Tender Value
₹94.8 L
EMD Value
₹1.9 L
Closing Date
5 Oct 2026, 3:00 pm
Executive Engineer, Agartala Division No.I
Executive Engineer, Agartala Division No.I
Improvement of perifery road of Banamalipur Dighir Par inc Connected road SH Development of road by providing BM, BC etc
2026_CEPWD_77177_1
78/SE-II/PWD(RandB)/2026-27
Open Tender
Civil Works - Roads
Works
180 days
AGARTALA
Please refer Tender documents.
8 documents required · 8 mandatory
₹4,000
₹1.9 L
25 Sept 2026
25 Sept 2026
5 Oct 2026
25 Sept 2026
5 Oct 2026
25 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Maintenance of Earthen shoulder (filling with fresh selectedsoil)
Making up loss of material / irregularities on shoulders tothe design level by adding fresh approved selected soil andcompacting it with appropriate equipment at OMC upto alead of 1000 m as per MoRT&H technical specificationClause 3003 | 2,736 | Sqm | 66.4 | ₹1,81,670.4 |
| 2 | Maintenance of Earthen shoulder (Stripping of excess soil)Stripping excess soil from the shoulder surface to achievethe approved level and compacting with plate compactor atOMC as per drawing and MoRT&H technical specificationClause 3003. | 3,075 | Sqm | 19.1 | ₹58,732.5 |
| 3 | Prime Coat
Providing and applying primer coat with bitumen
emulsion (SS-1) on prepared surface of granular
base including cleaning of road surface and
spraying primer at the rate of 0.90- 1.20 kg/sqm
using mechanical means as per MoRD Technical
Specification Clause 502 | 8,325 | Sqm | 91.05 | ₹7,57,991.25 |
| 4 | Tack Coat
Providing and applying tack coat with bitumen
emulsion (RS-1) using emulsion distributor at the
rate of 0.30 to 0.35 kg per sqm on the prepared
non-bituminous surfaces (cement concrete
pavement) cleaned with Hydraulic broom as per
MoRD Technical Specification Clause 503. | 8,325 | Sqm | 23.4 | ₹1,94,805 |
| 5 | Bituminous Macadam
Providing and laying bituminous macadam with hot mixplant using crushed aggregates of grading as perTable500.4 premixed with bituminous binder, transported to siteupto a lead of 1000 m laid over a previously preparedsurface with paver finisher to the required grade, level andalignment and rolled to achieve the desired compaction asper MoRD Technical Specification Clause 504
i. With Viscosity Graded Bitumen of VG-30 | 82.61 | Cum | 16,348.1 | ₹13,50,516.54 |
| 6 | Providing and laying bituminous concrete with higher capacitybatch type hot mix plant using crushed aggregates of specifiedgrading, premixed with bituminous binder @ 5.40 Percent of mixand filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the requiredgrade, level and alignment, rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction asper MORTH specification clause No. 507 complete in all respects.
Greading-II | 244.8 | cum | 23,036.23 | ₹56,39,269.1 |
| 7 | Maintenance of bituminous surface road
Repair to pot holes by removal of failed material,
trimming the sides to vertical and levelling the
bottom, cleaning the same with compressed air or
any appropriate method, filled with 75 mm B.M,
after applying bitumen emulsion prime coat at the
bottom and bitumen emulsion tack coat on sides
and on bottom as per MoRD technical specification
Clauses 1900, 502, 503 and 504. | 53.86 | cum | 18,296.21 | ₹9,85,483.64 |
| 8 | Road marking strips (retro-reflective) of specified shade/colour using Hot Applied Thermoplastic material withProviding and applying 2.5 mm thick thick road markingstrips (retro-reflective) of specified shade/ colour using hotthermoplastic material including reflectorising glass beads@ 250 gms per sqm area by fully/ semi automaticthermoplastic paint applicator machine fitted with profileshoe, glass beads dispenser, propane tank heater andprofile shoe heater including cost of cleaning the roadsurface of all dirt, seals, oil, grease and foreign materialetc, thickness of 2.5 mm is exclusive of surface appliedglass beads as per IRC:35. The finished surface to be level,uniform and free from streaks and holes as per MoRT&HTechnical Specification Clause 803.Reflectorising Glass Beads on Bituminous Surface | 432 | Sqm | 721.9 | ₹3,11,860.8 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.39 MB
Standard_SE_78.pdf
Tender Documents • 3.25 MB
BOQ_78558.xls
BOQ • 2.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .