| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.8 LAccepted-AOC | ₹9.8 L | L1 | Accepted-AOC Lowest Bidder |
| 2 | L2₹10.1 L+₹34,514.67 (3.53%)Rejected-Finance | ₹10.1 L+₹34,514.67 (3.53%) | L2 | Rejected-Finance Higher Bidder |
| 3 | L3₹10.2 L+₹46,639.04 (4.77%)Rejected-Finance | ₹10.2 L+₹46,639.04 (4.77%) | L3 | Rejected-Finance Higher Bidder |
Tender Value
₹9.8 L
EMD Value
₹20,000
Closing Date
10 Feb 2026, 2:00 pmClosed
OFFICE OF THE DY.CE(WS/IGWTP)
OFFICE OF THE DY.CE(WS/IGWTP) IGWTP, MONIRAMPUR, BARRACKPORE, PIN-700120
DEVELOPMENT OF THE VERTICAL COLUMN AND ITS CENTRAL CIRCULAR DRUM DRIVING ASSEMBLY OF CLARIFIER BRIDGE NO-2 AT 60 MGD PLANT,IGWTP
2026_KMC_992694_1
KMC/WS/IGWTP/093/25-26, DT-19/01/2026
Open Tender
MECHANICAL
Percentage
45 days
IGWTP, MONIRAMPUR, BARRACKPORE
AS PER NIT
4 documents required · 4 mandatory
₹0
₹20,000
OFFICE OF THE DY.CE(WS/IGWTP)
4 Jul 2026
28 Jan 2026
12 Feb 2026
28 Jan 2026
10 Feb 2026
3 Feb 2026
30 Jan 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0 | PART-A | - | - | - | - |
| 1 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 10. Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. | 420.24 | SQUARE METER | 19 | ₹7,984.56 |
| 2 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](iii) With 1:3 cement mortar (a) 20 mm thick plaster (3rd Corrigenda & addenda dated 04.06.2018) | 420.24 | SQUARE METER | 213 | ₹89,511.12 |
| 3 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m. | 102.24 | SQUARE METER | 34 | ₹3,476.16 |
| 4 | MATERIALS AND LABOUR ETC.(C)-(I) MISCELLANEOUS 28.Cleaning rubbish, sludge, weeds scum, liquid earth, mud etc.etc.from road side masonary drain/ hume pipe drain/ culvert etc. by mathor labour after removing concrete.Slab/manhole cover etc.without damaging the same and refixing the same properly after cleaning as necessary and removing thesludge etc.etc.by using iron pans,buckets including all labour, tools & plants including removing the spoils in dry condition and disposing thesame by truck beyond the road side in conformity with municipal/corporation rules for such disposal including loading into truck and cleaning the road side in all respects as per direction of the Engineerin- Charge. (Payment will be made on the basis of actual stack measurment of spoils in dry condition at roadside) | 95.42 | CUBIC METER | 289 | ₹27,575.22 |
| 5 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc 10?. Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.(i) Pakur Variety | 4.13 | CUBIC METER | 4,482 | ₹18,492.28 |
| 6 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc.40..Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.(a) For works in foundation and upto roof of ground floor/upto 4 m.(i) Tor steel/Mild Steel.I. SAIL/ TATA/RINL. | 0.19 | MATRIC TON | 58,249 | ₹11,242.06 |
| 7 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: B. MAINTENANCE WORKS : 1) Repairing crack in wall by cement grouting (1 : 2) including widening the crack on the surface (into V section) cleaning and packing the same with cement mortar (1 : 2) and finishing off to match with adjacent surface. (Cement-69 Kg/100 m) | 250 | METER | 13.6 | ₹3,400 |
| 8 | BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 1. M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length,fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. I) For structural members of specified sections weighing less than 22.5 Kg./m (3rd Corrigenda & addenda dated 04.06.2018) | 1.06 | MATRIC TON | 72,603 | ₹76,852.45 |
| 9 | SUPPLY RATE OF FOLLOWING MATERIALS AS MANTIONED BELOW | 2,306.6 | KILOGRAM | 73 | ₹1,68,382.14 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.22 MB
093TECHBID.pdf
Tender Documents • 1.52 MB
BOQ_2427577.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .