Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
| 2 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
Tender Value
₹9.5 L
EMD Value
₹19,000
Closing Date
9 Mar 2026, 12:00 pmClosed
E.E
MGCCD-3 Amroha
LOT 04 CONSTRUCTION OF V.R.B AT KM 9.300 OF HANDALPUR MINOR OF MGC STAGE-II
2026_UPIDC_1120808_11
01/EE/2025-26
Open Tender
Civil Works - Canal
Item Rate
MGCCD-3 Amroha
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹19,000
15 Apr 2026
28 Feb 2026
9 Mar 2026
28 Feb 2026
9 Mar 2026
28 Feb 2026
Earth work in excavation in foundation in ordinary soil for structure i/c all lead and req lift as per site requirement and proper disposal of earth as directed by engg.in charge
Earth work in filling in all type of soil with all lift and lead upto 600m. Including ramming, dressing and manual compaction etc. all cost of earth and T&P etc.complete.
Centering and shuttering for RCC work i/c all cost of labour and T&P etc. for complete for proper completion of work.
Providing and laying P.C.C. 1:3:6 in foundation including all cost of material, labour and T&P etc. complete.
M-100 brick work in 1:4 cement coarse sand mortar including all cost of material, labour and T&P etc. complete.
Shuttering for PCC work i/c all cost of labour and T&P etc. for complete for proper completion of work.
R.C.C.(M – 20) in 1:1.5:3 including all cost of material, labour and T&Petc complete
Supplying and placing steel reinforcement for RCC work in including all cost of material, labour , cutting, bending, binding and T&P complete
P.C.C.1:6:12 including all cost of material, labour and T&P etccomplete.
Struck deep Pointing in 1:2 cement mortar including all cost of material, labour and T&P etc complete.
S/F Drainage Spout P.V.C. 75 mm dia pipe including all cost of material, labour and T&P etc complete.
S/F 25 mm thick expansion joints i/c cost of material, labour and T&P etc complete
S/Laying Tarfelt in 2- layers for Bearing slab. i/c all cost of material, labour and T&P etc complete.
M-100 brick on edge paving i/c joints filled with sand i/c cost of all material,labour T&P etc complete for proper completion of work.
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.52 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.87 MB
TD04.pdf
Tender Documents • 2.99 MB
BOQ_2085727.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .