| 1 | L1₹10.4 LAccepted-AOC | L1 | Accepted-AOC AWARDED | |
| 2 | L2₹9.0 L+₹17,270 (1.95%)Rejected-AOC | L2 | Rejected-AOC REJECTED FINANCIALLY |
Tender Value
₹13.3 L
EMD Value
₹16,700
Closing Date
26 Apr 2024, 6:00 pmClosed
SO EnM
SO EnM OFFICE RAJRAPPA
Extension/ erection of LT Overhead line (approx route length for erection/ extension is 1.5Km and dismantling of LT line(app route length for dismantling is 750 mtr) for period of 1 year(365 days) on as when and where required basis
2024_CCL_306453_1
GM(R)/SO(EnM)/Rjp/24-25/Et/4dt 11.4.24
Open Tender
Electrical and Maintenance Works
Item Rate
365 days
RAJRAPPA
Please refer Tender documents.
2 documents required · 2 mandatory
₹16,700
20 Jul 2024
11 Apr 2024
27 Apr 2024
12 Apr 2024
26 Apr 2024
12 Apr 2024
12 Apr 2024 - 15 Apr 2024
Amount
Erection of metallic pole of length Above 10 metre and upto 12 metre in cement concrete 1:3:6 (1cement: 3 coarse sand: 6 graded stone aggregate 40mm size) foundation including excavation and re filling etc.as required
Labour cost for loading, unloading of metallic poles, conductor etc.for transportation from store to site (vice versa).(Truck will be provided departmentally)
Supplying and erection of stay set complete (galvanised) with 19/ 20 mm dia X 1.8 metres long stay rod, anchor plate of size 45 cm X 45 cm X 7.5 mm, thimble, stay clamps, turn buckle ( 20 mm X 60 cm ), 7/ 3.15 mm dia G.I. stay wire and strain insulator etc in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling etc. as required.
Supplying of channel iron 75 mm X 40 mm X 6 mm (7.14 kg per metre) cross arm for 4 wire over head line complete with clamps, bolts, nuts and washer etc including drilling of holes for insulator pins etc (as per drawing) and painting with primer and finished paint as required
Erection of angle iron/ channel iron cross arm on steel tubular/ rail pole etc. as required.( 48 no of conductors and 21 no of cradles)
Supplying and erection of 100 mm X 110 mm shackle insulator with G. I. Bolt, nuts and straps etc. as required .
Supplying and erection of 100 mm X 80 mm pin insulator complete with G. I. Spindle and nuts etc. as required .
Erection of all aluminium conductor of 7/1.96 mm to 7/3.10 mm diameter including binding etc. as required. (Approx. Route length for erection of 4-wire LT line is 1.5 Km).
Supply of 8 SWG GI Wire for cradling
Erection of Cradle guard 3 wire(15 no of spans)
Dismantling of pole/ street light standard/ strut embedded in cement concrete foundation etc. as required.
Dismantling of over head lines comprising of copper/ aluminium over head conductor, G.I. wire, cross arms, insulators etc. as required. 15 no of spans (Approx. route length for dismantling =750 mtr)].
Total impact of GST for the purpose of CTC
Coalfield Construction
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_317584.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .