & site, transportation as shown in the drawing. The liners shall be driven to the specified level below sea bed level through all types of soil, fixing the liners in position including necessary bracings for stability until the completion of all deck works etc with necessary equipment, all labour, materials, tools, equipment fuel etc. complete.., The quantity of liner shall be measured and paid up to required cut off level. However, contractor has to build the liner 0.6 m above cut off level for overflow of concrete and cut-off after the concreting work., as directed by Engineer-in-charge complete. All labour and materials. | 194 | MT | 1,29,428 | ₹2,51,09,032 |
| 7 | Boring for the 1600mm diameter RCC piles to the required depth through all types of soil strata for piles from the existing sea bed level till the top level of rock including cost of winch / Pile driving rig, rotary drilling machine, RCD machine, bailer, chisel, POL, all labour charges, minor tools and plant etc. complete. Pile termination criteria shall be as specified in the construction drawings and specifications and stacking the bored soil at convenient place and transported to the low lying area anywhere inside /outside the harbour area within a lead of 4 Km or as directed by the Engineer’s representative and pile shaft cleaning and keeping of all records etc. including bentonite solution, labour, tools, equipment, fuel etc. all as per drawing, specification etc. complete as directed by Engineer-in-charge complete. All labour and materials. Any tests including SPT, rock strength etc as required shall be carried out by the contractor in addition to the energy criteria specified in the construction drawings. The cost includes all such testing at the specified laboratories or field and no extra claim whatsoever shall be entertained in this regard. | 180 | Rmt. | 13,000 | ₹23,40,000 |
| 8 | Boring for the 1600mm diameter RCC piles to the required depth through all types of hard rock for piles from the top of hard strata to the founding level including cost of winch / Pile driving rig, rotary drilling machine, RCD machine, bailer, chisel, POL, all labour charges, minor tools and plant etc. complete. Pile termination criteria shall be as specified in the construction drawings and specifications and stacking the bored material at convenient place and transported to the low lying area anywhere inside /outside the harbour area within a lead of 4 Km or as directed by the Engineer’s representative and pile shaft cleaning and keeping of all records etc. including bentonite solution, labour, tools, equipment, fuel etc. all as per drawing, specification etc. as directed by Engineer-in-charge complete. All labour and materials. Any tests including SPT, rock strength etc as required shall be carried out by the contractor in addition to the energy criteria specified in the construction drawings. The cost includes all such testing at the specified laboratories or field and no extra claim whatsoever shall be entertained in this regard. | 86.4 | 1 Rmt | 19,000 | ₹16,41,600 |
| 9 | Providing and laying design mix concrete of RCC M40 grade in accordance with IS 456 (Latest Edition) using coarse aggregate, sand and Portland slag cement confirming to IS 455 for RCC piles by using tremie with hopper arrangements, excluding cost of fabrication, fixing of reinforcement which will be paid separately, but including cost of cement, stone chips, sand, cost of all labour charges and transportation charges of all materials to the Work Site, hire charges and running charges of batching plant, vibrator, consumables and all other equipment, cost of minor tools etc. as directed by Engineer-in-charge complete. All labour and materials. (The design mix shall be provided by the contractor from the NABL approved laboratory or equivalent). | 1,230 | 1m3 | 19,451 | ₹2,39,24,730 |
| 10 | Dressing / chipping of the RCC pile head of including cutting of steel liners & trimming of extra concreted pile above the designed cut off level and exposing the reinforcement to receive fresh concrete for beams, bracing, pile caps etc., bending the reinforcement for new works, cost of all equipment, all labour charges, minor tools etc. as directed by Engineer-in-charge complete. All labour and materials. | 18 | each | 11,295 | ₹2,03,310 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
cancelled_1.pdf
pdf • 0.15 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 3.33 MB
Tendernotice_2.pdf
PDF • 2.33 MB
BOQ_201967.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .