| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 LAccepted-AOC | L1 | Accepted-AOC OK | |
| 2 | L2₹1.9 L+₹96.25 (0.05%)Rejected-AOC | L2 | Rejected-AOC OK | |
| 3 | L3₹1.9 L+₹134.75 (0.07%)Rejected-AOC | L3 | Rejected-AOC OK |
Tender Value
₹1.9 L
EMD Value
₹3,850
Closing Date
4 Dec 2025, 1:00 pmClosed
THE BDO/EO, MAL
O/O, THE BDO, MAL
CONSTRUCTION OF WAITING SHED AT SHIV MANDIR SYLEE CHEL LINE AT PART NO. 20/88 UNDER RUNGAMUTTEE G.P. GRAM PANCHAYET MAL BLOCK, JALPAIGURI, FUND- APAS. APAS ID - APAS/01/020/88/0005
2025_ZPHD_945104_5
WB/41/BDO/MAL/2025-26
Open Tender
CIVIL WORKS
Percentage
RUNGAMUTTEE GP
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹3,850
Yes
28 Jul 2026
12 Nov 2025
8 Dec 2025
12 Nov 2025
4 Dec 2025
12 Nov 2025
Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm.
Cement concrete with 30 mm down graded shingles excluding shuttering NB Variety (a) 1:3:6 proportion PWD (b) River bazree
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement, if any, in ground floor as per relevant IS codes (b) River bazree
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction (a) For works in foundation, basement and upto roof of ground floor/upto 4 m (1) Tor steel/Mild Steel
Hire ang your charges for shuttering with catering and using aperroved spread thick hardwood of withrequired braong for concrete te bedre and colure intere corved molusing feting finansing outer completion of works proof of proundfisor) (*) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-Charge (Payment will be made as per measurement)
125 mm thick brick work with 1st class bricks in cement mortar (1:4) in grourid floor
Plaster (to wall, floor, ceiling etc) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating nosing and drip course, scaffolding/staging where necessary (Ground floor) [Excluding cost of chipping over concrete surface) (b) 15 mm thick plaster
Supplying, fitting & fixing Zn-Al alloy (55% Al & 45% Zn) coating of 150 grams per minimum yield strength of 550 Mpa of trapizoidal profile of approved make (excluding the supporting frame work) fitted and fixed with 55 mm & 25 mm self tapping screw, EPDM Washer 16 mm dia & 3 mm th. washer etc. complete with 150 mm end lap and one corrugation minimum side lap. (Payment to be made on area of finished work) (i) In Roof-a) With 0.5 mm thick sheet
M.S structural works in roof trusses with tubular sections conforming to IS: 806-1968 & IS: 1161-1998 cnnected to one another with bracket, gusset cleats as per design, direction of Engineer-in-charge complete ncluding cutting to requisite size, fabrication with necessary metal arc welding conforming to IS. 816-1969 & IS 9595 using electrodes of approved make and brand conforming to IS 814-2004, haulage hosting and erection all complete The rate includes the cost of rolled steel section consumables such as electrodes, gas and hire charge of all tools and plants and labour regired for the work including all incidental chages such as electricity charges, labour insurance charges etc Payment to be made on the basis of calculated weight of structural tubular memebrs as specified in relevent IS code in finished work. Payment for gusset, bracket, cleat may be made by adding the actual weight of such items with weight of finished structural members. The rates are considered for a height of erection 6m/2nd floor level from the ground. Add 15% extra over the rate for each additional floor or Am bexond the intial & or part thereof
White washing including cleaning and smoothening surface thoroughly. All floors : (c) Three coats (on new works only). (Payment will be made as per
Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete (Payment to be made on the basis of measurement of finished quantity of work)
(A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand (payment to be made on measurement of finished quantity)
Supplying, Fitting & Fixing Information Board Steel size (4'-0"x3'-0")
Add:- GST @ 18%
Add:- Cess @ 1%
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.87 MB
BOQ_2245573.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .