Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.6 CrAccepted-AOC KOLKATA METROPOLITAN DEVELOPMENT AUTHORITY OFFICE OF THE SUPERINTENDING ENGINEER CIRCLE II ROADS BRIDGES SECTOR KMDA UNNAYAN BHAWAN BLOCK A 7TH FLOOR SALT LAKE CITY KOLKATA 700091 WEST BENGAL INDIA | 24 PARAGANAS NORTH | WEST BENGAL | 700091 | ₹20.6 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹22.1 Cr+₹1.4 Cr (7.00%)Rejected-Finance WEST BENGAL INDIA | DARJEELING | WEST BENGAL | 734001 | ₹22.1 Cr+₹1.4 Cr (7.00%) | L2 | Rejected-Finance NOT L1 |
| 3 | L3₹22.1 Cr+₹1.5 Cr (7.27%)Rejected-Finance | ₹22.1 Cr+₹1.5 Cr (7.27%) | L3 | Rejected-Finance NOT L1 |
| 4 | L4₹22.3 Cr+₹1.7 Cr (8.12%)Rejected-Finance 54D A T CHATTERJEE ROAD KOLKATA 700031 WEST BENGAL | KOLKATA | KOLKATA | WEST BENGAL | 700031 | ₹22.3 Cr+₹1.7 Cr (8.12%) | L4 | Rejected-Finance NOT L1 |
| 5 | L5₹22.6 Cr+₹2.0 Cr (9.69%)Rejected-Finance 9 1 11 BL NO 8 JAGATDAL NORTH 24 PARGANAS WEST BENGAL 743125 | JAGATDAL | NORTH 24 PARGANAS | WEST BENGAL | 743125 | ₹22.6 Cr+₹2.0 Cr (9.69%) | L5 | Rejected-Finance NOT L1 |
Tender Value
₹22.2 Cr
EMD Value
₹10 L
Closing Date
15 Nov 2025, 1:19 pmClosed
Superintending Engineer, South Circle
SE, South Circle, SD Sector, KMDA Unnayan Bhawan, Gr Floor, Block-A, Salt Lake City, Kolkata 700091
Construction of RCC covered drain from Nabin Nagar Math to RB Road...North Dum Dum Municipality and Laying of 1400 mm, 1600 mm, and 1800 mm dia NP3 Hume pipe.....North Dum Dum and Panihati municipality..under Disaster Management progm
2025_KMDA_945345_1
03/SE(South)/SD/KMDA OF 2025-2026
Open Tender
CIVIL WORKS
Percentage
100 days
North Dumdum and panihati Municipality
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹10 L
Office of the SE, SOUTH CIRCLR, SD SECTOR,KMDA
27 Mar 2026
11 Nov 2025
6 Dec 2025
11 Nov 2025
4 Dec 2025
11 Nov 2025
14 Nov 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.
(a) Depth of excavation not exceeding 1,500 mm. | 17,401.5 | cum | 119.27 | ₹20,75,476.91 |
| 1.02 | (b) Depth of excavation for additional depth beyond 1,500 mm. and upto 3,000 mm. but not requiring shoring | 12,949.71 | Cum | 192.38 | ₹24,91,265.21 |
| 1.03 | (c) Depth of excavation for additional depth beyond 3000 mm. upto 4000mm. excluding cost of shoring as necessary. | - | Cum | 234.7 | - |
| 2 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) (a) With earth obtained from excavation of foundation. | - | Cum | 77.54 | - |
| 3 | (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity). | 1 | cum | 936.21 | ₹935.27 |
| 4.01 | Supply and delivery of NP3 SPIGOT / SOCKET TYPE OF PIPE WITH RUBBER GASKET. Rate of pipe including Loading, Unloading & Freight Charges.
(i) 1400 mm dia NP3 Pipe | - | Mtr | 10,130 | - |
| 4.02 | (ii) 1600 mm dia NP3 Pipe | - | Mtr | 12,879.6 | - |
| 4.03 | (iii) 1800 mm dia NP3 Pipe | - | Mtr | 15,294.4 | - |
| 5.01 | Laying of R.C.C. pipe with spigot -socket/Roll on jointed pipe, lowering the same into the trench laying on the bed in trenches in prescribed gradient, depth and alignment, filling the end grooves with necessary bitumastic compound, filling caulking space with tarred gasket or with rubber gasket of appropriate size & covering with cement mortar (1:2) & testing the joints etc. complete as per drawing, specification including carriage of pipes from site stacks to the place of laying etc. & as per direction of the Engineer-in- charge. (Payment to be made on the basis of actual finished length of the pipe line).
A) Class NP-3 Pipe (i) 1400 mm dia NP3 Pipe | - | Mtr | 1,013 | - |
| 5.02 | (ii) 1600 mm dia NP3 Pipe | - | Mtr | 1,234 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 3.45 MB
Tendernotice_2.pdf
PDF • 3.65 MB
BOQ_2246120.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .