Tender ID
Tender Value
₹1.9 Cr
EMD Value
₹1.9 L
Closing Date
22 Apr 2026, 6:00 pmClosed
Executive Engineer, S.B.C Division No-1/2, Dhandhuka
Pipe Diversion work on ODRB at Ch. 42.457 Km and VRB at Ch. 82.527 Km on Vallabhipur Branch canal.
292432
04 of 2026-27
Open
Miscellaneous Works
Works
Ahmedabad
6 documents required · 6 mandatory
₹4,248
Executive Engineer, S.B.C Division No-1/2, Dhandhuka
₹1.9 L
1 Apr 2026
1 Apr 2026
1 Apr 2026
22 Apr 2026
1 Apr 2026
Dismentalling the existing damage RCC/CC lining
including disposing off the dismentalled materials
& stacking the usefull material and conveying &
disposed off unuseful materials up to 3.0 km lead
and all lifts as directed(IN SLOPE + BED)
10.00 cm thick linning.
Providing and Laying in position Controlled
Plain/Reinforced Cement Concrete Lining of M-15
grade in Bed, Side Slopes and curvature including
batching, mixing, transporting, placing, vibrating,
smooth finishing, membreane curing & providing
bitumenous joint of specefic interval including
minor filling/deposition with murrum/earth/soil
as per site condition to correct profile, watering,
compaction, trimming etc to provide lining.
10.0 cm thick linning.
Excavation in all sort of strata and formations incl.
depositing the unuseful excavated stuff as and
where directed incl sorting and stacking useful
materials as directed upto 30 mt lead etc. complete
3 incl. dewatering. 792.23 Cum 83.00
( Depth 0 TO 3.0 mt )
(For all type canal & foundation trenches of C.D.
A) IN OVERBURDEN INCL. HARD MURRUM.
& hard murrum excavated from approved borrow
area / village tanks etc. excluding royalty charges,
conveying, spreading in uniform layersof 15 to
4 cm thickness and using of pad cutting excavated 29035.73 Cum 141.00
soil and hard murrumin embankment after
compaction ,breaking clods and dressing to
designed canal section etc. . with lead upto 1 km
and all lift.
Prov. and Laying in position Controlled cement
concrete using cement, sand and crushed
aggregate by mass and machine mix for R.C.C/CC
5 work including necessary formworks centering 1598.8904 Cum 5372.00
scaffolding compaction by vibrator,curing as
directed with all lead & lift etc complete
A) Concrete grade M-25 and MSA-20mm
Providing & filling Asphalt Joint of the approved
make and sand in the expansion and contraction
joints in the C.C. Lining including clearing the joints
with air water jet.
Providing, cutting, bending, binding and fixing in
position as per drawing. TMT BAR , Fe-415
7 reinforcement for R.C.C. works and anchor bars 34.96 MT 66268.00
incl cost of black annealed 16 to 18 BWG M.S. Wire
etc.complete with all lead and lift.
Providing, supplying & lowering, Laying, Jointing
ISI standared R.C.C. pipes (Of sulphate resisiting
cement) in standard length of following class and
diameter suitble for either coller joints or rubber
ring including all taxes, insurance, transportation,
freight charges, octroi, inspection charges, loading,
unloading, conveyance to departmental stores,
stacking etc.
Note: One coller should be supplied with each full
length plain ended RCC pipe, cost including in rates
below. One ribber ring should be supplied with
each full length socketed pipe, cost included in
rates below.
Class IRS/NP-4 1600 mm dia.
Providing and laying 300 mm thick Granular sub-
base in two layers by providing coarse graded
material Grading- I using B.T.M.C. (Black Trap
Machine Crushed) metal 53 mm to 26.5 mm at
% , crushed stone aggregate 26.5 mm to 4.75 mm
9 at 45% and below 2.36 mm at 20% ,having C.B.R. 388.75 Cum 1044.42
not less than 30%, as per table 402 of MORTH
gradation including leveling the material at site of
work ,mixing and spreading into grade and camber
, watering and consolidation at OMC with roller
including cost of material ,labour etc complete.
Providing, supplying, Lowering, and laying ISI
Standard R.C.C. NP-3 Class pipes in standard
lengths of following Diameter suitable for either
collar joints or rubber ring joints including all
taxes, insurance, transportation, freight charges,
octroi, inspection charges, loading, unloading,
conveyance to Site, and jointing in proper position,
grade and alignment at all level as directed by
Engineer-in-charge including all labour, giving
hydraulic testing as per ISI code. (I) 1200 mm dia.
Type - A, "W" : Metal Beam Crash Barrier
(Providing and erecting a "W" metal beam crash
barrier comprising of 3 mm thick corrugated sheet
metal beam rail, 70 cm above road/ground level,
fixed on ISMC series channel vertical post, 150 x
x 5 mm spaced 2 m centre to centre, 1.8 mhigh,
m below ground/road level, all steel parts and
fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal
beam rail to be fixed on the vertical post with a
spacer of channel section 150 x 75 x 5 mm, 330 mm
long complete as per clause 811).
Supplying and Fixing road sign board of M.S. plates
and angle iron including painting, lettering etc.
12 complete including fixing in C.C. 1:4:8 with 60.00 Nos. 3072.99
necessary excavation etc. complete as per I.R.C.
type design. (ii) Reflective type.
Providing & laying dry rubble pitching without
inverted graded filter and without header stone
13 but incl. hand packing trimming & dressing of 394.00 Sq.mt 526.00
slopes etc. complete. (a) 30 cms thick stone
Total Amount Rs.
Total Amount Rs.
I/We am/are willing to carry out the work at…...................... %above/below percent (Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our
tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………%below Add………%Above
In words In words
(B) For Item Rate Tender (For above INR 50 Cr.):
Item Description of Item(with Quantity Unit Rate Amount
No brief specification and
reference to book of In In
specifications) figures Words
(A)Total Tendered Amount
(B)Rebate on above tendered amount (if any) % (in figure)
(in words)
(C)NetTendered Amount(A-B) (in figure) ………………………………
(in words)
1 The Contractor shall exhibit a board with detailed specification and details of work as
directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all P.C.C./R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as
per vernacular office letter no. 04 of 2024, Dt. 20/01/2024 of The Chief Engineer, Quality
Control (SSNNL) as stated in S.O.R. therefore in P.C.C./R.C.C. items where there is a change
as per Nominal mix the cost of difference of cement consumption have been deducted from
the rate of original item at the rate of input rate (i.e. 5448.53 Rs / MT for OPC) in all the
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
04-SBD-Pipe Diversion.pdf
BOQ-Pipe Diversion.pdf
Drawings-Pipe Diversion.pdf
M0 Sheet 04.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .