| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.8 LAdmitted-Finance | ₹2.8 L | L1 | Admitted-Finance |
| 2 | L2₹2.9 L+₹18,666.60 (6.76%)Admitted-Finance | ₹2.9 L+₹18,666.60 (6.76%) | L2 | Admitted-Finance |
| 3 | L3₹3.2 L+₹41,809.97 (15.1%)Admitted-Finance | ₹3.2 L+₹41,809.97 (15.1%) | L3 | Admitted-Finance |
| 4 | L4₹3.4 L+₹59,527.97 (21.6%)Admitted-Finance | ₹3.4 L+₹59,527.97 (21.6%) | L4 | Admitted-Finance |
| 5 | L5₹3.4 L+₹63,759.43 (23.1%)Admitted-Finance | ₹3.4 L+₹63,759.43 (23.1%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Jamshed L2 | M/S RADHIKA CONSTRUCTION COMPANY L4 | M/s R.K.Constructions L5 | Shahbaz Khan L3 | RIYAZ KHAN L1 |
|---|---|---|---|---|---|---|---|---|
| 1.00 | E/W in embankment for making the road Diversion of Gorkha Dy. including all leads & lifts with proper dressing & manual compaction for proper compleation of work but excluding G.S.T | 302.93 | Cu M | 150 ₹45,439.5 | 50 ₹15,146.5 Lowest | 203 ₹61,494.79 | 190 ₹57,556.7 | 50 ₹15,146.5 Lowest |
| 2.00 | Dismantling brick work or stone work in lime or cement mortar including stacking of material as directed by Engineer-in-charge within a distance of 60 M But excluding GST | 0.41 | Cu M | 570 ₹233.7 | 500 ₹205 | 480 ₹196.8 | 449 ₹184.09 Lowest | 500 ₹205 |
| 3.00 | Dismantling Reinforcement cement concrete including stacking of dismantled material as directed by Engineer-in-charge within a distance of 60 M.but excluding GST | 1.75 | Cu M | 750 ₹1,312.5 | 700 ₹1,225 | 630 ₹1,102.5 | 591 ₹1,034.25 Lowest | 700 ₹1,225 |
| 4.00 | Ist class brick work in 1:4 C.M. with coarse sand of F.M. not less than 2.0 including cost of all material, labour and T&P. required for proper completion of work but excluding GST | 5.07 | Cu M | 6,000 ₹30,420 | 7,200 ₹36,504 | 6,100 ₹30,927 | 5,692 ₹28,858.44 Lowest | 6,000 ₹30,420 |
| 5.00 | S/F 20 mm thickness joint filler board in expansion joint including cost of all material labour and T&P etc required for proper compaction of work but excluding GST. | 4.78 | Sq M | 1,000 ₹4,780 Lowest | 1,800 ₹8,604 | 1,672 ₹7,992.16 | 1,568 ₹7,495.04 | 1,900 ₹9,082 |
| 6.00 | Two coat of bitumen painting with 2 layers of Tarfelt again followed by 2 coat of bitumen painting before laying R.C.C. slab including cost of all material, labour and T&P etc. required for proper completion of work but excluding GST | 3.59 | Sq M | 238 ₹854.42 | 230 ₹825.7 | 200 ₹718 | 188 ₹674.92 Lowest | 200 ₹718 |
| 7.00 | Centering & Shuttering for R.C.C. work including cost of all material , Labour and T & P etc.required for compleation of work but excluding G.S.T | 11.3 | Sq M | 700 ₹7,910 | 900 ₹10,170 | 850 ₹9,605 | 788 ₹8,904.4 | 600 ₹6,780 Lowest |
| 8.00 | Cutting, bending, binding & placing of Steel reinforcement in proper position including cost of steel, binding wire, all material labour and T&P. etc.required for proper completion of work but excluding GST | 0.37 | MT | 70,000 ₹25,900 Lowest | 92,000 ₹34,040 | 79,030 ₹29,241.1 | 74,088 ₹27,412.56 | 94,080 ₹34,809.6 |
| 9.00 | Laying R.C.C. 1:1½ :3 using 4.75 mm to 20 mm size crushed stone grit with coarse sand having F.M not less than 2.0 including cost of all material, labour and T&P.,except steel, required for proper completion of work but excluding GST | 4.67 | Cu M | 9,000 ₹42,030 | 11,700 ₹54,639 | 9,686 ₹45,233.62 | 9,082 ₹42,412.94 | 8,000 ₹37,360 Lowest |
| 10.00 | Deep struck Cement Pointing in 1:2 CM with fine coarse sand including cost of all material, labour & T&P. required for proper completion of work but excluding GST | 20.21 | Sq M | 192 ₹3,880.32 | 180 ₹3,637.8 | 161 ₹3,253.81 | 151 ₹3,051.71 Lowest | 192 ₹3,880.32 |
Tender Value
₹4.0 L
EMD Value
₹8,080
Closing Date
20 Aug 2026, 1:00 pmClosed
Executive Engineer
Office of the Executive Engineer, Saryu Nahar Khand-I Nanpara, Bahraich
CONSTRUCTION OF C.C. LINNING ON SLOPE AT US AND DS OF VRB AT Km. 7.440 OF GORKHA DY.
2026_UPIDC_1176198_19
02/EE/2026-27
Open Tender
Civil Works - Canal
Item Rate
45 days
Nanpara
Plz refer Tender Documents
3 documents required · 3 mandatory
₹677
₹8,080
Yes
15 Sept 2026
12 Aug 2026
20 Aug 2026
12 Aug 2026
20 Aug 2026
12 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | E/W in embankment for making the road Diversion of Gorkha Dy. including all leads & lifts with proper dressing & manual compaction for proper compleation of work but excluding G.S.T | 302.93 | Cu M | 10 | ₹3,029.3 |
| 2 | Dismantling brick work or stone work in lime or cement mortar including stacking of material as directed by Engineer-in-charge within a distance of 60 M But excluding GST | 0.41 | Cu M | 10 | ₹4.1 |
| 3 | Dismantling Reinforcement cement concrete including stacking of dismantled material as directed by Engineer-in-charge within a distance of 60 M.but excluding GST | 1.75 | Cu M | 10 | ₹17.5 |
| 4 | Ist class brick work in 1:4 C.M. with coarse sand of F.M. not less than 2.0 including cost of all material, labour and T&P. required for proper completion of work but excluding GST | 5.07 | Cu M | 10 | ₹50.7 |
| 5 | S/F 20 mm thickness joint filler board in expansion joint including cost of all material labour and T&P etc required for proper compaction of work but excluding GST. | 4.78 | Sq M | 10 | ₹47.8 |
| 6 | Two coat of bitumen painting with 2 layers of Tarfelt again followed by 2 coat of bitumen painting before laying R.C.C. slab including cost of all material, labour and T&P etc. required for proper completion of work but excluding GST | 3.59 | Sq M | 10 | ₹35.9 |
| 7 | Centering & Shuttering for R.C.C. work including cost of all material , Labour and T & P etc.required for compleation of work but excluding G.S.T | 11.3 | Sq M | 10 | ₹113 |
| 8 | Cutting, bending, binding & placing of Steel reinforcement in proper position including cost of steel, binding wire, all material labour and T&P. etc.required for proper completion of work but excluding GST | 0.37 | MT | 10 | ₹3.7 |
| 9 | Laying R.C.C. 1:1½ :3 using 4.75 mm to 20 mm size crushed stone grit with coarse sand having F.M not less than 2.0 including cost of all material, labour and T&P.,except steel, required for proper completion of work but excluding GST | 4.67 | Cu M | 10 | ₹46.7 |
| 10 | Deep struck Cement Pointing in 1:2 CM with fine coarse sand including cost of all material, labour & T&P. required for proper completion of work but excluding GST | 20.21 | Sq M | 10 | ₹202.1 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.75 MB
Bid_Doc.pdf
Tender Documents • 1.45 MB
BOQ_2210626.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .