| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹50.5 LAdmitted-Finance | -30.00% | ₹50.5 L | L1 | Admitted-Finance |
| 2 | L2₹51.6 L+₹1.1 L (2.11%)Admitted-Finance | -28.52% | ₹51.6 L+₹1.1 L (2.11%) | L2 | Admitted-Finance |
| 3 | L3₹52.1 L+₹1.5 L (3.03%)Admitted-Finance | -27.88% | ₹52.1 L+₹1.5 L (3.03%) | L3 | Admitted-Finance |
| 4 | L4₹52.1 L+₹1.5 L (3.04%)Admitted-Finance | -27.87% | ₹52.1 L+₹1.5 L (3.04%) | L4 | Admitted-Finance |
| 5 | L5₹55.5 L+₹4.9 L (9.71%)Admitted-Finance VILLAGE GWARAU KALAN HATHRAS HATHRAS UTTAR PRADESH 204212 | HATHRAS | UTTAR PRADESH | 204212 | -23.20% | ₹55.5 L+₹4.9 L (9.71%) | L5 | Admitted-Finance |
Tender Value
₹72.2 L
EMD Value
₹1.4 L
Closing Date
5 Aug 2026, 5:00 pmClosed
General Manager
Main administrative building, Sector-6, Noida
M/o Drain (Annual Repair and Maintenance of drains of Work Circle-7 area) Noida
2026_NOIDA_1171709_1
22/GM/SM/WC-7/ET/2026-27
Open Tender
Civil Works
Fixed-rate
365 days
NOIDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,832
NOIDA
₹1.4 L
17 Sept 2026
22 Jul 2026
6 Aug 2026
22 Jul 2026
5 Aug 2026
22 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar | 62.5 | Cum | 779.76 | ₹48,735 |
| 2 | Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in cement mortar | 6,250 | 1000 Nos | 2,569.38 | ₹1,60,58,625 |
| 3 | Demolishing RCC work manually by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. | 36.25 | Cum | 1,347.16 | ₹48,834.55 |
| 4 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 23 | Cum | 923.42 | ₹21,238.66 |
| 5 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m, as directed by engineer-in-charge. The Contractor has defect different utilities like sewer line, water supply line, electric cable, telephone cable , gas pipe line etc, using utility decteting machine before start of excavation and shall start excavation only after getting permission of Engineer-in-charge. | 86 | Cum | 136 | ₹11,696 |
| 6 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed,within a lead of 50 m. All kind of Soil. | 295.75 | Cum | 144.95 | ₹42,868.96 |
| 7 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 76.25 | Cum | 93 | ₹7,091.25 |
| 8 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all loads including all lifts involved. | 110.25 | Cum | 120.55 | ₹13,290.64 |
| 9 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level : 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). | 133.75 | Cum | 5,746.88 | ₹7,68,645.2 |
| 10 | Providing and laying C.C pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per Engineer- in -charge. (The panel shuttering work shall be paid for separately.) ( Note:- Cement content considered in this item is @330 Kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately). | 115.75 | Cum | 8,141.85 | ₹9,42,419.14 |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
TD.pdf
Tender Documents • 13.07 MB
BOQ_2199751.xls
BOQ • 0.39 MB
Capability.xls
Additional Documents • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .