Executive Engineer, Rajkot Irrigation Division, Rajkot.
VENU-II IRRIGATION SCHEME. Repairing and Strengthening of Bridge and Parapet of spillway of Venu-II Irrigation Scheme
279930
SBD-22 of 2025-26
Open
Civil - All
Works
Rajkot
5 documents required · 5 mandatory
₹3,600
Yes
Executive Engineer, Rajkot Irrigation Division Rajkot
₹2.0 L
Yes
23 Feb 2026
23 Feb 2026
23 Feb 2026
9 Mar 2026
23 Feb 2026
NAME OF WORK :-
Repairing and Strengthening of Bridge and Parapet of spillway of Venu-II Irrigation Scheme
BILL OF QUANTITIES (SCHEDULE - B)
(A) Percentage Rate Tender (Upto Rs. 50 Crore)
Item Description of Item Quantity Unit Estimated Rate Amount
No. (with brief specification and reference to book of specifications) In Figure In words
1 Dismantling of RCC work viz. slab, beam, lintel, barrel, staircase, etc. 36.10 Cum. 1362.00 Rupees: One Thousand
including removing the steel from the dismantled portion without damage to Three Hundred Sixty Two
reinforcement sorting and stacking of useful and unuseful material from the Only.
dismantled material as directed etc comp.
2 Dismantling C.C. foundation or flooring sorting & stacking useful and 218.10 Cum. 828.00 Rupees: Eight Hundred
unuseful material in lead upto 200mt as directed etc. complete. Twenty Eight Only.
3 Prov. & Laying. in position controlled cement concrete using cement, sand 27.50 Cum. 5081.00 Rupees: Five Thousand
and crushed metal aggregate by machine mix for R.C.C work incl. Eighty One Only.
necessary formworks, centring, scaffolding, compaction by mechanical
vibrator, curing as directed with all lead & lift etc complete Excluding the
cost of reinforcement.
2/f) Concrete grade M-25 and MSA - 20mm(Graded)
4 Prov. & Laying. in position controlled cement concrete using cement, sand 95.30 Cum. 4660.00 Rupees: Four Thousand Six
and crushed metal aggregate by machine mix for R.C.C work incl. Hundred Sixty Only.
necessary formworks, centring, scaffolding, compaction by mechanical
vibrator, curing as directed with all lead & lift etc complete Excluding the
cost of reinforcement.
For Wearing coat 75 mm thick..Filling expantion joint with asphalt 2/d)
Concrete grade M-25 and MSA - 20mm(Graded)
5 Prov. & Laying. in position controlled cement concrete using cement, sand 458.00 Rmt. 1522.00 Rupees: One Thousand
and crushed metal aggregate by machine mix for R.C.C work incl. Five Hundred Twenty Two
necessary formworks, centring, scaffolding, compaction by mechanical Only.
vibrator, curing as directed with all lead & lift etc complete Excluding the
cost of reinforcement.
For parapet up to 15 cms thick & 1.0 mt height
2/b) Concrete grade M-25 and MSA - 20mm(Graded)
Item Description of Item Quantity Unit Estimated Rate Amount
No. (with brief specification and reference to book of specifications) In Figure In words
6 Providing, cutting, bending, binding and fixing in position as per drawing 2.90 Rmt. 76574.00 Rupees: Seventy Six
.TMT BAR, reinforcement for R.C.C. works and anchor bars incl cost of Thousand Five Hundred
black annealed 16 to 18 BWG M.S.. Wire etc. complete with all lead and lift. Seventy Four Only.
7 Surface preparation by chipping/dismantling of the damaged concrete 1214.00 Sqm. 576.19 Rupees: Five Hundred
members by removing loose, cracked and unsound concrete to expose Seventy Six & Ps. Ninteen
steel reinforcement completely using heavy duty mechanical breakers with Only.
the required depth of cutting followed by cleaning the surface using High-
pressure water jet at suitable pressure to remove all loose particles,
organic matter, marine growth and impurities from the concrete surface
making it suitable for repair inclusive all Manpower, Material and
8 Strengthening and repairing to cracks in masonry and concrete structure of 3692.00 One kg of 1266.00 Rupees: One Thousand
dams, like waste weir, HR, piers, bridge, etc. by injecting neat epoxy resin epoxy Two Hundred Sixty Six
and hardener in ratio 2:1 under pressure 3 to 7 kg/cm2 and pointing with material Only.
silica mortar with proportion in 1:1/2:6(1resin 1/2 hardener, & 6 silica)
9 Rust Removal & Steel Protection-Cleaning as directed & specified all 1214.00 Sqm. 871.41 Rupees: Eight Hundred
corrosion / rust / scales from reinforcement bars using rust remover leaving Seventy One & Ps. Forty
to dry for 30 mins & washing surface with fresh water as required to One Only.
exposed reinforcement bars complete as specified also providing &
applying inhibition coats/system to exposed reinforcement bars after
drying & also new bars after cleaning & removing scales and rust
completely as specified. Two component inhibitor make as approved by
engineer shall be used as per manufacturers specification is including all
labour tools tackles, necessary surface preparation & necessary protection
after & during repair work.
10 Epoxy bonding of new concrete Or mortar to old surface in structure with 1214.00 Sqm. 307.00 Rupees: Three Hundred
proper application of coat of resin and hardener in proportion of 2:1 by Seven Only.
weight confirming to IS-9197 to give proper bond between old surface new
concrete Or mortar etc complete
Item Description of Item Quantity Unit Estimated Rate Amount
No. (with brief specification and reference to book of specifications) In Figure In words
11 Providing and Applying/laying in position Poly ironite ceramic cementeous 61.00 Cum. 184837.00 Rupees: One lac Eighty
mortar for spillway ogee, piers, bridge over concrete as per direction and Four Thousand Eight
instructions. Hundred Thirty Seven Only.
Rupees: One Carore Ninety Eight Lac Eleven Thousand Nine Hundred Thirty Four & Ps. Fifty Only
I/We are willing to carry out the work at …………………………………………………………...% above/below percent (should be written in figure and words) of the estimated rates
mentioned above. The amount of my/our tender works out as under;
*Estimated amount put to tender Rs. ……………… *Estimated amount put to tender Rs. ………………
Deduct : ……… % below Rs. ………………. Add : ……… % above Rs. ……………….
Net : Rs. ……………… Total : Rs. ………………
In words : Rupees ………………………………………………………………………… In words : Rupees………………………………………………………
The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e.1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt.G.R.:PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in
S.O.R.thereforeinR.C.C.items where there is a change as per actual mix design the cost of difference of cement consumption have been deducted from the rate of original item
at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of contractor. Rajkot Irrigation Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1 Tender P 1 to 16.pdf
2- SBD Bridge Parapet - Venu-II P 1 to 187.pdf
3 Sch B - Bridge Parapet - Venu-II - P 188 to 190.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .