Tender Value
₹98.5 Cr
EMD Value
₹12 L
Closing Date
5 Oct 2026, 4:00 pm
Additional Chief Engineer(Procurement & Contracts)
Supply, Laying, Erection, Testing and Commissioning of 66kV,1CX630 sqmm XLPE Cable with Poly.Al./Aluminum construction on EPC basis Various lines under Navsari Circle.
341613
ACE(P&C)/Contract/E-512/UG/66kV/S,L&E
Open
Electrical Works
Works
Vadodara
33 documents required · 24 mandatory · 9 optional
₹11,800
Gujarat Energy Transmission Corporation Limited
₹12 L
5 Oct 2026
9 Sept 2026
12 Oct 2026
9 Sept 2026
22 Sept 2026
9 Sept 2026
Seal & Signature of Bidder
CLAUSE TITLE PAGE
TENDER SPECIFICATION NUMBER
NOTICE INVITED TENDER
[I] GENERAL CONDITION OF CONTRACT (GCC)
1 GENERAL PARTICULARS
2 SCOPE OF THE PROPOSAL AND WORK
3 BIDDING COSTS
4 DETAILS OF DOCUMENTS
5 KNOWING THE BID DOCUMENTS
6 CLARIFICATIONS ON BID DOCUMENTS
7 AMENDMENT OF BIDDING DOCUMENT
8 LANGUAGE OF BID
9 LOCAL CONDITIONS
10 DOCUMENTS COMPRISING THE BID
12 BID SECURITY/EMD
13 FORMAT OF BID
14 SIGNATURE OF BIDS
15 SEALING AND MARKING OF BIDS
16 DEADLINE FOR SUBMISSION OF BIDS
18 MODIFICATION AND WITHDRAWAL OF BIDS
19 INFORMATION REQUIRED WITH THE PROPOSAL
20 OPENING OF BIDS BY OWNER
21 PURPOSE OF EVALUATION OF BIDS
22 POLICY FOR BIDS UNDER CONSIDERATION
23 PRELIMINARY EXAMINATION
24 AWARD CRITERIA
25 OWNER’S RIGHT TO ACCEPT ANY BID AND TO
REJECT ANY OR ALL BIDS
26 NOTIFICATION OF AWARD
27 SIGNING OF CONTRACT
28 DEFINITION OF TERMS
31 LANGUAGE AND MEASURES
33 TAXES AND DUTIES
34 TAXES, PERMITS & LICENCES
35 PRICE INCLUSIONS (INCLUDING TAXES & DUTIES)
36 CONTRACT PERFORMANCE GUARANTEE
38 PERFORMANCE GUARANTEE
39 TIME SCHEDULE
Seal & Signature of Bidder
40 TIME – THE ESSENCE OF CONTRACT
41 PENALTY FOR DELAY
42 DELAYS BY OWNER OR HIS AUTHORISED AGENTS
43 PRESENTATION OF BILLS
45 PAYMENT SCHEDULE
46 DEDUCTIONS FROM CONTRACT PRICE
47 TERMS OF PAYMENT
48 TAKING DELIVERY AND INSURANCE
50 CONTRACT QUALITY ASSURANCE
51 ERECTION TOOLS AND TACKLES
53 CONTRACT DOCUMENTS
54 USE OF CONTRACT DOCUMENTS AND
55 CONSTRUCTION OF THE CONTRACT
56 JURISDICTION OF CONTRACT
57 EXECUTION OF CONTRACT
58 ENFORCEMENT OF TERMS
59 COMPLETION OF CONTRACT
60 REPLACEMENT OF DEFECTIVE PARTS AND
61 PATENT RIGHTS AND ROYALTIES
62 DEFENCE OF SUITS
63 LIMITATION OF LIABILITIES
64 ENGINEER’S DECISION
65 POWER TO VARY OR OMIT WORK
66 ASSIGNMENT AND SUB-LE TTING OF CONTRACT
67 CHANGE OF QUANTITY
68 PACKING, FORWARDING AND SHIPMENT
69 COOPERATION WITH OTHER CONTRACTORS AND
CONSULTING ENGINEERS
70 NO WAIVER OF RIGHTS
71 CERTIFICATE NOT TO AFFECT RIGHT OF OWNER
AND LIABILITY OF THE CONTRACTOR
72 PROGRESS REPORTS
74 RISK DISTRIBUTION-TRANSFER OF TITLE
75 LIABILITY FOR ACCIDENTS AND DAMAGES
76 DEMURRAGE, WHARFAGE, ETC
77 FORCE MAJEURE
78 SUSPENSION OF WORK
Seal & Signature of Bidder
79 CONTRACTOR`S DE FAULT
80 TERMINATION OF CONTRACT ON OWNER`S
81 FRUSTRATION OF CONTRACT
82 GRAFTS AND COMMISSIONS ETC.
83 SETTLEMENT OF DISPUTES
85 RECONCILIATION OF ACCOUNTS
87 TERMINATION OF CONTRACT
88 TO CANCEL THE CONTRACT
89 MATCHING END COST
90 VENDOR REGISTRATION
92 Deduction of TDS under GST
93 GOI guideline of restrictions under rule 144(xi) of the
94 INCOME TAX (TDS)
GENERAL INFORMATION (TECHNICAL)
1 GENERAL INFORMATION (TECHNICAL)
3 APPROVED MAKES OF EQUIPMENTS /ITEMS OF
4 INSPECTION AND TESTING OF EQUIPMENT
5 OTHER CONDITIONS
Seal & Signature of Bidder
CLAUSE NO. TITLE Page
[II] ERECTION CONDITIONS OF CONTRACT (ECC)
2 REGULATION OF LOCAL AUTHORITIES AND STATUTES
3 OWNER’S LIEN ON EQUIPMENT
4 ACCESS TO SITE AND WORKS ON SITE
5 CONTRACTOR’S SITE ESTABLISHMENT
6 CO-OPERATION WITH OTHER CONTRACTORS
7 DISCIPLINE OF WORKMEN
8 CONTRACTOR’S FIELD OPERATION
9 PROGRESS REPORT
10 MAN-POWER REPORT
11 PROTECTION OF WORK
12 EMPLOYMENT OF LABOUR
13 FACILITIES TO BE PROVIDED BY THE OWNER
14 FACILITIES TO BE PROVIDED BY THE CONTRACTOR
15 LINES AND GRADES
16 FIRE PROTECTION
18 PRE-COMMISSIONING TRIALS AND INITIAL
19 MATERIALS HANDLING AND STORAGE
20 CONSTRUCTION MANAGEMENT
21 FIELD OFFICE RECORDS
22 CONTRACTOR’S MATERIALS BROUGHT TO SITE
23 PROTECTION OF PROPERTY AND CONTRACTOR’S
25 UNFAVOURABLE WORKING CONDITIONS
26 PROTECTION OF MONUMENTS AND REFERENCE
27 WORK & SAFETY REGULATIONS
28 CODE REQUIREMENTS
Seal & Signature of Bidder
CLAUSE TITLE PAGE
[III] SPECIAL CONDITIONS OF CONTRACT (SCC)
1 GENERAL PARTICULARS
3 EARNEST MONEY DEPOSIT (EMD)
4 DECLARATION BY BIDDER
5 QUALIFYING REQUIREMENT
6 ADDITIONAL DOCUMENTS
7 COMPLETION PERIOD
8 SD-CUM-PERFORMANCE GUARANTEE DEPOSIT
9 INSTRUCTIONS BEFORE BID SUBMISSION
9A Interse reverse bidding
10 ADDENDUM TO THE TECHNICAL SPECIFICATIONS.
12 PROGRESS REPORT
14 Welfare cess
15 Clarification
17 Right of owners
18 Bonus clause
Various forms, formats, schedules, Annexures etc.
3 CONTRACT AGREEMENT
4 BANK GUARANTEE FOR EMD
5 PERFORMANCE BANK GUARANTEE
6 PG for warrantee
7 INDEMINITY BOND
8 A/T ACCEPTANCE LETTER
9 Certificate for Technical compliance
10 Safety cum Indemnity bond
11 Annexure-A Safety A habit
12 Safety related check list
13 Confirmation of detail of bidder
14 Completion period
15 Financial capability
16 Latest Income tax certificate
17 Memorandum / Articles of association
18 Attested copy of resolution of partners
19 Details of HR
20 Details of documents
24 JOINT VENTURE AGREEMENT
25 PROFORMA OF POWER OF ATTORNEY BY THE JOINT VENTURE
26 Annexure-I(A)- Manufacture’s authorization
27 Integrity pact
28 BG’s formats
29 TCS Certificate format
30 Certificate-A
Seal & Signature of Bidder
NOTICE INVITED TENDER
GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED
VIDYUT BHAVAN, RACE COURSE, VADODARA - 390
The Additional Chief Engineer (Procurement & Contracts) GETCO for and on behalf of
Gujarat Energy Transmission Corporation Ltd., having its Corporate Office at Sardar Patel
Vidyut Bhavan, Race Course, Vadodara – 390 007, hereafter called as “GETCO”, intends to
invite Tender for Supply, Laying, Erection, Testing and Commissioning of
66kV,1CX630 sqmm XLPE Cable with Poly.Al./Aluminum construction on EPC
basis Various lines under Navsari Circle as per tender specifications.
S DESCRIPTION Particulars
1 Tender No. ACE(P&C)/Contract/E-512/UG/66kV/S,L&E
2 Name of UG Cable Line Supply, Laying, Erection, Testing and Commissioning of
66kV,1CX630 sqmm XLPE Cable with Poly.Al./Aluminum
construction on EPC basis Various lines under Navsari
3 Estimated Cost including GST
(1. Payment of EMD should be accepted by RTGS / NEFT
/ online or Demand draft or Banker’s cheque or Pay
order or Bank Guarantee)
(2. For BG Validity will be 06 (Six) Months from the date
of submission of tender.)
(3. Submission of EMD
Online only – if submitted by online/NEFT/RTGS.
Offline/Physical & Original copy – if submitted by DD /
Banker’s cheque / Pay order or Bank Guarantee, to be
submitted in original / physical copy in EMD cover as a
mandatory requirement by RPAD / speed post only and
scanned copy of the same to be submitted online. )
5 Tender Fee (Non-refundable) in Rs.
Rs. Non-Refundable (Incl. GST-18%, Rs. 1,800)
1. Note: Payment of Tender fee accepted by RTGS / NEFT /
2. Submission of tender is online only.
6 Time Limit 12 (Twelve) Months from the date of Commencement.
7 On line (E-tendering) tender / offer
submission last date up to
hours only (This is mandatory)
8 Physical submission of EMD
(Offline/Physical & Original copy
– if submitted by DD / Banker’s
cheque / Pay order or Bank
Guarantee, to be submitted in 29-09-2026
original / physical copy in EMD
cover as a mandatory
requirement by RPAD / speed
post only and scanned copy of
the same to be submitted
Seal & Signature of Bidder
S DESCRIPTION Particulars
online), last date up to 15.00 hours.
By RPAD or SPEED POST only..
9 Date of opening of Tender fee,
EMD cover, and QR bid on line
opening at 16.00 Hours.
10 Shall be intimated separately.
Date of opening of Price Bids:
Firm price basis except for (i) Supply of 66kV, 1CX630
sq.mm XLPE Power Cable with Poly.Al. /Aluminum
11 Prices construction and (ii) Supply of Tower Materials (Including
Bolts-Nuts) for which Price variation will be applicable.
12 Type of Tender Item Rate Basis
13 Validity of Offer 180 Days from the opening of Technical Bid.
Add. Chief Engineer (Procurement & Contracts)
Seal & Signature of Bidder
GENERAL TERMS AND CONDITION OF CONTRACT
1.0 General Particulars
The Gujarat Energy Transmission Corporation Ltd., Baroda hereinafter called
‘GETCO’/ ‘OWNER’ intends to receive bids for establishing 66KV Underground cable
line including Supply, Laying/Installation, testing and commissioning of 66KV U/G
cable system with all termination and accessories on turnkey basis for Supply, Laying,
Erection, Testing and Commissioning of 66kV,1CX630 sqmm XLPE Cable with
Poly.Al./Aluminum construction on EPC basis Various lines under Navsari Circle
detailed in the accompanying specifications in accordance with Terms and Conditions
herein. The bids shall be prepared and furnished as per these Instructions.
2.0 Scope of the proposal and Work
2.1 The Scope of the proposal shall be on the basis of a single Bidder’s
responsibility, completely covering all the equipments and installation services
specified under the accompanying Technical Specifications. It will include
among others as specified therein the following: -
a) Detailed Engineering and detailed calculation.
b) Complete manufacturing including shop testing.
c) Providing engineering drawings, data, operation manual, etc for the Owner’s
d) Packing and transportation from the manufacturer’s works to the Site.
e) Receipt, storage, preservation and conservation of equipment & at the Site.
f) Pre-assembly, if any, insurance, erection, testing and commissioning of all
the equipments/accessories etc.
g) Reliability tests and performance guarantee tests on completion of
2.2 No deviation whatsoever to certain conditions of the bidding documents
permitted by the Owner and therefore, the Bidders are advised that while
making Bid Proposals and quoting prices these conditions may appropriately
be taken into consideration. Bidders are required to furnish a certificate in this
regard as per the format provided in Special Conditions of Contract in a
separate sealed envelope containing Bid security, which shall accompany the
Technical Bid. Any Bid not accompanied by such certificate shall be
rejected by the Owner and shall not be opened.
2.3 Bids not covering the above cited entire scope of works may be treated as
incomplete and hence rejected.
2.4 The Bidder shall complete all the schedules & annexure in the Bid Proposal
Sheets, Technical Data Sheets and specified elsewhere. The Qualifying Data
should be filled in the required schedule of Bid Proposal Sheets.
2.5 This specification covers the detailing, engineering, manufacturing, testing at
works, packing, supply, storage, insurance and handling at site,
laying/installation, testing, commissioning and handing over in ready to switch
on condition to GETCO of complete equipments / accessories of 66kV U/G
cable line as stated below for Supply, Laying, Erection, Testing and
Seal & Signature of Bidder
Commissioning of 66kV,1CX630 sqmm XLPE Cable with Poly.Al./Aluminum
construction on EPC basis Various lines under Navsari Circle.
2.6 The work includes Supply, Laying/Installation, Testing and commissioning of
66KV underground incl. all the accessories and joints/termination, etc. as
stated hereunder & detailed in the BOQ, Schedules so as to complete the project
as per approved bill of quantities and layout drawings.
( I ) Scope of work : ( Electrical)
Survey, Design, engineering, manufacturing, testing, supply to destination site basis,
including transportation & insurance, storage, laying/installation, testing &
commissioning of the 66KV Underground cable line for Supply, Laying, Erection,
Testing and Commissioning of 66kV,1CX630 sqmm XLPE Cable with
Poly.Al./Aluminum construction on EPC basis Various lines under Navsari Circle
incl. all the accessories, joints/termination, etc. complete in all respects on turnkey
basis for the followings;
PROJECT PARTICULARS
Name of the Project:
Supply, Laying, Erection, Testing and Commissioning of 66kV,1CX630 sqmm
XLPE Cable with Poly.Al./Aluminum construction on EPC basis Various lines
under Navsari Circle.
1. System Voltage and : 66kV
System of Earthing Pipe type & Counter Pose
2. Rated frequency : 50 Hz ± 5%
3. Voltage variation : 66kV +5% -15%
4. Seismic Zone : Zone -III
List of 66kV UG cable Lines for Bharuch Circle:
1 66kV D/C Variyav- Prop. Variyav II UG Cable line 2*(3+1)
2 66kV Segachhama-Pala LILO at Prop. Jahangirpura,2X(3+1)
3 66kV 1st phase - Prop. Vapi 5th Phase,2X(3+1)
4 66kV Bhestan - Prop. Govalak II, 2X(3+1)
5 66kV Utran-Gothan LILO Prop. 66kV Mota Varachcha-II, 2X(3+1)
6 66kV Segvachhama - Prop. Gauravpath, 2X(3+1)
7 66kV Niyol Prop. Parvat II LILO Prop. 66kV Limbayat, 2X(3+1)
Seal & Signature of Bidder
8 66kV prop. Vanakla to prop.Bhesan, 2X(3+1)
1. Above Tentative list of 66kv UGC lines provided but list may be reviewed and
revised as per the GETCO’s requirement.
2. W.r.t .above tentative BOQ is shared and final BOQ will be fixed after
placement of order and survey by EPC agency)
3. Bidders have to start all line work simultaneously with different gang/ project
4. DOC will be given after verifying all the statutory approval status.
3.0 Bidding Costs
All costs/expenses in the preparation and submission of the Bid (including any
post Bid discussions/presentations) shall be fully borne by the Bidder. Owner
will not be responsible/ liable for these costs irrespective of the course and
conclusion of this Bidding.
4.0 BID DOCUMENTS
Details of Documents
The following Bid documents apart from Invitation to Bid detail the material and
equipment specifications/characteristics, the bidding procedures and the terms
& conditions of contract:
a. General Conditions of Contract (GCC-Part I)
b. Erection Conditions of Contract (ECC-Part I)
c. Special Conditions of Contract (SCC-Part I)
d. Technical Specifications (TSP-Part II – Electrical)
5.0 Knowing the Bid Documents
Every intending Bidder is to examine and understand all instructions, forms,
terms, conditions and specifications in the Bid Documents and fully know
himself all the conditions and contents therein, which may in any manner, affect
the scope & content of work and the costs thereof. Submission of a Bid not
substantially responsive to the Bid Document in all respects and/or failure to
furnish all information required by the Bid Document may entail rejection of the
Bid at the Bidder’s risk.
6.0 Clarifications on Bid Documents
6.1 In case an intending Bidder finds any discrepancy or omission in the documents
and specifications or is in doubt as to the true meaning of any part, he shall
make a request, in writing not later than one week before the date of submission
of bid, to the owner in triplicate. The owner will issue explanations,
interpretations and clarifications as deemed fit in writing as a response to this
request. On receipt of such interpretations/clarifications, the Bidder may submit
his Bid within the date and time stipulated in the Bid invitation, All such
explanations, interpretations and clarifications from the Owner shall be deemed
as part of Bid Documents and shall invariably accompany the Bidder’s proposal.
6.2 Any verbal/telephonic clarifications and information given by the Owner or his
employee (s) or his representative(s) will not in any way be binding on the
Seal & Signature of Bidder
7.0 Amendment of bidding document:
7.1 At any time prior to the deadline for submission of Bids the Owner may, for any
reason, whether at his own initiative or in response to a clarification requested
by the intending Bidder, modify the Bidding Document with amendment(s).
7.2 The amendment will be notified in writing or Fax /web site to all intending
Bidders who have received the Bidding Document at the address contained in
the letter of request for issue of Bidding document from the Bidders. Owner will
bear no responsibility or liability arising out of non-receipt of the same in time
7.3 In order to afford prospective bidders reasonable time in which to take the
amendment into account in preparing their bids, the Owner may, at his
discretion, extend the deadline for the submission of bids.
7.4 Such amendments, clarifications etc. shall be binding on bidders and will be
given due consideration by the Bidders while they submit their bids and shall
invariably enclose such documents as a part of the bid.
8.0 PREPARATION OF BIDS
Language of Bid:
8.1 The Bid prepared by the Bidder and all correspondence and documents relating
to the Bid, exchanged by the Bidder and the Owner, shall be written in the
English language, provided that any printed literature furnished by the Bidder
may be written in another language so long as accompanied by an English
translation of its pertinent passages. Failure to comply with this may disqualify
a bid. For purposes of interpretation of the bid, the English translation shall
Bidders have to make the Bid in the formats furnished with this Document.
verbatim without adding any printed/typewritten text of their own.
9.0 Local Conditions:
9.1 It will be imperative on each Bidder to fully inform himself of all local conditions
and factors which may have any effect on the execution of the Contract covered
under these documents and specifications. The Owner shall not entertain any
request for clarifications from the bidders, regarding such local conditions.
9.2 It must be understood and agreed that such factors have properly been
investigated and considered while submitting the proposals. No claim for
financial adjustment to the Contract awarded under these specifications and
documents will be entertained by the owner. Neither any change in the time
schedule of the Contract nor any financial adjustments arising thereof shall be
permitted by the Owner, which are based on the lack of such clear information
or its effect on the cost of the works to the Bidder.
10.0 Documents comprising the Bid:
Seal & Signature of Bidder
Data Requirements etc. furnished in the Bidding Documents, indicating, for the
goods to be supplied and services to be rendered, a brief description of goods
and services, quantity and price.
10.2 The Bidder shall also submit documentary evidence to establish that the Bidder
meets the Qualification Requirements as detailed in Special Conditions of
Contract and GCC.
10.3 All Tender Documents/ formats are to be returned completed in all respects
and signed by the Company Authorized Signatory wherever specified.
All Bid documents duly signed & sealed shall be submitted with technical
10.4 The Bid Guarantee shall be furnished in a separate cover in accordance with
11.0 Bid Price:
sheets, the unit end cost prices inclusive of GST of the goods, the price for erection,
testing and commissioning, structural works and other services it proposes to furnish
under the contract, along with the total bid price. The details of GST shall be clearly
indicated for each item in the prescribed format of price bid
GST shall be applicable at the rate of 9% CGST plus 9% SGST or 18%
IGST, or as applicable to composite supplies in the nature of Works
Contract applicable from time to time will be paid within the original
contractual delivery period. However, the Classification Codes (i.e. HSN
or SAC) for each item of different segments or portions of the Works
Contract, shall be specified separately, for information and technical
identification purpose only.
11.2 Detailed break up, covering all the price components of unit prices as well as total bid
provided by the bidder. This break up shall be entered separately in the following
A) For all goods offered:
Prices quoted should be FIRM and on F.O.R. Destination basis (i.e. any of the stores
of COMPANY in Gujarat). However, the Tenderer should indicate in Price Bid, the
break-up of Total Unit F.O.R. Destination Price stating the Unit Ex-works price, freight,
packing & forwarding charges, Insurance Charges, separately in price bid, which is a
must. The rate of GST shall be 9% CGST plus 9% SGST or 18% IGST or as applicable
to composite supply in the nature of Works Contract, applicable from time to time.
ii. This tender is to be treated as a contract for composite supply under the category of
Works Contract, which is, as per the provisions of Section 2(30), read with, Section
2(119), further read with, Paragraph 6(a) of the Schedule II, to the CGST Act,
and similar provisions, applicable under UTGST Act, 2017 and the IGST Act,
However, the classification Codes (HSN/SAC) for each item under different segments
or portions of the Works Contract, shall be specified separately for the knowledge and
transparency purpose which shall have no bearing on price or taxation payment.
Seal & Signature of Bidder
iii. The offered prices to be indicated in online mode of tender in the format given. The
price bid submitted in physical mode shall not be considered.
iv. The Tenderer should invariably indicate the unit end cost price excluding GST
considering all their costs / calculations in the Price bid itself for each item and all sub-
items if any. This is a must. Cost components hidden / furnished elsewhere will not be
considered and will be ignored out rightly.
v. Every bidder shall inform their GSTIN No. of the registered place(s) wherefrom the
bidder intends to supply the goods / services, meaning thereby the bidder has to supply
the goods / services from the relevant declared / registered place of supply only.
11.3 The bidder’s separation of price components in accordance with above clause No:
will be solely for the purpose of the facilitating the comparison of Bids by the owner,
for contract price amendment due to quantity variation and for on account payments
(in case of award) and shall not in any way limit the Owner’s rights.
11.4 The Price quoted by the bidder shall remain firm during the contract period and
shall not be subject to variation on any account or for change in quantity.
11.5 The Bidder shall specifically note that the Tenders are invited on item rate base.
12.0 Bid Security/EMD:
12.1 The bidder shall furnish, as a part of its bid EMD, bid security for an amount to be paid as
(a) The estimated cost for of Tender is more than Rs. 100 lacs, the EMD is payable
50 % of EMD by DD in favor of Gujarat Energy Transmission Corporation
Ltd. on any Scheduled Bank in Vadodara and Balance 50 % by Bank
Guarantee from any Nationalized Bank in the format provided herein.
(b) The estimated cost of tender is less than Rs.100 Lacs, the EMD is payable as
100 % of EMD by DD in favor of Gujarat Energy Transmission Corporation
Ltd. on any Scheduled Bank in Vadodara.
(c) Payment by Cheque / Coop Bank Guarantee/ Company Guarantee is not
(d) Validity Period: - The offer should be valid for a minimum period of 180 days
from the date of opening of Technical bid.
12.2 The bid security is required to protect the owner against the risk of Bidder’s
conduct, which would warrant the guarantee forfeiture, pursuant to relevant
paras elsewhere. The bid guarantee shall be made payable to the Owner
without any condition whatsoever.
12.3 Any bid not secured in accordance with above 12.1 will be rejected by the
Owner as non-responsive. No exemptions are made in the furnishing of the
Seal & Signature of Bidder
12.4 Unsuccessful Bidder’s bid security / EMD will be returned / refunded on
finalization of tender or three months from the date of submission of tender
whichever is later.
12.5 The successful bidders, Bid Security will be discharged upon, furnishing the
contract performance guarantee.
12.6 The bid guarantee may be forfeited.
a) If a Bidder withdraws its bid during the period of bid validity specified by
the bidder on the bid Form:
b) If a bidder refuses to accept the contract or fails to commence the works
(including supplies within thirty days of letter of award of contract)
13.0 Format of Bid:
13.1 The Bidder shall prepare two copies of the bid, clearly marking each “Original
bid” and “Copy of Bid”, as appropriate. In the event of any discrepancy between
them the original shall govern. All the documents furnished in original document
shall be furnished in other copies of Bids.
13.2 The original and all copies of the bid shall be typed or written in indelible ink
and shall be signed by the Bidder or a person or persons duly authorized by the
Bidder to sign the Contract. The letter of authorization shall be indicated by
written power-of-attorney accompanying the bid. All pages of the bid, except for
un-amended printed literature, shall be initiated by the person or persons
signing the bid.
13.3 The Bidders must submit the qualifying data in one original and one duplicate
copy as required in this Instructions to Bidders in separate envelopes sealed
and enclosed in the envelope submitting proposals, super scribed as under :
QUALIFYING DATA FOR THE SUPPLY AND ERECTION OF TENDER NO:
ACE(P&C)/Contract/E-512/UG/66kV/S,L&E
The bid shall contain no interlineations, erasures or overwriting except as necessary
to correct errors made by the Bidder, in which case such corrections shall be initiated
by the person or persons signing the bid.
13.4 Bids shall be submitted as under:
Cover-I Earnest Money Deposit (Bid-Security), as per relevant clause of
SCC duly signed and Contractor’s covering letter. Tender fee
details ( as per tender notice)
Cover-II Qualifying Requirements. (Electrical & Civil) Online Only
Separate covers/ files for relevant data shall be kept in one cover.
Cover-III Technical Bid (Electrical ) Online Only
Seal & Signature of Bidder
Must contain conditions and schedules of Part- III without prices and Technical
Data Requirement Sheets (Cover I, II, III will be collectively called Technical
All Bid documents duly signed & sealed shall be submitted with technical
Note: The prices are to be filled up online only. Price bid are not to be
submitted with the physical documents.
14.0 Signature Of Bids:
14.1 The bid must contain the name, residence and place of business of the person
or persons making the bid and must be signed and sealed by the Bidder with
his usual signature. The names of all persons signing should also be typed or
printed below the signature.
14.2 Bid by a partnership must be furnished with full names of all partners and be
signed with the partnership name, followed by the signature(s) and
designation(s) or the authorized partner(s) or other authorized
representative(s).
14.3 Bids by Corporation/Company must be signed with the legal name of the
Corporation/Company by the President/Managing Director or by the Secretary
or other person or persons authorized to bid on behalf of such
Corporation/Company in the matter.
14.4 A bid by a person who affixes to his signature the word ‘President’, ‘Managing
Director’, ‘Secretary’, ‘Agent’ or other designation without disclosing his
Principal will be rejected.
14.5 If it is found that two or more persons who are connected with one another
either financially or as a principal and agent have bid under different names
without disclosing their connection then such bids will be liable for rejection.
Satisfactory evidence of authority of the person signing on behalf of the Bidder
shall be furnished with the bid.
14.6 The Bidder’s name stated on the proposal shall be the exact legal name of the
14.7 Bids not conforming to the above requirements of signing may be disqualified
and EMD forfeited.
15.0 Sealing and marking of bids:
15.1 Cover-I 1. Bid No.
2. Due date for opening
3. Reference of tender fee & earnest money deposit
Cover-II 1. Bid No.
2. Due date for opening.
Seal & Signature of Bidder
3. Qualifying Requirements (Electrical & civil).
Cover-III 1. Bid No.
2. Due date for opening
3. Technical bid (Electrical) & reference and required certificates
Cover-I, Cover-II ,Cover-III shall be individually sealed and super scribed as
indicated above and should be enclosed in the main cover duly sealed and
super scribed as Tender for …………………………………… against Bid
No…………… due on…………… containing Cover-I, Cover-II, Cover-III , of this
The original Bid and accompanying documents clearly marked “Original” plus
one copy for Cover I, II , III shall be submitted by the Bidder at the date, time
and place specified. In the event of any discrepancy between the original and
the copies, the original shall govern.
The Bid shall be submitted by RPAD or through speed post services at
the Office of the ACE (Procurement & Contracts) GETCO, Bids submitted
should be posted with due allowance for any postal delay. The Bids received
after the Due Date and Time of opening are liable to be rejected.
Telegraphic/Telex/Fax/e-mail Bids shall not be entertained.
The price bid shall not be submitted in physical form. It shall be submitted online
15.2 The Bidders shall seal the original and each copy of the bid in an inner and an
outer envelope, duly marking the envelopes as “original” and “copy”.
15.3 a. Addressed to the Owner at the following address:
The Addl. Chief Engineer (Procurement & Contracts) - GETCO
8th Floor, Sardar Patel Vidyut Bhavan, Race Course,
b. Bear the name of package bid enquiry number, name of the work and the
words. “DO NOT OPEN BEFORE……………………
15.4 The inner envelope shall indicate the name and address of the Bidder to
enable the bid to be returned unopened in case it is declared “late” or “rejected”.
15.5 If the outer envelope is not sealed and marked as required by Clause No:
the Owner will assume no responsibility for the bid’s misplacement or premature
15.6 The Bid Security conditions must be submitted in a separate sealed envelope.
16.0 Deadline for submission of bids :
16.1 Bids submitted by telex/telegram will not be accepted. No request from any
Bidder to the Owner to collect the proposals from airlines, cargo agent etc. shall
be entertained by the Owner.
Seal & Signature of Bidder
16.2 Bids must be received by the Owner at the address specified under Clause No:
15.3, not later than the time & date mentioned in the Invitation to Bid.
16.3 The Owner may, at its discretion, extend this deadline for the submission of
bids by amending the Bidding Document in which case all rights and obligations
on the Owner and Bidders previously subject to the deadline will thereafter be
subject to the deadline as extended.
17.1 Any bid received by the Owner after the time and date fixed or extended for
submission of bids prescribed by the Owner, will be rejected and not
considered for evaluation.
18.0 Modification and withdrawal of bids:
18.1 The Bidder may modify or withdraw its bid after the bid’s submission provided
that written notice of the modification or withdrawal is received by the Owner
prior to the deadline prescribed for submission of bids.
18.2 The Bidder’s modification or withdrawal notice shall be prepared, sealed,
marked and dispatched in accordance with the provisions of clause No: 15.0.
The envelope should clearly indicate whether the modification is for the
Technical bid or the Price bid. No bid modifications notice by Telex/Grams/Fax
shall be entertained by the Owner.
18.3 No bid shall be modified in any manner, whatsoever subsequent to the deadline
for submission of bids.
18.4 No bid may be withdrawn in the interval between the deadline for submission
of bids and the expiration of the period of bid validity specified by the Bidder on
the Bid Form. Withdrawal/modification of a bid during this interval may result in
the Bidder’s forfeiture of its bid security.
19.0 Information required with the proposal:
19.1 The bids must clearly indicate the name of the manufacturer, the type and/or
model of each principal item of equipment proposed to be furnished and
erected. The bid should also contain drawings and descriptive materials
indicating general dimensions, materials from which the parts are
manufactured, principles of operation, the extent of pre-assembly involved,
major construction equipment proposed to be deployed, method of erection and
the proposed erection organizational structure.
19.2 The above information shall be provided by the Bidder in the form of separate
sheets, drawings, enclosed etc. in one copies along with soft copy.
19.3 Any bid not containing sufficient descriptive material to describe accurately the
equipment proposed may be treated as incomplete and hence rejected. Such
descriptive materials and drawings submitted by the Bidder will be retained by
the Owner. Any major departure from these drawings and descriptive material
submitted will not be permitted during the execution of the Contract without
specific written permission of the Owner.
Seal & Signature of Bidder
19.4 Oral statements made by the Bidder at any time regarding quality, quantity or
arrangement of the equipment or any other matter will not be considered.
19.5 Standard catalogue pages and other documents of the Bidder may be used in
the bid to provide additional information and data as deemed necessary by the
19.6 The Bidder, along with his Proposal, shall submit a list of recommended
erection equipment and materials which will be required for the purpose of
erection of equipment and materials supplied under the Contract.
19.7 In case the ‘Proposal’ information contradicts specification requirements, the
specification requirements will govern, unless otherwise brought out clearly in
the technical commercial deviation schedule.
BID OPENING AND EVALUATION
20.0 Opening of bids by owner:
20.1 The Owner will open the bids in the presence of Bidder’s representatives who
choose to attend on the date and time mentioned for opening of bids in the
Invitation to Bid or in case any extension has been given thereto, on the
extended bid opening date and time notified to all the Bidders who have
purchased the bidding document. The Bidder’s representatives who are present
shall sign a register evidencing their attendance.
20.2 The Bidder’s names, Technical modifications, Bid withdrawal and such other
details as the Owner, at his discretion may consider appropriate, will be
announced in the Technical Bid Opening.
20.3 The price bids of all the “Techno-Commercial” Responsive Bidders shall be
opened in the presence of representatives (up to two per firm) of such bidders
who choose to be present. The date & time of opening the Price Bid shall be
intimated to all such qualified bidders by Fax/Telex, at least one week in
advance besides inviting final price bid if found appropriate after evaluation of
Technical bids.
20.4 The Bidder’s name, Bid Price, all discounts if any, modifications in the Price Bid
and any such other details as the Owner, at his discretion, may consider
appropriate, will be announced/ furnished in the Price Bid Opening.
20.5 No electronic recording/transmitting devices will be permitted during Bid
21.0 Purpose of evaluation of bids:
21.1 The Bids received/accepted/opened will be evaluated by the Owner to ascertain
the technical responsiveness of the bid for the complete scope of the proposal,
as covered under these specifications and documents. All technically
responsive bids shall then be examined to determine the lowest evaluated
commercially and technically responsive bids.
22.0 Policy for bids under consideration:
Seal & Signature of Bidder
22.1 Bids shall be deemed to be under consideration immediately after opening of
Technical Bid and until such time official intimation of award/rejection is made
by the Owner to the Bidders. While the Bids are under consideration, Bidders
and/or their representatives and other interested parties are advised to refrain
from contacting by any means, the owner and/or his employee’s
representatives on the matters related to Bids under consideration.
22.2 Clarification of bids:
To assist in the examination evaluation and comparison of Bids the owner may
on his own ask the Bidder for a clarification of its bid. The request for clarification
and the response shall be in writing and no change in the price or substance of
the bid shall be sought, offered or permitted.
23.0 Preliminary Examination:
23.1 The Owner will examine the bids to determine whether they are complete,
whether any computational errors have been made, whether required sureties
have been furnished, whether the documents have been properly signed, and
whether the bids are generally in order.
23.2 Arithmetical errors will be rectified on the following basis:
If there is a discrepancy between the unit price and the total price that is
obtained by multiplying the unit price and quantity, the unit price shall prevail
and the total price shall be corrected. If there is a discrepancy between the total
bid amount and the sum of total costs, the latter shall prevail and the total bid
amount will be corrected accordingly. If there is a discrepancy between words
and figures, the amount advantageous to the Owner will prevail. If the Bidder
does not accept the correction of the errors as above, his Bid will be rejected
and the amount of Bid Security will be forfeited. The Bidder should ensure that
In the case of any inconsistency in the prices furnished in the specified prices
schedules to be identified in Bid Form for this purpose, the Owner shall be
entitled to consider the highest price for the purpose of evaluation and for the
purpose of award of Contract use the lowest of the prices in these schedules.
23.3 Prior to the detailed evaluation, the Owner will determine the substantial
responsiveness of each bid to the Bidding Document. For purpose of these
Clauses, a substantially responsive bid is one which conforms to all the terms
and conditions of the Bidding Document without material deviations. A material
deviation is one which affects in any way the prices, quality, quantity or delivery
period of the equipment, completion of works or which limits in any way the
responsibilities or liabilities of the Bidder of any right of the Owner as required
in these specifications and documents. The Owner’s determination of a bid’s
responsiveness shall be based on the contents of the bid itself without recourse
to extrinsic evidence.
23.4 A bid determined as not substantially responsive will be rejected by the Owner
and may not subsequently be made responsive by the Bidder by correction of
non-conformity.
Seal & Signature of Bidder
23.5 The Owner may waive any minor informality or non-conformity or irregularity in
a bid which does not constitute a material deviation, provided such waiver does
not prejudice or affect the relative ranking of any Bidder.
24.0 Award Criteria
24.1 The owner will award the contract to the successful Bidder, whose bid has been
determined to be substantially responsive and has been determined as the
lowest evaluated bid, providing further that the Bidder is determined to be
qualified to perform the contract satisfactorily. The Owner shall be the sole
judge in this regard.
24.2 In case of award of Contract on a bidder there shall be separate contracts one
for Civil works, second for supply of goods and third for the erection & services
works in substations.
24.3 Further, the Owner reserves the right to award separate contracts to two or
more parties in line with the terms and conditions specified in the accompanying
Technical Specifications.
25.0 Owner’s right to accept any bid and to reject any or all bids:
25.1 The Owner reserves the right to accept or reject any bid, and to annual the
bidding process and reject all bids at time prior to award of contract, any without
thereby incurring any liability to the affected Bidder or Bidders or any obligation
to inform the affected Bidder or Bidders of the grounds for the Owner’s action.
26.0 Notification of award:
26.1 Prior to the expiration of the period of bid validity and extended validity period,
if any, the Owner will notify the successful Bidder in writing by registered letter
or cable or telex or FAX, to be confirmed in writing by registered letter, that its
bid has been accepted.
26.2 The notification of award will constitute the formation of the Contract.
26.3 Upon the successful Bidder’s furnishing of performance guarantee pursuant to
relevant clause No: 36 & 38, the Owner will promptly notify each unsuccessful
Bidder and will discharge its bid security, pursuant to Clause No: 12.00.
27.0 Signing of contract:
27.1 At the same time as the Owner notifies the successful Bidder that his bid has
been accepted, the Owner will send the Bidder the detailed of Award,
incorporating all agreements between the parties.
27.2 Within 15 days of receipt of the detailed of Award, the successful bidder shall
sign the same with date and return it to the Owner.
27.2 The Bidder will prepare the Contract Agreement as per the proforma prescribed
and the same will be signed within 30 (Thirty) days of notification of Award.
28.0 DEFINITION OF TERMS
Seal & Signature of Bidder
28.1 The ‘Contract’ means the agreement entered into between the Owner and the Contractor
as per the Contract Agreement signed by the parties, including all attachments and
appendices thereto and all documents incorporated by reference therein.
28.2 ‘Owner’ shall mean the Gujarat Energy Transmission Corporation Limited, Vadodara
or any of its group companies i.e. GUVNL, GSECL, MGVCL, DGVCL, PGVCL, UGVCL
and shall include its legal representatives, successors and assigns.
28.3 ‘Contractor’ or ‘Manufacturer’ shall mean the Bidder whose bid is accepted by the
Owner for the award of the Works and shall include such successful Bidder’s legal
representatives, successors and permitted assigns.
28.4 ‘Sub-Contractor’ shall mean the person named in the Contract for any part of the Works
or any person to whom any part of the Contract has been sublet by the Contractor with
the consent in writing of the Engineer and will include the legal representatives,
successors and permitted assigns of such person.
28.5 ‘Engineer’ shall mean the officer appointed in writing by the Owner to act as Engineer
from time to time for the purpose of the Contract.
28.6 The terms ‘Equipment’, ‘Stores’ and ‘Materials’ shall mean and include equipment,
stores and materials to be provided by the Contractor under the Contract.
28.7 ‘Works’ shall mean and include the furnishing of equipment, labour and services, as
per the Specifications and complete erection, testing and putting into satisfactory
operation including all transportation, handling, unloading and storage at the Site as
defined in the Contract.
28.8 ‘Specifications’ shall mean the Specifications and Bidding Document forming a part of
the Contract and such other schedules and drawings as may be mutually agreed upon.
28.9 Site’ shall mean and include the land and other places on, into or through which the
works and the related facilities are to be erected or installed and any adjacent land,
paths, street or reservoir which may be allocated or used by the Owner or Contractor
in the performance of the Contract.
28.10 The term ‘Contract Price’ shall mean the Firm price quoted by the Contractor in his bid
with additions and/or deletions as may be agreed and incorporated in the Letter of
Award and the contract agreement for the entire scope of the works.
28.11 The term ‘Equipment Portion’ of the Contract price shall mean the ex-works value of the
equipment/Materials supplied include structures, town materials insulators, conducting
28.12 The term ‘Erection Portion’ of the Contract price shall mean the value of field activities
of the works including erection, testing and putting into satisfactory operation including
successful completion of performance and guarantee tests to be performed at Site by
the Contractor including cost of insurances.
28.13 ‘Manufacturer’s Works’ or ‘Contractor’s Works’, shall mean the place of work used by
the manufacturer, the Contractor, their collaborators/associates or Sub-Contractors for
the performance of the Contract.
28.16 Site Engineer ‘Inspector’ shall mean the Owner owner’s Engineers or any person
nominated by the time to inspect the equipment; stores or Works under the Contract
and/or the duly authorized representative of the Owner.
28.17 ‘Notice of Award of Contract’/’Letter of Award’/’Telex of Award’ shall mean the official
notice issued by the Owner notifying the Contractor that his bid has been accepted.
Seal & Signature of Bidder
28.18 ‘Order’ shall mean the official letter issued by the Owner informing the acceptance of
28.19 ‘Date of Contract’ shall mean the date on which Notice of Award of Contract/Letter of
Award has been issued.
28.20 ‘Month’ shall mean the calendar month. ‘Day’ or ‘Days’ unless herein otherwise
expressly defined shall mean calendar day or days of 24 hours each.
28.21 A ‘Week’ shall mean continuous period of seven (7) days.
28.22 Writing’ shall include any manuscript, type written or printed statement, under or over
signature and/or seal as the case may be.
28.23 When the words ‘Approved’, ‘Subject to Approval’, ‘Satisfactory’, ‘Equal to’, ‘Proper’,
‘Requested’, ‘As Directed’, ‘Where Directed’, ‘When Directed’, ‘Determined by’,
‘Accepted’, ‘Permitted’, or words and phrases of like importance are used the approval,
judgment, direction etc. is understood to be a function of the Owner/Engineer.
28.24 Test on completion shall mean such tests as prescribed in the Contract to be performed
by the Contractor before the work is taken over by the Owner.
28.25 ‘Performance and Guarantee Tests’, shall mean all operational checks and tests
required to determine and demonstrate capacity, efficiency, and operating
characteristics as specified in the Contract Documents.
28.26 The term ‘Final Acceptance’/‘Taking Over’ shall mean the Owner’s written acceptance
of the Works performed under the Contract, after successful
commissioning/completion of Performance and Guarantee Tests, as specified in the
accompanying Technical Specifications or otherwise agreed in the Contract.
28.27 ‘Guarantee Period’/’Maintenance Period’ shall mean the period during which the
Contractor shall remain liable for repair or replacement of any defective part of the
works performed under the Contract.
28.28 ‘Latent Defects’ shall mean such defects caused by faulty designs, material or work-
man- ship which cannot be detected during inspection, testing etc, based on the
technology available for carrying out such tests.
28.29 ‘Drawing’, ‘Plans, shall mean all:
a) Drawings furnished by the Owner/Consultant as a basis of Bid/Proposals.
b) Supplementary drawings furnished by the Owner/Consultant to clarify and to define
in greater detail the intent of the Contract.
c) Drawings submitted by the Contractor with his bid provided such drawings are
acceptable to the Owner/Consultant.
d) Drawings furnished by the Owner/Consultant to the Contractor during the progress
of the work; and
e) Engineering data and drawings submitted by the Contractor during the progress of
the work provided such drawings are acceptable to the Engineer/Owner.
28.30 ‘Codes’ shall mean the following including the latest amendments and/or
replacements, if any :
a) Indian Electricity Act, 1905 and Rules and Regulations made there under.
b) Electricity Act 2003 and Rules & Regulations made there under.
Seal & Signature of Bidder
c) Indian Factory Act, 1948 and Rules and Regulations made there under.
d) Indian Explosives Act, 1884 and Rules and Regulations made there under.
e) Indian Petroleum Act, 1934 and Rules and Regulations made there under.
f) A.S.M.E. Test Codes.
g) A.I.E.E. Test Codes.
h) American Society of Materials Testing Codes.
i) Standards of the Indian Standards Institution.
j) Other Internationally approved standards and/or rules and regulations touching the
subject matter of the Contract.
28.31 Words imparting the singular only shall also include the plural and vice –versa where
the context so requires.
28.32 Words imparting ‘Person’ shall include firms, companies, corporations and
associations or bodies of individuals, whether incorporated or not.
28.33 Terms and expressions not herein defined shall have the same meaning as are
assigned to them in the Indian Sale of Goods Act (1930), failing that in the Indian
Contract Act (1872) and failing that in the General Clauses Act (1897) including
amendments thereof, if any.
In addition to the above the following definitions shall also apply.
a) ‘All equipment and materials’ to be supplied shall also mean ‘Goods’.
b) ‘Constructed’ shall also mean ‘erected and installed’.
a) ‘Contract Performance Guarantee’ shall also mean ‘Contract Performance
28.34 GST/Cess means all applicable Tax/Cess under GST Laws. GST Laws means
IGST Act, GST(Compensation to the State for Loss of Revenue) Act, CGST
Act, UTGST Act and SGSCT Act, 2017and all related ancillary legislations.
28.35 Works contract means a Contract for composite supply and covered under the
definition of Works Contract as defined under Section 2(119) of the CGST
Act, 2017 or SGST Act, 2017 and similar provisions, applicable under the
UTGST Act, 2017and the IGST Act,
29.0 APPLICATION
These General Conditions shall apply to the extent that they are not superseded
by provisions in other parts of the Contract.
The goods supplied under this Contract shall conform to the standards
mentioned in the Technical Specifications, and, when no applicable standard is
mentioned, to the authoritative standard appropriate to the goods and such
standards shall be the latest issued by the concerned institution.
Seal & Signature of Bidder
31.0 LANGUAGE AND MEASURES
All documents pertaining to the Contract including specifications, schedules,
notices, correspondences, operating and maintenance instructions, drawings
or any other writing shall be written in English language. The Metric System of
measurement shall be used exclusively in the Contract.
32.0 Price Basis: (Price variation Applicable)
32.1 The Price shall be quoted on firm basis except for supply of 66KV, 1CX630
sq.mm XLPE Power Cable with Poly.Al. /Aluminum construction for which
Price variation will be applicable.
32.2 The Price quoted by the bidder shall remain fixed for all the items except 66KV
1CX630 sq.mm XLPE Power Cable with Poly.Al. /Aluminum construction;
during the bidder's performance of the contract and shall not be subject to
variation on any account save for change in quantity. A bid submitted with an
adjustable price quotation shall be treated as non-responsive and rejected.
(1) 66KV 1CX630 Sq.MM Cu. Wire screen, poly Aluminum laminated inner
sheathed, Aluminum wire armored XLPE cable
P = Po + AIF (Al – Alo) + XLFAl (CC – CCo) + CuFc (Cu –Cuo) + CCFAl (POC – POCo) + ALA (Al – Alo)
Sr.No. Sign = Description of Sign
1 P = Price payable as adjusted in accordance with above
appropriate formula (in Rs./KM).
2 Po = Price quoted / confirmed (in Rs./KM).
3 AIF = Variation factor for Aluminum.
4 Al = Price of Aluminum. This price is as applicable on Two
months prior to the date of delivery.
5 Alo = Price of Aluminum. This price is as applicable on One
month prior to date of tendering.
6 XLFAl = Variation factor for XLPE Compound for Aluminum
Conductor Cable
7 CC = Price of XLPE Compound. This price is as applicable on
Two months prior to the date of delivery.
8 CC0 = Price of XLPE Compound. This price is as applicable on One
month prior to date of tendering.
9 CuFc = Variation factor for copper screen
10 Cu = Price of CC Copper Rods. This price is as applicable on
Two months prior to the date of delivery.
11 Cuo = Price of CC Copper Rods. This price is as applicable on
One month prior to the date of tendering .
12 CCFAl = Variation factor for PE Compound for Aluminum Conductor
13 POC = Price of Polymer Compound. This price is as applicable on
Two months prior to the date of delivery.
14 POC0 = Price of Polymer Compound. This price is as applicable on
One month prior to the date of tendering .
15 ALA = Aluminum factor ALA
Seal & Signature of Bidder
The variation factors shall be as under:
[I] 66KV 1CX630 Sq.MM Cu. Wire screen, poly Aluminum laminated inner
sheathed, Aluminum wire armored XLPE cable.
Size of XLPE Cable AIF XLFAl CuFc CCFAl ALA
66 KV 1C x 630 sq mm (Poly-al-Poly) 1.828 1.743 2.104 0.792
(2) 66KV 1CX630 Sq.MM Aluminum corrugated sheath, XLPE cable
P = P0 + AIF (Al – Al0) + XLFAl (CC – CC0) + AlFs (Al –Al0) + CCFAl (POC – POC0)
Sr.No. Sign = Description of Sign
1 P = Price payable as adjusted in accordance with above appropriate
formula (in Rs./KM).
2 Po = Price quoted / confirmed (in Rs./KM).
3 AIF = Variation factor for Aluminum.
4 Al = Price of Aluminum. This price is as applicable on Two months
prior to the date of delivery.
5 Alo = Price of Aluminum. This price is as applicable on One month
prior to date of tendering.
6 XLFAl = Variation factor for XLPE Compound for Aluminum Conductor
7 CC = Price of XLPE Compound. This price is as applicable on Two
months prior to the date of delivery.
8 CC0 = Price of XLPE Compound. This price is as applicable on One
month prior to date of tendering.
9 AlFs = Variation factor for Corrugated Aluminum Sheath
10 Al = Price of Aluminum. This price is as applicable on Two months
prior to the date of delivery.
11 Alo = Price of Aluminum. This price is as applicable on One month
prior to the date of tendering .
12 CCFAl = Variation factor for PE Compound for Aluminum Conductor Cable
13 POC = Price of Polymer Compound. This price is as applicable on Two
months prior to the date of delivery.
14 POC0 = Price of Polymer Compound. This price is as applicable on
One month prior to the date of tendering .
The variation factors shall be as under:
[I] 66KV 1CX630 Sq.MM Aluminum corrugated sheath, XLPE cable.
Size of XLPE Cable AIF XLFAl AlFs CCFAl
66KV 1CX630 Sq.MM Aluminum 1.828 1.743 1.219
corrugated sheath, XLPE cable
The Prices and Indices are as published by IEEMA vide Circular reference
IEEMA(PVC)/CABLE(R-1)/--/-- prevailing as on First working day of the month
i.e.one month prior to the date of tendering.
The date of delivery is the date on which the cable is notified as being ready for
inspection/dispatch (in the absence of such notification, the date of
Seal & Signature of Bidder
manufacturer’s dispatch note is to be considered as the date of delivery) or the
contracted delivery date (including any agreed extension thereto), whichever is
(a) All prices of raw materials are exclusive of GST amount.
(b) All prices excluding Aluminum & Copper are as on first working day of the
(c) The details are as under:
1. Price of Aluminum is LME average Cash SELLER Settlement price of primary
Aluminum in US$ per MT as published by London Metal Bulletin(LME)
including premium for Aluminum ingot in US$ per MT is converted in Indian
2. Price of CC copper rods (in Rs./MT) is ex-works price as quoted by the primary
3. Price of Pig lead (in Rs./MT) is ex-works price as quoted by the primary
4. Price of Polymer Compound (in Rs./MT) is ex-works price as quoted by the
primary Manufacturer/s.
5. Price of XLPE Compound (in Rs./MT) is ex-works price as quoted by the
primary Manufacturer/s.
6. Price of PVC Compound (in Rs/MT) is the ex-works price, as quoted by the
manufacturer/s.
The bidder has to specify in his Bid copper screen component per MT (CuFc-
Copper Screen), lead component (PbF) and corrugated Aluminum sheath
component per MT base on short circuit current requirement for each type and size
Price Variation will be applicable only with respect to original contractual delivery
period only. The price variation will not be applicable for the intermediate delay in
the supply during the delivery schedule. However, if any decrease in the price
variation it will be applicable to the bidder.
No price increase shall be allowed beyond the original delivery schedule, unless
specifically stated in the extension letter. As a rule, no price adjustment shall be
allowed for period of delay for which supplier is responsible. The purchaser will
however be entitled to any decrease in the price.
Supplier has to submit P.V bills (Negative / Positive) along with supporting
documents / IEEMA circulars necessary for calculation of P.V. with the bills for
balance 20% payable against S.R notes for checking & verification of the earlier
claim. Till, P.V. bills are submitted as above, the balance 20% bills will not be
processed for payment.
To claim the price variation successful bidder has to submit the supporting
document like duly notary certified copy of IEEMA circulars, P.V. Calculation sheet
etc. along with their invoices.
The base date for the above price variation Formula will be First day of One month
prior to opening month of tender.
(3) For structure material:
The latest revised PV formula is as under:
P0 SBLR SBIR Zn W
100 SBLRo SBIRo Zno W0
Seal & Signature of Bidder
P = Price payable as adjusted in accordance with the above
P0 = Price quoted/confirmed.
SBLR0 = Price of Steel Blooms- Retail (refer notes)
This price is as applicable for the month, ONE month prior to the
date of tendering.
SBIR0 = Price of Steel Billets- Retail (refer notes)
This price is as applicable for the month, ONE month prior to the
date of tendering.
Zn0 = Price of Electrolytic high grade zinc (refer notes)
This price is as applicable for the month, ONE month prior to the
date of tendering.
Wo = All India average consumer price index number for industrial
workers, as published by the Labour Bureau, Ministry of Labour,
Govt. of India (Base: 2016 = 100) (Refer notes)
This index number is as applicable for the month, THREE months
prior to the date of tendering.
For example, if date of tendering falls in November 2023, the applicable prices of
Steel Bloom-Retail (SBLR0), Steel Billets-Retail (SBIR0) and Zinc (Zn0) should be
for the month October 2023 and all India average consumer price index number
(W0) should be for the month of August
The above prices and indices are as published by IEEMA vide circular reference
IEEMA (PVC)/TLT- 2022/_/_ ONE month prior to the date of tendering
SBLR = Price of Steel Bloom-Retail (refer notes)
This price is as applicable for the month, TWO months prior to the
date of delivery.
SBIR = Price of Steel Billets-Retail (refer notes)
This price is as applicable for the month, TWO months prior to the
date of delivery.
Zn = Price of Electrolytic high grade zinc (refer notes)
This price is as applicable for the month, TWO months prior to the
date of delivery.
W= All India average consumer price index number for industrial
workers, as published by the Labour Bureau, Ministry of
Labour, Govt. of India (Base: 2016 = 100) (refer notes)
This index number is as applicable for the month, FOUR months
prior to the date of delivery.
The price variation amount in the ex-works price of fabricated structure members
(including bolts & nuts) calculated by the above formula shall not be subject to any
ceiling, whatsoever.
Seal & Signature of Bidder
The price variation formula will be applicable from the date of inspection / waival of
inspection for the material offered.
The price variation will be applicable during contractual delivery period only.
However, any decrease in the price variation during delayed period shall be
Price variation shall not be allowed beyond the original delivery date unless
specifically stated in the time extension letter. As a rule, no price adjustment shall
be allowed for the period of delay for which the supplier is responsible; however
purchaser will be entitled for any decrease in the prices during this delayed period.
In case of non-publication of applicable indices on a particular month, which
happens to be the applicable month for price variation purpose, the published
indices prevailing immediately prior to the particular month shall be applicable.
If the price adjustment amount works out to be positive, the same is payable to the
contractor by the owner and if it works out to be negative, the same is to be
recovered by the owner from the contractor.
No price variation will be allowed on the freight and insurance component of FOR
destination prices.
The supplier has to submit PV bills (Negative / Positive) along with supporting
documents / IEEMA circulars necessary for calculation of PV bills along with bills
for payment against SR Notes. To claim the price variation successful bidder has to
submit the supporting documents duly notary certified copy of IEEMA circulars, PV
calculation sheet etc. along with their invoices.
The base date for the above Price Variation formula will be first day of the month
prior to opening month of the Tender.
In the above price variation formula, subscript “0” refers to indices as on 30 days
prior to the date of Bid opening (referred to base date indices). Subscript “1” refers
to the indices as on 60 days prior to date of inspection / waival of inspection of the
material offered.’
33.0 Taxes and Duties:
Goods and Service Tax (GST):
33. 1 The F.O.R. Destination prices are excluding GST and Cess as applicable
which will be paid extra on a given taxable goods and/or services within the
original contractual delivery period. The amount and % of GST and Cess as
applicable should clearly be indicated separately. (GST/Cess means all
applicable Tax/Cess under GST Laws. GST Laws means IGST Act,
GST(Compensation to the State for Loss of Revenue) Act, CGST Act, UTGST
Act and SGSCT Act, 2017 and all related ancilliary legislations).
33. 2 You shall have to submit a C.A Certificate & duly authorized Signatory of
successful bidder, certifying that you have not claimed Refund of any
applicable GST and Cess, charged to COMPANY or shall not claim any such
Refund, on a future date, from the concerned Authorities and if, any Refund,
in respect of such GST and Cess, is claimed by you, it will be immediately
passed on to the COMPANY, without COMPANY making any specific Claim,
for the same, either from the Department or from you.
Seal & Signature of Bidder
33. 3 The offers having price INCLUSIVE OF GST and Cess is likely to be rejected
if the rate of GST and Cess is not mentioned clearly unless the bidder has
opted for Compostion Scheme under GST Act, which should be clearly
indicated in the price bid. COMPANY may at its discretion consider such offer
with presumption of highest applicable rate of GST and Cess prevailing when
the price quoted is inclusive of GST and Cess.
33. 4 If the Supplier/Contractor has opted for the Composition scheme of GST, the
same must be clearly specified with valid Declaration & Certificate from
Department. In the event of withdrawal/cessation of the Supplier from
Composition scheme during the tenure of the contract, the rate mentioned in
the price bid shall be final and any additional GST will have to be borne by the
tenderer. In no case additional amount towards tax or otherwise will be paid /
reimbursed to supplier/contractor. Further Statutory Variation clause will not
be applicable in case of Supplier / Contractor has opted for Composition
Scheme under GST.
33. 5 Supplier/Contractor should charge GST in Invoice at the rate as agreed to /
mentioned in acceptance of tender only and any deviation in the same shall
not be accepted. Further, any additional liability of GST (later on due to wrong
mentioning of GST rate, mis-interpretation of HSN/SAC Code, etc.) over and
above as charged in the invoice shall be borne by the Supplier/Contractor.
However, any refund received by the supplier / contractor on account of GST
charged from the company; such refund shall have to be passed on to the
company, along with interest if any. Such refund along with interest needs to
be passed on suo-moto by the supplier / contractor.
33. 6 Further, the Company has a right to recover the amount of GST along with
penal interest at the rate of 15% per annum if GST charged is not paid / short
paid to the government or fail to upload the details or uploads inaccurate
particulars on GSTIN portal by the Supplier / Contractor within the stipulated
33. 7 In case, Govt. revises the rate of GST rate / Code during the tenure of the
contract, the provision of GETCO’s statutory variation clause shall apply.
33. 8 INPUT TAX CREDIT BENEFIT
In the event of any statutory increase in the rate of Input Tax Credit and / or
due to inclusion of any other additional item of their inputs / input services
under the ambit of the Input Tax Credit provisions under the GST Act,
subsequent to the date of submission of the offer, the same should be passed
on to COMPANY and you should inform such changes to COMPANY from
33. 9 GST, other taxes and other levies and duties including custom duty solely in
respect of the transaction between the owner and the contractor under this
contract, if any, shall be included in the bid price. These shall also be indicated
separately wherever applicable as mentioned in the Tender .
33. 10 As regards the income Tax, surcharge on income tax and any other corporate
tax, including GST if any the owner shall not bear any tax liability whatsoever.
The bidder shall be liable and responsible for payment of such taxes as
attracted under the provisions of the law.
Seal & Signature of Bidder
33. 11 Notwithstanding the tax liabilities as per the sub-clause 35.10 above the owner
shall have the right to make deduction at source from the amounts payable to
the contractor in respect of Income Tax (on the cost of items of supply included
in the works contract) as may be mandatory in terms of the law. The owner
shall not bear any liability in this regard but shall issue necessary certificate in
respect of such deduction made.
33. 12 Whenever concessional rate of GST is indicated by the bidders, it shall be
confirmed whether any increase in the rates that becomes applicable during
the performance of the contract would be absorbed by the supplier. Bidder
shall note that in case of absence of such confirmation; the tenders will be
evaluated taking into account the maximum rate of GST applicable.
33. 13 In case any tax or duty is newly introduced by the Government applicable for
this contract with effect from the next day of the date submission of the bid
and if the contractor is required to pay additional tax or duty, then the owner
shall reimburse the contractor the additional tax or duty so paid by the
contractor against submission by the contractor of documentary evidence to
the satisfaction of the owner. This provision will not be applicable to
transaction between the contractor and his sub-suppliers, sub-contractors for
raw materials etc and will be applicable only to the direct transactions between
the contractors and owner. Besides the said statutory variation, no other
statutory variation shall be payable by the owner.
33. 14 The owner’s liability for all taxes and duties including GST under the contract
shall be limited to those indicated by the Bidder in the Bid Proposal Sheets,
subject to the statutory variations and variations as per Clause No. 35.4.
33. 15 If the cost to the Contractor during the performance of the ‘Contract’ shall be
increased or reduced by reasons of the making, passing or promulgation of
any law after the date of submission of bid or by any order, regulation or bye-
law having the force of law the amount of such increase or reduction shall be
added to or deducted from the “Contract Price” as the case may be for direct
transactions between contactor & owner. It is the Bidders responsibility to
furnish details of taxes, duties, levies etc. applicable as on the date of
submission of the bid.
33. 16 No claim for any increase towards the statutory variation regarding
enhancement of existing tax or duty or introduction of a new tax or duty
applicable shall be entertained by the Owner during the extended period of
contract, if any, provided the extension of the contract is required by causes
attributable to the contractor. However, the decrease in any taxes/duties
shall be passed on to GETCO.
33. 17 The provision of statutory variation regarding enhancement of existing tax or
duty or introduction of a new tax or duty will be applicable only to the direct
transaction between the contractor and the owner.
33. 18 Before quoting, the bidder may ascertain from the concerned tax authorities
of Government for the applicability of Entry Tax, GST etc. in respect of this
work and include the same in the quoted price. No separate claim in this
regard will be entertained by the Owner, as it is the responsibility of the Bidder
to pay all these taxes.
Seal & Signature of Bidder
34.0 TAXES, PERMITS & LICENCES
The Contractor shall be liable and pay all non-Indian taxes, duties, levies
lawfully assessed against the Owner or the Contractor in pursuance of the
Contract. In addition, the Contractor shall be responsible for payment of all
Indian duties, levies and taxes including GST lawfully assessed against the
Contractor for his personal income & property only.
35.0 Price Inclusions (including Taxes & Duties):
35.1 GOODS AND SERVICE TAX (GST): GST and Cess as applicable shall
be payable/ receivable as mentioned in clause no.33 of GCC supra
35.2 The prices quoted shall be all inclusive of freight, transportation, loading, –
unloading & stacking at site of materials supplied by Contractor as well as
owner supplied item if any
35.3 No extra payment toward any type of templates and erection tools
/materials will be made.
35.4 Statutory Variations:
Any statutory increase or decrease in the taxes and duties including GST and
Cess as applicable or in the event of introduction of new tax/cess or
cessation of existing tax/cess subsequent to suppliers offer if it takes place
within the original contractual delivery date will be to COMPANY’s account
subject to the claim being supported by documentary evidence. However, if any
decrease takes place after the contractual delivery date, the advantage will
have to be passed on to COMPANY.
Statutory Variation clause will not be applicable in case of Supplier / Contractor
has opted for Composition Scheme under GST.
35.5 Income Tax
Income-tax at source at the prevailing rate will be deducted from bills in
accordance with the provision of Income-Tax Laws and to that effect a
certificate will be issued to the contractor.
36.0 CONTRACT PERFORMANCE GUARANTEE
36.1 As a contract performance security, the successful bidder, to whom the work is
awarded, shall be required to furnish a performance guarantee as per clause
No. 38 in form of Bank guarantee from a Public Sector Indian bank/Scheduled,
Commercial Bank in the form to be furnished and it shall guarantee the faithful
performance of the Contract in accordance with the terms and conditions
specified in these documents and specifications.
36.2 The Performance Guarantee shall cover additionally the following guarantees
a) The successful Bidder guarantees the successful and satisfactory operation
of the equipment furnished and erected under the Contract, as per the
specifications and documents.
Seal & Signature of Bidder
b) The successful Bidder further guarantees that the equipment provided by
him/his sub-vendors and installed by him shall be free from all defects in
design, material and workmanship and shall upon written notice from the
Owner fully remedy free of expenses to the Owner such defects as
developed under the normal use of the said equipment within the period of
guarantee specified in the relevant clause of the General Terms and
Conditions in the Part-I.
36.3 The Contract Performance Guarantee is intended to secure the performance of
the entire contract. However, it is not to be construed as limiting the damages
under clause entitled “Equipment Performance Guarantee” in Technical
Specifications, Part-II and damages stipulated in other clauses in the Bid
36.4 The Contract performance guarantee will be discharged without any interest on
successful completion of order and only after the performance guarantee
condition is fulfilled. The Contractor shall furnish Contract Performance
Guarantee(s) for the proper fulfillment of the Contract in the prescribed form
within fifteen(15) days of “Notice of Award of Contract”. The performance
guarantee(s) shall be as per terms prescribed.
GUARANTEES & LIABILITIES
37.1 The Contractor shall warrant that the whole project, in accordance with the
Contract documents and free from defects in material/equipment and
workmanship for a period of twenty-four (24) calendar months commencing
immediately upon the satisfactory commissioning of the project and issuance
of Taking Over Certificate (TOC). The Contractor’s liability shall be limited to
the replacement of any defective parts in the equipment of his own manufacture
or those of his Sub-Contractors under normal use and arising solely from faulty
design, materials and/or workmanship provided always that such defective
parts are repairable at the site and are not in meantime essential in the
commercial use of the equipment. Such replaced/defective parts shall be
returned to the Contractor unless otherwise arranged. No repairs or
replacement shall normally be carried out by the Engineer when the equipment
is under the supervision of the Contractor’s Supervisory Engineer.
37.2 In the event of any emergency where in the judgment of the Engineer, delay
would cause serious loss or damages, repairs or adjustment may be made by
the Engineer or a third party chosen by the Engineer without advance notice to
the Contractor and the cost of such work shall be paid by the Contractor. In the
event such action is taken by the Engineer, the Contractor will be notified
promptly and he shall assist wherever possible in making necessary
corrections. This shall not relieve the Contractor of his liabilities under the terms
and conditions of the Contract.
37.3 If it becomes necessary for the Contractor to replace or renew any defective
portions of the works the provision of this clause shall apply to portion of the
works so replaced or renewed until the expiry of twelve (12) months from the
date of such replacement or renewal. If any defects are not remedied within a
reasonable time, the Engineer may proceed to do the work at the Contractor’s
Seal & Signature of Bidder
risk and cost but without prejudice to any other rights which the Owner may
have against the Contractor in respect of such defects.
37.4 The repaired or new parts will be furnished and erected free of cost by the
Contractor. If any repair is carried out on his behalf at the site, the Contractor
shall bear the cost of such repairs.
37.5 The cost of any special or general overhaul rendered necessary during the
maintenance period due to defects in the equipment or defective work carried
out by the Contractor, the same shall be borne by the Contractor.
37.6 The acceptance of the equipment by the Engineer shall in no way relieve the
Contractor of his obligations under this clause
37.7 In the case of those defective parts, which are not repairable at site but are
essential for the commercial operation of the equipment, the Contractor and the
Engineer shall mutually agree to a program of replacement or renewal, which
will minimize interruption to the maximum extent in the operation of the
37.8 At the end of the guarantee period, the Contractor’s liability ceases except for
latent defects. For latent defects, the Contractor’s liability as mentioned in
Clause Nos. 37.1 through 37.7 above, shall remain till the end of 5 years from
the date of completion of guarantee period. In respect of goods supplied by Sub-
Contractors to the Contractor where a longer guarantee is provided by such Sub-
Contractor, the Owner shall be entitled to the benefits of such longer guarantee.
37.9 The provisions contained in this clause will not be applicable: a) If the Owner has
not used the equipment according to generally approved industrial practice and
in accordance with the conditions of operations specified and in accordance with
operating manuals, if any. b)In cases of normal wear and tear of the parts to be
specifically mentioned by the Contractor in the offer.
37.9 The Guarantee period for individual equipment / item indicated in the
tender specification remains unchanged and shall have to be adhere to as
indicated in specifications.
38.0 Performance Guarantee:-
“The successful bidder shall have to submit the performance guarantee in the
form of Bank Guarantee worth 10% of the total contract value (end cost) to cover
the entire execution. The Performance Bank Guarantee (covering the execution
of the contract) will be returned ONLY on successful commissioning & issuance
of TOC including material reconciliation & as built drawings and on receipt of the
Bank Guarantee towards Warranty worth 10% of the total contract value (end
cost), which will be retained till completion of the Guarantee period.
These Bank Guarantees shall be applicable for all the bidders irrespective
whether they are SSI/NSIC units.”
The above performance guarantee, to be submitted by successful tenderer,
towards execution period, is for the satisfactory execution of the contract.
Seal & Signature of Bidder
Whereas the performance guarantee, to be submitted by successful tenderer,
towards warrantee, is for satisfactory performance of the materials which should
be valid for 24 months from the date of commissioning.
If the full Performance Guarantee amount / BG is not paid / submitted within
(Fifteen) days after the receipt of the LOA, then the order will be out rightly
cancelled at the risk & cost of the Tenderer (at the discretion of the Corporation)
and without entering into any correspondences and this will be binding on the
39.0 Time Schedule:
39.1 The basic consideration and the essence of the Contract shall be strict adherence to
the time schedule for performing the specified works.
39.2 The Owner’s requirements of completion schedule for the Works are mentioned in the
accompanying Special Conditions of Contract.
39.3 The completion schedule as stated in the special conditions of contract shall be one of
the major factors in consideration of the bids.
39.4 The owner reserves the right to request for a change in the work schedule during pre-
award discussions with successful bidder.
39.5 The successful bidder will be required to prepare detailed PERT Network/ detailed
M.S. Project Bar chart and finalize the same with the owner as per the requirement of
40.0 TIME – THE ESSENCE OF CONTRACT
40.1 The time and the date of completion of the Contract as stipulated in the Contract by
the Owner without or with modifications, if any, and so incorporated in the Letter of
Award, shall be deemed to be the essence of the Contract. The Contractor shall so
organize his resources and perform his work as to complete it not later than the date
40.2 The Contractor shall submit a detailed PERT network/bar chart within the time frame
agreed consisting of adequate number of activities covering various key phases of the
work such as design, procurement, manufacturing, shipment and field erection
activities within fifteen (15) days of the date of Notification of Award. This network shall
also indicate the interface facilities to be provided by the Owner and the dates by which
such facilities are needed. The Contractor shall discuss the network so submitted with
the Owner and the agreed network shall form part of the Contract documents. During
the performance of the Contract, if in the opinion of the Engineer, proper progress is
not maintained, suitable changes shall be made in the Contractor’s operations to
ensure proper progress without any cost implication to the Owner. The interface
facilities to be provided by the Owner in accordance with the agreed network shall also
be reviewed while reviewing the progress of the Contractor.
40.3 Based on the above agreed network/bar chart fortnightly reports shall be submitted by
the Contractor as directed by the Engineer.
40.4 Subsequent to the finalization of the network, the Contractor shall make available to
the Engineer a detailed manufacturing program in line with the agreed Contract
Such manufacturing program shall be reviewed, updated and submitted to the
Engineer every month thereafter.
Seal & Signature of Bidder
40.5 The above bar charts/manufacturing program shall be compatible with the Owner’s
computer environment and furnished to the Owner on such media as may be desired
40.6 If the progress is found low, GETCO reserves the right to get the work executed
through any other agency at the risk & cost of contractor without assigning any
reason(s) and/or notice.
41.0 PENALTY FOR DELAY:
41.1 The tenderer should note that the completion time allowed for carrying out the
work should be strictly observed. Any delay that may take place in supply,
erection and civil beyond Contractual period stated shall be subject to the
penalty at the rate of ½ % per week or part there of plus GST as applicable
on delayed portion, with a ceiling of 10 % of the total contract value plus
GST as applicable. For calculating the delayed portion, date of actual
receipt of material at store shall be considered.
41.2 The penalty plus GST as applicable will be deducted from bills payable either
against this contract or from any Bank Guarantee or any other amount payable
under any other contract with the GETCO.
41.3 In event of failure of the contractor to pay the amount of penalty as demanded,
the owner shall be entitled to deduct the amount of penalty for delay from
the amounts payable to the contractors under any bills raised under this
contract or any other amount payable under any other contract with the
GUVNL and its Subsidiary companies i.e. GETCO, GUVNL, GSECL,
MGVCL, DGVCL, PGVCL, UGVCL. It is permissible for the owner to adjust the
amount of penalty of delay against any Bank Guarantee furnished by the
contractor under this contract or any other contract with GUVNL and/or its
subsidiary companies.
41.4 Tenderer shall have to supply all materials to match with the erection activities.
41.5 If the Contractor fails to successfully complete the commissioning within the
time fixed under the Contract, the Contractor shall pay to the Owner as penalty
plus GST as applicable a sum specified for each specified period of delay.
41.6 Equipment and materials will be deemed to have been delivered only when all
its components, parts are also delivered. If certain components are not
delivered in time the equipment and materials will be considered as delayed
until such time the missing parts are also delivered.
41.7 For the purpose of penalty, contractual obligation shall be completion of all the
Civil, supply and erection contracts as per time schedule & value of these
contracts shall be “total contract value” (Sum of three individual contract
value) for the working of penalty in line with above relevant cl. No.41.1
42.0 Delays by owner or his authorized agents
42.1 In case the Contractor’s performance is delayed due to any act of omission on the part
of the Owner or his authorized agents, then the Contractor shall be given due extension
of time for the completion of the Works, to the extent such omission on the part of the
Owner has caused delay in the Contractor’s performance of the Contract.
Seal & Signature of Bidder
Regarding reasonableness or otherwise of the extension of time, the decision of the
Engineer shall be final.
42.2 In addition, the Contractor shall not be entitled to any claim whether demonstrable or
reasonable compensation if such delays have resulted in any increase in cost.
43.0 Presentation of Bills
43.1 For supply: Monthly Bills for supply items for 80% value i.e. Ex-Works price with 100%
F&I and GST in original with one copy shall be submitted to Dy. CAO (Bills), at
Corporate Office for passing and processing for payment at Corporate Office. One
copy of such bill is to be submitted to Engineer in-charge i.e. concerned EE(Const) for
their record & preparation of all relevant documents.
For necessary payment against each consignment of material along with 100%
taxes, duties, F & I shall be duly recorded in the form of TRC & SR note by the
field office, which shall be now uploaded on Vendor Management System
(VMS) Portal, www.vms.guvnl.com including invoice, documents which are
digitally signed by Vendors / Suppliers. The supporting documents duly signed,
stamped and scanned are required to be uploaded. The VMS portal also
provides ‘real time’ tracking of invoice status, to monitor the process of
submissions and to receive timely updates.
43.2 10% payment out of balance 20% shall be released on completion of the line /
substation work, handing over and acceptance by the Site Engineers in charge after
rectification work if any and settlement of material account according to actual quantity
utilized for completion of work. Bill for this payment shall be raised to Dy. CAO (Bills),
Corporate Office with copy to concern Ex. Engr. (Const).
43.3 Balance 10% payment for supply shall be released only after finalization of material
account and passing of final bill only. The contractor has to submit the final bill along
with the material consumption statement and other required data of the work carried
out within 3 months from the date of completion of work.
43.4 For Erection & Civil works: Monthly R.A Bills for erection 90% value of work executed
in original with one copy shall be submitted to concerned EE(Const) for passing and
processing for payment.
43.5 Balance 10% payment for erection shall be released only after finalization of material
account and passing of final bill only. The contractor has to submit the final bill along
with the material consumption statement and other required data of the work carried
out within 3 months from the date of completion of work.
43.6 All the bills in accordance with the above clauses must be submitted with the following
a) Item wise work done during billing period.
b) Item wise cumulative work done.
c) Account for material consumed and balance stock.
43.7 For non-submission or part submission of above information, an additional 5% amount
of the respective RA bill shall be withheld and shall only be released at the time of final
CONTRACT SECURITY AND PAYMENTS
Seal & Signature of Bidder
44.1 The payment to the Contractor for the performance of the works under the Contract
will be made by the Owner as per the guidelines and conditions specified herein. All
payments made during the Contract shall be on account payments only. The final
payment will be made on completion of all Works and on fulfillment by the Contractor
of all his liabilities under the Contract.
44.2 Currency of Payment
All payments under the Contract shall be in Indian Rupees only.
44.3 Further the payment shall be subject to fulfilling of following conditions:
44.4 Welfare Cess
The modality of payment/ reimbursement of welfare cess will be as under.
On receipt of A/T, the contractor / bidder will get them registered under Welfare Cess
Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the
documentary evidence of registration. Only thereafter, the bill will be processed for
Before release of payment of subsequent R.A.Bills, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill.
Before release of payment of Final Bill, the contractor has to submit the documentary
evidence of payment of welfare cess of previous R.A.Bill as well as the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment,
contractor has to submit documentary evidence of registration under Welfare Cess Act
and evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy of
documentary evidence of payment by observing due formalities.
45.0 Payment Schedule
The tender BOQ is indicative. Supply & Erection of quantities shall be as per approved
Drgs. & BOQ and excess shall not be accepted.
45.1 Application for Payment
The Contractor shall submit application for the payment.
45.2 Each such application shall state the amount claimed and shall set forth in detail, in
the order of the Payment Schedule, particulars of the Works including the Works
executed at Site and of the equipment shipped/brought on to the site pursuant to the
Contract up to the date mentioned in the application and for the period covered since
the last preceding certificate, if any.
45.3 Every interim payment certificate shall certify the Contract value of the Works executed
up to the date mentioned in the application for the payment certificate, provided that
no sum shall be included in any interim payment certificate in respect of the works that,
according to the decision of the Engineer, does not comply with the Contract.
45.4 Mode of Payment
45.5 Payment due on dispatch of equipment shall be made by the Owner through Owner’s
Bank or directly to the Contractor as per the payment schedule.
45.6 The payment of test charges, if any, payment, taxes and duties (whenever admissible)
inland transportation (including port handling), insurance and the erection portion of
the Works shall be made direct to the Contractor by the Owner.
Seal & Signature of Bidder
45.7 All payments under the Contract shall be made as stipulated in the Contract after
signing the Contract Agreement. The payments linked with the dispatch of materials
shall only be made after production of all dispatch documents as specified in the
relevant Contract conditions which will interalia include the Material Inspection
Clearance Certificate issued by the Owner.
Progressive payments linked with erection shall only be made after the issue of
certificates by the Engineer, one for the quantum of work completed and the other for
the successful completion of quality check points involved in the quantum of work
45.8 Billing and breakup: Price breakup for supply items will be considered only for billing
purpose & not for actual payment. Payment for equipments supplied shall be released
45.9 Inland Transportation & Insurance
Inland transportation (including port handling) and inland insurance charges shall be
paid to the Contractor on pro-rata to the value of the equipment received at site and
on production of the invoices by the Contractor. However, wherever equipment wise
inland transportation charges have been called for in the ‘Bid Proposal Sheets’ and
have been furnished by the Contractor, the payment of inland transportation charges
shall be made after receipt of equipment at site based on the charges thus identified
by the Contractor in his Proposal and incorporated in the Contract. The aggregate of
all such pro-rata payments shall however not exceed the total amount quoted by the
all such pro-rata payments shall however not exceed the total amount quoted by the
Bidder in his bid and incorporated in the Contract.
46.0 DEDUCTIONS FROM CONTRACT PRICE
All costs, damages or expenses which the Owner may have paid, for which
under the Contract the Contractor is liable, or any other retention award will be
claimed by the Owner. All such claims shall be billed by the Owner to the
Contractor regularly as and when they fall due. Such bills shall be supported by
appropriate and certified vouchers or explanations, to enable the Contractor to
properly identify such claims. Such claims shall be paid by the Contractor within
thirty (30) days of the receipt of the corresponding bills and if not paid by the
Contractor within the said period, the Owner may then deduct the amount, from
any monies due or becoming due by him to the Contractor under the Contract
or may be recovered by sections of Law or otherwise.
47.0 Terms of Payment
The payment for materials to be supplied and erected shall be made as under
only after execution of the contract documents/furnishing of Security Deposit
and on execution of substation work.
47.1 For supply
(i) 80% of supply value for each consignment of Line / Sub-Station material
including bolt nuts and accessories on submission of invoice along with
100% GST, duties, F & I shall be paid from corporate office within
days from actual material receipt date mentioned in SR Note after
verifying the following documents.
Seal & Signature of Bidder
A. Tax invoice.
B. Delivery challan.
C. Endorsed RR / LR copy.
D. Dispatch clearance certificate / letter wherever applicable.
E. E Way Bill, if applicable
(ii) 10% payment out of balance 20% shall be released from corporate office
on completion of Line / Substation work, handing over and preliminary
acceptance certificate issued by the Site Engineers in charge after
rectification work if any. Supply to be made as per approved drawing/
(iii) Balance10% of supply value shall be paid from corporate office on
successful commissioning of Sub-Station / Line against completion
certificate and only after settlement of material account statement of
items supplied, used, erected and successful commissioning is settled
for complete job and will be released only after passing of final bill.
47.2 For erection and Civil works.
(i) 90% payment of amount claimed covering various activities such as
excavation, foundation, erection, earthing, stringing of bus bar and earthwire
including insulator hoisting works against R.A. bills duly certified by EIC within
30 days from the date of R.A. bill.
(ii) Balance 10% of erection value shall be paid within 30 days against
commissioning of Line/ Substation only after settlement of material account
statement of items supplied, used, erected and successful commissioning of
Sub-Station/ line the same amount will be release in final bill only and
payment will be made only after passing of final bill.
(iii) If net payable amount is more than Rs 5.0 Lacs, payment will be released
from circle office/corporate office.
47.3 As mentioned in clause no. 47.1 & 47.2 the payment will be released within
days. However, in case of any delay due to any eventuality no interest charges
47.4 Welfare Cess
The modality of payment/ reimbursement of welfare cess will be as under.
On receipt of A/T, the contractor / bidder will get them registered under Welfare
Cess Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the
documentary evidence of registration. Only thereafter, the bill will be processed
Before release of payment of subsequent R.A.Bills, the contractor has to submit
the documentary evidence of payment of welfare cess of previous R.A.Bill.
Seal & Signature of Bidder
Before release of payment of Final Bill, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill as well
as the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment,
contractor has to submit documentary evidence of registration under Welfare
Cess Act and evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy
of documentary evidence of payment by observing due formalities.
48.0 TAKING DELIVERY AND INSURANCE:
48.1 The contractor has to keep the materials in safe custody and transport to the
respective sites and will be fully responsible for any damage to or loss of all
materials at any stage during transportation or erection till taking over of the line
48.2 The Contractor has to open site store and ensure for safe custody of all the
stored materials at his own cost.
48.3 The Contractor shall have total responsibility for the entire materials stored,
loose, semi assembled and/or erected by him at site in his custody. The
Contractor shall make suitable security arrangements at his own cost to ensure
the protection of all materials, equipment and works from theft, fire pilferage and
any other damages and loss. It shall be the responsibility of the contractor to
arrange for security till the works are finally taken over by the GETCO.
48.4 STORAGE-CUM-INSURANCE:
The contractor shall take suitable storage-cum-erection insurance cover at his cost
to the extent of 100 % cost of the materials, which are required to complete the
work. Contractor shall have to take comprehensive insurance policy against any
loss, damage, theft, pilferage, fire etc. for the complete period of storage, erection
and commissioning up to the time of taking over of the line by GETCO. The
Contractor shall deal directly and pursue the claim with the Insurance Company
and shall be responsible in regard to maintenance of all insurance coverage as
well as for settlement of claim. The proof of insurance policy taken by the
successful Contractor shall be furnished to Engineer-In-Charge. In absence of the
above insurance policy, R.A. Bill payment will be withheld.
48.5 In the event of any damage, theft, loss, pilferage, fire etc., Contractor will be
responsible to lodge, pursue and settle all the claims with the Insurance Company
for all items, materials and the GETCO shall be kept informed about it. Contractor
shall replace the lost / damaged materials / items promptly irrespective of the
settlement of the claims by underwriter and ensure that the work progress is as per
agreed schedule. The loss, if any, such replacement will have to be borne by the
Contractor and GETCO will not entertain any claim / representation in this regard.
However, it will be contractor's responsibility to insure the entire project till the line
/ substation is taken over by the GETCO.
49.0 Insurance:
The Bidder’s insurance liabilities pertaining to the scope of Works are detailed
out in Clauses titled Insurance Bidder’s attention is specifically invited to these
Seal & Signature of Bidder
clauses. Bid price shall include all the costs in fulfilling all the insurance liabilities
under the Contract.
49.1 The Contractor at his cost shall arrange, secure and maintain all insurance as
may be pertinent to the Works and obligatory in terms of law to protect his
interest and interests of the Owner against all perils detailed herein. The form
and the limit of such insurance as defined herein together with the under-writer
in each case shall be acceptable to the Owner. However, irrespective of such
acceptance, the responsibility to maintain adequate insurance coverage at all
time during the period of Contract shall be of Contractor alone. The
Contractor’s failure in this regard shall not relieve him of any of his contractual
responsibilities and obligations. The insurance covers to be taken by the
Contractor shall be in the joint name of the Owner and the Contractor. The
Contractor shall, however, be authorized to deal directly with Insurance
Company or Companies and shall be responsible in regard to maintenance of
all insurance covers. Further the insurance should be in freely convertible
49.2 Any loss or damage to the equipment during handling, transportation, storage,
erection, putting into satisfactory operation and all activities to be performed till
the successful completion of commissioning of the equipment shall be to the
account of the Contractor. The Contractor shall be responsible for preference
of all claims and make good the damages or loss by way of repairs and/or
replacement of the equipment, damaged or lost. The transfer of title shall not
in any way relieve the Contractor of the above responsibilities during the period
of Contract. The Contractor shall provide the Owner with copy of all insurance
policies and documents taken out by him in pursuance of the Contract. Such
copies of documents shall be submitted to the Owner immediately after such
insurance coverage. The Contractor shall also inform the Owner in writing at
least sixty (60) days in advance regarding the expiry/cancellation and/or change
in any of such documents and ensure revalidation, renewal etc., as may be
necessary well in time.
49.3 The perils required to be covered under the insurance shall include, but not be
limited to fire and allied risks, miscellaneous accidents (erection risks) workman
compensation risks, loss or damage in transit, theft, pilferage, earth quake, riot
and strikes and malicious damages, civil commotion, weather conditions,
accidents of all kinds, etc. The scope of such insurance shall be adequate to
cover the replacement/reinstatement cost of the equipment for all risks up to
and including delivery of goods and other costs till the equipment is delivered
at Site. The insurance policies to be taken should be on replacement value
basis and/or incorporating escalation clause. Notwithstanding the extent of
insurance cover and the amount of claim available from the underwriters, the
Contractor shall be liable to make good the full replacement/rectification value
of all equipment/materials and to ensure their availability as per project
49.4 All costs on account of insurance liabilities covered under the Contract will be
on Contractor’s account and will be included in Contract Price, However, the
Owner may from time to time, during the pendency of the Contract, ask the
Contractor in writing to limit the insurance coverage, risks and in such a case,
the parties to the Contract will agree for a mutual settlement, for reduction in
Contract price to the extent of reduced premia amount. The Contractor, while
arranging the insurance shall ensure to obtain all discounts on premia which
Seal & Signature of Bidder
may be available for higher volume or for reason of financing arrangement of
49.5 The clause entitled ‘Insurance’, covers the additional insurance requirements
for the portion of the works to be performed at the Site.
50.0 Contract Quality assurance:
50.1 The Bidder shall include in his proposal the Quality Assurance Program
containing the overall quality management and procedures which he proposes
to follow in the performance of the Works during various phases as detailed in
relevant clause of the General Technical Conditions.
50.2 At the time of Award of Contract, the detailed Quality Assurance Program to be
followed for the execution of the Contract will be mutually discussed and
agreed and such agreed Program shall form a part of the Contract.
50.3 The Bidder shall clearly specify the list of sub-vendors from whom the bought
out items are being supplied. Such details shall be accompanied by their list of
previous supplies made performance reports etc. However, in case of orders
are placed, specific approval shall be obtained from the owner for the vendor
supplied materials. The quality assurance program shall be furnished for each
material separately for approval.
51.0 Erection Tools And Tackles:
The Bidder under a separate schedule, in his proposal shall include a list of all-
special equipment tools & tackles etc. which he proposes to bring to site for the
purpose of erection, handling, testing and commissioning including
performance and guarantee tests of the equipment. However, such tools
tackles brought to the site for purpose of erection, handing testing &
commissioning shall remain property of the contractor and can be taken back
after completion of the work.
52.0 Brand Names:
52.1 The specific reference in these specifications and documents to any
material/equipment by brand name make or catalogue number shall be
construed as establishing standards of quality and performance and not as
limiting competition. However, Bidders may offer other similar
material/equipment provided they meet the specified standard, design and
performance requirements. The Bidder shall furnish adequate technical
information about such alternative material equipment to enable the Owner to
determine its acceptability. The Owner shall be the sole judge on the
acceptability or otherwise of such alternatively material/equipment.
52.2 The bidder shall note that standards for workmanship material and equipment,
and reference to brand name of catalogue numbers designed by the Owner in
its Technical Specifications are intended to be descriptive only and not
restrictive. The Bidder may substitute alternative standards, brand name and/or
catalogue numbers in its bid, provided that it demonstrates to the Owner’s
satisfaction that the substitutions are substantially equivalent or superior to
those designed in the Technical Specification.
Seal & Signature of Bidder
53.0 CONTRACT DOCUMENTS
53.1 The term Contract Documents shall mean and include the following which shall
be deemed to form an integral part of the Contract:
a) Invitation to Bid including letter forwarding the Bidding Documents,
General Terms and Conditions of Contract and all other documents
included under Part I and the Special Conditions of Contract.
b) Specifications of the equipment to be furnished and erected under the
Contract as brought out in the accompanying Technical Specifications.
c) Contractor’s Bid Proposal and the documents attached there to including
the letters of clarifications thereto between the Contractor and the Owner
prior to the Award of Contract except to the extent of repugnancy.
d) All the materials, literature, data and information of any sort given by the
Contractor along with his bid, subject to the approval of the Owner
e) Letter of Award and any agreed variations of the conditions of the
documents and special terms and conditions of Contract, if any.
53.2 In the event of any conflict between the above mentioned documents the matter
shall be referred to the Engineer whose decision shall be considered as final
and binding upon the parties.
54.0 USE OF CONTRACT DOCUMENTS AND INFORMATION
54.1 The Contractor shall not, without the Owner’s prior written consent, disclose the
Contract, or any provision thereof, or any specification, plan, drawing, pattern,
sample or information furnished by or on behalf of the Owner in connection
therewith, to any person other than a person employed by the Contractor in the
performance of the Contract. Disclosure to any such employed person shall be
made in confidence and shall extend only so far as may be necessary for the
purpose of such performance.
54.2 The Contractor shall not, without the Owner’s prior written consent, make use
of any document or information enumerated in various Contract documents
except for the purpose of performing the Contract.
54.3 The Contractor shall not communicate or us in advertising, publicity, sales
releases or in any other medium, photographs or other reproduction of the
Works under this Contract, or descriptions of the site, dimensions, quantity,
quality or other information, concerning the works unless prior written
permission has been obtained from the Owner.
54.4 Any document, other than the Contract itself, enumerated in various Contract
documents shall remain the property of the Owner and shall be returned (in all
copies) to the Owner on completion of the Contractor’s performance under the
Contract if so required by the Owner.
55.0 CONSTRUCTION OF THE CONTRACT
Seal & Signature of Bidder
55.1 Notwithstanding anything stated elsewhere in the bid documents, the Contract
to be entered into will be treated as a divisible Civil, Supply and Erection
Contract. Award shall be placed on the successful Bidder as follows:
i) First Contract: For supply of all equipment and materials the site.
ii) Second Contract: For providing all other services like storage at site, handling
at site, installation, testing, pre-commissioning and commissioning including
performance testing in respect of all the equipment material supplied under the
“second Contract” and any other equipment/materials given by the owner for
transport from owner’s stores, insurance, unloading storage handling at site
installation testing & commissioning.
55.2 In case of divisible supply and erection Contract, or where the Owner hands
over his equipment to the Contractor for executing, then the Contractor shall at
the time of taking delivery of the equipment/dispatch documents be required to
execute an Indemnity Bond in favour of the Owner in the form acceptable to the
GETCO for keeping the equipment in safe custody and to utilize the same
exclusively for the purpose of the said Contract. Samples of proforma for the
Indemnity Bond will be furnished during award of Contract.
55.3 The Contract shall in all respects be construed and governed according to
55.4 It is clearly understood that the total consideration for the Contract(s) has been
broken up into various components only for the convenience of payment under
the Contract(s) and for the measurement of deviations or modifications under
the Contract(s).
56.0 JURISDICTION OF CONTRACT
56.1 The laws applicable to the Contract shall be the laws in force in India. The
Courts of Vadodara shall have exclusive jurisdiction in all matters arising under
57.0 EXECUTION OF CONTRACT :
57.1 The Owner, after the issue of the Letter of Award to the Contractor, will send
one copy of the final agreement to the Contractor for his scrutiny and approval.
57.2 The Agreement, unless otherwise agreed to, shall be signed within 30 days of
the acceptance of the Letter of Award, at the office the Owner at Vadodara on
a date and time to be mutually agreed. The Contractor shall provide for signing
of the Contract, Performance Guarantee, appropriate power of attorney and
other requisite materials. In case the Contract is to be signed beyond the
stipulated time, the Bid Guarantee submitted with the Proposal will have to be
extended accordingly.
57.3 The Agreement will be signed in copies to be specified and the Contractor shall
be provided with one signed original and the rest will be retained by the Owner.
57.4 The Contractor shall provide free of cost to the Owner all the Engineering data,
drawings, and descriptive materials submitted with the bid including soft copy,
to form a part of the Contract immediately after issue of Letter of Award.
Seal & Signature of Bidder
57.5 Subsequent to signing of the Contract, the Contractor at his own cost shall
provide the Owner with copies of agreement within fifteen (15) days after the
signing of the Contractor.
58.0 ENFORCEMENT OF TERMS
58.1 The failure of either party to enforce at any time any of the provisions of this
Contract or any rights in respect thereto or to exercise any option therein
provided, shall in no way be construed to be a waiver of such provisions, rights
or options or in any way to affect the validity of the Contract. The exercise by
either party of any of its rights herein shall not preclude or prejudice either party
from exercising the same or any other right it may have under the Contract.
59.0 COMPLETION OF CONTRACT
59.1 Unless otherwise terminated under the provisions of any other relevant clause,
this Contract shall be deemed to have been completed on the expiry of the
guarantee period as provided for under the clause entitled ‘Guarantee’.
60.0 REPLACEMENT OF DEFECTIVE PARTS AND MATERIALS
60.1 If during the performance of the Contract, the Engineer shall decide and inform
in writing to the Contractor that the Contractor has manufactured any
equipment, material or part of equipment unsound and imperfect or has
furnished any equipment inferior to the quality specified, the Contractor on
receiving details of such defects or deficiencies shall at his own expense within
seven (7) days of his receiving the notice, or otherwise, within such time as may
be reasonably necessary for making it good, proceed to alter, reconstruct or
remove such works and furnish fresh equipment/materials up to the standards
of the specifications.
In case, the Contractor fails to do so, the Engineer may on giving the Contractor
seven (7) days’ notice in writing of his intentions to do so, proceed to remove
the portion of the works so complained of and at the cost of the Contractor
perform all such Works or furnish all such equipment/ material provided that
nothing in this clause shall be deemed to deprive the Owner of or affect any
rights under the Contract which the Owner may otherwise have in respect of
such defects and deficiencies.
60.2 The Contractor’s full and extreme liability under this clause shall be satisfied by
the payment to the Owner of extra cost, of such replacement procured including
erection as provided for in the Contract, such extra cost being the ascertained
difference between the price paid by the Owner for such replacements and the
Contract Price by portion for such defective equipment/materials/works and
repayments of any sum paid by the Owner to the Contractor in respect of such
defective equipment/material. Should the Owner not so replace the defective
equipment/materials the Contractor’s extreme liability under this clause shall be
limited to repayment of all sums paid by the Owner under the Contract for such
defective equipment/materials.
61.0 PATENT RIGHTS AND ROYALTIES
Royalties and fees for patents covering materials, articles, apparatus, devices,
equipment or processes used in the works shall be deemed to have been
included in the Contract Price. The Contractor shall satisfy all demands that
Seal & Signature of Bidder
may be made at any time for such royalties or fees and he alone shall be liable
for any damages or claims for patent infringements and shall keep the Owner
indemnified in that regard. The Contractor shall, at his own cost and expense,
defend all suits or proceedings that may be instituted for alleged infringement
of any patents involved in the Works, and, in case of an award of damages, the
Contractor shall pay for such award. In the event of any suit or other
proceedings instituted against the Owner, the same shall be defended at the
cost and expense of the Contractor who shall also satisfy/comply with any
decree, order or award made against the Owner. But it shall be understood
that no such machine, plant, work, material or thing has been used by the
Owner for any purpose or any manner other than that for which they have been
furnished and installed by the Contractor and specified under these
specifications. Final payment to the Contractor by the Owner will not be made
while any such suit or claim remains unsettled. In the event any apparatus or
equipment, or any part thereof furnished by the Contractor, is in such suit or
proceedings held to constitute infringement, and its use is enjoined, the
Contractor shall at his option and at his own expense, either procure for the
Owner, the right to continue the use of said apparatus, equipment or part
thereof, replace it with non-infringing apparatus or equipment or modify it, so it
becomes non-infringing.
62.0 DEFENCE OF SUITS
If any action in court is brought against the Owner or Engineer or an officer or
agent of the Owner, for the failure, omission or neglect on the part of the
Contractor to perform any acts, matters, covenants or things under the
Contract, or for damage or injury caused by the alleged omission or negligence
on the part of the Contractor, his agents, representatives or his Sub-
Contractors, or in connection with any claim based on lawful demands of Sub-
Contractors, workmen, suppliers or employees, the Contractor shall in all such
cases indemnify and keep the Owner, and the Engineer and/or his
representative, harmless from all losses, damages, expenses or decrees
arising of such action.
63.0 LIMITATION OF LIABILITIES
The final payment by the Owner in pursuance of the Contract shall mean the
release of the Contractor from all his liabilities under the Contract. Such final
payment shall be made only at the end of the Guarantee/Warranty period, and
till such time as the Contractual liabilities and responsibilities of the Contractor,
shall prevail. All other payments made under the Contract shall be treated as
on-account payments. The aggregate liabilities are limited up to the total
contract value.
64.0 ENGINEER’S DECISION
64.1 In respect of all matters which are left to the decision of the Engineer including
the granting or with-holding of the certificates, the Engineer shall, if required to
do so by the Contractor, give in writing a decision thereon.
64.2 If, in the opinion of the Contractor, a decision made by the Engineer is not in
accordance with the meaning and intent of the Contract, the Contractor may file
with the Engineer, within fifteen (15) days after receipt of the decision, a written
objection to the decision.
Seal & Signature of Bidder
Failure to file an objection within the allotted time will be considered as an
acceptance of the Engineer’s decision and the decision shall become final and
64.3 The Engineer’s decision and the filing of the written objection thereto shall be a
condition precedent to the right to request arbitration. It is the intent of the
Agreement that there shall be no delay in the execution of the works and the
decision of the Engineer as rendered shall be promptly observed.
65.0 POWER TO VARY OR OMIT WORK
65.1 No alterations, amendments, omissions, suspensions or variations of the Works
(hereinafter referred to as ‘variation’) under the Contract as detailed in the
Contract Documents, shall be made by the Contractor except as directed in
writing by the Engineer, but the Engineer shall have full powers subject to the
provisions hereinafter contained, from time to time during the execution of the
Contract, by notice in writing to instruct the Contractor to make such variation
without prejudice to the Contract. The Contractor shall carry out such variation
and be bound by the same conditions as far as applicable as though the said
variations occurred in the Contract Documents. If any suggested variations
would, in the opinion of the Contractor, if carried out, prevent him from fulfilling
any of his obligations or guarantees under the Contract, he shall notify the
Engineer thereof in writing and the Engineer shall decide forthwith whether or
not, the same shall be carried out and if the Engineer confirms his instructions,
the Contractor’s obligations and guarantees shall be modified to such an extent
as may be mutually agreed. Any agreed difference in cost occasioned by any
such variation shall be added to or deducted from the Contract Price as the
65.2 In the event of Engineer requiring any variation, a reasonable and proper notice
shall be given to the Contractor to enable him to work his arrangement
accordingly, and in cases where goods or materials are already prepared or
any design, drawings or pattern made or work done as per the contract requires
to be altered, a reasonable and agreed sum in respect thereof shall be paid to
the Contractor.
65.3 In any case in which the Contractor has received instructions from the Engineer
as to the requirement of carrying out the alterations or additional or substituted
work which either then or later on, will in the opinion of the Contractor, involve
a claim for additional payment, the Contractor shall immediately and in no case
later than thirty (30) days, after receipt of the instructions aforesaid and before
carrying out the instructions, advise the Engineer to that effect. But the
Engineer shall not become liable for payment of any charges in respect of any
such variations, unless the instructions for the performance of the same shall
be confirmed in writing by the Engineer.
65.4 If any variation in the Works results in reduction of Contract Price, the parties
shall agree, in writing, so to the extent of any change in the price, before the
Contractor proceeds with the change.
65.5 In all the above cases, in the event of a disagreement as to the reasonableness
of the said sum, the decision of the Engineer shall prevail.
Seal & Signature of Bidder
65.6 Notwithstanding anything stated above in this clause, the Engineer shall have
the full power to instruct the Contractor, in writing, during the execution of the
Contract to vary the quantities of the items or groups of items in accordance
with the provisions of clause entitled ‘Change of Quantity’ in section GCC. The
Contractor shall carry out such variations and be bound by the same conditions
as though the said variations occurred in the Contract Documents. However,
the Contract Price shall be adjusted at the rates and the prices provided for the
original quantities in the Contract.
66.0 ASSIGNMENT AND SUB-LE TTING OF CONTRACT
66.1 The Contractor may, after informing the Chief Engineer & getting written
approval, assign or sub-let the Contract or any part thereof other than for raw
material, for minor items or for any part of the plant for which makes are
identified in the Contract. Suppliers of the equipment not identified in the
Contract or any change in the identified suppliers shall be subject to approval
by the Chief Engineer. The experience of equipment vendors under
consideration by the Contractor for this Contract shall be furnished to the Chief
Engineer for approval prior to procurement of all such items/equipment. Such
assignment/sub-letting shall not relieve the Contractor from any obligation, duty
or responsibility under the Contract. Any assignment as above, without prior
written approval of Chief Engineer, shall be void.
In case of Erection activity, the contractor may after getting written approval
from Chief Engineer, assign or sublet any part of erection or as a whole. To do
so contractor have to apply for such subletting with a clear proposal stating
details & experience of the subletting agency, along with the tender or within
days from the date of LOI & decision thereof will be conveyed within 30 days
thereafter by GETCO. The proposed erection agency shall have experience of
executing similar job of voltage class of 66kV & above and value equivalent to
erection portion during last five years. The decision of competent authority in
this regard shall remain final and binding to the agency.
66.2 For components/equipment procured by the Contractor for the purposes of the
Contract, after obtaining the written approval of the Owner, the Contractor’s
purchase specifications and enquiries shall call for quality plan to be submitted
by the suppliers along with their Proposals. The quality plans called for from
the Vendors shall set out, during the various stages of manufacture and
installation, the quality practices and procedures followed by the Vendors’
quality control organization, the relevant reference document/standard used,
acceptance level, inspection documentation raised, etc. Such quality plans of
the successful vendors shall be discussed and finalized in consultation with the
Engineer and shall form a part of the Purchase Order/Contract between the
Contractor and the Vendor. Within three weeks of the release of the Purchase
Orders/Contracts for such bought out items/components a copy of the same
without price details but together with detailed purchase specifications, quality
plans and delivery conditions shall be furnished to the Engineer by the
67.0 CHANGE OF QUANTITY
67.1 During the execution of the Contract, the Owner reserves the right to increase
or decrease the quantities of items under the Contract but without any change
in unit price or other terms & conditions. Such variations unless otherwise
specified in the accompanying GCC and/or Technical Specifications, shall not
Seal & Signature of Bidder
be subjected to any limitation for the individual items but the total variations in
all such items under the Contract shall be limited to the extent of 30%(Thirty
Percent) of the contract price by way of suitable amendment to the contract.
67.2 The Contract price shall accordingly be adjusted based on the unit rates
available in the Contract for the change in quantities as above. The base unit
rates, as identified in the Contract shall however remain constant during the
currency of the Contract, in case the unit rates are not available for the change
in quantity, the same shall be subjected to mutual agreement.
67.3 As this is an EPC contract, Design will be done by the Contractor. Responsibility
of material will be that of the contractor.
68.0 PACKING, FORWARDING AND SHIPMENT
68.1 The Contractor, wherever applicable, shall after proper painting, pack and crate
all equipment in such a manner as to protect them from deterioration and
damage during rail and road transportation to the Site and storage at the Site
till the time of erection. The Contractor shall be held responsible for all
damages due to improper packing.
68.2 The Contractor shall notify the Owner of the date of each shipment from his
works, and the expected date of arrival at the Site for the information of the
68.3 The Contractor shall also give all shipping information concerning the weight,
size and content of each packing including any other information the Owner
68.4 The following documents shall be sent by registered post to the Owner within
three days from the date of shipment, to enable the Owner to make progressive
payments to the Contractor: -
Application for payment in the standard format of the Owner
Pre-dispatch clearance certificate, if any
Test Certificate, wherever applicable
Insurance Certificate
68.5 The Contractor shall prepare detailed packing list of all packages and
containers, bundles and loose materials forming each and every consignment
dispatched to Site.
The Contractor shall further be responsible for making all necessary
arrangements for loading, unloading and other handling right from his works up
to the Site and also till the equipment is erected, tested and commissioned. He
shall be solely responsible for proper storage and safe custody of all equipment.
69.0 CO-OPERATION WITH OTHER CONTRACTORS AND CONSULTING
The Contractor shall agree to cooperate with the Owner’s other Contractors and
Consulting Engineers and freely exchange with them such technical information
Seal & Signature of Bidder
as is necessary to obtain the most efficient and economical design and to avoid
unnecessary duplication of efforts. The Engineer shall be provided with three
copies of all correspondence addressed by the Contractor to other Contractors
and Consulting Engineers of the Owner in respect of such exchange of
technical information, wherever needed.
70.0 NO WAIVER OF RIGHTS
Neither the inspection by the Owner or the Engineer or any of their officials,
employees, or agents nor any order by the Owner or the Engineer for payment
of money or any payment for or acceptance of, the whole or any part of the
Works by the Owner or the Engineer, nor any extension of time, nor any
possession taken by the Engineer shall operate as a waiver of any provision of
the Contract, or of any power herein reserved to the Owner or any right to
damages herein provided nor shall any waiver of any breach in the Contract be
held to be a waiver of any other or subsequent breach.
71.0 CERTIFICATE NOT TO AFFECT RIGHT OF OWNER AND LIABILITY OF
THE CONTRACTOR.
No interim payment certificate of the Engineer, nor any sum paid on account by
the Owner, nor any extension of time for execution of the Works granted by the
Engineer shall affect or prejudice the rights of the Owner against the Contractor
or relieve the Contractor of his obligation for the due performance of the
Contract, or be interpreted as approval of the Works done or of the equipment
furnished and no certificate shall create liability for the Owner to pay for
alterations, amendments, variations or additional works not ordered, in writing
, by the Engineer or discharge the liability of the Contractor for the payment of
damages whether due, ascertained, or certified or not or any sum against the
payment of which he is bound to indemnify the Owner, nor shall any such
certificate nor the acceptance by him of any sum paid on account or otherwise
affect or prejudice the rights of the Owner against the Contractor.
72.0 PROGRESS REPORTS
During the various stages of the work in pursuance of the Contract, the
Contractor shall at his own cost submit periodic progress reports as may be
reasonably required by the Engineer with such materials as, in approved MS
PROJECT, charts, net-works, photographs, test certificates, etc. Such progress
reports shall be on monthly base for supply items & fortnightly for erection
activities in the form and size as may be required by the Engineer.
73.0 TAKING OVER
Upon successful completion of all the tests and commissioning by the
Contractor, the Engineer shall issue to the Contractor a Taking Over Certificate
(TOC) as a proof of the final acceptance of the equipment. Such certificate shall
not unreasonably be withheld nor will the Engineer delay the issuance thereof
on account of minor omissions or defects which do not affect the commercial
operation and/or cause any serious risk to the equipment. Such certificate shall
not relieve the Contractor of any of his obligations which otherwise survive, by
the terms and conditions of the Contract after issue of such certificate.
Seal & Signature of Bidder
In the event of completion of pre commissioning tests carried out jointly, if
energization of the substation is prevented for reasons not attributable to the
successful bidder, the Preliminary Acceptance Certificate shall be given within
30 days of pre commissioning tests prior to Taking Over Certificate (TOC).
74.0 RISK DISTRIBUTION--TRANSFER OF TITLE
74.1 Transfer of title in respect of equipment and materials supplied by the
Contractor to GETCO pursuant to the terms of the Contract shall pass on to
GETCO with negotiation of dispatch documents.
74.2 This Transfer of Title shall not be construed to mean the acceptance and the
consequent “Taking Over” of equipment and materials. The Contractor shall
continue to be responsible for the quality and performance of such equipment
and materials and for their compliance with the specifications until “Taking
Over” and the fulfillment of guarantee provisions of this Contract.
74.3 This Transfer of Title shall not relieve the Contractor from the responsibility for
all risks of loss or damage to the equipment and materials as specified under
the clause entitled “Insurance” of this Section.
75.0 LIABILITY FOR ACCIDENTS AND DAMAGES
Under the Contract, the Contractor shall be responsible for loss or damage to
the plant until the successful completion of commissioning as defined
elsewhere in the Bid document.
76.0 DEMURRAGE, WHARFAGE, ETC.
All demurrage, wharf age and other expenses incurred due to delayed
clearance of the material or any other reason shall be to the account of the
77.0 FORCE MAJEURE
77.1 Force majeure is herein defined as any cause which is beyond the control of
the Contractor or the Owner as the case may be, which they could not foresee
or with a reasonable amount of diligence could not have foreseen and which
substantially affects the performance of the Contract, such as:
a. Natural phenomena, including but not limited to floods, droughts,
earthquakes and epidemics;
b. Acts of any Government, domestic or foreign, including but not limited to
war, declared or undeclared, priorities, guarantees, embargoes.
Provided either party shall within fifteen (15) days from the occurrence of such
a cause notify the other in writing of such causes.
77.2 The Contractor or the Owner shall not be liable for delays in performing his
obligations resulting from any force majeure cause as referred to and/or defined
Seal & Signature of Bidder
The date of completion will, subject to hereinafter provided, be extended by a
reasonable time even though such cause may occur after Contractor’s
performance of obligation has been delayed due to other causes.
78.0 SUSPENSION OF WORK
78.1 The Owner reserves the right to suspend and reinstate execution of the whole
or any part of the Works without invalidating the provisions of the Contract.
Orders for suspension or reinstatement of the Works will be issued by the
Engineer to the Contractor in writing. The time for completion of the works will
be extended for a period equal to duration of the suspension.
78.2 Any necessary and demonstrable cost incurred by the Contractor as a result of
such suspension of the works will be paid by the Owner, provided such costs
are substantiated to the satisfaction of the Engineer. The Owner shall not be
responsible for any liabilities if suspension or delay is due to some default on
the part of the Contractor or his Sub-Contractor.
79.0 CONTRACTOR`S DE FAULT
79.1 If the Contractor shall neglect to execute the works with due diligence and
expedition or shall refuse or neglect to comply with any reasonable order given
to him, in writing by the Engineer in connection with the works or shall
contravene the provisions of the Contract, the Owner may give notice in writing
to the Contractor to make good the failure, neglect or contravention complained
of. Should the contractor fail to comply with the notice within thirty (30) days
from date of serving the notice, then and in such case the Owner shall be at
liberty to employ other workmen and forthwith to execute such part of the works
as the Contractor may have neglected to do or if the Owner shall think fit,
without prejudice to any other right he may have under the Contract to take the
work wholly or in part out of the Contractor’s hands and re-contract with any
other person or persons to complete the works or any part thereof and in that
event the Owner shall have free use of all Contractor’s equipment that may
have been at the time on the Site in connection with the works without being
responsible to the Contractor for fair wear and tear thereof and to the exclusion
of any right of the Contractor over the same, and If the sum that the
Contractor is entitled to be paid plus the costs incurred by the Owner in
completing the works, exceeds the Contract Price or the entire works if
entire works have been completed or the price for part of the works if part
of the works have been completed, the Contractor shall be liable for such
If such excess in greater than the sums due to the Contractor, the
Contractor shall pay the balance to the Owner and if such excess is less
than the sums due to the Contractor, Owner shall pay the balance to the
Contractor. For facilitating such payment, Owner shall encash the Bank
Guarantees of Contractor available with Owner/s and retain such other
payments due to the Contractor under Contract in question or any other
Contract that the Owner/s may have with the Contractor. Such payment of
excess amount shall be independent of the liquidated damages for delay which
the Contractor shall have to pay if the completion of work is delayed.
Seal & Signature of Bidder
79.2 In addition, such action by the Owner as aforesaid shall not relieve the
Contractor of his liability to pay liquidated damages for delay in completion of
79.3 Such action by the Owner as aforesaid the termination of the Contract under
this clause shall not entitle the Contractor to reduce the value of the Contract
Performance Guarantee nor the time thereof. The Contract Performance
Guarantee shall be valid for the full value and for the full period of the Contract
including guarantee period.
80.0 TERMINATION OF CONTRACT ON OWNER`S INITIATIVE
80.1 The Owner reserves the right to terminate the Contract either in part or in full
due to reasons other than those mentioned under clause entitled ‘Contractor’s
Default’. The Owner shall in such an event give fifteen (15) days’ notice in
writing to the Contractor of his decision to do so.
80.2 The Contractor upon receipt of such notice shall discontinue the work on the
date and to the extent specified in the notice, make all reasonable efforts to
obtain cancellation of all orders and Contracts to the extent they are related to
the work terminated and terms satisfactory to the Owner, stop all further sub-
contracting or purchasing activity related to the work terminated, and assist
Owner in maintenance, protection, and disposition of the works acquired under
the Contract by the Owner.
In the event of such a termination the Contractor shall be paid compensation,
equitable and reasonable, dictated by the circumstances prevalent at the time
of termination.
80.3 If the Contractor is an individual or a proprietary concern and the individual or
the proprietor dies and if the Contractor is a partnership concern and one of the
partners dies then unless the Owner is satisfied that the legal representatives
of the individual Contractor or of the proprietor of the propriety concern and in
the case of partnership, the surviving partners, are capable of carrying out and
completing the Contract the Owner shall be entitled to cancel the Contract as
to its in completed part without being in any way liable to payment of any
compensation to the estate of deceased Contractor and/or to the surviving
partners of the Contractor’s firm on account of the cancellation of the Contract.
The decision of the Owner that the legal representatives of the deceased
Contractor or surviving partners of the Contractor’s firm cannot carry out and
complete the Contract shall be final and binding on the parties. In the event of
such cancellation the Owner shall not hold the estate of the deceased
Contractor and/or the surviving partners of the estate of the deceased
Contractor and/or the surviving partners of the Contractor’s firm liable to
damages for not completing the Contract.
81.0 FRUSTRATION OF CONTRACT
81.1 In the event of frustration of the Contract because of supervening impossibility
in terms of Section 56 of the Indian Contract Act, parties shall be absolved of
their responsibility to perform the balance portion of the Contract, subject to
provisions contained in sub-clause 84.3 below.
Seal & Signature of Bidder
81.2 In the event of non-availability or suspension of funds for any reasons,
whatsoever (except for reason of willful or flagrant breach by the Owner) and/or
Contractor then the works under the Contract shall be suspended.
Furthermore, if the Owner is unable to make satisfactory alternative
arrangements for financing to the Contractor in accordance with the terms of
the Contract within three months of the event, the parties hereto shall be
relieved from carrying out further obligations under the Contract treating it as
frustration of the Contract.
81.3 In the event referred to in sub-clauses 81.1& 81.2 above the parties shall
mutually discuss to arrive at reasonable settlement on all issues including
amounts due to either party for the work already done on quantum merit basis
which shall be determined by mutual agreement between the parties.
82.0 GRAFTS AND COMMISSIONS ETC.
Any graft, commission, gift or advantage given, promised or offered by or on
behalf of the Contractor or his partner(s), agent(s), officer(s), director(s),
employee(s) or servant(s) or any one on his or their behalf in relation to the
obtaining or to the execution of this or any other Contract with the Owner, shall
in addition to any criminal liability which it may incur, subject the Contractor to
the cancellation of this and all other Contracts and also to payment of any loss
or damage to the Owner resulting from any cancellation. The Owner shall then
be entitled to deduct the amount so payable from any monies otherwise due to
Contractor under the Contract.
Definition of terms:
“Tribunal” means the Gujarat Public Works Contracts Disputes Arbitration Tribunal
constituted under the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act,
83.0 DISPUTE RESOLUTION MECHANISM
83.1 Amicable Settlement:
Any dispute, difference, controversy or claim between the Parties arising out of or
relating to this contract, including interpretation, breach, termination or validity
(hereinafter referred to as “Dispute”), shall, upon written request of either Party, be
referred to the authorized representatives of the Disputing Parties for resolution. The
authorized representatives shall promptly meet and attempt to negotiate in good faith a
resolution of the Dispute within thirty (30) days of the service of the request.
83.2 Arbitration Under the Gujarat Public Works Contracts Disputes Arbitration Tribunal
If the Parties fail to amicably resolve the Dispute as per Clause 83.1 above, or if contrary
claims remain unresolved, then, notwithstanding anything to the contrary elsewhere in
the Contract, the same shall be referred to arbitration under the provisions of the Gujarat
Public Works Contracts Disputes Arbitration Tribunal Act, 1992 (hereinafter referred to
as “the Act”) as amended from time to time, and the rules framed thereunder. The
decision, award and proceedings of the Tribunal shall be final, binding and conclusive
upon the parties, subject only to such remedies as may be available under the Act and
any other applicable law in force.
Seal & Signature of Bidder
83.3 Continuity of Performance:
During the pendency of any Dispute or arbitration proceedings, both Parties shall
continue to perform their respective obligations under the Contract.
83.4 Non-Affectation of Powers:
Reference to any Dispute resolution procedure, including arbitration, shall not affect the
right of the Owner and/or Engineer-in-Charge to take possession of or utilize the
Contractor’s tools, plants, materials, stores or works as per the terms and conditions of
the Contract, nor shall it entitle the Contractor to stop the progress of work or affect the
Owner’s rights under the Contract to get work executed through alternate means, if so
required under the contract.
83.5 Limitation:
Neither Party shall be entitled to invoke dispute resolution or arbitration under this
clause later than thirty (30) days after the expiration of the defects liability period, unless
otherwise provided under the Act.
84.0 ARBITRATION
All arbitration matters are governed by Clause 83.0 above, in compliance with the
Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 and GUVNL
84.1 All disputes or differences in respect of which the decision, if any, of the
Engineer has not become final or binding as aforesaid shall be settled by
arbitration in the manner hereinafter provided.
84.1.1 The arbitration shall be conducted by three arbitrators, one each to be
nominated by the Contractor and the Owner and the third to be appointed as
an umpire by both the arbitrators in accordance with the Indian Arbitration Act.
If either of the parties fails to appoint its arbitrator within sixty (60) days after
receipt of a notice from the other party invoking the Arbitration clause, the
arbitrator appointed by the party invoking the arbitration clause shall become
the sole arbitrator to conduct the arbitration.
84.1.2 The arbitration shall be conducted in accordance with provisions of Indian
Arbitration Act 1996 or latest amendment thereof.
84.2 The decision of the majority of the arbitrators shall be final and binding upon
The arbitrators may, from time to time with the consent of all the parties enlarge
the time for making the award. In the event of any of the aforesaid arbitrators
dying, neglecting, resigning or being unable to act for any reason, it will be
lawful for the party concerned to nominate another arbitrator in place of the
outgoing arbitrator.
84.3 The arbitrator shall have full powers to review and/or revise any decision,
opinion, direction, certification or valuation of the Engineer in accordance with
the Contract, and neither party shall be limited in the proceedings before such
arbitrators to the evidence or arguments put before the Engineer for the
purpose of obtaining the said decision.
Seal & Signature of Bidder
84.4 No decision given by the Engineer in accordance with the foregoing provisions
shall disqualify him as being called as a witness or giving evidence before the
arbitrators on any matter whatsoever relevant to the dispute or difference
referred to the arbitrators as aforesaid.
84.5 During settlement of disputes and arbitration proceedings, both parties shall be
obliged to carry out their respective obligations under the Contract.
84.6 All questions, disputes or differences, whatsoever which may at any time arise
between the parties to this contract in connection with the contract or any matter
arising out of or in relation there to shall be referred to the “Gujarat public works
contracts disputes arbitration tribunal” as per the provisions of the Gujarat
public works contracts disputes arbitration tribunalact,1992.
The reference to arbitration proceedings under this clause shall not
a) Affect the right of the Engineer -in charge to take possession of all or any
tools, plants, materials and stores, in or upon the work or site thereof or
belonging to the contractor or procured by him and intended to be used
for the execution of the work or any part thereof.
b) Preclude the Engineer-in charge from utilizing the materials purchased
by the Contractor in any work or from removing such materials to other
place, during the period the work is stopped or suspended in pursuance
of notice given to the contractor under General Conditions.
c) Entitle the contractor to stop the progress of the work or carrying out the
additional or altered work in accordance with the prevision of General
Conditions for the work where there are no specifications.
d) Preclude the GETCO from getting the work done by another agency.
Neither party is entitled to bring a claim to arbitration latest by thirty days
after the expiration of the defects liability period. The provisions of the
Arbitration Act,1992, Gujarat Public Works Contract Disputes Arbitration
Tribunal Act, 1992, and rules made there under shall apply to the
arbitration proceeding under this clause. “
85.0 RECONCILIATION OF ACCOUNTS
The Contractor shall prepare and submit every two months, a statement
covering payments claimed and the payments received vis-à-vis the works
executed, for reconciliation of accounts with the Owner. The Contractor shall
also prepare and submit a detailed account of Owner Issue materials received
and utilized by him for reconciliation purpose in a format to be discussed &
finalized with the Owner before the award of Contract.
86.0 LABOUR LAWS:
86.0.1 Persons below the age of 18 years shall not be employed for the work. No
female worker shall be employed in the night shift between 07.00 p.m. and
06.00 a.m. next day.
86.0.2 Contractor shall maintain a valid labour license under the contract Labour
(Regulation and abolition) Act for employing necessary manpower required by
him. In the absence of such license, the contract shall be liable to be terminated
without assigning any reason thereof.
Seal & Signature of Bidder
86.0.3 The Contractor shall at his own expenses comply with all labour laws and keep
the GETCO indemnified in respect thereof. Some of the major liabilities under
various labour and industrial laws which the Contractor shall comply with, are
i) Payment of contribution by way of Employer’s Contribution towards
provident Fund, Family Pension Scheme, Deposit Linked Insurance
Scheme, Administrative charges, etc. at the rates made applicable from
time to time by the Government of Gujarat / Government of India or other
Statutory Authority.
ii) Payment of deposit in respect of each contract labour at the rate of Rs.
30/- or later prevailing rate with the Office of Commissioner of Labour as
per the Contract Labour (Regulation and Abolition) Act.
iii) License fee as prescribed under the Contract Labour (Regulation and
Abolition) Act and Rules framed there under depending upon the number
iv) Paid leave facility and wages as per the provision of the Factories Act at
the rate of one day for every 20 days of working.
v) Identity cards as prescribed under the Factories Act with photo affixed
thereto, for identification.
vi) Payment of retrenchment compensation, Notice Pay and other liabilities
as per Industrial Dispute Act. Any payment to the Contractor’s employee
arising out of any claim of disputes under the Industrial Disputes Act
1947 or any other Labour Laws.
vii) Payment of compensation in case of accidental injury.
viii) Provision of crèche if the female laborers employed are more than
ix) Maternity Leave as per the provisions of the Maternity Benefit Act.
The above are some of the major liabilities of the Contractor in addition to other
liabilities prescribed under the various labour laws, in force from time to time, from
Statutory Authorities like State Government/ Government of India, which the
Contractor shall have to comply with.
86.1 PROVIDENT FUND AND FAMILY PENSION SCHEME:
The Contractor shall submit along with his bills (month wise) a statement
regarding deduction against employees Provident Fund and Family Pension
Scheme in respect of each concerned employee. Provident Fund and Family
pension Scheme at the rate of 18% (or at the rate made applicable by the
Government from time to time of the wages. The Contractor’s contribution and
his worker’s contribution towards Provident Fund and Family Pension Scheme
shall be deposited by the Contractor with Regional Provident Fund
Commissioner, Ahmedabad.
86.2 DEPOSIT LINKED INSURANCE SCHEME
The contractor shall have to deposit ½ % of the wages in respect of employees
who is a member of the Provident Fund, as the contribution to the Deposit
Linked Insurance Scheme with Regional Provident Fund Commissioner,
86.3 ADMINISTRATIVE CHARGES:
Seal & Signature of Bidder
Administrative charges for maintaining Provident Fund Account shall be
deposited by the Contractor with Regional Provident Fund Commissioner,
Ahmedabad at the rates applicable.
86.4 PAID LEAVE FACILITY:
Paid Leave Facility at the rate of one day for every twenty days worked by the
Contract Labour, shall be provided by the Contractor to his workers. He shall
maintain Leave Records, Leave Cards, for individual laborer which shall be duly
verified, approved and certified by the authorized Officer of the GETCO.
86.5 WORKMAN’S COMPENSATION FUND AND EMPLOYER’S LIABILITY
The contractor shall cover all his employees under workmen’s compensation
fund and under the liability insurance. The purchaser shall not be responsible
for any payments of compensation to the workers/supervisor of the contractor
for fatal or non-fatal accidents during the pendency of the contract.
86.6 The contractor shall employ adequate number of experienced skilled at site for
daily supervision and for maintenance of various registers and records required
under the law and contract. No payment for supervision shall be admissible.
86.7 CONTRCTOR TO INDEMNIFY THE GETCO:
The Contractor shall Indemnify the GETCO and every member officer and
employees of the GETCO also, Engineer-in-Charge and his staff against all
actions, proceedings, claims, demands, costs and expenses whatsoever,
arising out of or in connection with the matters referred herein above elsewhere
and against all actions, proceedings, claims, demands, costs and expenses
which may be made against the GETCO or Government for or in respect of
performance of his obligation under the contract documents. The GETCO shall
not be liable for intervention of authority Government for or in respect of
performance of his obligation under the contract documents. The GETCO shall
not be liable for or in respect of or in consequence of any accident or injury to
any workman or other person in the employment of the Contractor or his Sub-
Contractor and the contractor shall indemnify and keep indemnified the GETCO
against all claims, demands, proceedings, cost, charges and expenses
whatsoever in respect thereof or in relation thereto.
86.8 WORKMEN’S COMPENSATION AND EMPLOYER’S LIABILITY
Insurance shall be effected for all the Contractor’s employee engages in the
performance of this contract. If any of the work is sublet, the Contractor shall
require the Sub-Contractor to provide workmen’s employer’s liability insurance
for the latter’s employees, such employees shall be covered under the
Contractor’s Insurance.
86.9 WAGES TO BE PAID & TIME OF PAYMENT ETC. BY THE CONTRACTOR
a) The Contractor shall pay minimum wages per day to his Labours/ Workers as
per rates fixed under the minimum wages act. The wages of every Contract
Labour employed by him under this contract shall also be paid by him before
the expiry of 7th day of the last day of the month in respect of the wages are
payable (i.e. wages of a month have to be paid by him in the first week of the
Seal & Signature of Bidder
next month). Any default will result in cancellation of contract forthwith or else
the contractor shall be punishable to the extent of Rs. 100/- per each day or as
per the prevailing rules of labour laws.
b) The Contractor shall give his Telephone Number and Address to the GETCO,
so that, in case of labour trouble etc. the Contractor can be contacted. The
Contractor shall arrange to have his office outside the factory work premises
and the Contractor shall arrange to have his office outside the factory work
premises and the Contractor shall keep himself present throughout the working
86.10 REGISTRATION WITH PROVIDENT FUND OFFICE
I) The separate P.F. code issued from P.F. commissioner is required to be taken
ii) If the contractor does not possess separate P.F. code number of RPFC, his
tender will not be considered for acceptance.
iii) The contractor should mention separate P.F. code number allotted by RPFC,
along with the tender.
87.0 Termination of Contract:
In case of contractor fails to deliver the stocks or any consignment thereof within
contractual period of delivery or in case the stores are found not in accordance
with prescribed specification and/or the approved sample, the GETCO shall
exercise its discretionary power either:
87.1 To recover, from the contractor as agreed, by way of penalty clause above, or
87.2 To purchase from elsewhere after giving due notice to the contractor on account
and at the risk of the contractor for such stores not so delivered or other similar
description without canceling the contract in respect of the consignment not yet
due for delivery
88.00 To cancel the contract.
In the event of the risk purchase of stores of similar description, the opinion of
the GETCO shall be final. In the event of action taken under clause above, the
contractor shall be liable to pay for any loss which the GETCO may sustain on
that account, but the contractor shall not be entitled to have any saving on such
purchases made against default.
The decision of the GETCO shall be final as regards to the acceptability of stores
supplied by the contractor and the GETCO shall not be required to give any
reason in writing or otherwise at any time for rejection of the stores.
89.0 MATCHING OF END COST:
In case the GETCO decides to award contract on matching end-cost basis,
the bidder has to reduce all the quoted rates proportionately. The reduction
on overall basis will not be accepted (i.e. all unit rates of erection schedule
shall be reduced proportionately by difference in percentage). The
confirmation for matching end cost shall be given within 7 (seven) days from
the letter from GETCO.
90.0 VENDOR REGISTRATION:
Seal & Signature of Bidder
All new bidders / Vendors have to register themselves with the GETCO by
paying Rs.10,000/- (Non-refundable) plus GST as applicable. Regular
suppliers are registered automatically looking to their performance. They
shall have to fill up a prescribed form attached herewith within two months
giving basic details of their set up, turn over, ISO certification, etc. However,
they shall have to re-register by paying Rs.10,000/-(Non-Refundable) plus
GST as applicable after 05 years from 01/03/2001. Factory inspection for
new entrants is a must. Factory inspection shall be conducted for the period
of every 2 years from where the supplier is supposed to supply the
materials. This new rule shall come in to force after 06 months from
01/03/2001 so that party gets enough time for registration. However, in the
meantime all the New Vendors shall have to pay Rs. 10,000/-(Non-
refundable) plus GST as applicable towards registration fees as explained
above, before submission of bids and the proof of the same may be given
with the technical bid otherwise tender will be ignored out rightly.
Vendor registration up to tender value of Rs.1 Lac (One Lac) for the new
entrant is not required. However, Rs.1000/- plus GST as applicable towards
Vendor registration shall be payable for the tender value between Rs.1 Lac
and including up to Rs.5 Lacs. Vendor registration beyond Rs.5 lacs will be
applicable and shall have to pay Rs.10,000/- plus GST as applicable for
new entrant as specified above.
If the New Vendors are already registered by paying of Rs.10,000/- (Non-
Refundable), then it is requested to please quote the Vendor Registration
Number date in Annexure–“X” which is attached with the tender and also
enclose the copies of Money Receipt and vendor registration letter in the
If the tendered is new & not registered with the GETCO, then they should
Pay Rs.10,000/- plus GST as applicable before opening of the tender itself
and the copy of Money Receipt should be submitted in the EMD Cover,
otherwise their tender will be ignored without any further communication in
91.0 INTRODUCTION OF LEAVY OF TCS.
TCS @ 0.075% / 0.1% will be payable extra subject to fulfilment of the conditions
of sub section (1H) of section 206C of Income Tax Act, 1961. The format of
undertaking is attached in the tender.
92.0 Deduction of TDS under GST:
“TDS under GST @ 2 % (1 % CGST & 1 % SGST or 2 % IGST, as applicable)
or at the applicable rate from time to time, will be deducted from the bill of the
Suppliers / Contractors at the time of credit or payment. TDS certificates in the
prescribed format will be issued as per prescribed rules under GST.”.
93.0 Bidder should follow the GOI guideline of ‘Restrictions under rule 144 (xi) of the
General Financial Rules (GFRs), 2017 vide office memorandum no.
F.No.6/18/2019-PPD Dt: 23.07.2020. The copy of subject memorandum is
attached in technical specification of Tender.
Seal & Signature of Bidder
94.0 INCOME TAX (TDS)
TDS under Income Tax will be deducted on purchase of goods by GETCO @
0.1% of the sum exceeding Rs. 50 lacs u/s 194Q from the bill of
suppliers/contractors at the time of credit or payment whichever is earlier. TDS
will be deducted on advance payment being also made by GETCO to supplier.
Further in some of the cases, where TCS u/s 206 (1H) is applicable also along
with TDS u/s 194Q, then only TDS on purchase of Goods u/s 194Q shall be
deductible, as TDS u/s 194Q overrides TCS u/s 206C (1H).
• As per the Section 206AB of Income Tax Act, TDS under Income Tax will be
deducted at higher rates of the following rates: (non-fillers of ITRs for the past
two fiscal years will be subjected to higher TDS).
(a) At twice the rate specified in the relevant provision of the Act
(b) At twice the rates in force
(c) At the rate of 5%
95. Responsibility for correctness of the information submitted in the bid lies with
bidder. If any information furnished in the bid is proved to be false at a later date,
GETCO reserve right to reject the bid and the bid will not only be rejected but the
bidder will be BLACKLISTED as per GUVNL Policy.
96. Use of ‘Call Before u Dig’ (CBuD) mobile application:
Bidder is note that it is mandatory to use ‘Call Before u Dig’ (CBuD) mobile
application for all excavators prior to any type of excavation / digging.
97. Conflict of Interest among Bidders / Agents
A bidder shall not have conflict of interest with other bidders for particular quoted
item. Such conflict of interest can lead to anti-competitive practices to the detriment
of Procuring Entity’s interests. The bidder found to have a conflict of interest shall
be disqualified. A bidder may be considered to have a conflict of interest with one
or more parties in this bidding process for particular quoted item, if:
a) they have proprietor/ partner(s)/ Director(s) in common; or
b) they receive or have received any direct or indirect subsidy/ financial stake from any
c) they have the same legal representative/ agent for purposes of this bid; or
Seal & Signature of Bidder
d) they have relationship with each other, directly or through common third parties,
that puts them in a position to have access to information about or influence on the
bid of another bidder; or
e) bidder participates in more than one bid in this bidding process. Participation by a
bidder in more than one Bid will result in the disqualification of all bids in which the
parties are involved. However, this does not limit the inclusion of the components/
sub-assembly/ assemblies from one bidding manufacturer in more than one bid.
f) in cases of agents quoting in offshore procurements, on behalf of their principal
manufacturers, one agent cannot represent two manufacturers or quote on their
behalf in a particular tender enquiry. One manufacturer can also authorize only one
agent/ dealer. There can be only one bid from the following:
1. The principal manufacturer directly or through one Indian agent on his behalf; and
2. Indian/ foreign agent on behalf of only one principal.
g) a Bidder or any of its affiliates participated as a consultant in the preparation of the
design or technical specifications of the contract that is the subject of the Bid;
h) in case of a holding company having more than one independently manufacturing
units, or more than one unit having common business ownership/ management,
only one unit should quote. Similar restrictions would apply to closely related sister
companies. Bidders must proactively declare such sister/ common business/
management units in same/ similar line of business.
i) Bidder shall not act in contravention/ violation to the provisions of competition act,
as amended from time to time.
Every bidder should, at the time of submission of bid, give a declaration, that bidder
shall not have conflict of interest with other bidders, as above.
98 Relationship clause:
Every bidder should at time of bid give a declaration as under:
“If any Bidder Company/Firm, the interest(i.e. share holding in company and share
in partnership firm) of any employee of the tendering company of his/her relative
as defined in section 2(77) of Company act 2013 is 10% or more, the tendering
company will not deal with such company/Firm at all.
Tenderer therefore must specifically disclose the fact in his technical bid Non
disclosure of such facts would immediately disqualify the tenderer for further
dealing with the tendering company”
Seal & Signature of Bidder
GENERAL INFORMATION (TECHNICAL)
1.1. CODES, STANDARDS & REGULATIONS
The design, manufacture, erection and testing of the equipments and material to be
supplied shall comply with latest revisions of relevant Indian Standards or equivalent
In addition, the Indian Electricity Rules, Electricity Act 2003,Statutory requirements of
Central Govt., GERC and State Government of Gujarat( applicable codes), shall also
be complied with. Any complications arising out of it will be set right by the bidder
without any implication to Corporate.
The bidder shall submit his offer as per information given in submission of tender.
Drawings, Data and Documents
The bidder shall furnish following documents/ information along with offer in spiral
General description of equipment offered specifying the important features, make,
technical parameters, materials of construction etc. To enable GETCO to have proper
understanding of the material offered and its operation.
The following drawings and documents shall be furnished to GETCO by the successful
bidder for approval of GETCO, within the period stipulated in the draft
contract/mutually agreed terms at the time of placement of order, the bidder shall
submit a list of all such drawings and documents he proposes to submit. The list will
be approved by GETCO and may be modified, if necessary. Each drawing /document
in the list shall be identified with a serial number, description and scheduled date of
submission. This should be submitted in a spiral bound volumes.
1.2. MAJOR DOCUMENTS & DRAWINGS REQUIRED FOR APPROVAL:
Route details of cable line
Cable layout drawing along with cable trenches. Cable support of galvanized angle
or channel/pipe
Installation drawings
* Layout of Line
* Layout of cabling
* Section layout for cable in normal soil
All the equipment’s Structure drawings along with Design Calculations.
Drawings for all the equipments & materials as per bidding schedule supported by
required calculations related to design/rating /temp rise
Field Quality Plan for U/g cable laying work.
1.3. FOR REFERENCE
OEM’s Complete and comprehensive instruction manuals with drawings for
operation and maintenance of the equipments supplied by the bidder. This shall also
include the following:
a) Preventive maintenance schedule
b) Procedure for shutdown and energization of line
c) Safety procedures for safe operation of 220 KV cable line
Seal & Signature of Bidder
d) Test procedure for site tests.
1.4. AS- BUILT DRAWINGS
On completion of installation, testing and commissioning, the bidder shall incorporate
revisions/ modification if any, in the reproducible and submit ‘as built’ drawing for
GETCO’s record in spiral bound volumes and soft copy. The drawings shall be in
AutoCAD DXF format.
1.5. TEST AND INSPECTION FOR INDIVIDUAL ITEM
Routine test/ Acceptance tests shall be carried out on all equipment at manufacture’s
works as per appropriate IS/IEC. The bidder shall make reasonable facilities, at his
cost for inspection and testing of the equipment/material by GETCO’s Officials. No
equipment shall be dispatched to site without provisional certificates of acceptance
issued by GETCO. Inspection and test shall be carried out at the place of manufacture
as well as on receipt of the equipment at site if required. Inspection and tests do not
relieve the bidder of his contractual obligations regarding performance of the
equipment at site/in actual use.
The bidder shall submit the brief summary of all type test certificates for similar
equipment supplied by him elsewhere and the actual type test certificates as and when
asked. In case type test certificates for similar equipment is not available, the same
shall be conducted in the presence of GETCO’s Authorized representative if GETCO
so desires, without any financial implications to the GETCO. The type test report shall
not be older than 5 year from the date of tender opening (Technical bid opening).
The supplier of the equipment shall ensure that the equipment available at his works
for routine test/type test/acceptance test are duly calibrated and necessary certificate
shall be made available to the inspecting officer of GETCO.
As far as possible, the supplier of equipment shall give a minimum of 15 days’ notice
of readiness of material and give the inspection call accordingly. If on arrival of
inspecting officer at the works, the material is not found to be ready, the concerned
supplier of equipment shall be liable for additional expenditure GETCO may incur on
account of retention or re-deputation of the inspecting officer.
The officer deputed for inspecting for particular lot of material according to intimation
from you may also like to check Quality Control Plan and for that purpose he may
demand the Test Reports of raw material being procured.
1.6. FUNCTIONAL AND COMPOSITE TESTING
Following test shall be conducted on equipment after completion of erection in the
presence of Engineer -in-charge from point of view of completeness in the presence
of GETCO’s Authorized Representative.
Visual inspection of total system.
Checking of continuity of power cables.
Checking of insulation.
Verification and measurement of earthing resistance.
Checking of cable terminations and laying, dressing etc.
Checking of safe accessibility of components.
The insulation resistance test shall be carried out
All tests as specified in Technical Specification Part -II
Seal & Signature of Bidder
All the equipments and materials shall be passed through checks and test as per
approved Field Quality Plan.
The insulation resistance test shall be carried out on the following equipments.
EHV installation - by 5000 V Megger
HV installation above 11 KV - by 2500V Megger
Power circuit of voltage up to 1KV- by 1000 V Megger
A.C. & D.C. auxiliary circuits - by 500 V Megger
1.7. BAR CHARTS
The Bidder shall furnish along with the bid, the bar charts in M.S. Project and project
schedules indicating starting and completion dates of each activity, such as
preparation & approval of drawings, manufacturing/supply/ delivery, civil works,
erection, testing, pre commissioning and commissioning etc.
Identification labels shall be provided on all equipments as per client’s approval. All
labels shall be engraved on plastic (white letters with black background) and all text
shall be in English language.
Any exclusion /deviation from specification shall be clearly spelt out and listed at one
place only and bidder shall substantiate the same with appropriate reasons. In the
absence of clearly spelt out and mutually agreed deviation, it shall be considered that
the bidder has undertaken to comply with the technical specification totally, in letter
It will be responsibility of the successful bidder to obtain necessary approval of
statutory authority as per rules of Govt. of Gujarat and Central Electricity Authority for
the work under his scope before energizing/ charging the equipment/system. However
bidder shall be extended all assistance by the GETCO in regard to application for the
The installation for the equipment shall include civil works and necessary material
required to complete the Installation. It may be noted that foundation details for
structure should be got approved from GETCO.
Before dispatch to the Site, but before energization, all components/ accessories
which are intended to be painted shall be thoroughly cleaned of rust, scales, greases,
etc. and painted with two coats of proper primer. This shall be followed by two coats
of finishing paint of the color specified/approved by the GETCO. Damage to the
painting surface during transit/ erection shall be made good by the bidder free of cost
before the equipment is finally accepted by the Engineer- In charge.
For installation work at site, the bidder shall be fully responsible for arranging the
supply of required tools and tackles, welding sets, pipe bending machine, cable
crimping tools, labours, scaffolding, ladders, etc.
The power connection will be provided by GETCO at one point only at the prevailing
tariff, from where the bidder has to arrange for temporary connection and further
distribution of supply at his own cost. Similarly, bidder has to arrange for water by
pipeline or by water tankers or by drilling bore in S/S at his cost.
Seal & Signature of Bidder
The installation of energy meter, cut out, switches etc. for construction power shall be
as per prevailing norms of Distribution Department of GETCO. The test report and
other requirement to release the connection shall be as per prevailing rules of
Distribution Department of GETCO.
On completion of the installation but before energizing the system, all installation shall
be physically checked and properly tested. These checks and tests shall be conducted
by the bidder under the supervision of Engineer In-charge and bidder shall furnish the
final status and test results shall be made good by the bidder free of cost within
contract completion period.
All clamps, brackets, bolts, nuts, screws, markers, ferrules, lugs and glands and other
hardware necessary for erection work, shall include in the scope of work and shall be
arranged by the bidder.
2.0 GALVANISING
All the Equipments / material shall be hot dip galvanized. Wherever it is not feasible to
provide galvanized equipment/material shall be painted to withstand heavily polluted
atmospheric conditions. Painting should be done with two coats of Red oxide & two
coats of epoxy paints of standard make.
3.0 APPROVED MAKES OF EQUIPMENTS /ITEMS OF SUPPLY
a. The 66KV cable, Earthing cable and Accessories can be supplied from the
manufacturer meeting technical specifications.
(ii) The Corporate reserves the right to make changes (add or delete names of other
makes) in the list during execution of contract.
(i) If bidder wants to propose additional vendors for any of the items, same shall be
stated along with the tender or within 30 days from the date of LOI & decision
thereof will be conveyed within 30 days thereafter by GETCO.
(ii) Bidder has to supply all materials as per GETCO specifications and from the
regular supplier of GETCO.
4.0 INSPECTION AND TESTING OF EQUIPMENT
Manufacturing Progress reviews, inspection & testing of equipment covered under the
technical specification shall be carried out by the GETCO’s Authorized Representative
at the manufacturer’s works/premises prior to dispatch, to ensure that their quality &
workmanship are in conformity with the contract specifications and approved
4.2 RESPONSIBILITY FOR INSPECTION
Any inspection by the GETCO’s Authorized Representative does not relieve the Bidder
from his responsibility of quality assurance and quality control functions.
As such, any approval which the Inspecting Engineer of the GETCO may have given
in respect of equipment and other particulars and the work or workmanship involved
in the contract (whether with or without test carried out) shall not bind the GETCO to
accept the plant & equipment, should it on further tests at site be found not comply,
with the requirements of the contract. If required, audit wing of GETCO HO Inspection
Seal & Signature of Bidder
Department shall also be entrusted with inspection of particular item/equipment
received at site.
The bidder is to meet the inspection & testing requirements for the equipment coming
under the statutory regulations e.g. weights & measures, safety, IE rules, etc. and
submit calibration certificates and documents from appropriate authority to the GETCO
Inspecting Engineer for the same, on demand.
4.3 EXTENT OF INSPECTION
The extent of inspection & testing by the GETCO shall vary from equipment to
equipment as per design requirements, if necessary.
Extent of inspection to be carried out shall be finalized with the Bidder after award of
the contract on the basis of scope of supply, technical specification and approved GA
4.4 METHOD OF GIVING INSPECTION CALLS
Inspection calls shall be given by the Bidder to Chief Engineer, Engineering, GETCO
in accordance with mutually agreed program with 15 days’ clear time for all
equipments. Four sets of relevant test certificates and inspection report of the Bidder/
Sub-bidder after satisfactory completion of internal inspection and test shall be
submitted along with acceptance/routine test certificate of the tests witnessed by
GETCO Inspector.
The GETCO reserves the right to visit at any stage of manufacture at plant and ask
for additional inspection & tests if it is found necessary after completion of detailed
design & engineering and approval of drawings.
The GETCO or his duly authorized representative shall on giving written instructions
to the bidder, setting out any grounds of objection which he may have in respect of the
work, be at liberty to reject all or any part of plant/equipment or workmanship which
are not in conformity with the contract provisions.
4.5 BIDDER’S RESPONSIBILITY
The Bidder shall provide all reasonable facilities to the Inspecting Engineer of the
GETCO to the Bidder’s or their sub-bidder’s premises at any time during contract
period, to facilitate him to carryout inspection & testing of equipment during
manufacture of equipment.
The Bidder shall delegate a representative/coordinator to deal with GETCO on all
inspection matters.
The Bidder shall comply with instructions of the GETCO’s Inspecting Engineer fully.
The Bidder shall ensure that the equipment and materials once rejected by the
Inspecting Engineer are not reused in the manufacturing of the equipment and
materials. Where parts rejected by the Inspecting Engineer have been rectified as per
agreed procedures laid down in advance, such parts shall be segregated for separate
inspection and approval, before being used in the work.
4.6 INSPECTION WAIVER
Seal & Signature of Bidder
For certain standard bought-out items and the products of reputed firms where the
GETCO has earlier experience on the quality of their products, the GETCO may
consider allowing of inspection waiver for such items. The Chief Engineer, GETCO,
Baroda shall issue approval of inspection waiver certificate after scrutiny of bidder’s
internal inspection report, test certificates and other documents. However, it is not
binding upon GETCO to give waiver on bidder’s request. GETCO may weigh the
important issues like quantity of material, cost of material, importance of material,
distance of travel & time of travel required to inspect before deciding the waiver of the
5.0 OTHER CONDITIONS
Any clarification / amendment necessary, in any or more clauses incorporated in the
present A/T, you will have to make a detailed reference to the GETCO latest within ten
days from the receipt of A/T. If you fail to do so, no request for any clarification /
amendment shall be considered thereafter. Please also note that all the points which
need clarification / amendment should be brought out at once. No piecemeal
clarification/amendment will be entertained.
Seal & Signature of Bidder
ERECTION CONDITIONS OF CONTRACT
1.1 The following shall supplement the conditions already contained in other parts
of these specifications & document and shall govern the portion of the work of
this Contract to be performed at Site.
1.2 The Contractor upon signing of the Contract shall, nominate a responsible
officer as his representative at Site suitably designated for the purpose of
overall responsibility and coordination of the works to be performed at Site.
Such person shall function from the Site office of the Contractor during the
pendency of Contract.
2.0 REGULATION OF LOCAL AUTHORITIES AND STATUTES
2.1 The Contractor shall comply with all the rules and regulations of local authorities
during the performance of his field activities. He shall also comply with the
Minimum Wages Act, 1948 and the Payment of Wages Act (both of the
Government of India) and the rules made there under in respect of any
employee or workman employed or engaged by him or his Sub-Contractor. He
shall abide by labour laws .
2.2 All initial registration and statutory inspection fees, if any, in respect of his work
pursuant to this Contract shall be to the account of the GETCO. Should any
such inspection or registration need to be re-arranged due to the fault of the
Contractor or his Sub Contractor, the additional fees to such inspection and/or
registration also shall be borne by the Contractor.
3.0 OWNER’S LIEN ON EQUIPMENT
The Owner shall have lien on all equipment brought to the Site for the purpose
of erection, testing and commissioning of the equipment to be supplied &
erected under the Contract. The Owner shall continue to hold the lien on all
such equipment throughout the period of Contract. No material brought to the
Site shall be removed from the Site by the Contractor and/or his Sub-
Contractors without the prior written approval of the Engineer.
4.0 ACCESS TO SITE AND WORKS ON SITE
4.1 Suitable access to and possession of the Site shall be afforded to the Contractor
by the Owner in reasonable time.
4.2 The works so far as it is carried out on the Owner’s premises, shall be carried
out at such time as the Owner may approve and the Owner shall give the
Contractor reasonable facilities for carrying out the works.
4.3 In the execution of the works, no person other than the Contractor or his duly
appointed representative, Sub- Contractor and workmen, shall be allowed to do
work on the Site, except by the special permission, in writing of the Engineer or
his representative.
Seal & Signature of Bidder
5.0 CONTRACTOR’S SITE ESTABLISHMENT
The Contractor shall at all times keep posted an authorized representative for
the purpose of the Contract. Any written order or instruction of the Engineer or
his duly authorized representative shall be communicated to the said authorized
resident representative of the Contractor and the representative shall be
available at a stated address for this purpose.
6.0 CO-OPERATION WITH OTHER CONTRACTORS
6.1 The Contractor shall co-operate with all other Contractors or tradesmen of the
Owner, who may be performing other works on behalf of the Owner and the
workmen who may be employed by the Owner and doing work in the vicinity of
the Works under the Contract. The Contractor shall also so arrange to perform
his work as to minimize, to the maximum extent possible, interference with the
work of other Contractors and their workmen. Any injury or damage that may
be sustained by the employees of the other Contractors and the Owner, due to
the Contractor’s work shall promptly be made good at the Contractor’s own
7.0 DISCIPLINE OF WORKMEN
The Contractor shall adhere to the disciplinary procedure set by the Engineer
in respect of his employees and workmen at Site. The Engineer shall be at
liberty to object to the presence of any representative or employee of the
Contractor at the Site, if in the opinion of the Engineer such employee has
misconducted himself or is incompetent or negligent or otherwise undesirable
and then the Contractor shall remove such a person objected to and provide in
his place a competent replacement.
8.0 CONTRACTOR’S FIELD OPERATION
8.1 The Contractor shall keep the Engineer informed in advance regarding his field
activity plans and schedules for carrying-out each part of the works. Any review
of such plan or schedule or method of work by the Engineer shall not relieve
the Contractor of any of his responsibilities towards the field activities. Such
reviews shall also not be considered as an assumption of any risk or liability by
the Engineer or the Owner or any of his representatives and no claim of the
Contractor will be entertained because of the failure or inefficiency of any such
plan or schedule or method of work reviewed. The Contractor shall be solely
responsible for the safety, adequacy and efficiency of plant and equipment and
his erection methods.
8.2 The Contractor shall have the complete responsibility for the conditions of the
Work-site including the safety of all persons employed by him or his Sub–
Contractor and all the properties under his custody during the performance of
the work. This requirement shall apply continuously till the completion of the
Contract and shall not be limited to normal working hours.
9.0 PROGRESS REPORT
9.1 The Contractor shall furnish three (3) copies each to the Engineer of progress
including if any, photographs of the work done at Site.
Seal & Signature of Bidder
9.2 The monthly progress report detailing-out the progress achieved on all erection
activities shall highlight comparison to the schedules. The report shall also
indicate the reasons for the variance between the scheduled and actual
progress and the action proposed for corrective measures, wherever
10.0 MAN-POWER REPORT
10.1 The Contractor shall submit to the Engineer, on the first day of every month, a
man hours schedule for the month, detailing the man hours scheduled for the
month, skill-wise and area-wise.
11.0 PROTECTION OF WORK
The Contractor shall have total responsibility for protecting his works till it is
finally taken over by the Engineer. No claim will be entertained by the Owner
or by the Engineer for any damage or loss to the Contractor’s works and the
Contractor shall be responsible for complete restoration of the damaged works
to original conditions to comply with the specification and drawings.
12.0 EMPLOYMENT OF LABOUR
12.1 The Contractor will be expected to employ on the work only his regular skilled
employees with experience of his particular work. No person below the age of
eighteen years shall be employed.
12.2 All traveling expenses including provisions of necessary transport to and from
Site, lodging, allowances and other payments to the Contractor’s employees
shall be the sole responsibility of the Contractor.
12.3 In case the Owner becomes liable to pay any wages or dues to Labour or any
Government agency under any of the provisions of the Minimum Wages Act,
Workmen Compensation Act, Contract Labour Regulation Abolition Act or any
other law due to act of omission of the Contractor, the Owner may make such
payment and shall recover the same from the Contractor’s bills.
13.0 FACILITIES TO BE PROVIDED BY THE OWNER
Land for Contractor’s Store, Workshop etc.
a) The Engineer shall at his discretion and for the duration of execution of the
Contract make available at site, land for construction of Contractor’s field office,
workshop, stores, etc. required for execution of the Contract. Any such
temporary construction shall be done by the Contractor at his cost.
b) On completion of work the Contractor shall hand over the land duly cleaned to
the Engineer. Until and unless the Contractor has handed over the vacant
possession of land allotted to him for the above purpose, the payment of his
final bill shall not be made.
Seal & Signature of Bidder
13.2 Electricity:
The concerned EE (Const.) shall apply for 11KV Transformer Center at the site
of new Substation and for which concerned DISCOM shall erect the required
line and install the transformer Center, for which, the cost is to be borne by
GETCO. Subsequently, the Agency finalized for EPC contract by GETCO, shall
apply for temporary connection to the concerned DISCOM Sub-Division paying
required Service Charges and Deposit. Such temporary connections to be
released on the name of EPC-Contractor on recommendation of the concerned
EE (Const.). The power so consumed shall be charged at the prevailing tariff
14.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR
14.1 Tools, tackles and scaffoldings
The Contractor shall provide all the construction equipments, tools, tackles and
scaffoldings required for pre-assembly, erection, testing and commissioning of
the equipment covered under the Contract. He shall submit a list of all such
materials to the Engineer before the commencement of work at Site. These
tools and tackles shall not be removed from the Site without the written
permission of the Engineer.
14.3 The Contractor shall provide necessary first-aid facilities for all his employees,
representatives and workmen working at the Site. Enough number of
Contractor’s personals shall be trained in administering first-aid.
14.4 Cleanliness
14.4.1 The Contractor shall be responsible for keeping the entire area allotted to him
clean and free from rubbish, debris etc. during the period of Contract. The
Contractor shall employ enough number of personnel to keep the work area
clean. Materials and stores shall be so arranged to permit easy cleaning of the
area. In areas where equipment might drip oil and cause damage to the floor
surface, a suitable protective cover of a flame resistant, oil proof sheet shall be
provided to protect the floor from such damage.
15.0 LINES AND GRADES
All the works shall be performed to the lines, grades and elevations indicated
on the drawings. The Contractor shall be responsible to locate and lay-out the
works. Basic horizontal and vertical control points will be established and
marked by the Engineer at site at suitable points. These points shall be used
as datum for the works under the Contract. The Contractor shall inform the
Engineer well in advance of the times and places at which he wishes to do work
in the area allotted to him so that suitable datum points may be established and
checked by the Engineer to enable the Contractor to proceed with his works.
Any work done without being properly located may be removed and/or
dismantled by the Engineer at Contractor’s expense.
Seal & Signature of Bidder
16.0 FIRE PROTECTION
16.1 The work procedures that are to be used during the erection shall be those,
which minimize fire hazards to the extent practicable. Combustible materials,
combustible waste and rubbish shall be collected and removed from the Site at
least once each day. Fuels, oils and volatile or inflammable materials shall be
stored away from the construction and equipment and materials storage areas.
16.2 All the Contractor’s supervisory personnel and select number of workers shall
be trained for firefighting. Enough of such trained personnel must be available
at the Site during the entire period of the Contract.
The Contractor shall have total responsibility for all equipment and materials in
his custody/stores, loose, semi-assembled and/or erected by him at Site. The
Contractor shall make suitable security arrangements ensure the protection of
all materials, equipment and works from theft, fire, pilferage and any other
damages and loss.
18.0 PRE-COMMISSIONING TRIALS AND INITIAL OPERATIONS
The pre-commissioning trials and initial operations of the equipment furnished
and erected by the Contractor shall be the responsibility of the Contractor as
detailed in relevant clauses of Technical Specifications. The Contractor shall
provide, in addition, test instruments, calibrating devices, etc and labour
required for successful performance of these trials. If it is anticipated that the
above test may prolong for a long time, the Contractor’s workmen required for
the above test shall always be present at Site during such trials.
19.0 MATERIALS HANDLING AND STORAGE
19.1 All the equipment furnished under the Contract and arriving at Site shall be
promptly received, unloaded, transported and stored in the storage spaces by
the Contractor.
19.2 Contractor shall be responsible for examining all the shipment and notify the
Engineer immediately of any damages, storage, discrepancy etc, for the
purpose of Engineer’s information only. The Contractor shall submit to the
Engineer every week a report detailing all the receipts during the week.
However, the Contractor shall be solely responsible for any shortages or
damages in transit, handling and / or in storage and erection of the equipment
at Site. Any demurrage, wharf age and other such charges claimed by the
transporters, railways etc, shall be to the account of the Contractor.
19.3 The Contractor shall maintain an accurate and exhaustive record detailing out
the list of all equipment materials received by him for the purpose of erection
and keep such record open for the inspection of the Engineer in-charge.
19.4 All equipment shall be handled very carefully to prevent any damage or loss.
The equipment stored shall be properly protected to prevent damage either to
the equipment or to the floor where they are stored. The equipment from the
store shall be moved to the actual location at the appropriate time so as to avoid
damage of such equipment at Site.
Seal & Signature of Bidder
19.5 All electrical panels, control gears, motors and such other devices shall be
properly dried by heating before they are installed and energized. Motor
bearings, slip ring, commutators and other exposed parts shall be protected
against moisture ingress and corrosion during storage and periodically
19.6 All the electrical equipment such as motors, generators, etc. shall be tested for
insulation resistance at least once in three months from the date of receipt till
the date of commissioning and a record of such measured insulation values
maintained by the Contractor. Such records shall be opened for inspection by
19.7 The consumable and other supplies likely to deteriorate due to storage must be
thoroughly protected and stored in a suitable manner to prevent damage or
deterioration in quality by storage.
19.8 All the materials stored in the open or dusty location must be covered with
suitable weatherproof and flame proof covering material wherever applicable.
19.9 If the materials belonging to the Contractor are stored in areas other than those
earmarked for him, the Engineer will have the right to get it moved to the area
earmarked for the Contractor at the Contractor’s cost.
19.10 The Contractor shall be responsible for making suitable indoor storage facilities
to store all equipment, which require indoor storage. Normally, all the electrical
equipment such as motors, control gears, generators, exciters and
consumables like electrodes, lubricants etc. shall be stored in the closed
storage space. The Engineer, in addition, may direct the Contractor to move
certain other materials, which in his opinion will require indoor storage, to indoor
storage areas, which the Contractor shall strictly comply with.
20.0 CONSTRUCTION MANAGEMENT
20.1 The field activities of the Contractors working at Site will be coordinated by the
Engineer and the Engineer’s decision shall be final in resolving any disputes or
conflicts between the Contractor and other Contractors and the tradesmen of
the Owner regarding scheduling and coordination of work. Such decision by
the Engineer shall not be a cause for extra compensation or extension of time
for the Contractor.
20.2 The Engineer shall hold weekly meetings of the Contractor at Site, at a time
and place to be designated by the Engineer. The Contractor shall attend such
meetings and take notes of discussions during the meeting and the decision of
the Engineer and shall strictly adhere to those decisions in performing his
works. In addition to the above weekly meeting, the Engineer may call for other
meetings either with individual Contractors or with selected number of
Contractors and in such a case the Contractors if called, will also attend such
20.3 Time is the essence of the Contract and the Contractor shall be responsible for
performance of his works in accordance with the specified construction
schedule. If at any time, the Contractor is falling behind the schedule, he shall
Seal & Signature of Bidder
take necessary action to make good for such delays by increasing his work
force or by working overtime or otherwise accelerate the progress of the work
to comply with the schedule and shall communicate such actions in writing to
the Engineer, satisfying that his action will compensate for the delay. The
Contractor shall not be allowed any extra compensation for such action.
20.4 The Engineer shall, however, not be responsible for provision of additional labour
and/or materials or supply or any other services to the Contractor except for the
coordination work between various Contractors if any at site.
21.0 FIELD OFFICE RECORDS
The Contractor shall maintain up to date copies of all drawings, specifications
and other Contract Documents and any other supplementary data complete
with all the latest revisions thereto. The Contractor shall also maintain in
addition the continuous record of all changes to the above Contract Documents,
drawings, specifications, and supplementary data, etc. effected at the field and
on completion of his total assignment under the Contract shall incorporate all
such changes on the drawings and other Engineering data to indicate as
installed conditions of the equipment furnished and erected under the Contract.
Such drawings and Engineering data shall be submitted to the Engineer in
required number of copies.
22.0 CONTRACTOR’S MATERIALS BROUGHT TO SITE
22.1 The Contractor shall bring to Site all equipment, components, parts, materials,
including construction equipment, tools and tackles for the purpose of the works
under intimation to the Engineer. All such goods shall, from the time of their
being brought vest in the Owner, but may be used for the purpose of the works
only and shall not on any account be removed or taken away by the Contractor
without the written permission of the Engineer. The Contractor shall
nevertheless be solely liable and responsible for any loss or destruction thereof
and damage thereto.
22.2 The Owner shall have a lien on such goods for any sum or sums which may at
any time be due or owing to him by the Contractor, under, in respect of or by
reasons of the Contract. After giving a fifteen (15) days’ notice in writing of his
intention to do so, the Owner shall be at liberty to sell and dispose off any such
goods, in such manner as he shall think fit and to apply the proceeds in or
towards the satisfaction of such sum or sums due as aforesaid.
22.3 After the completion of the Works, the Contractor shall remove from the Site
under the direction of the Engineer the materials such as construction
equipment, erection tools and tackles, scaffolding etc. with the written
permission of the Engineer.
23.0 PROTECTION OF PROPERTY AND CONTRACTOR’S LIABILITY
23.1 The Contractor shall be responsible for any damage resulting from his
operations. He shall also be responsible for protection of all persons including
members of public and employees of the Owner and the employees of other
Contractors and Sub-Contractors and all public and private property.
Seal & Signature of Bidder
24.1 In addition to the conditions covered under the Clause entitled ‘Insurance’ in
General Terms and Conditions of Contract, the following provisions will also
apply to the portion of works to be done beyond the Contractor’s own or his
Sub-Contractor’s manufacturing Works.
24.2 Workmen’s Compensation Insurance
This insurance shall protect the Contractor against all claims applicable under
the Workmen’s Compensation Act, 1948 (Government of India). This policy
shall also cover the Contractor against claims for injury, disability, disease or
death of his or his Sub-Contractor’s employee, which for any reason are not
covered under the Workmen’s Compensation Act, 1948. The liabilities shall not
Workmen’s- As per statutory
Compensation Provisions
Employee’s liability As per statutory Provisions
24.3 Comprehensive General Liability Insurance
The insurance shall protect the Contractor against all claims arising from
injuries, disabilities, disease or death of members of public or damage to
property of others, due to any act of omission on the part of the Contractor, his
agents, his employees, his representatives and Sub-Contractors or from riots,
strikes and civil commotion.
24.4 The hazards to be covered will pertain to all the works and areas where the
Contractor, his Sub-Contractors, his agents and his employees have to perform
work pursuant to the Contract.
24.5 The above are only illustrative list of insurance covers normally required and it
will be the responsibility of the Contractors to maintain all necessary insurance
coverage to the extent both in time and amount to take care of all his liabilities
either direct or indirect, in pursuance of the Contract.
25.0 UNFAVOURABLE WORKING CONDITIONS
The Contractor shall confine all his field operations to those works, which can
be performed without subjecting the equipment and materials to adverse effects
during inclement weather conditions, like monsoon, storms etc. and during
other unfavorable construction conditions. No field activities shall be performed
by the Contractor under conditions, which might adversely affect the quality and
efficiency thereof, unless special precautions or measures are taken by the
Contractor in a proper and satisfactory manner in the performance of such
Works and with the concurrence of the Engineer. Such unfavorable
construction conditions will in no way relieve the Contractor of his responsibility
to perform the Works as per the schedule.
Seal & Signature of Bidder
26.0 PROTECTION OF MONUMENTS AND REFERENCE POINTS
The Contractor shall ensure that any finds such as relic, antiquity, coins, fossils,
etc. which he may come across during the course of performance of his Works
either during excavation or elsewhere, are properly protected and handed over
to the Engineer. Similarly, the Contractor shall ensure that the bench marks,
reference points, etc, which are marked either with the help of Engineer or by
the Engineer shall not be disturbed in any way during the performance of his
Works. If any work is to be performed which disturbs such reference the same
shall be done only after these are transferred to other suitable locations under
the direction of the Engineer. The Contractor shall provide all necessary
materials and assistance for such relocation of reference points etc.
27.0 WORK & SAFETY REGULATIONS
27.1 The Contractor shall ensure proper safety of all the workmen, materials, plant
and equipment belonging to him or to GETCO or to others, working at the Site.
The Contractor shall also be responsible for provision of all safety notices and
safety equipment required both by the relevant legislations and the Engineer,
as he may deem necessary.
27.4 All equipment used in construction and erection by Contractor shall meet
Indian/International Standards and where such standards do not exist, the
Contractor shall ensure these to be absolutely safe. All equipment shall be
strictly operated and maintained by the Contractor in accordance with
manufacturer’s Operation Manual and safety instructions and as per
Guidelines/rules of GETCO in this regard.
27.5 Periodical examinations and all tests for all lifting/hoisting equipment & tackles
shall be carried-out in accordance with the relevant provisions of Factories Act
1948, Indian Electricity Act 1910 and associated Laws/Rules in force from time
to time. A register of such examinations and tests shall be properly maintained
by the Contractor and will be promptly produced as and when desired by the
Engineer or by the person authorized by him.
27.6 The Contractor shall provide suitable safety equipment of prescribed standard
to all employees and workmen according to the need.
27.8 The Contractor shall provide safe working conditions to all workmen and
employees at the Site including safe means of access, railings, stairs, ladders,
scaffoldings etc. The scaffoldings shall be erected under the control and
supervision of an experienced and competent person. For erection, good and
standard quality of material only shall be used by the Contractor.
27.9 The Contractor shall not interfere or disturb electric fuses, wiring and other
electrical equipment belonging to the Owner or other Contractors under any
circumstances, whatsoever, unless expressly permitted in writing by GETCO to
handle such fuses, wiring or electrical equipment
27.10 Before the Contractor connects any electrical appliances to any plug or
socket belonging to the other Contractor or Owner, he shall:
a. Satisfy the Engineer that the appliance is in good working condition;
Seal & Signature of Bidder
b. Inform the Engineer of the maximum current rating, voltage and phases of
the appliances;
c. Obtain permission of the Engineer detailing the sockets to which the
appliances may be connected.
27.11 The Engineer will not grant permission to connect until he is satisfied that;
a. The appliance is in good condition and is fitted with suitable plug;
b. The appliance is fitted with a suitable cable having two earth conductors,
one of which shall be an earthed metal sheath surrounding the cores.
27.12 No electric cable in use by the Contractor/Owner will be disturbed without prior
permission. No weight of any description will be imposed on any cable and no
ladder or similar equipment will rest against or attached to it.
27.13 No repair work shall be carried out on any live equipment. The equipment must
be declared safe by the Engineer and a permit to work shall be issued by the
Engineer before any repair work is carried out by the Contractor. While working
on electric lines/equipment, whether live or dead, suitable type and sufficient
quantity of tools will have to he provided by the Contractor to
electricians/workmen/officers.
27.14 In case any accident occurs during the construction/ erection or other associated
activities undertaken by the Contractor thereby causing any minor or major or
fatal injury to his employees due to any reason, whatsoever, it shall be the
responsibility of the Contractor to promptly inform the same to the Engineer in
prescribed form and also to all the authorities envisaged under the applicable
27.15 The Engineer shall have the right at his sole discretion to stop the work, if in his
opinion the work is being carried out in such a way that it may cause accidents
and endanger the safety of the persons and/or property, and/or equipment. In
such cases, the Contractor shall be informed in writing about the nature of
hazards and possible injury/accident and he shall comply to remove
shortcomings promptly. The Contractor after stopping the specific work can, if
felt necessary, appeal against the order of stoppage of work to the Engineer
within 3 days of such stoppage of work and decision of the Engineer in this
respect shall be conclusive and binding on the Contractor.
27.16 The Contractor shall not be entitled for any damages/compensation for
stoppage of work due to safety reasons and the period of such stoppage of
work will not be taken as an extension of time for completion of work and will
not be the ground for waiver of levy of liquidated damages.
27.17 It is mandatory for the Contractor to observe during the execution of the works,
requirements of Safety Rules which would generally include but not limited to
a) Each employee shall be provided with initial indoctrination regarding safety
by the Contractor, so as to enable him to conduct his work in a safe manner.
Seal & Signature of Bidder
b) No employee shall be given a new assignment of work unfamiliar to him
without proper introduction as to the hazards incident thereto, both to
himself and his fellow employees.
c) Employees must not leave naked fires unattended. Smoking shall not be
permitted around fire prone areas and adequate firefighting equipment shall
be provided at crucial location.
d) There shall be a suitable arrangement at every work site for rendering prompt
and sufficient first aid to the injured.
j) Requirements of ventilation in underwater working to licensed and
experienced divers, use of gum boots for working in slushy or in inundated
conditions are essential requirements to be fulfilled.
27.18 The Contractor shall follow and comply with all GETCO Safety Rules, relevant
provisions of applicable laws pertaining to the safety of workmen, employees,
plant and equipment as may be prescribed from time to time without any demur,
protest or contest or reservations. In case of any discrepancy between statutory
requirement and GETCO Safety Rules referred above, the latter shall be
binding on the Contractor unless the statutory provisions are more stringent.
a. Fatal injury or accident-Rs. 1, 00,000/- :
These are causing death per person applicable for death/
b. Major injuries or accident causing Rs. 20,000/- injury to
25% or more permanent disablement per person: any person,
to Workmen or employees : whosoever.
Permanent disablement shall have same meaning as indicated in Workmen’s
Compensation Act. The compensation mentioned above shall be in addition to
the compensation payable to the workmen/employees under the relevant
provisions of the Workmen’s Compensation Act and rules framed there under
or any other applicable laws as applicable from time to time. In case the Owner
is made to pay such compensation then the Contractor is liable to reimburse
the Owner such amount in addition to the compensation indicated above.
28.0 CODE REQUIREMENTS
The erection requirements and procedures to be followed during the installation
of the equipment shall be in accordance with the relevant Codes and accepted
good engineering practice, the Engineer’s drawings and other applicable Indian
recognized codes and laws and regulation of the Government of India.
Seal & Signature of Bidder
SPECIAL CONDITIONS OF CONTRACT
1.0 General Particulars:
This part of the Bid Document relates to certain specific/special terms and
conditions particular to the Contract. The provisions herein are to be read and
understood in conjunction with the relevant provisions elsewhere in the General
Conditions of Contract (GCC) and Erection Conditions of Contract (ECC). The
intent of provisions herein are specific to this contract and are, in general,
supplementary to related provisions under GCC and ECC. However, in certain
provisions which are contrary to those in GCC and ECC, the provisions in these
Special Conditions of Contract will prevail.
2.0 Tender Fee:
The tender fee plus GST as applicable specified in notice inviting tender is payable by
Demand Draft (DD) at Vadodara drawn on any Scheduled Bank in favour of Gujarat
Energy Transmission Corporation Ltd. The same will be furnished in Cover-1 of Bid
along with EMD (Bid Security).
3.0 Earnest Money Deposit (EMD): (Ref.Cl.12.1 of GCC)
3.1 (a) The estimated cost of Tender is more than Rs. 100 lacs, the EMD is payable
50 % of EMD by DD in favour of Gujarat Energy Transmission
Corporation Ltd. on any Scheduled Bank in Vadodara and Balance 50%
by Bank Guarantee from any Nationalized Bank in the format provided
(b) The estimated cost of tender is less than Rs.100 Lacs, the EMD is payable as under:
100 % of EMD by DD in favour of Gujarat Energy Transmission
Corporation Ltd. on any Scheduled Bank in Vadodara.
3.2 Payment by Cheque/Coop Bank Guarantee/ Company Guarantee is not
3.3 Validity Period: - The offer should be valid for a minimum period of 180 days from
the date of opening of Technical bid.
4.0 Declaration by Bidder:
The Bidder shall sign the Declaration enclosed to this SCC and not furnishing
the same will make the Bid invalid.
5.0 QUALIFYING REQUIREMENT
Qualifying Requirements for 66kV 630sqmm. Cable supply, Laying & Erection
1.0 QUALIFICATION OF THE BIDDER
Seal & Signature of Bidder
Qualification of Bidder will be based on meeting the minimum pass/fail criteria
specified herein regarding the Bidder's Technical Experience Requirements and
Financial Position Requirements as demonstrated by the Bidder's responses and
supporting documents submitted with the Bid. Technical experience and financial
resources of any proposed subcontractor shall not be taken into account in
determining the Bidder's compliance with the qualifying requirements. The bid can be
submitted by an individual firm or a Joint Venture/Consortium of not more than two (2)
firms, one of whom is designated as the Lead Partner. For the purpose of the
qualification the following shall also apply:
a. For the purpose of qualifying requirements, cumulative supply/erection shall be
calculated based on the certificate(s) from the respective Transmission Utilities
or major industries only.
b. "Rkm" denotes "Route kilometer".
c. Satisfactory operation shall be substantiated by certificate(s) issued by the end
user/Employer certifying operation without adverse remarks.
d. Relevant supporting documents (e.g., supply/erection completion certificates,
performance certificates) from the original customer must be submitted.
e. No firm shall be associated, in any role, with more than one bid for this package
The roles a firm may participate in bidding under this QR are: (i) OEM Bidder
under Route-1; (ii) Non-OEM Bidder under Route-2;(iii) nominated OEM under
Route-2; (iv) OEM Partner of a Joint Venture/Consortium under Route-3; and
(v) Erection Partner of a Joint Venture/Consortium under Route-3. A firm that
has participated in any one of these roles in a bid shall not participate in any
role — the same role or a different one — in any other bid for this package.
Accordingly, without limitation to the generality of the above, a firm that:
i. is the OEM Bidder under Route-1 in one bid, shall not participate as the
nominated OEM under Route-2, or as the OEM Partner of a JV/Consortium
under Route-3, in another bid, or vice versa;
ii. is the Non-OEM Bidder under Route-2 in one bid, shall not participate as the
Erection Partner of a JV/Consortium under Route-3, in another bid, or vice
iii. participates in any OEM-side role (as OEM Bidder, nominated OEM, or OEM
Partner) in one bid, shall not participate in any non-OEM/erection-side role (as
Non-OEM Bidder or Erection Partner) in another bid, or vice versa.
Any bid found in violation of this requirement shall be rejected, along with every
other bid in which the firm concerned has so participated.
1.1 TECHNICAL EXPERIENCE REQUIREMENTS
1.1.1 Route-1: Original Equipment Manufacturer (OEM) Bidder
(I). The Bidder must be an Original Equipment Manufacturer (OEM) of 66kV or higher
voltage class XLPE cables.
Seal & Signature of Bidder
(II). The Bidder must have designed, manufactured, type tested (as per relevant
IS/IEC/ANSI standards with latest amendments), supplied and erected at least:
(a) Supplied: Cumulatively supplied a minimum of 50 km length of 66kV or above
voltage class XLPE cable during the last seven (7) years preceding the date of NIT,
to one or more Transmission Utilities or major industries. Additionally, out of the
aforesaid cumulatively supplied length, the Bidder shall submit satisfactory
performance certificate(s) evidencing that a minimum of 10 km length of 66kV or
above voltage class XLPE cable has been in satisfactory service for a minimum
period of two (2) years as on the date of NIT, issued by the Transmission Utilities
or major industries.
(b) Erected: Erected at least 20 Rkm route length cumulatively of 66kV or above
voltage class XLPE cables during last seven (7) years preceding the date of NIT
with a Transmission Utility or major industry. Out of which at least one line should
of minimum 2km route length. Subletting work experience shall not be counted
unless authenticated by order placing authority (CE(P&C)/CE(Project)/CE(AM)).
(c) Performance: At least One (1) 66kV or above cable lines supplied and erected as
above shall be in satisfactory operation for not less than One (1) year as on the date
1.1.2 Route-2: Non-OEM Bidder
(I). Non-OEM Bidders are eligible, provided that the 66kV cable is sourced from an
OEM manufacturer that conforms to the technical specifications and is an approved
vendor of GETCO.
The sourcing of 66kV cable under this Route shall be carried out from a single OEM,
who shall be an approved vendor of GETCO, unless GETCO specifically agrees
otherwise in writing. Accordingly, the Bidder shall pre-identify and nominate such
OEM, who shall meet the qualifying requirements specified under Route-1 (I) and
(II)(a), and shall submit, along with its bid, all relevant supporting documents
establishing that the nominated OEM meets the aforesaid requirements, including
Type Test Reports, Supply Orders, and Performance Certificates for the 66kV & above
voltage cable supplied by the nominated OEM. The Bidder shall, in addition, furnish
jointly with the nominated OEM a MOA/ MOU. It shall be the sole responsibility of the
Bidder to finalize and maintain the nominated OEM source without any adverse impact
on the delivery or completion schedule, and any delay or consequential damages
arising from the selection or sourcing of the OEM shall be entirely borne by the Bidder.
No change of the nominated OEM shall be permitted after bid submission, unless
specifically approved by GETCO.
(II). The Non-OEM Bidder must:
(a) Procurement & Supply: Have procured, and supplied a minimum of 50 km length
cumulative of 66kV or above voltage class XLPE cables from recognized cable
manufacturers during the last seven (7) years preceding the date of NIT, to one or
more Transmission Utilities or major industries.
(b) Erected: Have erected at least 20 Rkm route length cumulatively of 66kV or above
voltage class XLPE cables during the last seven (7) years preceding the date of NIT
with one or more Transmission Utilities or major industries. Out of which at least one
line should of minimum 2km route length. Subletting work experience shall not be
Seal & Signature of Bidder
counted unless authenticated by order placing authority
(CE(P&C)/CE(Project)/CE(AM)).
(c) Performance: At least One (1) 66kV or above cable lines supplied and erected as
above shall be in satisfactory operation for not less than One (1) year as on the date
1.1.3 Route-3: Joint Venture (JV)/Consortium
Where a bidder does not individually meet the technical requirements as specified
under Route-1 or Route-2 above, submission/participation by a Joint
Venture/Consortium is permitted, provided the JV/Consortium collectively meets all
requirements specified below.
JOINT VENTURE / CONSORTIUM BIDS
(I). Bids may be submitted by a Joint Venture/Consortium of not more than 2 (two)
partners, one of whom must be an Original Equipment Manufacturer (OEM) and the
other a non-OEM erection firm.
(II) Provided that a duly executed Joint Venture/Consortium Agreement as per
Annexure-B (SCC) shall be submitted by all partners, which shall inter alia contain
provisions establishing that all partners of the JV/Consortium shall be jointly and
severally liable and responsible for the successful performance of the Contract,
including but not limited to completion within the stipulated time, adherence to
technical specifications, quality standards, and fulfilment of all contractual obligations.
The JV/Consortium Agreement shall explicitly state that each partner assumes full
responsibility for the acts, omissions, defaults,and liabilities of the other partner(s), and
that GETCO shall be entitled to enforce the Contract against any or all partners
individually or collectively at its sole discretion, failing which the bid from the
JV/Consortium shall be deemed non-responsive and non-compliant and shall be
rejected. Further, and a Joint Deed of Undertaking in favour of GETCO as per
Annexure-C (SCC) jointly signed by the partners of the JV shall also be submitted
along with its bid. Suitable Power of Attorney/Board Resolution authorizing the
signatories on behalf of each partner shall also be submitted along with the bid.
(III) The Joint Venture/Consortium shall collectively meet the complete technical
experience requirements as specified under Route-1 in respect of manufacturing
(including supply) and erection of 66kV or above voltage class XLPE cables, with each
Partner meeting the respective requirements specified below.
(a) OEM Partner Requirements:
One partner of the JV/Consortium must be an Original Equipment Manufacturer (OEM)
with experience in design, manufacturing, and supply of the required cables, and must
meet the qualifying requirements as per Route-1 (II) (a), as follows:
Supply Experience: Cumulatively designed, manufactured, type tested and supplied
a minimum of 50 km length of 66kV or above voltage class XLPE cable during the last
seven (7) years preceding the date of NIT, to one or more Transmission Utilities or
major industries either directly or through subcontractor. Additionally, out of the
aforesaid cumulatively supplied length, the OEM partner shall submit satisfactory
performance certificate(s) evidencing that a minimum of 10 km length of 66kV or above
Seal & Signature of Bidder
voltage class XLPE cable has been in satisfactory service for a minimum period of two
(2) years as on the date of NIT, issued by the Transmission Utility or major industry.
(b) Erection Partner Requirements:
The other partner of the JV/Consortium must have experience in erection of the
required cable systems, as defined under Route-1 (II) (b), as follows:
Erection Experience: Erected at least 20 Rkm route length cumulatively of 66kV or
above voltage class XLPE cables during the last seven (7) years preceding the date
of NIT with one or more Transmission Utilities or major industries. Out of which at
least one line should of minimum 2km route length. Subletting work experience shall
not be counted unless authenticated by order placing authority (CE(P&C)/
CE(Project)/CE(AM)).
(IV) Performance:
The collective performance requirement shall be considered met if:
(a) at least one (1) cable line of 66kV or above voltage class, manufactured and supplied
by the OEM Partner, has been in satisfactory operation for not less than one (1) year
as on the date of NIT; and
(b) at least one (1) cable line of 66kV or above voltage class has been erected by the
Erection Partner, as per clause (III)(b) above, and has been in satisfactory operation
for not less than one (1) year as on the date of NIT,
wherein, the cable line(s) referred to in (a) and (b) above may relate to the same
project, i.e., where the cable was manufactured and supplied by the OEM Partner and
erected by the Erection Partner, or to different projects, with each partner
independently executing its respective scope of supply or erection in its own project.
(V) Documentary Evidence:
The JV bidder and each JV Partner must provide comprehensive documentary
evidence in the bid demonstrating their respective qualifying experience:
OEM Partner: Manufacturing credentials, supply certificates, and performance
certificates in support of the requirements specified in clause (III)(a) and clause (IV)(a)
Erection Partner: Erection completion certificates and performance certificates in
support of the requirements specified in clause (III)(b) and clause (IV)(b) above; and
Same-project evidence: Where the cable line(s) relied upon under clause (IV) relate
to the same project, documentary evidence establishing that the cable on that project
was manufactured and supplied by the OEM Partner and erected by the Erection
Note: To have clarity to all bidders participating through all above routes i.e.
Route-1, Route-2 & Route-3- “In the event of a Joint Venture (JV) between the
OEM and the Agency, the OEM shall be responsible for the supply of cables,
while the Agency shall be responsible for cable laying, erection, installation, and
Seal & Signature of Bidder
related execution activities at site.”----Bidders past experience will be
considered accordingly.
2.0 FINANCIAL QUALIFYING CRITERIA: -
2.1 MAAT (Minimum Average Annual Turnover)
Route -1 & Route -2 :- Bidder’s Minimum Average Annual Turnover (MAAT) for best
three years out of last five financial years shall not be less than the 50% of estimated
amount of tender.
Route -3 :- Minimum Average Annual Turnover (MAAT) of the consortium/ Joint
Venture (JV) company added together for best three years out of last five financial
years shall not be less than the 50% of the estimated cost. However Minimum Average
Annual Turnover (MAAT) for best three years out of last five financial years of the lead
partner shall be at least 25% of the estimated cost & for each other partners shall be
at least 17% of the estimated cost
Note:- For the purpose of arriving at MAAT, Turnover shall be taken as revenue from
operation (excluding GST) as stated in Financial statement of the bidder, but excluding
2.2 Liquid Assets
Route -1 & Route -2 :- Last Financial Year Liquid Assets should not be less than 20%
of estimated cost of tender.
Route -3 :- Last Financial year liquid asset of the consortium/ Joint Venture (JV)
company added together should not be less than 20% of estimated cost of tender.
However Last Financial Year Liquid assets of the lead partner shall be at least 10% of
estimated Cost of tender and for each other partners shall be at least 7% of estimated
cost of tender.
Note: For the purpose of arriving at Liquid Assets Current Assets Less Inventories
shall be considered.
Bidder’s Networth for last Financial Year should be positive including all JV Partners
Note: Net Worth means Paid-up Share Capital, Share Application Money pending
allotment and Reserves & Surplus less Accumulated Losses and Deferred revenue
expenditure/Miscellaneous Expenses to the extent not Written Off.
Reserves and Surplus to be considered for the purpose of net worth shall be all
reserves created out of the profits and securities premium account but shall not include
reserves created out of revaluation of assets, write back of depreciation and
Share Application Money pending allotment will be considered only if it is in respect of
shares to be allotted.
Seal & Signature of Bidder
Bidder to submit the following documents in support of meeting financial qualifying
1. CA Certificate with valid UDIN Number failing which certificate shall not be
considered for the purpose of evaluation and Audited Balance Sheet and Profit & Loss
account along with the schedules referred therein and the Auditor’s Report for the
preceding five financial years, in line with one of the following
2. In case last financial year’s closing date was within 6 months prior to bid due date
and audited Balance Sheet and Profit & Loss account of last financial year are not
available, bidder has the option to submit the financial details of five previous years
immediately prior to the last financial year. For example, in case bid due date is up to
30th September and financial details of immediate preceding financial years (year
ending 31st March of same year) are not available, the financial details of the five
previous years immediately prior to the last financial year may be submitted.
3. Otherwise it is compulsory to submit the financial details of immediate preceding
five financial years.
4. In case bidder is a holding company, the Financial Position criteria referred to in
Financial Qualification criteria shall be that of holding company only (i.e. excluding its
subsidiary / group companies). In case bidder is a subsidiary of a holding company,
the Financial Position criteria referred to above shall be that of subsidiary company
only (i.e. excluding its holding company).
5. In case the date of constitution / incorporation of bidder is less than five years old
the MAAT in respect of the completed financial year after the date of constitution shall
be taken into account. Provided further that the date of constitution / incorporation of
the bidder shall not be less than one year old and audited financial statements of at
least one completed financial year is available.
Details as per qualifying requirement to be submitted along-with offer, in a separate
CA certificate to be attached for MAT. (This is must)
Supply/Order executed details for offered items with name of purchaser, date and
location to be mentioned.
Performance certificate for satisfactory operation/working for period as per qualifying
requirement attached with specification. (This is must for getting the offer qualified)
6.0 Additional Documents:
Apart from various documents to be furnished along with the Bid as required in the
GCC and ECC, the following documents / details are to be furnished by the Bidder:
1. GST Registration No. date/ issuing authority.
2. Regn. No. under Shops & Estt. Act/ issuing authority
3. Details of Partners/Directors of the Firm/Company.
4. Experience Record and details of orders pending / executed for various utilities
5. Last five years Audited Accounts
6. Detail of Manufacturing /Fabrication facilities if applicable
7. Factory Registration/license details if applicable
8. Solvency certificate from Bank (up to 20 % of Bid value)
Seal & Signature of Bidder
7.0 COMPLETION PERIOD
7.1 Overall Completion periods for this Contract will be 12 (Twelve) calendar
months from the date of Commencement.
7.2 If the execution period falls between the predictable/seasonal rain period i.e.
1st June to 30th September, the applicable period is to be excluded from the
execution time as per standard guidelines issued by various municipal
authorities while issuing the permission for cable laying within the limits of the
7.3 However, it should be noted that whenever the clear work front is available for
execution of the work and the statutory permission is not restricting for work
execution during the rain period, the work should be executed as per instruction
of E-I-C. For such instances, the period mentioned above shall be considered
under execution period. Proper records with relevant documents for the same
shall be kept by the successful bidder while executing the work.
7.4 No mobilization period, idling will be allowed during the period of the Contract.
7.5 The completion date will be deemed to be the date on which all works on the
Contract are demonstrated to be complete to the satisfaction of the
GETCO/Engineer and is complete in all respects as per the terms and
conditions of this Contract.
8.0 SECURITY DEPOSIT-CUM-PERFORMANCE GUARANTEE DEPOSIT
8.1 The supplier shall submit the Security Deposit / Performance Bank Guarantee
to cover execution period by DD / Bank Guarantee within 15 days from the date
of issue of Letter of Acceptance (LOA).
8.2 The successful bidder will be required to pay an amount equivalent to 10 % of
the value of the order (END cost) as a Security Deposit for satisfactory
execution of the contract and as performance guarantee. Such Security Deposit
will be payable either in DD payable at Vadodara / Bank guarantees from
Scheduled / Nationalized Banks will be acceptable, if the amount of security
deposit payable exceeds 50,000/- Bank Guarantees will be furnished. The
Bank Guarantees furnished should have clear one time validity till the
completion of the order in all respect and up to the expiry of the Guarantee
period of 25 Months (2 years +1 month) from the date of Commissioning of
Transmission line. Bank Guarantee for interim period will not be allowed. If by
any reason the contract period is extended, then contractor should undertake
to renew the Bank Guarantee at least one month before the expiry of the validity
failing which Board will be at liberty to redeem the same, without entering into
further correspondence in the matter.
8.3 No interest will be allowed on amount of Security deposit.
8.4 The Security Deposit-cum-performance Guarantee deposit as above on total
shall be kept deposited up to 2 years + 1 month from the date of charging of
Seal & Signature of Bidder
8.5 This security deposit is for the performance of contract and the same is liable
to be forfeited by the GETCO in event of non-fulfillment of the term and
conditions of this contract by the contractor.
8.6 Corporate Guarantees are not admissible.
8.7 The ‘Signing of Contract’ and ‘Contract Agreements’ will be done as per
prevalent GETCO Terms and Conditions.
8.8 A/T shall be issued on receipt of Bank Guarantee, contract agreement &
Indemnity Bond within 30 days of issue of LOA.
8.9 Further, in case of the bid to be furnish as a JV/Consortium partner then each
JV/Consortium partners has to furnish 5% of the overall tender cost towards the
B.G. in addition to the 10% of the Bank Guarantee to be submitted by the lead
partner (as security deposit). The terms, conditions & validity of all such BG’s
shall be the same.
9.0 Instructions before submitting your bid.
9.1) All the drawings, i.e. elevation, side view, plan, cross sectional view etc., in
AutoCAD DXF format and manuals in PDF format, for offered item shall be
submitted by successful bidder. Also the hard copies as per specification shall
9.2) The bidder shall submit Quality Assurance Plan (QAP) & Field Quality Plan (FQP)
with the technical bid.
9.3) The bidder must fill up all the point of GTP for offered item/s. Instead of indicating
“refer drawing, or as per IS/IEC”, the exact value/s must be filled in.
9.4) All the points other than GTP, which are asked to confirm in technical
specifications must be submitted separately with the bid.
9.5) Please note that the evaluation will be carried out on the strength of content of
bid only. No further correspondence will be made.
9.6) The bidder shall bring out all the technical deviation/s only at the specified
9.7) The bidder shall bring out all the technical deviation/s only at the specified
9.8) Preparing of Erection Key Diagram (EKD) indicating all the quantity required for
successful erections, testing and commissioning of line is in Bidders scope.
9.9) All equipments, material shall be supplied as per approved EKD (Drawing/BOQ).
9.10) Bar chart with completion period of 12 (Twelve) months in MS Project shall be
9.11) For all straight joints, contractor has to provide B.B. masonry chambers as per
instruction of engineer in charge.
9.12) In entire cable trench, RCC precast slab is to be provided on both the side &
upper side of power cable for protection purpose as per specifications.
9.13) Please refer specification of end termination, Straight through Joint, Link box
with or without SVL for providing & fixing arrangement.
9.14) It will be necessary for the successful Bidder to arrange technical supervision
during installation of cable laying and termination.
9.15) The successful Bidder shall arrange for the services of fully qualified and
competent supervising Engineer / Engineers and necessary minimum number
of jointers, semiskilled labourers, as he deems it absolutely necessary.
Seal & Signature of Bidder
9.16) Provision of special tools / appliances required for conductor jointing and
stripping /dressing and application of XLPE insulation etc. shall be made by the
successful Bidder.
9.17) The successful Bidder shall furnish all necessary information, including
drawings, manuals and instructions relating to both cable laying and jointing
9.18) The associated civil works, which are necessary in laying / installation of power
cable, though not specifically mentioned, but shall be completely in the scope of
successful Bidder.
9.19) No idling charges or cost over run for the entire project shall be entertained.
9.20) The cables shall be completely surrounded by a layer of having a low thermal
resistivity (selected sand) sand as per specification over & below of the cable
surface throughout width of the cable trench at no extra cost. (River sand shall
be allowed for surrounding layer)
9.21) The scope of work shall also include assistance in obtaining required permission
/approval from various statutory authorities i.e. Municipal Corporation, Gram
Panchayat (if any), PWD, Electrical Inspector, Telecom Department etc.
Payment demanded by any statutory authority as a compensation shall be
reimbursed by GETCO on submission of documentary evidence i.e. receipt of
such payment made.
9.22) Wherever it is required to cross the cable through Railways/Highways(Roads)/
Nala/ Canal/Gas lines/ Water supply & sewerage lines etc.; the bidder has to
carry out the excavation as per the requirement of respective department
ensuring full safety and through using HDD Machine Only as per instruction of
EIC. The depth of the excavation may vary with respect to different utilities. For
all above requirement, bidder should not claim any extra money on account of
deep excavation.
Being Turnkey contract any missing items in BOQ are to be supplied by
Agency free of cost to GETCO.
9.23) After the commissioning of line, contractor shall arrange thermos scanning of
joints/termination & submit detailed reports. However, this will not be
contractual hold point. GETCO reserves the right to ask the contractor to
conduct the same on entire line under full load condition.
9.24) All earthpits shall be Maintenance free as per specifications and approval from
Engg. Or Site in charge.
9.25) The required Earthing strips, Maintenance free treated Earthpits etc. are
inclusive part of contract and prices shall be quoted accordingly. No separate
price shall be paid for that.
9.26) All civil work e.g joint pits, Otta for SVL Boxes etc. are considered inclusive part
of respective line items and shall be considered in prices. No separate price shall
be paid for that.
9.27) All the materials shall be supplied as per GETCO Technical Specifications and
GETCO approved vendor only. All work has to be executed as per GETCO FQP
9.28) Cable remains in air is not part of U/g cable laying. However, it is to be covered
under the part of terminations on tower/H frame/ respective substation area.
Seal & Signature of Bidder
9A) Interse reverse bidding:
For the tenders having estimated value more than 5 Crore, The Interse
reverse bidding shall be carried out on the same day of price bid opening.
The L1 price shall be put up for starting price for Interse reverse bidding. Interse
reverse bidding shall be for reducing the price and the bidders have to reduce
their quoted price in decrement of value as decided before start of Interse
reverse bidding.
If any bidder bids in last 2 minutes of deadline for submission of bid for Interse
reverse bidding then, the time for Interse reverse bidding shall be extended for
further 5 minutes from its previous closing time.
Time of the Interse Revised Bidding shall be intimated to bidder along with the
intimation of price bid opening.
The procedure to be followed for elimination of Bidders for Interse reverse bidding
shall be as below:
Sr. No. of Particulars
1 1 No scope of bidding. Re-invite tender
2 2 Scope of Interse reverse bidding. No elimination.
3 3 or 4 Scope of elimination:
(A) Within 10% of L-1 bidder price - No elimination.
(B) Above 10% of L-1 Bidder price - Eliminate H1
4 5 or more Scope of elimination:
bidders (A) Within 10% of L-1 bidder price - No elimination.
(B) Above 10% of L-1 Bidder price - H1 and H2 to be
Bidder has to register themselves on following website and submit E-Auction
ID with EMD cover: https://e-auction.nprocure.com/.
It is mandatory to submit the same along with physical Technical bid (In EMD
cover); so that the bidder shall be allowed to participate the Interse reverse
After Interse reverse bidding process, L1 bidder shall be decided on lowest
The L1 bidder after Interse reverse bidding shall have to submit break-up in line
with their quoted price bid within three days.
GETCO at its discretion may call L1 bidder for negotiation. The price bid of
qualified bidders shall be shared after completion of Interse reverse bidding.
10.0 Addendum to the technical specifications.
The addition /alternations mentioned here under will supersede the related
clauses of respective technical specifications, if differs with original clause.
Seal & Signature of Bidder
All the hardwares, conductor accessories, clamps and connector used in
switchyard erections shall have corona free performance and related type tests
as per standards shall have to be submitted.
1. All the accessories, clamps and connector used shall have corona free
performance and related type tests as per standards shall have to be
2. All testing and measurement for all the equipments/materials shall have to
be measured in presence of site in charge of GETCO and complete record
should be included in as built drawing/document set.
Successful bidder has to arrange training at their expense at GETCO
premises covering erection, O&M, testing & commissioning aspect of 66 KV
cable line. This training program is to be organized prior to erection of these
Complete training materials in soft & hard copy shall be given to participants.
12. Progress Report (Refer Cl. No. 9.00 of ECC)
The successful bidder shall submit progress report monthly for supply activities &
fortnightly for erection activities along with site photographs.
13. Guarantee (Refer GCC Cl. No. 37.1)
Commencement of Guarantee period could be considered in phase manner as per
owner’s requirement to commission portion of job as per scope & specification on
priority. Site in charge accordingly in such condition will issue TOC and relevant
clause of guarantee shall be applicable.
14. Welfare Cess
As per the Welfare Cess Act, the welfare cess @ 1% is applicable on supply and
erection items for supply, erection, testing & commissioning of substation,
transmission lines, EPC/Turnkey projects and civil works. The welfare cess@1%
shall be paid by the contractor and the same shall be reimbursed by employer
on production of documentary evidence of payment.
Contractor shall get registered under Welfare Cess Act before commencement
of work. Office of the Factory Inspector is authorized at present as a registering
GETCO shall pay the welfare cess by way of reimbursing to contractors on
production of documentary evidence of payment.
The contracts for which supply or part supply of material are in the scope of
GETCO, then contractors shall deposit welfare cess on estimated cost of
supplied items to GETCO on progressive basis of utilization. As this part of
welfare cess is on GETCO account, the same shall be reimbursed to the
contractor on receipt of request letter along with documentary evidence of
payment. For calculation of welfare cess on supply part, valuation as per MR
shall be taken and informed to the contractor for payment. This will be over and
above the A/T value.
Seal & Signature of Bidder
The welfare cess@1% is not considered in the estimate for this project and
therefore, bidders are requested not to load welfare cess in the price
schedules as welfare cess@1% is on reimbursement basis.
15. Clarification on the tender documents if any shall reached to ACE (Procurement
& Contracts) on or before 10 days of due date. Clarification received thereafter
will not be considered & out Rightly ignored.
16. Payment (refer GCC Cl. No 47.0)
Successful bidder must submit “No Claim certificate “along with final bill.
Tender specification gives only BOQ asking for unit rate & accordingly bidder
shall quote the prices against each unit and payment will be made accordingly.
Price break up if any for supply items will be considered for billing purpose & not
for actual payment.
17. RIGHTS OF THE OWNER:
Whenever any claim or claims for payments of a sum of money arises out of or
under the contract against the Contractor, the Owner shall be entitled to withhold
and also have a lien to retain such sum or sums in whole or in part from the
security, if any, deposited by the Contractor and for the purpose aforesaid, the
Owner shall be entitled to encash and withhold the amount of Performance Bank
Guarantee or other security, if any, furnished as the case may be. The Owner
shall also have a lien over the same pending finalization or adjudication of any
such claim. In the event of the security is insufficient to cover the claimed amount
or amounts, the owner shall be entitled to withhold and have lien to retain to the
extent of the such claimed amount or amounts referred to above, from any sum
or sums found payable or which at any time-thereafter may become payable to
the Contractor under the same contract or any contract with the Owner or GUVNL
or its subsidiary companies pending finalization or adjudication of any such claim.
Lien in respect of Claims in other Contracts:
a) Any sum of money due and payable, to the Contractor (including the security
deposit) under the contract may be withheld or retained by way of lien by the
Owner against any of its claim in respect of payment of a sum of money arising
out of or under any other contract made by the Contractor with the Owner or
GUVNL or any of its subsidiary companies.
b) It is an agreed that the sum of money so withheld or retained under this clause
by the Owner will be kept withheld or retained as such by the Owner till its claim
arising out of the same contract or any other contract is either mutually settled or
determined by the arbitrator or competent court, as the case may be, and the
Contractor shall have no claim for interest or damages whatsoever on this
account or on any other ground in respect of any sum of money withheld or
retained under this clause and as may be duly notified to the Contractor.
18. For necessary payment against each consignment of material along with 100% taxes, duties, F
& I shall be duly recorded in the form of TRC & SR note by the field office and works related bills,
which shall be now uploaded on Vendor Management System (VMS) Portal, www.vms.guvnl.com
including invoice, documents which are digitally signed by Vendors / Suppliers/Contractors. The
supporting documents duly signed, stamped and scanned are required to be uploaded. The VMS
Seal & Signature of Bidder
portal also provides ‘real time’ tracking of invoice status, to monitor the process of submissions
and to receive timely updates.
Seal & Signature of Bidder
Tender No. ACE(P&C)/Contract/E-512/UG/66kV/S&L,E
Tender for Supply, Laying, Erection, Testing and Commissioning of 66kV,1CX630
sqmm XLPE Cable with Poly.Al./Aluminum construction on EPC basis Various
lines under Navsari Circle as per tender specifications complete along with all the
tender Terms and Conditions.
In connection with above subject, I / we confirm the following:
a) I/ We, the undersigned, have read and understand the Tender Specification No.
ACE(P&C)/Contract/E-512/UG/66kV/S&L,E
b) The supply & erection price components in the bid are firm prices in line with
Tender Specifications and shall stand valid till completion of the Contract, if awarded.
c) I/We declare that our bid is strictly in line with Tender Specifications and there is
no deviation. Further, I / we also agree that additional conditions / deviations, if any
found in bid, the offer shall be out rightly rejected without assigning any reason thereof.
Signature of Authorized representative
of Company / Agency
Seal & Signature of Bidder
Vendor must fill up below details & should place at the top of the Technical Bid.
[FIRM ONLY] (Please specify YES / No.)
[IN PERCENTAGE]
Please quote your
a. GST Registration No. & Date. :
b. PAN No. & Date :
c. PF Registration No. :
3. PENALTY TERMS AGREE :
(Please specify YES / No.)
4. SECURITY TERMS AGREE :
(Please specify YES / No.)
5. P.B.G. TERMS AGREED (Wherever applicable) :
(P.B.G. – Performance Bank Guarantee)
6. PAYMENT TERMS AGREE :
(Please specify YES / No.)
7. WORK INVOLVED :
8. TELEPHONE NOS , Mail Id & FAX NO. :
9. AUTHORISED PERSON OF THE FIRM :
10. NAME OF THE PROPRIETOR, :
PARTNERS, DIRECTORS
[AS THE CASE MAY BE],
ALONG WITH ADDRESS, TELEPHONE,
11. If Vendor Registration is Done :
(Please Furnish the details of Vendor
Registration No. )
Signature of Authorized representative
of Company / Agency
Seal & Signature of Bidder
CONTRACT AGREEMENT
(Non-judicial stamp paper of Rs. 300/- )
This agreement is made at Vadodara, the _________________day of __________in
the Christian year Two Thousand Five between
referred to as “THE CONTRACTOR” which expression shall unless excluded by or
repugnant to context include its successors or permitted assigns) of the one part and
the Gujarat Energy Transmission Corporation Limited, having their Corporate Office
at Race Course, Vadodara, (hereinafter called “Corporation” which expression shall
unless excluded by or repugnant to the context include its successors or assigns) of
the other part.
“WHEREAS” the aforesaid Corporation has accepted the tender of the aforesaid
_____________________________________________ as per Corporation’s Order
No. ____________________________________ hereinafter called “The works” and
more particularly described enumerated or referred to in the specification, terms and
conditions prescribed in the order letter, covering letter arid other letters and
schedule of price which for the purpose of identification have been signed by Shri
__________________________________________ on behalf of the Contractors
Corporation, a list where of is made out in the schedule hereunder written and all of
which said documents are deemed to form part of this contract and included in the
expression ‘The Works” wherever herein used, upon the terms and subject to the
conditions hereinafter mentioned AND WHEREAS THE GETCO has accepted the
tender of the contractor for the work of _____________ for the sum of
terms and subject to the conditions herein mentioned.
NOW THIS AGREEMENT WITNESSES AND IT IS HEREBY AGREED AND
DECLARED THAT :
1. The contractors shall do and perform all works and things in this contract
mentioned and described or which are implied therein or there from respectively or
are reasonably necessary for the completion of the works as mentioned and at the
times, in the manner and subject to the terms conditions and stipulations contained
in this contract, and in consideration of the due provision, executions, construction
and completion of the works agreed to by the contractors as aforesaid, the
Corporation doth hereby covenant with the contractor to pay all the sums of money
as and when they become due and payable to the contractors under the provisions
of the contract. Such payment to be made at such times and in such manner as is
provided by the contract.
2. The conditions and covenants stipulated hereinbefore in this contract, are
subject to and without prejudice to the rights of the Corporation to enforce penalty
for delays and / or any other rights whatsoever including the right to reject and cancel
on default or breach by the contractors of the conditions and the covenants as
stipulated in the general conditions, specifications, forms, or tender schedule,
drawing, etc. attached with Corporation’s Order
The contract value, extent of works / supply, completion / delivery dates,
specifications and other relevant matters may be altered by mutual agreement and
if so altered shall not be deemed or construed to mean or apply to affect or alter
other terms and conditions of the contract and the general conditions and the
contract so altered or revised shall be and shall always be deemed to have been
subject to and without prejudice to said stipulation.
Seal & Signature of Bidder
List of documents forming part of the contract:
1) Corporation’s Tender Specification No-
ACE(P&C)/Contract/E-512/UG/66kV/S&L,E
2) Corporation’s Contract booklet – “Tender & Contract of Works”.
3) Corporation’s A/T No
4) A/T Acceptance letter no.
5) Memorandum & Article of Association.
6) Board Resolution authorizing person to sign on behalf of firm.
In witness whereof the parties hereto have set their hands and seals this day and
month year first above written.
Signed, Sealed and Delivered by
In the presence of, signature with names and
Signed, Sealed and Delivered by
for and on behalf of Gujarat Energy Transmission Corporation Limited,
Sardar Patel Vidyut Bhavan,
Race Course, Vadodara -390
In the presence of, signature with names and
Seal & Signature of Bidder
(On stamp paper of Rs 300/-)
E.M.D BANK GUARANTEE FORMAT
Format for EMD BG is attached separately.
Seal & Signature of Bidder
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
4. EMD BG Format.pdf
EMD BG Format.pdf
Erection BOQ for Reference.pdf
Supply BOQ for Reference.pdf
Form for Networth Annual turnover LA.pdf
Public Procurement Circular of GOI.pdf
SD cum PBG Format.pdf
48F FODP Ref Drg-1.pdf
48F FODP Ref Drg-2pdf.pdf
End to End Test Final.pdf
Joint Box FOAC-OPGW Ref Drg-2.pdf
Joint Box FOAC-FOAC Ref Drg.pdf
OFC Underground cable Manhole Chamber.pdf
1. 66 kv MOC 3 plus 1 29.10.2025 R4.pdf
02_TOWER MATERIAL-66KV LINE-PANTHER.pdf
2 66KV MOC 6 plus1 DT. 29.10.25 R3.pdf
3 66KV MOC 2plus 1 DT. 29.10.25 R2.pdf
4 66KV MOC 2x6 plus0 DT. 29.10.25 R2.pdf
66 KV LA R6 June 22.pdf
66KV 630 SQ MM - ALUMINUM CORRUGATED -R5 Print.pdf
66KV 630 SQ MM 1C POLY AL POLY-R4 - Print Copy 08.07.22.pdf
66KV CABLE TRENCH APPROVED DRAWING 10.04.19.pdf
G.I. EARTHING STRIPS.PDF
MOC 66 kV cable 13.01.22 CE(Project) letter.pdf
Notes for FOAC laying.pdf
Standard MQP GI Tower material for issuence to SUPPLIER COPY.PDF
TS LAYING CABLE 66KV R2 new - Final.pdf
1. Tender Specification Part-I 66kV UG_Navsari Circle.pdf
2. Amendment -I Part-I Tender Spec 66kV UG_Navsari Circle.pdf
3. Tender Notice E-512 66kV Navsari EPC.pdf
Corrigendum No. 1 Date Extension.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .